You are on page 1of 7

Name of Project: Doubling of Track between Rajpura and Kakrala PKG-1

Client: RAIL VIKAS NIGAM LIMITED


PMC: AARVEE ASSOCIATES.
Contractor: JMC-KPTL-EESPL (JV)

Subject: Compressive Strength of Concrete checked with Rebound Hammer (Non Destructive Strength)

Details of Concrete Test Hammer: Contractor’s own testing equipment


Model No : ZC3-A (Schmidt Hammer)
Part of Structure : Return wall 2nd Lift
Location : Minor Bridge No.15
Date of Casting : 7/10/2020
Date of Testing : 04/02/2021
Grade of Concrete : M25

S.No Testing Point Test Description Rebound Final Compressive Strength Quality of concrete
Hammer N/MM2 (After correction as per test results
Reading factor taken from Graph)
1 Front side of wall Older than 35 days
(Top) 32 29 Good
2 Front side of wall Older than 35 days
(Middle) 34 32 Good
3 Front side of wall Older than 35 days
(Bottom) 30 26 Medium
4 Front side of wall Older than 35 days
(Top) 33 30 Good
5 Front side of wall Older than 35 days
(Middle) 31 28 Good
6 Front side of wall Older than 35 days
(Bottom) 31 28 Good
7 Back side of wall Older than 35 days
(Top) 30 26 Medium
8 Back side of wall Older than 35 days
(Middle) 34 32 Good
9 Back side of wall Older than 35 days
(Bottom) 31 28 Good
10 Back side of wall Older than 35 days
(Top) 32 29 Good
11 Back side of wall Older than 35 days
(Middle) 33 30 Good
12 Back side of wall Older than 35 days
(Bottom) 32 29 Medium

Avg. Compressive Strength 28.92

JMC-KPTL-EESPL (JV) PMC


Name of Project: Doubling of Track between Rajpura and Kakrala PKG-1
Client: RAIL VIKAS NIGAM LIMITED
PMC: AARVEE ASSOCIATES.
Contractor: JMC-KPTL-EESPL (JV)

Subject: Compressive Strength of Concrete checked with Rebound Hammer (Non Destructive Strength)

Details of Concrete Test Hammer: Contractor’s own testing equipment


Model No : ZC3-A (Schmidt Hammer)
Part of Structure : Return wall 1st Lift
Location : Ch.30/780 to 30/800 Near Bhakda Canal
Date of Casting : 28/10/2020
Date of Testing : 15/12/2021
Grade of Concrete : M30

S. Testing Point Test Description Rebound Final Compressive Strength Quality of concrete
No Hammer N/MM2 (After correction factor as per test results
Reading taken from Graph)
1 Front side of wall Older than 35 days
(Top) 38 40 Good
2 Front side of wall Older than 35 days
(Middle) 37 38 Good
3 Front side of wall Older than 35 days
(Bottom) 35 34 Good
4 Front side of wall Older than 35 days
(Top) 34 32 Medium
5 Front side of wall Older than 35 days
(Middle) 35 34 Good
6 Front side of wall Older than 35 days
(Bottom) 38 40 Good
7 Back side of wall Older than 35 days
(Top) 37 38 Good
8 Back side of wall Older than 35 days
(Middle) 38 40 Good
9 Back side of wall Older than 35 days
(Bottom) 35 34 Good
10 Back side of wall Older than 35 days
(Top) 36 36 Good
11 Back side of wall Older than 35 days
(Middle) 37 38 Good
12 Back side of wall Older than 35 days
(Bottom) 34 32 Medium

Avg. Compressive Strength 36.33

JMC-KPTL-EESPL (JV) PMC


Name of Project: Doubling of Track between Rajpura and Kakrala PKG-1
Client: RAIL VIKAS NIGAM LIMITED
PMC: AARVEE ASSOCIATES.
Contractor: JMC-KPTL-EESPL (JV)

Subject: Compressive Strength of Concrete checked with Rebound Hammer (Non Destructive Strength)

