CONSTRUCTION DAILY ACTIVITY REPORT

Project Name : REMAINING CIVIL WORK AT ROW AREA Report Number : JTB / CV /2021 / VII / 156
Location : Bojonegoro Date : 7/4/2021
Rev :0 Sheet Number : 156

Manpower Equipment and Transportation Unit Total


No. Description Man Hours Total No. Description Ea hours Hours
1 Indirect Manpower
PM 1 0 0 1 Transport Pekerja 1 7 7
SM 1 0 0 2 Genset 1 7 7
CM 1 7 7 3 Jack Hammer 1 0 0
PC 1 7 7 4 Gunting Besi 1 7 7
FE 1 7 7 5 Concrete vibrator 1 0 0
6 Gerinda Potong beton 1 7 7
7 Lampu penerangan 3 0 0
8 Concrete Core Drill 1 7 7
9 Tube Scaffolding 171 7 1197
10 Kompor Gas dan LPG 1 0 0
11 Mortar Mixer 1 7 7

Sub Total 21 Grand Total 1239


2 Direct Manpower
Foreman 1 7 7
Mason 1 7 7 Weather
No. Condition Remarks
Rebarman 1 7 7 Time
Carpenter 1 7 7
Helper 4 7 28 1 C : 07.00 - 08.00 Clear
2 C : 08.01 - 09.00 Clear
3 C : 09.01 - 10.00 Clear
4 C : 10.01 - 11.00 Clear
5 C : 11.01 - 12.00 Clear
6 C : 12.01 - 13.00 Clear
7 C : 13.01 - 14.00 Clear
8 C : 14.01 - 15.00 Clear
9
10

Sub Total 56
Grand Total 77 Note : C = Clear R = Rainy CD= Cloudy W= Windy

No. Work Activity QTY No Work Plan Activity for Next Day

1 Pekerjaan Guard House 1 Pekerjaan Guard House


- Pemasangan dinding batako m2 2.11 - Fabrikasi dan pemasangan bekisting beton praktis

2 Pekerjaan Security Post


- Fabrikasi dan pemasangan bekisting beton praktis

Remarks :

No. Item of Concern Corrective Action

Made by, Prepared by, Acknowledged by,


PT USAHA BHAKTI PT RECON SARANA UTAMA PT RECON SARANA UTAMA

Julkarnain Fahmi Ismail Achmad Basuki


SM Project Control Construction Manager
REMAINING CIVIL WORK AT ROW AREA

DAILY PICTURE
Sunday, July 04, 2021

Pekerjaan Guard House


- Pemasangan dinding batako
FIELD DAILY REPORT BY SUPERVISOR
Hari / Tanggal : Sunday, 04 July 2021
Report No : 156
Status (√)
No Manpower Qty Manpower Qty No Equipment Qty Remarks
W I S B
I Indirect 1 Excavator PC 200 (W)orking
PM 1 SPV 2 Excavator PC 78 (I)dle
SM 1 QC 3 Vibroroller/ babyroller (S)tandby
CM 1 QC Adm 4 Hand stamper (B)roken
PC 1 HSE Coord 5 Pick Up 1 √
FE 1 HSE SPV 6 Dump Truck
Surveyor MatCon 7 Bar Bending/Cutting
Ast. Surveyor Driver 1 8 Air Compressor
9 Water Tank Truck 2 √
10 Water Pump 1 √
11 Asphalt Cutter
II Direct 12 Portable Genset 1 √
Opt. Exca PC 200 Helper 4 13 Electric Vibrator 1 √
Opt. Exca PC 78 Welder 14 Tube Scaffolding 171 √
Opt. Vibroroller Scaffolder 15 Surveyor Equipment
Foreman 1 Flagman 16 DCP Test
Mason 1 Driver Pickup 1 17 CBR Test
Rebarman 1 Driver DT 18 Sandcone
Carpenter 1 Helper survey 19 Jack Hammer 1 √
20 Gerinda Potong beton 1 √
21 Lampu Penerangan 3 √
22 Concrete Core Drill 1 √
23 Gunting Besi 1 √
24 Kompor Gas dan LPG 1 √
25 Mortar Mixer 1 √

No Area Aktivitas Unit Quantity

1 ROW Sta 4+775 Pekerjaan Guard House


- Pemasangan dinding batako m2 27.24

Cuaca HSE Concern

1 07.00 - 09.00 C 3 13.00 - 15.00 C


2 09.01 - 11.30 C 4 15.01 - 17.00 C

PERMASALAHAN/PENGHAMBAT
CONSTRUCTION DAILY ACTIVITY REPORT

Project Name : REMAINING CIVIL WORK AT ROW AREA Report Number : JTB / CV /2021 / VII / 157
Location : Bojonegoro Date : 7/5/2021
Rev :0 Sheet Number : 157

