1

၆ခန္းတဲြ (၂)ထပ္ ၀န္ထမ္ းေနအိမ္

Name of Work…………………..3000 Gals Ground Tanks……..


Detail Of Measurements
Sr Measurement
Particular No Deduction Contents Total
No L B H

1 Earth Work For Excavation For Foundation

1 1 15' 9'' 10' 3'' 6' 9'' 1089.70 1089.70


Cft
2 6"x9" Stone Pitching & Sand Filling Work

1 1 15' 9'' 10' 3'' 0' 9'' 121.08 121.08

Cft
3 (1:3:6) Lean Concrete work

1 1 15' 9'' 10' 3'' 0' 3'' 40.36 40.36

Cft

4 (1:2:4) R.C.C Work

Footing 1 1 15' 9'' 10' 3'' 0' 9'' 121.08

Cover Slab 1 1 14' 0'' 7' 0'' 0' 3'' 24.50


Deduction
ManHole 2 1 1' 6'' 1' 6'' 0' 4'' 1.50
1.50 145.58 144.08

Cft

5 Rebar Work 12mmØ 10mmØ

Footing ½"Ø M.S 31 1 10' 6'' 325.50


(6" c/c Both Way) 20 1 16' 3'' 325.00

Cover Slab ⅜"Ø M.S 14 1 14' 0'' 196.00


(6" c/c Both Way) 28 1 7' 0'' 196.00
Rft 650.50 392.00
Lbs 0.596 0.414
387.70 162.29 549.99
Lbs
2
၆ခန္းတဲြ (၂)ထပ္ ၀န္ထမ္ းေနအိမ္

Name of Work…………………..3000 Gals Ground Tanks……..


Detail Of Measurements
Sr Measurement
Particular No Deduction Contents Total
No L B H
6 Formwork 1 1 14' 0'' 7' 0'' 98.00 98.00

Sft

7 Brick Work With (1:3) Cement Motor

13½" Brick Wall 2 1 14' 9'' 1' 1.5'' 2' 0'' 66.38

2 1 7' 0'' 1' 1.5'' 2' 0'' 31.50


9" Thk Brick Wall 2 1 14' 0'' 0' 9'' 4' 0'' 84.00

2 1 7' 0'' 0' 9'' 4' 0'' 42.00

1 1 7' 0'' 0' 4.5'' 6' 0'' 15.75 239.63


Cft

8 ¾" Thk Plastering Work with

(1:3) Cement motor

Internal 2 1 12' 6'' 6' 0'' 150.00


2 1 7' 0'' 6' 0'' 84.00

External 2 1 14' 0'' 1' 0'' 28.00


2 1 8' 6'' 1' 0'' 17.00
Divide 2 1 7' 0'' 6' 0'' 84.00 363.00
Sft

9 1½" thk (1:2:4) cement concrete Topping


1 1 12' 6'' 7' 0'' 87.50 87.50
Sft

10 Emulsion Painting Work 2 1 14' 0'' 1' 0'' 28.00


2 1 8' 6'' 1' 0'' 17.00 45.00
Sft
3
၆ခန္းတဲြ (၂)ထပ္ ၀န္ထမ္ းေနအိမ္

Name of Work…………………..3000 Gals Ground Tanks……..


Detail Of Measurements
Sr Measurement
Particular No Deduction Contents Total
No L B H
11 Manhole Cover & Step Iron Fitting Work

Manhole Cover (18"x18") 2 1 2.00 Nos

Step Iron (12" Long) 3 1 3.00 Nos


4

2625
5

၆ခန္းတဲြ (၂)ထပ္ ၀န္ထမ္ းေနအိမ္

Name of Work…………………..3000 Gals Ground Tanks……..


