Northern Builders

Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 0.465%

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 12 0.470%

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22 16 0.141%

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 1.487%
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4 1.997%

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22 8 7.694%
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 6 4.154%
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 20.468%
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 8.374%

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 7 8.832%

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 4 0.253%

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 15 2.848%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start March April
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 0.465%

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 12 0.470%

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22 16 0.141%

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 1.487%
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4 1.997%

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22 8 7.694%
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 6 4.154%
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 20.468%
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 8.374%

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 7 8.832%

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 4 0.253%

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 15 2.848%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start May


Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 0.465%

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 12 0.470%

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22 16 0.141%

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 1.487%
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4 1.997%

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22 8 7.694%
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 6 4.154%
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 20.468%
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 8.374%

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 7 8.832%

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 4 0.253%

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 15 2.848%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start May June July
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 0.465%

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 12 0.470%

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22 16 0.141%

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 1.487%
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4 1.997% 0.00105 0.00105 0.00105 0.00105 0.00105

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22 8 7.694%
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 6 4.154%
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 20.468%
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 8.374%

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 7 8.832%

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 4 0.253%

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 15 2.848%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start July August September
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 0.465% 0.00019 0.00019 0.00019

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 12 0.470%

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22 16 0.141%

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 1.487% 0.00062 0.00062 0.00062
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4 1.997% 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22 8 7.694%
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 6 4.154%
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 20.468%
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 8.374%

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 7 8.832%

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 4 0.253% 9.73E-05

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 15 2.848%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start September October November
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 0.465% 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 12 0.470%

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22 16 0.141%

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 1.487% 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4 1.997% 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22 8 7.694% 0.00769 0.00769
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 6 4.154% 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 20.468% 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 8.374% 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 7 8.832% 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 4 0.253% 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 15 2.848%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start November December January
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 0.465% 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 12 0.470%

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22 16 0.141%

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 1.487% 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4 1.997%

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22 8 7.694% 0.00769 0.00769 0.00769 0.00769 0.00769 0.00769 0.00769 0.00769
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 6 4.154% 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 20.468% 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 8.374% 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 7 8.832% 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 4 0.253% 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 15 2.848%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February March
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 0.465% 0.00019 0.00019 0.00019 0.00019 0.00019

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 12 0.470% 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22 16 0.141%

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 1.487% 0.00062 0.00062 0.00062 0.00062 0.00062
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4 1.997%

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22 8 7.694%
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 6 4.154% 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 20.468% 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 8.374% 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 7 8.832% 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 4 0.253% 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 15 2.848%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start March April May
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 0.465%

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 12 0.470% 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22 16 0.141%

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 1.487%
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4 1.997%

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22 8 7.694%
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 6 4.154% 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 20.468% 0.00758 0.00758 0.00758 0.00758
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 8.374% 0.0031 0.0031 0.0031 0.0031

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 7 8.832% 0.00327 0.00327 0.00327 0.00327 0.00327

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 4 0.253%

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 15 2.848%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start May June July
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 0.465%

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 12 0.470% 0.00026 0.00026 0.00026 0.00026

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22 16 0.141% 0.00035 0.00035 0.00035 0.00035

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 1.487%
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4 1.997%

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22 8 7.694%
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 6 4.154%
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 20.468%
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 8.374%

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 7 8.832%

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 4 0.253%

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 15 2.848% 0.00712 0.00712 0.00712
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start July


Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 0.465%

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 12 0.470%

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22 16 0.141%

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 1.487%
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4 1.997%

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22 8 7.694%
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 6 4.154%
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 20.468%
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 8.374%

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 7 8.832%

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 4 0.253%

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 15 2.848% 0.00712
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22 5 2.280%
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22 6 0.195%
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22 13 0.014%
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22 5 0.736%
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22 12 0.019%

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22 3 1.363%
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22 2 1.170%
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21 6 0.009%
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21 5 0.015%
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22 10 0.249%
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7 0.001%
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22 7 2.632%
Assemblies