Manpower Equipment and Transportation Unit Total


No. Description Man Hours Total No. Description Ea hours Hours
1 Indirect Manpower
PM 1 2 2 1 Transport Pekerja 1 8 8
SM 1 8 8 2 Genset 1 8 8
CM 1 8 8 3 Jack Hammer 1 0 0
PC 1 8 8 4 Gunting Besi 1 8 8
FE 1 8 8 5 Concrete vibrator 1 0 0
6 Gerinda Potong beton 1 8 8
7 Lampu penerangan 3 0 0
8 Concrete Core Drill 1 8 8
9 Tube Scaffolding 171 8 1368
10 Kompor Gas dan LPG 1 0 0
11 Mortar Mixer 1 8 8

Sub Total 34 Grand Total 1416


2 Direct Manpower
Foreman 1 8 8
Mason 1 8 8 Weather
No. Condition Remarks
Rebarman 1 8 8 Time
Carpenter 1 8 8
Helper 4 8 32 1 C : 07.00 - 08.00 Clear
2 C : 08.01 - 09.00 Clear
3 C : 09.01 - 10.00 Clear
4 C : 10.01 - 11.00 Clear
5 C : 11.01 - 12.00 Clear
6 C : 12.01 - 13.00 Clear
7 C : 13.01 - 14.00 Clear
8 C : 14.01 - 15.00 Clear
9 C : 15.01 - 16.00 Clear
10 C : 16.01 - 17.00 Clear

Sub Total 64
Grand Total 98 Note : C = Clear R = Rainy CD= Cloudy W= Windy

No. Work Activity QTY No Work Plan Activity for Next Day

1 Pekerjaan Guard House 1 Pekerjaan Guard House


- Fabrikasi dan pemasangan besi tulangan praktis Kg 194.56 - Fabrikasi dan pemasangan bekisting beton praktis

2 Pekerjaan Security Post 2 Pekerjaan Security Post


- Fabrikasi dan pemasangan besi tulangan praktis Kg 73.44 - Fabrikasi dan pemasangan bekisting beton praktis

Remarks :

No. Item of Concern Corrective Action

Made by, Prepared by, Acknowledged by,


PT USAHA BHAKTI PT RECON SARANA UTAMA PT RECON SARANA UTAMA

Julkarnain Fahmi Ismail Achmad Basuki


SM Project Control Construction Manager
REMAINING CIVIL WORK AT ROW AREA

DAILY PICTURE
Monday, July 05, 2021

Pekerjaan Guard House Pekerjaan Security Post


- Fabrikasi dan pemasangan besi tulangan praktis - Fabrikasi dan pemasangan besi tulangan praktis
FIELD DAILY REPORT BY SUPERVISOR
Hari / Tanggal : Monday, 05 July 2021
Report No : 157
Status (√)
No Manpower Qty Manpower Qty No Equipment Qty Remarks
W I S B
I Indirect 1 Excavator PC 200 (W)orking
PM 1 SPV 2 Excavator PC 78 (I)dle
SM 1 QC 3 Vibroroller/ babyroller (S)tandby
CM 1 QC Adm 4 Hand stamper (B)roken
PC 1 HSE Coord 5 Pick Up 1 √
FE 1 HSE SPV 6 Dump Truck
Surveyor MatCon 7 Bar Bending/Cutting
Ast. Surveyor Driver 1 8 Air Compressor
9 Water Tank Truck 2 √
10 Water Pump 1 √
11 Asphalt Cutter
II Direct 12 Portable Genset 1 √
Opt. Exca PC 200 Helper 4 13 Electric Vibrator 1 √
Opt. Exca PC 78 Welder 14 Tube Scaffolding 171 √
Opt. Vibroroller Scaffolder 15 Surveyor Equipment
Foreman 1 Flagman 16 DCP Test
Mason 1 Driver Pickup 1 17 CBR Test
Rebarman 1 Driver DT 18 Sandcone
Carpenter 1 Helper survey 19 Jack Hammer 1 √
20 Gerinda Potong beton 1 √
21 Lampu Penerangan 3 √
22 Concrete Core Drill 1 √
23 Gunting Besi 1 √
24 Kompor Gas dan LPG 1 √
25 Mortar Mixer 1 √

No Area Aktivitas Unit Quantity

1 ROW Sta 4+775 Pekerjaan Guard House


- Fabrikasi dan pemasangan besi tulangan praktis Kg 194.56

2 ROW Sta 4+810 Pekerjaan Security Post


- Fabrikasi dan pemasangan besi tulangan praktis Kg 73.442

Cuaca HSE Concern

1 07.00 - 09.00 C 3 13.00 - 15.00 C


2 09.01 - 11.30 C 4 15.01 - 17.00 C

PERMASALAHAN/PENGHAMBAT
CONSTRUCTION DAILY ACTIVITY REPORT

Project Name : REMAINING CIVIL WORK AT ROW AREA Report Number : JTB / CV /2021 / VII / 158
Location : Bojonegoro Date : 7/6/2021
Rev :0 Sheet Number : 158