Details of Concrete Test Hammer: Contractor’s own testing equipment


Model No : ZC3-A (Schmidt Hammer)
Part of Structure : Return wall 1st Lift
Location : Minor Bridge No.94
Date of Casting : 6/10/2020
Date of Testing : 04/02/2021
Grade of Concrete : M25
S.N Testing Point Test Description Rebound Final Compressive Strength Quality of concrete as per
o Hammer N/MM2 (After correction test results
Reading factor taken from Graph)
1 Front side of wall Older than 35 days
(Top) 32 29 Good
2 Front side of wall Older than 35 days
(Middle) 33 30 Good
3 Front side of wall Older than 35 days
(Bottom) 30 26 Medium
4 Front side of wall Older than 35 days
(Top) 33 30 Good
5 Front side of wall Older than 35 days
(Middle) 32 29 Good
6 Front side of wall Older than 35 days
(Bottom) 31 28 Good
7 Back side of wall Older than 35 days
(Top) 30 26 Medium
8 Back side of wall Older than 35 days
(Middle) 32 29 Good
9 Back side of wall Older than 35 days
(Bottom) 31 28 Good
10 Back side of wall Older than 35 days
(Top) 32 29 Good
11 Back side of wall Older than 35 days
(Middle) 33 30 Good
12 Back side of wall Older than 35 days
(Bottom) 31 28 Good

Avg. Compressive Strength 28.50

JMC-KPTL-EESPL (JV) PMC


Name of Project: Doubling of Track between Rajpura and Kakrala PKG-1
Client: RAIL VIKAS NIGAM LIMITED
PMC: AARVEE ASSOCIATES.
Contractor: JMC-KPTL-EESPL (JV)

Subject: Compressive Strength of Concrete checked with Rebound Hammer (Non Destructive Strength)

Details of Concrete Test Hammer: Contractor’s own testing equipment


Model No : ZC3-A (Schmidt Hammer)
Part of Structure : Return wall 2nd Lift
Location : Ch.18/320 to 18//340 Near Daunkalan Station
Date of Casting : 06/10/2020
Date of Testing : 04/02/2021
Grade of Concrete : M30

S.No Testing Point Test Description Rebound Final Compressive Quality of


Hammer Strength N/MM2(After concrete as per
Reading correction factor taken test results
from Graph)
1 Front side of wall Older than 35 days
(Top) 35 34 Good
2 Front side of wall Older than 35 days
(Middle) 34 32 Medium
3 Front side of wall Older than 35 days
(Bottom) 37 38 Good
4 Front side of wall Older than 35 days
(Top) 38 40 Good
5 Front side of wall Older than 35 days
(Middle) 34 32 Medium
6 Front side of wall Older than 35 days
(Bottom) 38 40 Good
7 Back side of wall Older than 35 days
(Top) 36 36 Good
8 Back side of wall Older than 35 days
(Middle) 35 34 Good
9 Back side of wall Older than 35 days
(Bottom) 37 38 Good
10 Back side of wall Older than 35 days
(Top) 35 34 Good
11 Back side of wall Older than 35 days
(Middle) 38 40 Good
12 Back side of wall Older than 35 days
(Bottom) 34 32 Medium

Avg. Compressive Strength 35.83

JMC-KPTL-EESPL (JV) PMC


Name of Project: Doubling of Track between Rajpura and Kakrala PKG-1
Client: RAIL VIKAS NIGAM LIMITED
PMC: AARVEE ASSOCIATES.
Contractor: JMC-KPTL-EESPL (JV)

Subject: Compressive Strength of Concrete checked with Rebound Hammer (Non Destructive Strength)

Details of Concrete Test Hammer: Contractor’s own testing equipment


Model No : ZC3-A (Schmidt Hammer)
Part of Structure : Return wall 1st Lift
Location : Ch. 32/660 to 32/680 Near Bhakda Canal
Date of Casting : 06/10/2020
Date of Testing : 15/12/2020
Grade of Concrete : M30
S.No Testing Point Test Description Rebound Final Compressive Strength Quality of concrete
Hammer N/MM2(After correction as per test results
Reading factor taken from Graph)
1 Front side of wall Older than 35 days
(Top) 37 38 Good
2 Front side of wall Older than 35 days
(Middle) 35 34 Good
3 Front side of wall Older than 35 days
(Bottom) 35 34 Good
4 Front side of wall Older than 35 days
(Top) 36 36 Good
5 Front side of wall Older than 35 days
(Middle) 34 32 Medium
6 Front side of wall Older than 35 days
(Bottom) 37 38 Good
7 Back side of wall Older than 35 days
(Top) 34 32 Medium
8 Back side of wall Older than 35 days
(Middle) 35 34 Good
9 Back side of wall Older than 35 days
(Bottom) 37 38 Good
10 Back side of wall Older than 35 days
(Top) 34 32 Medium
11 Back side of wall Older than 35 days
(Middle) 36 36 Good
12 Back side of wall Older than 35 days
(Bottom) 35 34 Good