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4 1.241%

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5 2.484%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start March April
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22 5 2.280%
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22 6 0.195%
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22 13 0.014%
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22 5 0.736%
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22 12 0.019%

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22 3 1.363%
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22 2 1.170%
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21 6 0.009%
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21 5 0.015%
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22 10 0.249%
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7 0.001%
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22 7 2.632%
Assemblies

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4 1.241%

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5 2.484%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start May


Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22 5 2.280%
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22 6 0.195%
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22 13 0.014%
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22 5 0.736%
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22 12 0.019%

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22 3 1.363%
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22 2 1.170%
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21 6 0.009%
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21 5 0.015%
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22 10 0.249%
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7 0.001%
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22 7 2.632%
Assemblies

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4 1.241%

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5 2.484%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start May June July
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22 5 2.280%
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22 6 0.195%
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22 13 0.014%
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22 5 0.736%
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22 12 0.019%

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22 3 1.363%
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22 2 1.170%
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21 6 0.009%
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21 5 0.015%
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22 10 0.249%
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7 0.001%
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22 7 2.632%
Assemblies

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4 1.241%

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5 2.484%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start July August September
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22 5 2.280%
Depot
0.00081
206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22 6 0.195%
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22 13 0.014%
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22 5 0.736%
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22 12 0.019%

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22 3 1.363%
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22 2 1.170%
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21 6 0.009%
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21 5 0.015%
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  
5E-05
206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22 10 0.249%
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7 0.001%
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22 7 2.632%
Assemblies

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4 1.241%

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5 2.484%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start September October November
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22 5 2.280%
Depot
0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081
206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22 6 0.195%
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22 13 0.014%
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22 5 0.736%
Integral Bridge
0.00092
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22 12 0.019%

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22 3 1.363%
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22 2 1.170%
Integral Bridge
0.00059 0.00059 0.00059 0.00059 0.00059
206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21 6 0.009%
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)
3E-05
206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21 5 0.015%
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  
5E-05 5E-05
206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22 10 0.249%
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7 0.001%
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
0.001%
209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22 7 2.632%
Assemblies
0.00439
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4 1.241%
0.00103 0.00103 0.00103 0.00103
Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5 2.484%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start November December January
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22 5 2.280%
Depot
0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081
206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22 6 0.195%
GRS
0.00022 0.00022
206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22 13 0.014%
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22 5 0.736%
Integral Bridge
0.00092 0.00092
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22 12 0.019%

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22 3 1.363%
(include waterstop at construction joint)
0.00091 0.00091 0.00091 0.00091 0.00091 0.00091
205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22 2 1.170%
Integral Bridge
0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059
206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21 6 0.009%
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)
3E-05 3E-05
206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21 5 0.015%
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22 10 0.249%
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7 0.001%
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22 7 2.632%
Assemblies
0.00439 0.00439
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4 1.241%
0.00103 0.00103 0.00103 0.00103 0.00103 0.00103 0.00103 0.00103
Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5 2.484%
0.00226
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February March
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22 5 2.280%
Depot
0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081
206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22 6 0.195%
GRS
0.00022 0.00022 0.00022 0.00022
206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22 13 0.014%
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22 5 0.736%
Integral Bridge
0.00092 0.00092
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22 12 0.019%

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22 3 1.363%
(include waterstop at construction joint)
0.00091 0.00091 0.00091 0.00091 0.00091 0.00091
205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22 2 1.170%
Integral Bridge
0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059
206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21 6 0.009%
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21 5 0.015%
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22 10 0.249%
for Retaining Wall, including compacted crushed stone
layer (200mm)
0.0005 0.0005 0.0005 0.0005 0.0005
206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7 0.001%
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22 7 2.632%
Assemblies
0.00439 0.00439
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4 1.241%

