Sr. No. Particular Amount (Kyat) Remark

A Material Cost 11,191,512.50


B Labour Cost 3,953,537.50

Total 15,145,050.00

1
Pobba Thiri Market External Water Supply
External Water Supply
Bill of Quantity

Sr. No. Particular Unit Quantity Rate Per Amount (Kyat)

Material
1 4" Ø P.V.C Pipe (13.5) No. 1537.00 2,800 No. 4,303,600.00
2 4" Ø P.V.C Elbow (13.5) No. 3.00 5,500 No. 16,500.00
3 4" Ø P.V.C Socket (13.5) No. 77.00 4,100 No. 315,700.00
4 4" Ø P.V.C Tee (13.5) No. 2.00 15,000 No. 30,000.00
5 4" Ø P.V.C R-Tee (13.5) No. 12.00 16,000 No. 192,000.00
6 4" Ø P.V.C R-Socket (13.5) No 12.00 5,000 No 60,000.00
7 2" Ø P.V.C Pipe (13.5) No. 180.00 760 No. 136,800.00
8 2" Ø P.V.C Elbow (13.5) No. 48.00 900 No. 43,200.00
9 2" Ø P.V.C Socket (13.5) No. 12.00 1,100 No. 13,200.00
10 2" Ø P.V.C Tee (13.5) No. 12.00 1,300 No. 15,600.00
11 2" Ø Gate Valve (Azuma) No. 12.00 33,600 No. 403,200.00
12 4" Ø Gate Valve (ANA) No. 7.00 228,000 No. 1,596,000.00
13 4" Ø P.V.C V-Socket (13.5) No. 24.00 3,000 No. 72,000.00
14 2" Ø P.V.C V-Socket (13.5) No. 24.00 600 No. 14,400.00
15 1" Ø Air Released Valve No. 2.00 150,000 No. 300,000.00
16 2" Ø P.V.C Float Ball Valve No. 12.00 50,000 No. 600,000.00
17 Seal tape No. 36.00 500 No. 18,000.00
18 PVC Cement Tin 9.00 4,000 Tin 36,000.00
19 Sand Sud 61.69 15,000 Sud 925,312.50
20 Valve Chamber (Material+Labour) No 7.00 300,000 No 2100000
Total of Material Cost 11,191,512.50

Labour
1 Plumber No. 82.25 9,000 No. 740,250.00
2 Worker No. 316.41 7,000 No. 2,214,887.50
3 4" Ø Pusher(Material+Labour) Rft 96.00 10,400 Rft 998,400.00

Total of Labour Cost 3,953,537.50


Total of Material and Labour Cost 15,145,050.00
5% Commercial Tax 757,252.50
Grand Total 15,902,302.50
Say 15,900,000.00

2
Pobba Thiri Market External Water Supply
External Water Supply
Abstract of Cost
Sr. Amount (KYAT)
Particular Unit Quantity Rate Per
No. Material
1 Site Clearing along the pipe line route by cutting bushes and site preparation
Sft 8585.00

2 Eathwork Excavation Work


Cft 6580.00

3 Sand filling including watering and ramming


Cft 1645.00 308,437.50

Piping Work
4 Pipe line laying work
Main Line (4"ØPVC Pipe) Rft 1537.00
Sub-main Line (2"ØPVC Pipe) Rft 180.00
Rft 1717.00 8,166,200.00

3
Pobba Thiri Market External Water Supply
External Water Supply
Builder's Estimate
Sr. Amount (KYAT)
Particular Unit Quantity Rate Per
No. Material Labour
1 Site Clearing along the pipe line route by cutting bushes and site preparation
Sft 8585.00
Labour
Worker No. 21.46 7,000 No. 150,237.50

2 Eathwork Excavation Work


Cft 6580.00
Labour
Worker No. 131.60 7,000 No. 921,200.00

3 Sand filling including watering and ramming


Cft 1645.00
Material
Sand Sud 20.56 15,000 Sud 308,437.50
Labour
Worker No. 16.45 7,000 No. 115,150.00

Piping Work
4 Pipe line laying work
Main Line (4"ØPVC Pipe) Rft 1537.00
Sub-main Line (2"ØPVC Pipe) Rft 180.00