Manpower Equipment and Transportation Unit Total


No. Description Man Hours Total No. Description Ea hours Hours
1 Indirect Manpower
PM 1 2 2 1 Transport Pekerja 1 8 8
SM 1 8 8 2 Genset 1 8 8
CM 1 8 8 3 Jack Hammer 1 0 0
PC 1 8 8 4 Gunting Besi 1 8 8
FE 1 8 8 5 Concrete vibrator 1 0 0
6 Gerinda Potong beton 1 8 8
7 Lampu penerangan 3 0 0
8 Concrete Core Drill 1 8 8
9 Tube Scaffolding 171 8 1368
10 Kompor Gas dan LPG 1 0 0
11 Mortar Mixer 1 8 8

Sub Total 34 Grand Total 1416


2 Direct Manpower
Foreman 1 8 8
Mason 1 8 8 Weather
No. Condition Remarks
Rebarman 1 8 8 Time
Carpenter 1 8 8
Helper 4 8 32 1 C : 07.00 - 08.00 Clear
2 C : 08.01 - 09.00 Clear
3 C : 09.01 - 10.00 Clear
4 C : 10.01 - 11.00 Clear
5 C : 11.01 - 12.00 Clear
6 C : 12.01 - 13.00 Clear
7 C : 13.01 - 14.00 Clear
8 C : 14.01 - 15.00 Clear
9 C : 15.01 - 16.00 Clear
10 C : 16.01 - 17.00 Clear
Sub Total 64
Grand Total 98 Note : C = Clear R = Rainy CD= Cloudy W= Windy

No. Work Activity QTY No Work Plan Activity for Next Day

1 Pekerjaan Guard House 1 Pekerjaan Guard House


- Fabrikasi dan pemasangan bekisting beton praktis m2 6.80 - Fabrikasi dan pemasangan bekisting beton praktis

2 Pekerjaan Security Post 2 Pekerjaan Acces Road STA 0+000 sd 0+015


- Fabrikasi dan pemasangan bekisting beton praktis m2 2.38 Sales Gas Metering
- Isi Joint Sealant

Remarks :

No. Item of Concern Corrective Action

Made by, Prepared by, Acknowledged by,


PT USAHA BHAKTI PT RECON SARANA UTAMA PT RECON SARANA UTAMA

Julkarnain Fahmi Ismail Achmad Basuki


SM Project Control Construction Manager
REMAINING CIVIL WORK AT ROW AREA

DAILY PICTURE
Tuesday, July 06, 2021

Pekerjaan Security Post


- Fabrikasi dan pemasangan bekisting beton praktis
FIELD DAILY REPORT BY SUPERVISOR
Hari / Tanggal : Tuesday, 06 July 2021
Report No : 158
Status (√)
No Manpower Qty Manpower Qty No Equipment Qty Remarks
W I S B
I Indirect 1 Excavator PC 200 (W)orking
PM 1 SPV 2 Excavator PC 78 (I)dle
SM 1 QC 3 Vibroroller/ babyroller (S)tandby
CM 1 QC Adm 4 Hand stamper (B)roken
PC 1 HSE Coord 5 Pick Up 1 √
FE 1 HSE SPV 6 Dump Truck
Surveyor MatCon 7 Bar Bending/Cutting
Ast. Surveyor Driver 1 8 Air Compressor
9 Water Tank Truck 2 √
10 Water Pump 1 √
11 Asphalt Cutter
II Direct 12 Portable Genset 1 √
Opt. Exca PC 200 Helper 4 13 Electric Vibrator 1 √
Opt. Exca PC 78 Welder 14 Tube Scaffolding 171 √
Opt. Vibroroller Scaffolder 15 Surveyor Equipment
Foreman 1 Flagman 16 DCP Test
Mason 1 Driver Pickup 1 17 CBR Test
Rebarman 1 Driver DT 18 Sandcone
Carpenter 1 Helper survey 19 Jack Hammer 1 √
20 Gerinda Potong beton 1 √
21 Lampu Penerangan 3 √
22 Concrete Core Drill 1 √
23 Gunting Besi 1 √
24 Kompor Gas dan LPG 1 √
25 Mortar Mixer 1 √