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5 2.484%
0.00226 0.00226 0.00226 0.00226 0.00226 0.00226 0.00226 0.00226
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start March April May
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22 5 2.280%
Depot
0.00081 0.00081 0.00081
206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22 6 0.195%
GRS
0.00022 0.00022 0.00022
206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22 13 0.014%
Electrical Manhole
0.014%
206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22 5 0.736%
Integral Bridge
0.00092 0.00092 0.00092
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22 12 0.019%

9.5E-05 9.5E-05
206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22 3 1.363%
(include waterstop at construction joint)
0.00091 0.00091 0.00091
205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22 2 1.170%
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21 6 0.009%
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21 5 0.015%
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22 10 0.249%
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7 0.001%
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22 7 2.632%
Assemblies
0.00439
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4 1.241%

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5 2.484%
0.00226 0.00226
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start May June July
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22 5 2.280%
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22 6 0.195%
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22 13 0.014%
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22 5 0.736%
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22 12 0.019%

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22 3 1.363%
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22 2 1.170%
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21 6 0.009%
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21 5 0.015%
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22 10 0.249%
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7 0.001%
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22 7 2.632%
Assemblies

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4 1.241%

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5 2.484%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start July


Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22 5 2.280%
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22 6 0.195%
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22 13 0.014%
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22 5 0.736%
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22 12 0.019%

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22 3 1.363%
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22 2 1.170%
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21 6 0.009%
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21 5 0.015%
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22 10 0.249%
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7 0.001%
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22 7 2.632%
Assemblies

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4 1.241%

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5 2.484%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3 1.125%

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2 2.419%

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2 0.657%

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2 0.471%

RIVER BANK PROTECTION WORKS FOR -3 25.630%


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0 0.041%

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.066%

100.000%
Legend: Accomplishment 0% 0% 0% 0% 0% 0% 0% 0%
Notes / Remarks
BidDocs Schedule -Slack Time Commulative Accomplishment 0% 0% 0% 0% 0% 0% 0% 0%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start March April
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3 1.125%

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2 2.419%

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2 0.657%

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2 0.471%

RIVER BANK PROTECTION WORKS FOR -3 25.630%


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0 0.041%

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.066%

100.000%
Legend: Accomplishment 0% 0% 0% 0% 0% 0% 0% 0%
Notes / Remarks
BidDocs Schedule -Slack Time Commulative Accomplishment 0% 0% 0% 0% 0% 0% 0% 0%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start May


Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3 1.125%

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2 2.419%

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2 0.657%

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2 0.471%

RIVER BANK PROTECTION WORKS FOR -3 25.630%


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER 0.01068 0.01068 0.01068
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0 0.041%

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.066%

100.000%
Legend: Accomplishment 1% 1% 1%
Notes / Remarks
BidDocs Schedule -Slack Time Commulative Accomplishment 1% 2% 3%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start May June July
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3 1.125%

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2 2.419%

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2 0.657%

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2 0.471%

RIVER BANK PROTECTION WORKS FOR -3 25.630%


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0 0.041%

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.066%

100.000%
Legend: Accomplishment 1% 1% 1% 1% 1% 1% 1% 1%
Notes / Remarks
BidDocs Schedule -Slack Time Commulative Accomplishment 4% 5% 6% 8% 9% 10% 11% 12%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start July August September
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3 1.125%
0.0007 0.0007 0.0007 0.0007 0.0007
Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2 2.419%

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2 0.657%

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2 0.471%

RIVER BANK PROTECTION WORKS FOR -3 25.630%


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER 0.01068
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0 0.041%

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.066%

100.000%
Legend: Accomplishment 1% 0% 0% 0% 0% 0% 0% 0%
Notes / Remarks
BidDocs Schedule -Slack Time Commulative Accomplishment 13% 14% 14% 14% 14% 14% 15% 15%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start September October November
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3 1.125%
0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007
Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2 2.419%

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2 0.657%

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2 0.471%

RIVER BANK PROTECTION WORKS FOR -3 25.630%


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER 0.01068 0.01068 0.01068 0.01068
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0 0.041%

