Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
2 4.1, 4.2.1, 4.2.2, a) Are the Quality Manual, Work Procedure, Forms, Formats,
4.2.3, 4.2.4, 5.5.3 Process Flowcharts and Checklists issued as part of Quality
Management System (QMS) available at site as per latest copy
of List of QMS Forms and Documents ? Are these Forms &
Documents stamped 'Controlled' ? Check familiarity of sample
staff with above documents.
b) Check if in case of deviation from QMS Forms and
Documents abbreviated site name has been used in
Form/Document no. after SIL for distinction from QMS
Form/Document.
c) Check if necessity for change in QMS Form/Document from
site has been brought to the notice of MR's office by Project
Manager before making any change.
3 4.2.2, 4.2.3, 4.2.4 Has any extra copy of Quality Manual issued to Project
Manager been made ? If yes, check record of distribution, and
numbers used in these copies.
4 4.2.3, 4.2.4 a) Check if Project Manager has marked on all documents
received at site to whom to be distributed or copy to be issued
for action.
b) Check record of distribution of copy of QMS Forms and
Documents to relevant staff members at site for use and if such
copies are initialled against 'CONTROLLED' stamp by PM or his
authorised representitive.
5 4.2.4, 7.2.3, 8.2.1 Is File for correspondence with Customer maintained ? Check
whether Customer's letters are replied and status of letters with
respect to reply is mentioned on top of letters filed. Check if a
copy of all correspondences with Customer is sent to Project
Co-ordinator at Zonal / Sub-Office.
6 4.2.4, 7.2.2, 7.2.3(c) , Is there any procedure of Site Instructions issued by Customer ?
8.2.1 If yes, check if a copy is retained at PM's office and action has
been taken on all such instructions.
7 4.2.1, 4.2.3, 4.2.4, Check whether except for confidential files which may be kept
6.3(a) locked, other useful files and documents are stored properly in
almirah / cupboard / open shelf in a sequence with sticker marks
on shelves for easy identification and retrieval. (This is to be
checked in all departments / section).
8 4.2.1(c), 4.2.3(e) Check whether unique identification number and date are given
in letter and file for easy traceability and retrieval as per filing
system introduced.
9 4.2.1(c), 4.2.3(f) Check whether documents received from outside are recorded
in a register and their distribution is controlled.
11 4.2.3, 4.2.4 Check if file covers have been printed or sheet pasted as per
format in Form No. SIL/FIL/COV/01/1.
12 4.2.3(d), 4.2.3 (f) Are documents like Technical Books, latest Codes, Journals /
Periodicals etc. received at site recorded ? Check records.
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Form No. : SIL/QC/IQAC-S/08/1 of 20
Date : 26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
16 4.2.3(c), 4.2.3(d), Are current relevant Construction Drawings available at all work
4.2.3 (f), 4.2.4 locations at site ? Are changes & the current revision status
identified ? Check at random.
18 4.2.3, 4.2.4 Check whether index of all drawings is pasted on inside cover of
drawing folder or list separately maintained for verification of
contents.
19 4.2.3(g) Check whether the documents that have become out of use and
superseded are prevented from any un-intended use by
promptly destroying such document. In case, however, such
documents are to be stored for any future reference
'CONTROLLED' stamp shall be properly struck and
'OBSOLETE' stamp put on these documents. Check at random.
20 4.2.3, 4.2.4 Check if there is any record of all files in use at the site in
different sections and a Master List is available with the Project
Manager.
22 4.2.1, 4.2.3 Check from sample if in all documents produced at site Co's
name, Name of Project, Revision Status (where applicable),
Doc. No., date, Prepared by, Checked by, Approved by have
been printed or not.
23 5.3, 5.4.1 Is Co.'s Quality Policy and Objectives displayed in Project
Manager's office and in Meeting Room where built ?
24 5.3, 5.4.1 Is a copy of Co.'s Key Quality Objectives with Action Plan and
Measurable Goal for current year available with each staff
member at Site ? Find out by sample check.
25 4.2.1 Check whether a copy of Company's Safety Manual and Safety
Policy is available at site. Find out from sample checks if the site
personnel are aware of it.
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Date : 26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
27 4.2.4 Are Safety Reports prepared regularly in given format and sent
to RO / ZO ?
28 4.2.4, 5.5.3 a) Have all kinds of accidents, if any, been reported to Zonal
Office / Registered Office as per procedure alongwith probable
cause(s) of accident ?