No Area Aktivitas Unit Quantity

1 ROW Sta 4+775 Pekerjaan Guard House


- Fabrikasi dan pemasangan bekisting beton praktis m2 6.8

2 ROW Sta 4+810 Pekerjaan Security Post


- Fabrikasi dan pemasangan bekisting beton praktis m2 2.38

Cuaca HSE Concern

1 07.00 - 09.00 C 3 13.00 - 15.00 C


2 09.01 - 11.30 C 4 15.01 - 17.00 C

PERMASALAHAN/PENGHAMBAT
CONSTRUCTION DAILY ACTIVITY REPORT

Project Name : REMAINING CIVIL WORK AT ROW AREA Report Number : JTB / CV /2021 / VII / 159
Location : Bojonegoro Date : 7/7/2021
Rev :0 Sheet Number : 159

Manpower Equipment and Transportation Unit Total


No. Description Man Hours Total No. Description Ea hours Hours
1 Indirect Manpower
PM 1 2 2 1 Transport Pekerja 1 8 8
SM 1 8 8 2 Genset 1 8 8
CM 1 8 8 3 Jack Hammer 1 0 0
PC 1 8 8 4 Gunting Besi 1 8 8
FE 1 8 8 5 Concrete vibrator 1 0 0
6 Gerinda Potong beton 1 8 8
7 Lampu penerangan 3 0 0
8 Concrete Core Drill 1 8 8
9 Tube Scaffolding 171 8 1368
10 Kompor Gas dan LPG 1 8 8
11 Mortar Mixer 1 8 8

Sub Total 34 Grand Total 1424


2 Direct Manpower
Foreman 1 8 8
Mason 1 8 8 Weather
No. Condition Remarks
Rebarman 1 8 8 Time
Carpenter 1 8 8
Helper 4 8 32 1 C : 07.00 - 08.00 Clear
2 C : 08.01 - 09.00 Clear
3 C : 09.01 - 10.00 Clear
4 C : 10.01 - 11.00 Clear
5 C : 11.01 - 12.00 Clear
6 C : 12.01 - 13.00 Clear
7 C : 13.01 - 14.00 Clear
8 C : 14.01 - 15.00 Clear
9 C : 15.01 - 16.00 Clear
10 C : 16.01 - 17.00 Clear
Sub Total 64
Grand Total 98 Note : C = Clear R = Rainy CD= Cloudy W= Windy

No. Work Activity QTY No Work Plan Activity for Next Day

1 Pekerjaan Guard House 1 Pekerjaan Guard House


- Fabrikasi dan pemasangan bekisting beton praktis m2 11.30 - Cor beton praktis kolom dan balok

2 Pekerjaan Acces Road STA 0+000 sd 0+015 2 Pekerjaan Guard House


Sales Gas Metering - Cor beton praktis kolom dan balok
- Isi Joint Sealant m 45.80

Remarks :

No. Item of Concern Corrective Action

Made by, Prepared by, Acknowledged by,


PT USAHA BHAKTI PT RECON SARANA UTAMA PT RECON SARANA UTAMA

Julkarnain Fahmi Ismail Achmad Basuki


SM Project Control Construction Manager
REMAINING CIVIL WORK AT ROW AREA

DAILY PICTURE
Wednesday, July 07, 2021

Pekerjaan Acces Road STA 0+000 sd 0+015 Pekerjaan Acces Road STA 0+000 sd 0+015
Sales Gas Metering Sales Gas Metering
- Isi Joint Sealant - Isi Joint Sealant

Pekerjaan Guard House


- Fabrikasi dan pemasangan bekisting beton praktis
FIELD DAILY REPORT BY SUPERVISOR
Hari / Tanggal : Wednesday, 07 July 2021
Report No : 159
Status (√)
No Manpower Qty Manpower Qty No Equipment Qty Remarks
W I S B
I Indirect 1 Excavator PC 200 (W)orking
PM 1 SPV 2 Excavator PC 78 (I)dle
SM 1 QC 3 Vibroroller/ babyroller (S)tandby
CM 1 QC Adm 4 Hand stamper (B)roken
PC 1 HSE Coord 5 Pick Up 1 √
FE 1 HSE SPV 6 Dump Truck
Surveyor MatCon 7 Bar Bending/Cutting
Ast. Surveyor Driver 1 8 Air Compressor
9 Water Tank Truck 2 √
10 Water Pump 1 √
11 Asphalt Cutter
II Direct 12 Portable Genset 1 √
Opt. Exca PC 200 Helper 4 13 Electric Vibrator 1 √
Opt. Exca PC 78 Welder 14 Tube Scaffolding 171 √
Opt. Vibroroller Scaffolder 15 Surveyor Equipment
Foreman 1 Flagman 16 DCP Test
Mason 1 Driver Pickup 1 17 CBR Test
Rebarman 1 Driver DT 18 Sandcone
Carpenter 1 Helper survey 19 Jack Hammer 1 √
20 Gerinda Potong beton 1 √
21 Lampu Penerangan 3 √
22 Concrete Core Drill 1 √
23 Gunting Besi 1 √
24 Kompor Gas dan LPG 1 √
25 Mortar Mixer 1 √