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.066% 0.0001 0.0001 0.0001

100.000%
Legend: Accomplishment 0% 2% 2% 2% 3% 4% 4% 4%
Notes / Remarks
BidDocs Schedule -Slack Time Commulative Accomplishment 15% 17% 19% 21% 24% 27% 31% 35%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start November December January
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3 1.125%
0.0007 0.0007 0.0007
Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2 2.419%
0.00242 0.00242 0.00242
STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2 0.657%
0.00066 0.00066 0.00066 0.00066 0.00066 0.00066 0.00066
Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2 0.471%
0.00052 0.00052 0.00052
RIVER BANK PROTECTION WORKS FOR -3 25.630%
DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0 0.041%

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.066% 0.0001

100.000%
Legend: Accomplishment 4% 4% 4% 4% 4% 5% 4% 4%
Notes / Remarks
BidDocs Schedule -Slack Time Commulative Accomplishment 39% 43% 47% 51% 55% 60% 64% 68%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February March
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3 1.125%

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2 2.419%
0.00242 0.00242 0.00242 0.00242 0.00242 0.00242 0.00242
STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2 0.657%
0.00066 0.00066 0.00066
Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2 0.471%
0.00052 0.00052 0.00052 0.00052 0.00052 0.00052
RIVER BANK PROTECTION WORKS FOR -3 25.630%
DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0 0.041%

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.066%

100.000%
Legend: Accomplishment 2% 3% 3% 2% 2% 2% 3% 2%
Notes / Remarks
BidDocs Schedule -Slack Time Commulative Accomplishment 71% 74% 76% 79% 81% 83% 86% 88%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start March April May
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3 1.125%

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2 2.419%

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2 0.657%

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2 0.471%

RIVER BANK PROTECTION WORKS FOR -3 25.630%


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0 0.041%

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.066%

100.000%
Legend: Accomplishment 2% 2% 2% 2% 0% 0% 0% 0%
Notes / Remarks
BidDocs Schedule -Slack Time Commulative Accomplishment 90% 92% 94% 96% 96% 97% 97% 97%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start May June July
Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3 1.125%

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2 2.419%

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2 0.657%

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2 0.471%

RIVER BANK PROTECTION WORKS FOR -3 25.630%


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0 0.041%

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.066%

0.00016 0.00016 0.00016


100.000%
Legend: Accomplishment 0% 0% 0% 0% 0% 1% 1% 1%
Notes / Remarks
BidDocs Schedule -Slack Time Commulative Accomplishment 97% 97% 97% 97% 97% 98% 99% 99%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start July


Duration RL. WT.
Bill No. Item Description Duration Start End Duration Start End Week 4
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3 1.125%

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2 2.419%

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2 0.657%

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2 0.471%

RIVER BANK PROTECTION WORKS FOR -3 25.630%


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0 0.041%

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.066%

0.00016
100.000%
Legend: Accomplishment 1%
Notes / Remarks
BidDocs Schedule -Slack Time Commulative Accomplishment 100%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start


RL. WT.
Duration
Bill No. Item Description Duration Start End Duration Start End
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 0.465%

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 12 0.470%

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22 16 0.141%

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 1.487%
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4 1.997%

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22 8 7.694%
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 6 4.154%
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 20.468%
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 8.374%
January February March April May June
Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1
June July August September October
Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4

0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019

0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062

0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105

0.00143 0.00143 0.00143 0.00143

0.00758 0.00758 0.00758 0.00758

0.0031 0.0031 0.0031 0.0031


November December January February March
Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2

0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019

0.00026 0.00026 0.00026 0.00026 0.00026

0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062

0.00105

0.00769 0.00769 0.00769 0.00769 0.00769 0.00769 0.00769 0.00769 0.00769 0.00769

0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143

0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758

0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031
March April May June July
Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4

0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026

0.00035 0.00035 0.00035 0.00035

0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143

0.00758 0.00758 0.00758 0.00758 0.00758

0.0031 0.0031 0.0031 0.0031 0.0031


Geogrid, 37.5KN/m

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 7 8.832%

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 4 0.253%

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 15 2.848%

Structura Works (Part D)