30 4.2.3, 4.2.4, 6.3(b) Check whether backup for important files used in Computer are
kept in the form of CD or in another Computer elsewhere.
33 5.5.3 & 5.6.1 Check if Project Managers and Section Heads at site are aware
of 'Summary of Decisions' taken during last Management
Review Meeting.
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Date :26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
4 5.5.1, 5.5.3 Are duties of various staff members well defined and are they
well aware of the same ? Have sample checks.
5 6.2.1, 6.2.2 Is updated bio-data of all staff members available at site ? Have
these been checked and a copy sent to Zonal / Sub Office and
to MR's office ?
6 6.2.1, 6.2.2 Is the Project Manager satisfied with the performance of all his
staff members or he has asked for replacement of any staff ?
7 6.2.1, 6.2.2 Has the Customer made any complaint about performance of
any staff member or asked for his removal from site for any
reason ?
8 6.2.1, 6.2.2 Has the Project Manager identified any training programme for
any of the staff members through Annual Appraisal Report
and/or through Training Need Intimation Form ? Check from
record.
9 6.2.1, 6.2.2 Has Introduction Training been imparted to all new entrants at
site on the basis of CD received from Training Dept. at
Z.O./Sub-office or through any other training programme ?
Check record.
10 6.2.1, 6.2.2 Has any of the existing staff members undergone any training
through inhouse, external agencies during last one year ?
Check if these are recorded in Training File maintained
separately at site.
12 5.5.3 Are contact details of all staff members available at site office to
be used in case of any emergency ?
14 6.3, 6.4 Is access to site establishment well marked with signs ? Are all
the units located on high ground with proper drainage facilities ?
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Project
Clients Audited by :
Consultant, if any Date of Audit :
17 6.3, 6.4 Collect details of Telephone, Fax and E-mail connection at site
alongwith Mobile Phone connection, if any.
20 6.3, 6.4 Are all staff members provided with Company's transport
between workplace and their accommodation ?
21 6.3, 6.4 Are all staff members provided with Company's hired/built
accommodation in nearby town or near site ?
27 5.1, 6.4 a) Check if all staff and workmen required to wear safety gears
at work places are using the same.
28 5.1, 6.4 Check if there is enough stock of PPEs at site and those are of
proper quality.
29 6.3, 7.6 Check whether fitness tests have been carried out for all lifting
equipments.
30 4.2.4, 6.2.2 a) Is safety induction training given to workers and their record
properly maintained ?
b) Are all staff members joining site briefed
about safety hazards on first day by Safety Officer / Project
Manager ? Enquire with some newcomers.
31 4.2.4, 6.2.2 Are regular tool box meetings delivered to workers and their
record properly maintained ?
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Form No. : SIL/QC/IQAC-S/08/ 5 of 20
Date :26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
35 6.4 At major site is any rest room available for giving First-Aid and
initial treatment in case of accident ?
36 6.4 Are portable fire extinguishers available in store and site offices
and are they in running condition at the time of audit ? Check by
sample operation ?
37 6.2.2 Check whether some people other than Safety Officers at site
are trained to operate Fire Extinguishers confidently in case of
emergency and record of such training is maintained.
39 6.1, 6.3, 6.4 Is intensity of lighting required for safe working provided at all
places of work at night and the same inspected on daily basis ?
Verify some of the reports.
42 6.4, 8.5.3 Has any preventive action been taken to prevent recurrence in
future of type of accident already occurred ?
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Date :26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
50 6.2.2, 7.5.1(b) Check whether do's & don'ts / safety slogans / precautions are
displayed at key locations near machines..
52 6.3(b), 7.6 Check if computer software used for any monitoring and
measurement at site satisfied the intended application and if the
same is original version of the package or not.
53 6.2.2, 6.4 a) Check to ensure that Safety Engineer / Officer of one unit has
not conducted audit of his own unit.
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Date :26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
5 4.2.1, 7.1(b), 8.2.3 Has resource based detailed Project planning been done and
approval obtained from Customer ? Is it regularly monitored and
updated for all major activities based on commitments made to
Customer ? Check the latest one.
10 4.2.4 Check whether data for As-Built Drawings are regularly sent by
Construction Engineers. Also check status of submission of As-
Built drawings, if included in Contract.
11 5.2, 7.2.3, 8.2.1 Is Customer happy with performance so far on the project and
any letter of appreciation received ?