No Area Aktivitas Unit Quantity

1 ROW Sta 4+775 Pekerjaan Guard House


- Fabrikasi dan pemasangan bekisting beton praktis m2 11.3

2 SGM STA 0+000 sd 0+015 Pekerjaan Acces Road STA 0+000 sd 0+015
Sales Gas Metering
- Isi Joint Sealant m 45.8

Cuaca HSE Concern

1 07.00 - 09.00 C 3 13.00 - 15.00 R


2 09.01 - 11.30 C 4 15.01 - 17.00 C

PERMASALAHAN/PENGHAMBAT
CONSTRUCTION DAILY ACTIVITY REPORT

Project Name : REMAINING CIVIL WORK AT ROW AREA Report Number : JTB / CV /2021 / VII / 160
Location : Bojonegoro Date : 7/8/2021
Rev :0 Sheet Number : 160

Manpower Equipment and Transportation Unit Total


No. Description Man Hours Total No. Description Ea hours Hours
1 Indirect Manpower
PM 1 2 2 1 Transport Pekerja 1 8 8
SM 1 8 8 2 Genset 1 8 8
CM 1 8 8 3 Jack Hammer 1 0 0
PC 1 8 8 4 Gunting Besi 1 8 8
FE 1 8 8 5 Concrete vibrator 1 8 8
6 Gerinda Potong beton 1 8 8
7 Lampu penerangan 3 0 0
8 Concrete Core Drill 1 8 8
9 Tube Scaffolding 171 8 1368
10 Kompor Gas dan LPG 1 0 0
11 Mortar Mixer 1 8 8

Sub Total 34 Grand Total 1424


2 Direct Manpower
Foreman 1 8 8
Mason 1 8 8 Weather
No. Condition Remarks
Rebarman 1 8 8 Time
Carpenter 1 8 8
Helper 4 8 32 1 C : 07.00 - 08.00 Clear
2 C : 08.01 - 09.00 Clear
3 C : 09.01 - 10.00 Clear
4 C : 10.01 - 11.00 Clear
5 C : 11.01 - 12.00 Clear
6 C : 12.01 - 13.00 Clear
7 C : 13.01 - 14.00 Clear
8 C : 14.01 - 15.00 Clear
9 C : 15.01 - 16.00 Clear
10 C : 16.01 - 17.00 Clear
Sub Total 64
Grand Total 98 Note : C = Clear R = Rainy CD= Cloudy W= Windy

No. Work Activity QTY No Work Plan Activity for Next Day

1 Pekerjaan Guard House 1 Pekerjaan Guard House


- Cor beton praktis kolom dan balok m3 1.30 - Pemasangan dinding batako

2 Pekerjaan Security Post


- Cor beton praktis kolom dan balok m3 0.16

Remarks :

No. Item of Concern Corrective Action

Made by, Prepared by, Acknowledged by,


PT USAHA BHAKTI PT RECON SARANA UTAMA PT RECON SARANA UTAMA

Julkarnain Fahmi Ismail Achmad Basuki


SM Project Control Construction Manager
REMAINING CIVIL WORK AT ROW AREA

DAILY PICTURE
Thursday, July 08, 2021

Pekerjaan Guard House


- Cor beton praktis kolom dan balok

-
-
FIELD DAILY REPORT BY SUPERVISOR
Hari / Tanggal : Thursday, 08 July 2021
Report No : 160
Status (√)
No Manpower Qty Manpower Qty No Equipment Qty Remarks
W I S B
I Indirect 1 Excavator PC 200 (W)orking
PM 1 SPV 2 Excavator PC 78 (I)dle
SM 1 QC 3 Vibroroller/ babyroller (S)tandby
CM 1 QC Adm 4 Hand stamper (B)roken
PC 1 HSE Coord 5 Pick Up 1 √
FE 1 HSE SPV 6 Dump Truck
Surveyor MatCon 7 Bar Bending/Cutting
Ast. Surveyor Driver 1 8 Air Compressor
9 Water Tank Truck 2 √
10 Water Pump 1 √
11 Asphalt Cutter
II Direct 12 Portable Genset 1 √
Opt. Exca PC 200 Helper 4 13 Electric Vibrator 1 √
Opt. Exca PC 78 Welder 14 Tube Scaffolding 171 √
Opt. Vibroroller Scaffolder 15 Surveyor Equipment
Foreman 1 Flagman 16 DCP Test
Mason 1 Driver Pickup 1 17 CBR Test
Rebarman 1 Driver DT 18 Sandcone
Carpenter 1 Helper survey 19 Jack Hammer 1 √
20 Gerinda Potong beton 1 √
21 Lampu Penerangan 3 √
22 Concrete Core Drill 1 √
23 Gunting Besi 1 √
24 Kompor Gas dan LPG 1 √
25 Mortar Mixer 1 √