207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22 5 2.280%
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22 6 0.195%
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22 13 0.014%
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22 5 0.736%
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22 12 0.019%

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22 3 1.363%
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22 2 1.170%
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21 6 0.009%
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21 5 0.015%
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  
0.00327 0.00327 0.00327

9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05

0.00081 0.00081 0.00081 0.00081 0.00081 0.00081

0.00059 0.00059

3E-05

5E-05 5E-05 5E-05


0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327

9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05

0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081

0.00022 0.00022 0.00022 0.00022 0.00022 0.00022

0.00092 0.00092 0.00092 0.00092 0.00092

0.00091 0.00091 0.00091 0.00091 0.00091 0.00091 0.00091 0.00091 0.00091 0.00091 0.00091

0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059

3E-05 3E-05
0.00327 0.00327 0.00327 0.00327 0.00327 0.00327

9.73E-05

0.00712 0.00712 0.00712 0.00712

0.00081 0.00081 0.00081 0.00081

0.00022 0.00022 0.00022

0.014%

0.00092 0.00092 0.00092

9.5E-05 9.5E-05

0.00091 0.00091 0.00091 0.00091


206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22 10 0.249%
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7 0.001%
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22 7 2.632%
Assemblies

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4 1.241%

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5 2.484%

Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3 1.125%

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2 2.419%

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2 0.657%

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2 0.471%

RIVER BANK PROTECTION WORKS FOR -3 25.630%


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0 0.041%

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.066%

100.000%
Legend: Accomplishment
Notes / Remarks
BidDocs Schedule -Slack Time Commulative Accomplishment

BidDocs Schedule Actual Accomplishment


Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule Commpulative Accomplishment
0.01068 0.01068 0.01068 0.01068 0.01068

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 1% 1% 1% 1%
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 2% 3% 4% 5%
0.00103

0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007

0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068

1% 1% 1% 1% 1% 1% 1% 0% 0% 0% 0% 0% 0% 0% 0% 2% 2% 2% 3%
6% 8% 9% 10% 11% 12% 13% 14% 14% 14% 14% 14% 15% 15% 15% 17% 19% 21% 24%
0.0005 0.0005 0.0005 0.0005 0.0005

0.001%

0.00439 0.00439 0.00439 0.00439 0.00439

0.00103 0.00103 0.00103 0.00103 0.00103 0.00103 0.00103 0.00103 0.00103 0.00103 0.00103

0.00226 0.00226 0.00226 0.00226 0.00226 0.00226 0.00226 0.00226

0.0007 0.0007 0.0007 0.0007 0.0007 0.0007

0.00242 0.00242 0.00242 0.00242 0.00242 0.00242 0.00242 0.00242 0.00242 0.00242

0.00066 0.00066 0.00066 0.00066 0.00066 0.00066 0.00066 0.00066 0.00066 0.00066

0.00052 0.00052 0.00052 0.00052 0.00052 0.00052 0.00052 0.00052 0.00052

0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068

0.0001 0.0001 0.0001 0.0001

4% 4% 4% 4% 4% 4% 4% 4% 5% 4% 4% 2% 3% 3% 2% 2% 2% 3%
27% 31% 35% 39% 43% 47% 51% 55% 60% 64% 68% 71% 74% 76% 79% 81% 83% 86%
0.00439

0.00226 0.00226 0.00226

0.00016 0.00016 0.00016 0.00016

2% 2% 2% 2% 2% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 1% 1% 1%
88% 90% 92% 94% 96% 96% 97% 97% 97% 97% 97% 97% 97% 97% 98% 99% 99% 100%
Northern Builders
Project Schedule
Project Title: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)