Avg. Compressive Strength 34.83

JMC-KPTL-EESPL (JV) PMC


Name of Project: Doubling of Track between Rajpura and Kakrala PKG-1
Client: RAIL VIKAS NIGAM LIMITED
PMC: AARVEE ASSOCIATES.
Contractor: JMC-KPTL-EESPL (JV)

Subject: Compressive Strength of Concrete checked with Rebound Hammer (Non Destructive Strength)

Details of Concrete Test Hammer: Contractor’s own testing equipment


Model No : ZC3-A (Schmidt Hammer)
Part of Structure : Return wall 2nd Lift
Location : Ch. 32/320 to 32/340 Near Bhakda Canal
Date of Casting : 06/10/2020
Date of Testing : 15/12/2020
Grade of Concrete : M30
S.No Testing Point Test Description Rebound Final Compressive Strength Quality of concrete
Hammer N/MM2(After correction as per test results
Reading factor taken from Graph)
1 Front side of wall Older than 35 days
(Top) 34 32 Medium
2 Front side of wall Older than 35 days
(Middle) 36 36 Good
3 Front side of wall Older than 35 days
(Bottom) 36 36 Good
4 Front side of wall Older than 35 days
(Top) 36 36 Good
5 Front side of wall Older than 35 days
(Middle) 34 32 Medium
6 Front side of wall Older than 35 days
(Bottom) 37 38 Good
7 Back side of wall Older than 35 days
(Top) 37 38 Good
8 Back side of wall Older than 35 days
(Middle) 35 34 Good
9 Back side of wall Older than 35 days
(Bottom) 36 36 Good
10 Back side of wall Older than 35 days
(Top) 34 32 Medium
11 Back side of wall Older than 35 days
(Middle) 35 34 Good
12 Back side of wall Older than 35 days
(Bottom) 37 38 Good

Avg. Compressive Strength 35.16

JMC-KPTL-EESPL (JV) PMC


Name of Project: Doubling of Track between Rajpura and Kakrala PKG-1
Client: RAIL VIKAS NIGAM LIMITED
PMC: AARVEE ASSOCIATES.
Contractor: JMC-KPTL-EESPL (JV)

Subject: Compressive Strength of Concrete checked with Rebound Hammer (Non Destructive Strength)

Details of Concrete Test Hammer: Contractor’s own testing equipment


Model No : ZC3-A (Schmidt Hammer)
Part of Structure : Return wall Raft
Location : Ch. 49/572 to 49/596 Near LC No.40
Date of Casting : 09/10/2020
Date of Testing : 04/02/2021
Grade of Concrete : M30
S.No Testing Point Test Description Rebound Final Compressive Strength Quality of concrete
Hammer N/MM2(After correction as per test results
Reading factor taken from Graph)
1 Left side of Raft Older than 35 days
32 34 Good
2 Middle of Raft Older than 35 days
35 40 Good
3 Right Side of Raft Older than 35 days
31 33 Good
4 Left side of Raft Older than 35 days
35 40 Good
5 Middle of Raft Older than 35 days
32 34 Good
6 Right Side of Raft Older than 35 days
32 34 Good
7 Left side of Raft Older than 35 days
31 33 Good
8 Middle of Raft Older than 35 days
30 31 Medium
9 Right Side of Raft Older than 35 days
32 34 Good
10 Left side of Raft Older than 35 days
32 34 Good
11 Middle of Raft Older than 35 days
33 36 Good
12 Right Side of Raft Older than 35 days
30 31 Medium

Avg. Compressive Strength 35.25

JMC-KPTL-EESPL (JV) PMC