No Area Aktivitas Unit Quantity

1 ROW Sta 4+775 Pekerjaan Guard House


- Cor beton praktis kolom dan balok m3 1.30

2 ROW Sta 4+810 Pekerjaan Security Post


- Cor beton praktis kolom dan balok m3 0.16

Cuaca HSE Concern

1 07.00 - 09.00 C 3 13.00 - 15.00 C


2 09.01 - 11.30 C 4 15.01 - 17.00 C

PERMASALAHAN/PENGHAMBAT
CONSTRUCTION DAILY ACTIVITY REPORT

Project Name : REMAINING CIVIL WORK AT ROW AREA Report Number : JTB / CV /2021 / VII / 161
Location : Bojonegoro Date : 7/9/2021
Rev :0 Sheet Number : 161

Manpower Equipment and Transportation Unit Total


No. Description Man Hours Total No. Description Ea hours Hours
1 Indirect Manpower
PM 1 2 2 1 Transport Pekerja 1 8 8
SM 1 8 8 2 Genset 1 8 8
CM 1 8 8 3 Jack Hammer 1 0 0
PC 1 8 8 4 Gunting Besi 1 8 8
FE 1 8 8 5 Concrete vibrator 1 0 0
6 Gerinda Potong beton 1 8 8
7 Lampu penerangan 3 0 0
8 Concrete Core Drill 1 8 8
9 Tube Scaffolding 171 8 1368
10 Kompor Gas dan LPG 1 0 0
11 Mortar Mixer 1 8 8

Sub Total 34 Grand Total 1416


2 Direct Manpower
Foreman 1 8 8
Mason 1 8 8 Weather
No. Condition Remarks
Rebarman 1 8 8 Time
Carpenter 1 8 8
Helper 4 8 32 1 C : 07.00 - 08.00 Clear
2 C : 08.01 - 09.00 Clear
3 C : 09.01 - 10.00 Clear
4 C : 10.01 - 11.00 Clear
5 C : 11.01 - 12.00 Clear
6 C : 12.01 - 13.00 Clear
7 R : 13.01 - 14.00 Clear
8 R : 14.01 - 15.00 Clear
9 C : 15.01 - 16.00 Clear
10 C : 16.01 - 17.00 Clear
Sub Total 64
Grand Total 98 Note : C = Clear R = Rainy CD= Cloudy W= Windy

No. Work Activity QTY No Work Plan Activity for Next Day

1 Pekerjaan Guard House 1 Pekerjaan Guard House


- Pemasangan dinding batako m2 3.93 - Plesteran dinding batako

Remarks :

No. Item of Concern Corrective Action

Made by, Prepared by, Acknowledged by,


PT USAHA BHAKTI PT RECON SARANA UTAMA PT RECON SARANA UTAMA

Julkarnain Fahmi Ismail Achmad Basuki


SM Project Control Construction Manager
REMAINING CIVIL WORK AT ROW AREA

DAILY PICTURE
Friday, July 09, 2021

Pekerjaan Guard House


- Pemasangan dinding batako
FIELD DAILY REPORT BY SUPERVISOR
Hari / Tanggal : Friday, 09 July 2021
Report No : 161
Status (√)
No Manpower Qty Manpower Qty No Equipment Qty Remarks
W I S B
I Indirect 1 Excavator PC 200 (W)orking
PM 1 SPV 2 Excavator PC 78 (I)dle
SM 1 QC 3 Vibroroller/ babyroller (S)tandby
CM 1 QC Adm 4 Hand stamper (B)roken
PC 1 HSE Coord 5 Pick Up 1 √
FE 1 HSE SPV 6 Dump Truck
Surveyor MatCon 7 Bar Bending/Cutting
Ast. Surveyor Driver 1 8 Air Compressor
9 Water Tank Truck 2 √
10 Water Pump 1 √
11 Asphalt Cutter
II Direct 12 Portable Genset 1 √
Opt. Exca PC 200 Helper 4 13 Electric Vibrator 1 √
Opt. Exca PC 78 Welder 14 Tube Scaffolding 171 √
Opt. Vibroroller Scaffolder 15 Surveyor Equipment
Foreman 1 Flagman 16 DCP Test
Mason 1 Driver Pickup 1 17 CBR Test
Rebarman 1 Driver DT 18 Sandcone
Carpenter 1 Helper survey 19 Jack Hammer 1 √
20 Gerinda Potong beton 1 √
21 Lampu Penerangan 3 √
22 Concrete Core Drill 1 √
23 Gunting Besi 1 √
24 Kompor Gas dan LPG 1 √
25 Mortar Mixer 1 √