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Form No. : SIL/QC/IQAC-S/08/8 of 20
Date :26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
18 4.2.4, 5.5.3, 8.2.3 Check whether records of internal progress review and resource
requirement meeting held fortnightly between Project Manager
and site staff in QMS Form SIL/ISR/ROD/00/1 to 3 maintained
including 'Action by', 'Target date' and 'Verified by'. Verify
minutes of some recent meetings.
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Date :26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
27 7.2.1(c) Are any cases / complaints with Police / Octroi / Excise / Sales
Tax / Labour Court etc. pending ?
28 7.2.1 (a) a) Check whether a copy of Contractors All Risk (CAR) Policy is
available, if specified in contract.
30 6.3(a) Check if identification to all site facilities i.e. office, store, quality
lab etc.has been given by writing with paint or with stickers.
34 7.2.1, 7.2.2 Check if extra items of work are notified and rate analysis
submitted to Customer for approval in time preferably before
execution of work.
35 7.2.1, 7.2.2 Check whether the increase / reduction in BOQ quantities and /
or total Contract Value has been notified to Customer well in
advance (if applicable).
37 4.2.4 Check list of mobilised Plant & Equipment available at site with
its rating / capacity and their current running status.
38 4.2.4, 7.5.1 a) Are maintenance norms and procedure for routine and
preventive maintenance being followed as per Instruction
Manual and Job Instructions for Plant & Equipment issued as
QMS documents ? Records of ________ machines checked
and no delay / miss-out noticed.
b) Check from records if preventive maintenance plan of all
motors in use at site has been prepared and the same is being
effectively implemented.
c) Check if maintenance records of hired major machines are
being kept in record.
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Date :26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
40 4.2.4, 7.5.1 a) Is Equipment History Card (EHC) for each machine as per
QMS Form issued being filled up and maintained ?
41 4.2.4 Are Fuel & Oil consumption limits chart set by P&M Dept.,
Regd. Office available at site for all major plants ?
42 8.4, 8.5 Check whether actual consumption of Fuel & Oil is maintained
and action taken, if Fuel / Oil consumption is found more than
limit.
43 4.2.1(d), 4.2.4, 7.5.3 a) Are spare parts codes available at site ?
44 4.2.1(d), 4.2.4, 7.5.1 a) Is the QMS Form 'Daily Equipment Maintenance schedule
submitted on monthly basis' issued beingfilled-up for all
equipment and sent to RO/ZO as per procedure ? Check
samples.
45 7.5.1(e), 8.4, 8.5 Is effective action taken to increase the plant utilisation ?
46 4.2.1(d), 4.2.4, 7.5.1 a) Is the QMS Form 'Details of Machine breakdown during the
month' being filled-up regularly at site and report being sent to
RO/ZO as per procedure ? Check samples.
47 5.5.3, 7.5.1, 7.5.2(b) Has any report been sent by Plant Manager at site to registered
office / zonal office for discontinuing a machine and its
replacement by a new one on the basis of its maintenance
history ?
48 7.5.1, 7.5.2 Is there any complaint about any particular model of equipment
based on its low performance, frequent breakdown records and
high maintenance cost compared to other models of the same
equipment ? If yes, has it been reported to Registered Office /
Zonal Office ?
49 7.1, 7.5.1, 7.5.2 i) Check if release of plant from site has been made as per plan
given to P&M Dept., RO/ZO.
ii) If not, check if revised plan has been sent along with reasons
for delay in release.
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Date :26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
51 4.2.4, 7.5.1 a) Check whether Daily Works Diary (with serialled page
numbers) is maintained by all Engineers at site to record
important information, brief specifications etc ?
b) Check if record is maintained of names of Section-in-charge
involved in construction of various component structures in the
project from beginning till end.
52 4.2.4 Check if all Inspection Checklists are available at points of use,
explained to persons using the same, properly filled-up and
records maintained. Check from samples.
54 4.2.4, 7.2.3 Check if any interim certificate during execution and completion
certificate on completion of Project have been collected from
Customer as a measure of Customer Satisfaction.
55 7.2.3, 8.2.1 Has any 'Customer Feedback Request Form' received through
Project Coordinator been submitted to Customer for filling-up at
least once a year since start of project and on completion of
project ? If yes, check if filled-up Form is satisfactory.