BUILDER'S ESTIMATE

Sr
Particular Quantity Unit Rate Per Amount Remarks
No

1 Earth Work For Excavation For Foundation 1089.70 Cft


Worker 21.79 Nos 7,000 Nos 152,558.44

2 Stone Pitching & Sand Filling Work 121.08 Cft

Boulder Stone 121.08 Cft 340 Cft 41166.56

Mason 0.61 Nos 9,000 Nos 5448.52


Worker 0.61 Nos 7,000 Nos 4237.73

3 (1:3:6) Lean Concrete work 40.36 Cft

Cement 5.19 Bags 5,500 Bags 28,539.84

Sand 19.37 Cft 120 Cft 2,324.70


Chipping 38.75 Cft 500 Cft 19,372.50

Mason 0.40 Nos 9,000 Nos 3,632.34

Worker 3.23 Nos 7,000 Nos 22,601.25

4 (1:2:4) R.C.C Work 144.08 Cft

Cement 26.63 Bags 5,500 Bags 146,457.99

Sand 66.28 Cft 120 Cft 7,953.11


Chipping 132.55 Cft 500 Cft 66,275.94

Mason 2.88 Nos 9,000 Nos 25,934.06

Worker 21.61 Nos 7,000 Nos 151,282.03

5 Rebar Work 549.99 Lbs

12mm Ø M.S Rod 0.18 Tons 750,000 Tons 136,300.08


6

၆ခန္းတဲြ (၂)ထပ္ ၀န္ထမ္ းေနအိမ္

Name of Work…………………..3000 Gals Ground Tanks……..


BUILDER'S ESTIMATE

Sr
Particular Quantity Unit Rate Per Amount Remarks
No

10mm Ø M.S Rod 0.08 Tons 750,000 Tons 57,054.38

Binding Wire 4.91 Lbs 700 Lbs 3,437.41


Steel Fixer 4.91 Nos 9,000 Nos 44,195.30

Worker 4.91 Nos 7,000 Nos 34,374.13

6 Timber Shuttering Formwork 98.00 Sft

Inn Wood (Scant)2-Timed Used 9.80 Cft 11,000 Cft 107,800.00


5-Ply Wood ,2-Timed Used 1.76 Sht 15,000 Sht 26,414.06

Wire Nail 2.94 Lbs 700 Lbs 2,058.00

Carpenter 5.88 Nos 9,000 Nos 52,920.00

Worker 1.96 Nos 7,000 Nos 13,720.00

7 Brick Work With (1:3) Cement Motor 239.63 Cft


Brick 3234.94 Nos 60 Nos 194,096.25
Cement 16.69 Bags 5,500 Bags 91,784.93
Sand 62.30 Cft 120 Cft 7,476.30
Mason 9.59 Nos 9,000 Nos 86,265.00
Worker 14.38 Nos 7,000 Nos 100,642.50
8 ¾" Thk Plastering Work with
(1:3) Cement motor 363.00 Sft
Cement 7.43 Bags 5,500 Bags 40,837.50
Sand 27.23 Cft 120 Cft 3,267.00
Mason 5.45 Nos 9,000 Nos 49,005.00
Worker 10.89 Nos 7,000 Nos 76,230.00

9 1½" thk (1:2:4) cement concrete Topping


87.50 Sft
7

၆ခန္းတဲြ (၂)ထပ္ ၀န္ထမ္ းေနအိမ္

Name of Work…………………..3000 Gals Ground Tanks……..


BUILDER'S ESTIMATE

Sr
Particular Quantity Unit Rate Per Amount Remarks
No

Cement 2.06 Bags 5,500 Bags 11,331.25


Sand 5.03 Cft 120 Cft 603.75
Chipping 10.06 Cft 500 Cft 5,031.25
Mason 0.66 Nos 9,000 Nos 5,906.25
Worker 1.31 Nos 7,000 Nos 9,187.50

10 Emulsion Painting Work 45.00 Sft


Emulsion Paint 0.23 Gals 12,000 Gals 2,700.00
Putty 0.11 Gals 6,000 Gals 675.00

Sand Paper 0.11 Doz 3,000 Doz 337.50

Painter 0.34 Nos 9,000 Nos 3,037.50

11 Manhole Cover & Step Iron Fitting Work


Manhole G.I Cover (18"x18") 2.00 Nos 6,500 Nos 13,000.00

Step Iron (12" Long) 3.00 Nos 2,000 Nos 6,000.00


Worker 1.00 Nos 7,000 Nos 7,000.00

Total 1,870,472.86
8

0.17307946429 0.0017308
9

0.07245 0.0007245 0.002455294642857

0.24552946429
10

1,869,347.86
11
၆ခန္းတဲြ (၂)ထပ္ ၀န္ထမ္ းေနအိမ္

Name of Work………………...3000 Gals Ground Tanks……..