No Area Aktivitas Unit Quantity

1 ROW Sta 4+775 Pekerjaan Guard House


- Pemasangan dinding batako m2 3.93

Cuaca HSE Concern

1 07.00 - 09.00 C 3 13.00 - 15.00 C


2 09.01 - 11.30 C 4 15.01 - 17.00 C

PERMASALAHAN/PENGHAMBAT
CONSTRUCTION DAILY ACTIVITY REPORT

Project Name : REMAINING CIVIL WORK AT ROW AREA Report Number : JTB / CV /2021 / VII / 162
Location : Bojonegoro Date : 7/10/2021
Rev :0 Sheet Number : 162

Manpower Equipment and Transportation Unit Total


No. Description Man Hours Total No. Description Ea hours Hours
1 Indirect Manpower
PM 1 2 2 1 Transport Pekerja 1 8 8
SM 1 8 8 2 Genset 1 8 8
CM 1 8 8 3 Jack Hammer 1 0 0
PC 1 8 8 4 Gunting Besi 1 8 8
FE 1 7 7 5 Concrete vibrator 1 0 0
6 Gerinda Potong beton 1 8 8
7 Lampu penerangan 3 0 0
8 Concrete Core Drill 1 8 8
9 Tube Scaffolding 171 8 1368
10 Kompor Gas dan LPG 1 0 0
11 Mortar Mixer 1 8 8

Sub Total 33 Grand Total 1416


2 Direct Manpower
Foreman 1 8 8
Mason 1 8 8 Weather
No. Condition Remarks
Rebarman 1 8 8 Time
Carpenter 1 8 8
Helper 4 8 32 1 C : 07.00 - 08.00 Clear
2 C : 08.01 - 09.00 Clear
3 C : 09.01 - 10.00 Clear
4 C : 10.01 - 11.00 Clear
5 C : 11.01 - 12.00 Clear
6 C : 12.01 - 13.00 Clear
7 C : 13.01 - 14.00 Clear
8 C : 14.01 - 15.00 Clear
9 C : 15.01 - 16.00 Clear
Sub Total 64
Grand Total 97 Note : C = Clear R = Rainy CD= Cloudy W= Windy

No. Work Activity QTY No Work Plan Activity for Next Day

1 Pekerjaan Guard House 1 Pekerjaan Guard House


- Plesteran dinding batako m2 9.80 - Plesteran dinding batako

Remarks :

No. Item of Concern Corrective Action

Made by, Prepared by, Acknowledged by,


PT USAHA BHAKTI PT RECON SARANA UTAMA PT RECON SARANA UTAMA

Julkarnain Fahmi Ismail Achmad Basuki


SM Project Control Construction Manager
REMAINING CIVIL WORK AT ROW AREA

DAILY PICTURE
Saturday, July 10, 2021

Pekerjaan Guard House


- Plesteran dinding batako
FIELD DAILY REPORT BY SUPERVISOR
Hari / Tanggal : Saturday, 10 July 2021
Report No : 162
Status (√)
No Manpower Qty Manpower Qty No Equipment Qty Remarks
W I S B
I Indirect 1 Excavator PC 200 (W)orking
PM 1 SPV 2 Excavator PC 78 (I)dle
SM 1 QC 3 Vibroroller/ babyroller (S)tandby
CM 1 QC Adm 4 Hand stamper (B)roken
PC 1 HSE Coord 5 Pick Up 1 √
FE 1 HSE SPV 6 Dump Truck
Surveyor MatCon 7 Bar Bending/Cutting
Ast. Surveyor Driver 1 8 Air Compressor
9 Water Tank Truck 2 √
10 Water Pump 1 √
11 Asphalt Cutter
II Direct 12 Portable Genset 1 √
Opt. Exca PC 200 Helper 4 13 Electric Vibrator 1 √
Opt. Exca PC 78 Welder 14 Tube Scaffolding 171 √
Opt. Vibroroller Scaffolder 15 Surveyor Equipment
Foreman 1 Flagman 16 DCP Test
Mason 1 Driver Pickup 1 17 CBR Test
Rebarman 1 Driver DT 18 Sandcone
Carpenter 1 Helper survey 19 Jack Hammer 1 √
20 Gerinda Potong beton 1 √
21 Lampu Penerangan 3 √
22 Concrete Core Drill 1 √
23 Gunting Besi 1 √
24 Kompor Gas dan LPG 1 √
25 Mortar Mixer 1 √