BidDocs Schedule Current Schedule


Bill No. Item Description Duration Start End Duration Start End January February March April May June July August September October November December January February March April May June July
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

i BidDoc Schedule Cosnt.n Period Construction Period (Feb. 1, 2021 - May 31,2022) - 7 Months Left and Additonal a Month Based on Current Schedule (Duration:14mons)
ii Current Schedule BDSCP Construction Period (Mar. 1, 2021 -May 31,2022) -7 Months Left Based on Current Schedule (Duration:14mons)
iii Revised Schedule for Const. P. Construction Period (May 5, 2021 - July 29, 2022)

GRS-IBS, GRS-Retaining Wall. &


Bill No. 2 RC Retaining Wall 348 1-Feb-21 15-Jan-22 348 2-Mar-21 13-Feb-22

29 Days
Offset
BidDocs End
Date Schedule
Part A Earth Works 124 1-Feb-21 5-Jun-21 124 2-Mar-21 4-Jul-21 April 30, 2022
(Monday)

Part C Surface Course 23 18-Mar-21 10-Apr-21 23 16-Apr-21 9-May-21

Current
Schedule -
Part D Structural Works 289 1-Apr-21 15-Jan-22 289 30-Apr-21 13-Feb-22 Offset at 29
days due to
turnover of
area. End Date
is May 31,2022
Part E Miscellaneous Structures 87 1-Jun-21 27-Aug-21 87 30-Jun-21 25-Sep-21 (Tuesday)

Part F Plumbing & Sanitary Works 75 1-Sep-21 15-Nov-21 75 30-Sep-21 14-Dec-21

Base on our
Actual Site
Bill No. 4 Depot Buildings 118 1-Jun-21 27-Sep-21 118 30-Jun-21 26-Oct-21 Condition &
Material Status
29 Days - End Date We
Offset Need to Finish
The Project July
Earth Works 118 1-Jun-21 27-Sep-21 118 30-Jun-21 26-Oct-21 29, 2022
(Friday)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5 6 7 8 9 10 11

Drainage System & River Bank


Bill No. 5 Protection 175 6-Sep-21 28-Feb-22 175 5-Oct-21 29-Mar-22
29 Days
Offset

Part A Earth Works 53 6-Sep-21 29-Oct-21 53 5-Oct-21 27-Nov-21

Part B Structural Works 77 15-Oct-21 31-Dec-21 77 13-Nov-21 29-Jan-22

Part C Drainage Works 61 1-Dec-21 31-Jan-22 61 30-Dec-21 1-Mar-22

River Bank Protetion Works for


Part D Dolores River 175 6-Sep-21 28-Feb-22 175 5-Oct-21 29-Mar-22

Bill. No. 6 Substation 28 1-Nov-21 29-Nov-21 28 30-Nov-21 28-Dec-21


29 Days
Offset

Reason of Delay How to Catchup Legend:


TURNOVER OF AREA - BidDocs Major Activity - BidDocs Activity - Allowance Duration - Activity Offset Cs - Rs - End Duration of BidDocs Schedule
CONTROL POINTS VALIDATION Increase the Manpower -increasing manpower may
increase our productivity output. We can make two (2) or
REVISION OF PLANS & WORKING DRAWINGS (Rev. 29 - Rev. 31) more activities at the same time. - Current Major Activity - Current Activity - Duration Need to Catchup - Activity Offset BDs - Cs
MATERIAL APPROVAL Overtime -having an Overtime (4hrs) or having 2 shifts, - End Duration of Current Schedule
WEATHER CONDITION depends on our condition on site. (this may apply if all - Revised Major Activity - Revised Activity - Slack Time - Major Activity Offset
queries, issues, concernsuch as IFC drawings,revisios,
Bar Bending Schedule Material approval, IFC drawing, etc)
Northern Builders
Project Title: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)

Bill No. Item Description


1 2 3 4 5 6 7 8 9 10

0.750% 10.360% 10.360% 12.615% 13.200% 4.796% 3.695% 3.825% 6.658% 7.319%

0.750% 11.110% 21.469% 34.084% 47.285% 52.080% 55.775% 59.600% 66.258% 73.577%

1 2 3 4 5 6 7 8 9 10
0.000% 0.000% 0.000% 0.000% 0.844% 1.990% 3.233% 4.857% 6.006% 6.401%
11 12 13 14 15

