CM Developers

Vinayak Colony, Bhainsepat


Rate Analysis of Water Tank 4000 ltrs capacity

Date: 2069/05/29
S.N. Particulars Unit Qty Rate Amount (Rs) Remarks
A STRUCTURAL WORK
1 Earthwork in excavaton cf ### 12.00 14,276.00
2 Earthwork in filling Cf 387.28 9.00 3,485.50
3 Brick soling Sf 172.34 42.00 7,238.43
4 100 micron DPM Sf 172.34 5.00 861.72
5 M10 (PCC) Cf 43.09 ### 7,669.29
6 M20 (RCC) Cf 262.39 ### 64,547.71
7 Normal Formwork (12 mm Ply) Sf 583.61 45.00 26,262.37
8 Reinforcement Work Kg 673.75 112.08 75,514.00

B FINISHING WORK
1 Plaster work Sf 198.00 29.00 5,742.00
2 Punning work Sf 198.00 22.00 4,356.00
3 IPS work Sf 120.00 57.00 6,840.00
4 Water Proofing work Sf 265.61 66.00 17,530.14
Total 234,323.15