1 Excavation Cft 17 347.02 5899.37
2 Soling Sft 72 277.85 20004.84
3 PCC Sft 120 277.85 33341.40
4 Formwork Sft 70 643.82 45067.40
5 RCC Cft 480 174.23 83631.30
6 9'' Brick Wall Cft 450 589.37 265214.87
7 Rebar Kg 120 724.00 86880.00
Amount 540039.19
Cost With 6'' extra depth
1 Excavation Cft 17 137.51 2337.62
2 9'' Brick Wall Cft 450 50.12 22554.11
Amount 24891.73
Extra Cost
1 Water 4000
2 Labour Backfilling and in road laying 11000
3 Extra Brick Work 7340.63
4 PCC top 3132
Amount 25472.63
Side Wall
1 Excavation Cft 17 555.00 9435.00
Stone Soling (Labor
2 Cft 150 55.50 8325.00
only)
3 PCC Sft 120 55.50 6660.00
4 9'' Wall Cft 450 162.75 73237.50
Filling (Road+side
5 Mds 1000 2.00 2000.00
Wall)
Amount 99657.50
Total Amount 690061.05
Advance Amount 500000
Remaining Amount 190061.05

In Words: One Lakh Ninety Thousand Sixty One Rupees Five Paisa Only.