6.936% 7.291% 6.624% 4.822% 0.750%

80.513% 87.804% 94.428% 99.250% 100.000%

11 12 13 14 15 16 17 18
6.401% 6.401% 6.401% 6.401% 6.401% 6.401% 6.401% 6.401%
Northern Builders
Project Schedule
Project Title: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)

BidDocs Schedule Current Schedule


Bill No. Item Description Duration Start End Duration Start End January February March April May June July August September October November December January February March April May June July
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

i BidDoc Schedule Cosnt.n Period Construction Period (Feb. 1, 2021 - May 31,2022) - 7 Months Left and Additonal a Month Based on Current Schedule (Duration:14mons)
ii Current Schedule BDSCP
iii Revised Schedule for Const. P.

GRS-IBS, GRS-Retaining Wall. &


Bill No. 2 RC Retaining Wall 348 1-Feb-21 15-Jan-22 348 2-Mar-21 13-Feb-22

29 Days
Offset
BidDocs End
Date Schedule
Part A Earth Works 124 1-Feb-21 5-Jun-21 124 2-Mar-21 4-Jul-21 April 30, 2022
(Monday)

Part C Surface Course 23 18-Mar-21 10-Apr-21 23 16-Apr-21 9-May-21

Current
Part D Structural Works 289 1-Apr-21 15-Jan-22 289 30-Apr-21 13-Feb-22 Schedule -
Offset at 29
days due to
turnover of
area. End Date
is May 31,2022
Part E Miscellaneous Structures 87 1-Jun-21 27-Aug-21 87 30-Jun-21 25-Sep-21 (Tuesday)

Part F Plumbing & Sanitary Works 75 1-Sep-21 15-Nov-21 75 30-Sep-21 14-Dec-21

Base on our
Actual Site
Bill No. 4 Depot Buildings 118 1-Jun-21 27-Sep-21 118 30-Jun-21 26-Oct-21 Condition &
Material Status
29 Days - End Date We
Offset
Need to Finish
The Project July
Earth Works 118 1-Jun-21 27-Sep-21 118 30-Jun-21 26-Oct-21 29, 2022
(Friday)

Drainage System & River Bank 29 Days


Bill No. 5 Protection 175 6-Sep-21 28-Feb-22 175 5-Oct-21 29-Mar-22 Offset

Part A Earth Works 53 6-Sep-21 29-Oct-21 53 5-Oct-21 27-Nov-21

Part B Structural Works 77 15-Oct-21 31-Dec-21 77 13-Nov-21 29-Jan-22

Part C Drainage Works 61 1-Dec-21 31-Jan-22 61 30-Dec-21 1-Mar-22

River Bank Protetion Works for


Part D Dolores River 175 6-Sep-21 28-Feb-22 175 5-Oct-21 29-Mar-22

Bill. No. 6 Substation 28 1-Nov-21 29-Nov-21 28 30-Nov-21 28-Dec-21 29 Days


Offset

Reason of Delay How to Catchup Legend:


TURNOVER OF AREA - BidDocs Major Activity - BidDocs Activity - Allowance Duration - Activity Offset Cs - Rs - End Duration of BidDocs Schedule
CONTROL POINTS VALIDATION Increase the Manpower -increasing manpower may
increase our productivity output. We can make two (2) or
REVISION OF PLANS & WORKING DRAWINGS (Rev. 29 - Rev. 31) more activities at the same time. - Current Major Activity - Current Activity - Duration Need to Catchup - Activity Offset BDs - Cs
MATERIAL APPROVAL Overtime -having an Overtime (4hrs) or having 2 shifts, - End Duration of Current Schedule
WEATHER CONDITION depends on our condition on site. (this may apply if all - Revised Major Activity - Revised Activity - Slack Time - Major Activity Offset
queries, issues, concernsuch as IFC drawings,revisios,
Bar Bending Schedule Material approval, IFC drawing, etc)
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