BILLS OF QUANTITY
Sr Amount
Particulars Quantity Units Rate Per
No. Kyats
Material List
1 Sand 180.21 Cft 120 Cft 21,624.86
2 Boulder Stone 121.08 Cft 340 Cft 41,166.56
3 Cement 57.99 Bags 5500 Bags 318,951.51
4 3/8"~3/4" ေက်ာက္ 181.36 Cft 500 Cft 90,679.69
5 12mm Ø M.S Rod 0.18 Tons 750000 Tons 136,300.08
6 10mm Ø M.S Rod 0.08 Tons 750000 Tons 57,054.38
7 Binding Wire 4.91 Lbs 700 Lbs 3,437.41
8 Inn Wood(Scant) 9.80 Cft 11000 Cft 107,800.00
9 5-Plywood 1.76 Sht 15000 Sht 26,414.06
10 Wire Nail 2.94 Lbs 700 Lbs 2,058.00
11 Brick 3234.94 Nos 60 Nos 194,096.25
12 Emulsion Paint 0.23 Gals 7000 Gals 1,575.00
13 Putty 0.11 Gals 6000 Gals 675.00
14 Sand Paper 0.11 Doz 3,000 Doz 337.50
15 Manhole G.I Cover (18"x18") 2.00 Nos 6500 Nos 13,000.00
16 Step Iron (12" Long) 3.00 Nos 2000 Nos 6,000.00
1,021,170.30
Labour List
1 Mason 19.58 Nos 9000 Nos 176,191.17
2 Steel Fixer 4.91 Nos 9000 Nos 44,195.30
3 Carpenter 5.88 Nos 9000 Nos 52,920.00
4 Painter 0.34 Nos 9000 Nos 3,037.50
6 Worker 81.69 Nos 7000 Nos 571,833.58
848,177.55

Total 1,869,347.86
12

446.428571429

1,870,472.86 (1,125.00)
13

၆ခန္းတဲြ (၂)ထပ္ ၀န္ထမ္ းေနအိမ္

Name of Work………………...3000 Gals Ground Tanks……..

Abstract of Cost
Sr
Particulars Quantity Unit Rate Per Amount Remarks
No

1 Earth Work For Excavation For Foundation

1089.70 Cft 140.00 Cft 152,558.44


2 6"x9" Stone Pitching & Sand Filling Work 121.08 Cft 420.00 Cft 50,852.81
3 (1:3:6) Lean Concrete work 40.36 Cft 1894.74 Cft 76,470.64

4 (1:2:4) R.C.C Work 144.08 Cft 2761.72 Cft 397,903.13

5 Rebar Work 549.99 Lbs 500.67 Lbs 275,361.29


6 Timber Shuttering Formwork 98.00 Sft 2070.53 Sft 202,912.06

7 Brick Work With (1:3) Cement Motor 239.63 Cft 2004.24 Cft 480,264.98
8 ¾" Thk Plastering Work with

(1:3) Cement motor 363.00 Sft 466.50 Sft 169,339.50

9 1½" thk (1:2:4) cement concrete Topping 87.50 Sft 366.40 Sft 32,060.00
10 Emulsion Painting Work 45.00 Sft 150.00 Sft 6,750.00

11 Manhole Cover & Step Iron Fitting Work 26,000.00

Total 1,870,472.86
14

1,870,472.86 -
1,870,472.86 -
၆ခန္းတဲြ (၂)ထပ္ ၀န္ထမ္ းေနအိမ္

Name of Work………………...3000 Gals Ground Tanks……..

Summary

Sr
Material Cost Labour Cost Total Amount
Particulars Nos
(Kyats) (Kyats) (Kyats)
No

5 Civil Work (3000 Gals Ground Tanks…) 1 1,021,170 848,178 1,869,348

Total Cost For Ground Tank -1 Nos 1,869,348