56 7.1(d), 8.2.3, 8.3 a) Check various structures and components if there are any
cracks, honeycombs, joint marks, loss of slurry, out of plumb /
location and any such ir-regularities.
b) Check if route cause analysis has been done,
corrective/preventive action taken and monitoring of such action
done.
59 4.2.4, 7.5.1 Check if component parts of Batching Plant and other Plant
installations are secured properly, readings on all fixed
instruments are legible and can be sighted by the respective
Operator from his seat and all these are properly maintained.
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Project
Clients Audited by :
Consultant, if any Date of Audit :
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Date :26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
15 7.5.3, 7.5.5 Check whether identification and traceability is there for major
materials in the store racks and yard.
17 6.3 (a), 6.4 Are storage racks properly built and stable ?
19 6.3(a), 7.5.5 Are gas cylinder storage sheds properly made and maintained ?
22 6.3(a), 7.5.5 a) Check if useable reinforcement bars are stored properly and
separately from cut-pieces while cut-pieces kept separately in
scrap bin.
23 7.5.5 Is 'First come First use' principle being followed in issue of all
materials ?
24 7.5.5 Are all materials with specified shelf life being used within the
mentioned period ? Check if there is any wastage on this
account.
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Date :26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
33 4.2.1(d), 8.2.3 a) Check whether Debit Notes in standard format are being
prepared towards recovery against use of Company's tools and
materials by Sub-contractor's / PRWs and those are in order.
34 4.2.1(d), 4.2.4, 7.5.1 Are gate passes issued & maintained before sending-out any
material from site premises ?
35 4.2.4, 7.4.3, 8.2.4 a) Are manufacturer’s test certificates (MTC) available for
manufactured goods and are they correlated with challans to
which such materials correspond ? Verify from records.
b) Are all MTCs ' Verified and Reviewed ' by Quality Control
Engineer at Site ?
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Project
Clients Audited by :
Consultant, if any Date of Audit :
6.2.1, 6.2.2(a)
3 4.2.3, 7.2.1, 7.2.3, Check whether Integrated Test Plan / Field Quality Plan has
7.5.1, 8.2.3 been prepared in accordance with Contract requirements and
got approved by the Customer.
4 4.1(e), 7.2.1, 7.5.1, Are test formats given in QMS being followed or formats
8.2.3 supplied by Customer in use ?
5 4.2.4, 8.2.3 Check from records whether tests are being conducted and all
Quality records being maintained as per Integrated Test Plan /
Field Quality Plan approved by the Customer.
6 4.2.4, 7.1(d), 8.2.4 a) Check whether Control Chart for Tests are being maintained
properly to identify if there had been any rejection and
percentage of the same.
7 7.1(d), 8.2.1, 8.2.4, a) Check from random samples if all concrete cubes in curing
8.3 tank have identification mark and date of casting printed/painted
on surface.
8 7.1(d), 8.2.4, 8.3, 8.4 Are any non-destructive tests in use at the Project site ? If yes,
check reasons and verify the test results.
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Project
Clients Audited by :
Consultant, if any Date of Audit :
13 7.1(d), 7.6 Are all weights and weighing balances being used at site
calibrated ?
16 4.2.4, 7.4.3, 8.2.4 Check whether following Quality Records are available and
easily traceable. Verify some samples.
(iii) Admixtures
(iv) Other important manufactured items
b) Check if all MTCs and results of Third Party tests in record are
'Verified and Reviewed' by Quality Control Engineer at Site
before filing them.
c) Third Party Tests conducted as per contract requirement or
otherwise.
22 8.4 Has the root cause been analysed for such non-conforming
products, if any ?
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Date :26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
25 8.5.3 Check whether Preventive action has been taken towards re-
occurrence of non-conforming products.
29 7.1(d), 7.2.1, 8.2.4 Is any load test on structure included within the scope of work ?
If yes, verify test results.
30 8.3 For any non-conformance product has any penal recovery been
imposed by Customer ? Verify records.
31 7.6 Any other relevant points noted during Audit. Check if ongoing
suitability of all monitoring and measuring software in use has
been verified prier to use.
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Date :26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.
Date :26.07.10
SIMPLEX INFRASTRUCTURES LIMITED
Audit Requirement
Internal Quality Audit Checklist (for Project Site) ISO 9001 : 2008
Project
Clients Audited by :
Consultant, if any Date of Audit :
NOTE : Objective evidence against each Sl. No. shall be noted by Internal Quality Auditors as much as possible.