No Area Aktivitas Unit Quantity

1 ROW Sta 4+775 Pekerjaan Guard House


- Plesteran dinding batako m2 9.80

Cuaca HSE Concern

1 07.00 - 09.00 C 3 13.00 - 15.00 C


2 09.01 - 11.30 C 4 15.01 - 17.00 C

PERMASALAHAN/PENGHAMBAT
Maret April Mei
3/1/2021 31 III 4/1/2021 62 IV 5/1/2021
3/2/2021 32 III 4/2/2021 63 IV 5/2/2021
3/3/2021 33 III 4/3/2021 64 IV 5/3/2021
3/4/2021 34 III 4/4/2021 65 IV 5/4/2021
3/5/2021 35 III 4/5/2021 66 IV 5/5/2021
3/6/2021 36 III 4/6/2021 67 IV 5/6/2021
3/7/2021 37 III 4/7/2021 68 IV 5/7/2021
3/8/2021 38 III 4/8/2021 69 IV 5/8/2021
3/9/2021 39 III 4/9/2021 70 IV 5/9/2021
3/10/2021 40 III 4/10/2021 71 IV 5/10/2021
3/11/2021 41 III 4/11/2021 72 IV 5/11/2021
3/12/2021 42 III 4/12/2021 73 IV 5/12/2021
3/13/2021 43 III 4/13/2021 74 IV 5/13/2021
3/14/2021 44 III 4/14/2021 75 IV 5/14/2021
3/15/2021 45 III 4/15/2021 76 IV 5/15/2021
3/16/2021 46 III 4/16/2021 77 IV 5/16/2021
3/17/2021 47 III 4/17/2021 78 IV 5/17/2021
3/18/2021 48 III 4/18/2021 79 IV 5/18/2021
3/19/2021 49 III 4/19/2021 80 IV 5/19/2021
3/20/2021 50 III 4/20/2021 81 IV 5/20/2021
3/21/2021 51 III 4/21/2021 82 IV 5/21/2021
3/22/2021 52 III 4/22/2021 83 IV 5/22/2021
3/23/2021 53 III 4/23/2021 84 IV 5/23/2021
3/24/2021 54 III 4/24/2021 85 IV 5/24/2021
3/25/2021 55 III 4/25/2021 86 IV 5/25/2021
3/26/2021 56 III 4/26/2021 87 IV 5/26/2021
3/27/2021 57 III 4/27/2021 88 IV 5/27/2021
3/28/2021 58 III 4/28/2021 89 IV 5/28/2021
3/29/2021 59 III 4/29/2021 90 IV 5/29/2021
3/30/2021 60 III 4/30/2021 91 IV 5/30/2021
3/31/2021 61 III 5/31/2021
Juni Juli
92 V 6/1/2021 123 VI 7/1/2021 153 VII
93 V 6/2/2021 124 VI 7/2/2021 154 VII
94 V 6/3/2021 125 VI 7/3/2021 155 VII
95 V 6/4/2021 126 VI 7/4/2021 156 VII
96 V 6/5/2021 127 VI 7/5/2021 157 VII
97 V 6/6/2021 128 VI 7/6/2021 158 VII
98 V 6/7/2021 129 VI 7/7/2021 159 VII
99 V 6/8/2021 130 VI 7/8/2021 160 VII
100 V 6/9/2021 131 VI 7/9/2021 161 VII
101 V 6/10/2021 132 VI 7/10/2021 162 VII
102 V 6/11/2021 133 VI 7/11/2021 163 VII
103 V 6/12/2021 134 VI 7/12/2021 164 VII
104 V 6/13/2021 135 VI 7/13/2021 165 VII
105 V 6/14/2021 136 VI 7/14/2021 166 VII
106 V 6/15/2021 137 VI 7/15/2021 167 VII
107 V 6/16/2021 138 VI 7/16/2021 168 VII
108 V 6/17/2021 139 VI 7/17/2021 169 VII
109 V 6/18/2021 140 VI 7/18/2021 170 VII
110 V 6/19/2021 141 VI 7/19/2021 171 VII
111 V 6/20/2021 142 VI 7/20/2021 172 VII
112 V 6/21/2021 143 VI 7/21/2021 173 VII
113 V 6/22/2021 144 VI 7/22/2021 174 VII
114 V 6/23/2021 145 VI 7/23/2021 175 VII
115 V 6/24/2021 146 VI 7/24/2021 176 VII
116 V 6/25/2021 147 VI 7/25/2021 177 VII
117 V 6/26/2021 148 VI 7/26/2021 178 VII
118 V 6/27/2021 149 VI 7/27/2021 179 VII
119 V 6/28/2021 150 VI 7/28/2021 180 VII
120 V 6/29/2021 151 VI 7/29/2021 181 VII
121 V 6/30/2021 152 VI 7/30/2021 182 VII
122 V 7/31/2021 183 VII