Material
4" Ø P.V.C Pipe (13.5) Rft 1537.00 2,800 Rft 4,303,600.00
4" Ø P.V.C Elbow (13.5) No. 3.00 5,500 No. 16,500.00
4" Ø P.V.C Socket (13.5) No. 77.00 4,100 No. 315,700.00
4" Ø P.V.C Tee (13.5) No. 2.00 15,000 No. 30,000.00
4" Ø P.V.C R-Tee (13.5) No. 12.00 16,000 No. 192,000.00
4" Ø P.V.C R-Socket (13.5) No. 12.00 5,000 No. 60,000.00
2" Ø P.V.C Pipe (13.5) Rft 180.00 760 Rft 136,800.00
2" Ø P.V.C Elbow (13.5) No. 48.00 900 No. 43,200.00
2" Ø P.V.C Socket (13.5) No. 12.00 1,100 No. 13,200.00
2" Ø P.V.C Tee (13.5) No. 12.00 1,300 No. 15,600.00
2" Ø Gate Valve (Azuma) No. 12.00 33,600 No. 403,200.00
4" Ø Gate Valve (ANA) No. 7.00 228,000 No. 1,596,000.00
4" Ø P.V.C V-Socket (13.5) No. 24.00 3,000 No. 72,000.00
2" Ø P.V.C V-Socket (13.5) No. 24.00 600 No. 14,400.00
1" Ø Air Released Valve No. 2.00 150,000 No. 300,000.00
2" Ø P.V.C Float Ball Valve No. 12.00 50,000 No. 600,000.00

4
Pobba Thiri Market External Water Supply
External Water Supply
Builder's Estimate
Sr. Amount (KYAT)
Particular Unit Quantity Rate Per
No. Material Labour
Seal tape No. 36.00 500 No. 18,000.00
PVC Cement Tin 9.00 4,000 Tin 36,000.00
Labour
Plumber No. 82.25 9,000 No. 740,250.00
Worker No. 97.62 7,000 No. 683,340.00

5 Sand Filling in pipe line trench


Cft 3290.00
Material
Sand Sud 41.13 15,000 Sud 616,875.00
Labour
Worker No. 32.90 7,000 No. 230,300.00

6 Backfilling Work
Cft 1637.53
Labour
Worker No. 16.38 7,000 No. 114,660.00

7 Masonary Gate Valve Chamber including MS cover


Valve Chamber (Material+Labour) No 7.00 300,000 2,100,000.00

8 Pipe Line Pusher Work under concrete road


4" Ø Pusher(Material+Labour) Rft 96.00 10,400 998,400.00

Total of Material Charges 9,091,512.50


Total of Labour Charges 6,053,537.50
Total of Material and Labour Charges 15,145,050.00
5% Commercial Tax 757,252.50
Grand Total 15,902,302.50
Say 15,900,000.00

5
Pobba Thiri Market External Water Supply
External Water Supply
Detail of Measurements
Measurement Deduc-
Sr. No. Particular No Contents Total of Each
L B H tion

1 Site Clearing along the pipe line route by cutting bushes and site preparation
Main Line (4"ØPVC Pipe) 1x1 1537'- 0" 5'- 0" 7685.00 Sft
Sub-main Line (2"ØPVC Pipe) 1 x 12 15'- 0" 5'- 0" 900.00 Sft
from main to ground tank 8585.00 Sft

2 Eathwork Excavation Work


Main Line (4"ØPVC Pipe) 1x1 1465'- 0" 2'- 0" 2'- 0" 5860.00 Cft
Sub-main Line (2"ØPVC Pipe) 1 x 12 15'- 0" 2'- 0" 2'- 0" 720.00 Cft
from main to ground tank 6580.00 Cft

3 Sand filling including watering and ramming


Main Line (4"ØPVC Pipe) 1x1 1465'- 0" 2'- 0" 0'- 6" 1465.00 Cft
Sub-main Line (2"ØPVC Pipe) 1 x 12 15'- 0" 2'- 0" 0'- 6" 180.00 Cft
from main to ground tank 1645.00 Cft

4 Pipe line laying work


Main Line (4"ØPVC Pipe) 1x1 1537'- 0" 1537.00 Rft
Sub-main Line (2"ØPVC Pipe) 1 x 12 15'- 0" 180.00 Rft
from main to ground tank 1717.00 Rft

5 Sand Filling in pipe line trench


Main Line (4"ØPVC Pipe) 1x1 1465'- 0" 2'- 0" 1'- 0" 2930.00 Cft
Sub-main Line (2"ØPVC Pipe) 1 x 12 15'- 0" 2'- 0" 1'- 0" 360.00 Cft
from main to ground tank 3290.00 Cft

6 Backfilling Work
Eathwork Excavation Work 6580.00 Cft
Sand filling including watering and ramming 1645.00
Sand Filling in pipe line trench 1717.00
Main Line (4"ØPVC Pipe) 1x1 3.14'- 0" 0'- 4" 1465'- 0" 1533.37
Sub-main Line (2"ØPVC Pipe) 12 x 1 3.14'- 0" 0'- 1" 15'- 0 47.10
from main to ground tank 1637.53 Cft

6
Pobba Thiri Market External Water Supply
External Water Supply
Detail of Measurements
Measurement Deduc-
Sr. No. Particular No Contents Total of Each
L B H tion

7 Masonary Gate Valve Chamber including MS cover


1x7 7.00 No
7.00 No

8 Pipe Line Pusher Work under concrete road


Main Line (4"ØPVC Pipe) 1x4 24'- 0" 96.00 Rft
96.00 Rft

You might also like