Revised Detailed Schedule January February March April May


Bill No. Item Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA) Tue, 07-Sep-21 Tue, 03-May-22


102(1) Unsuitable Excavation for dry condition 150 Tue, 07-Sep-21 Mon, 28-Feb-22

201(4)d Backfill 115 Thu, 10-Feb-22 Thu, 23-Jun-22

104(1) Subgrade Preparation (Common Material) 24 Wed, 01-Jun-22 Tue, 28-Jun-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 150 Tue, 07-Sep-21 Mon, 28-Feb-22
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 119 Mon, 21-Jun-21 Fri, 05-Nov-21

103(1)c Embankment for At grade section for Depot 96 Sat, 06-Nov-21 Fri, 25-Feb-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 180 Wed, 06-Oct-21 Tue, 03-May-22
(Common Material)

205(1) Cement Mixed Approach Block for internal 170 Wed, 06-Oct-21 Thu, 21-Apr-22
bridge

205(2) Geogrid, 37.5KN/m 170 Wed, 06-Oct-21 Thu, 21-Apr-22

205(3) Geogrid, 75.0KN/m 170 Tue, 12-Oct-21 Wed, 27-Apr-22

205(5) Gravel Bag filled with Crushed Stone 160 Mon, 20-Sep-21 Thu, 24-Mar-22

Surface Cource (Part C)


107(1) Sub-ballast 20 Mon, 04-Jul-22 Tue, 26-Jul-22

Structura Works (Part D) Sat, 25-Sep-21 Fri, 13-May-22


207(1)c Reinforcing Steel, Grade 60 for Structure in 172 Sat, 25-Sep-21 Wed, 13-Apr-22
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Mon, 21-Mar-22
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Tue, 10-May-22 Wed, 11-May-22
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Fri, 13-May-22
Integral Bridge
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

Revised Detailed Schedule June July August September October


Bill No. Item Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA) Tue, 07-Sep-21 Tue, 03-May-22


102(1) Unsuitable Excavation for dry condition 150 Tue, 07-Sep-21 Mon, 28-Feb-22

201(4)d Backfill 115 Thu, 10-Feb-22 Thu, 23-Jun-22

104(1) Subgrade Preparation (Common Material) 24 Wed, 01-Jun-22 Tue, 28-Jun-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 150 Tue, 07-Sep-21 Mon, 28-Feb-22
Structure (GRS), Integral Bridge, Retaining Wall, Electrical 0% 0% 0% 0% 0%
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 119 Mon, 21-Jun-21 Fri, 05-Nov-21
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

103(1)c Embankment for At grade section for Depot 96 Sat, 06-Nov-21 Fri, 25-Feb-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 180 Wed, 06-Oct-21 Tue, 03-May-22
(Common Material)

205(1) Cement Mixed Approach Block for internal 170 Wed, 06-Oct-21 Thu, 21-Apr-22
bridge

205(2) Geogrid, 37.5KN/m 170 Wed, 06-Oct-21 Thu, 21-Apr-22

205(3) Geogrid, 75.0KN/m 170 Tue, 12-Oct-21 Wed, 27-Apr-22

205(5) Gravel Bag filled with Crushed Stone 160 Mon, 20-Sep-21 Thu, 24-Mar-22
0% 0% 0%

Surface Cource (Part C)


107(1) Sub-ballast 20 Mon, 04-Jul-22 Tue, 26-Jul-22

Structura Works (Part D) Sat, 25-Sep-21 Fri, 13-May-22


207(1)c Reinforcing Steel, Grade 60 for Structure in 172 Sat, 25-Sep-21 Wed, 13-Apr-22
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Mon, 21-Mar-22
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Tue, 10-May-22 Wed, 11-May-22
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Fri, 13-May-22
Integral Bridge
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

Revised Detailed Schedule November December January February March


Bill No. Item Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA) Tue, 07-Sep-21 Tue, 03-May-22


102(1) Unsuitable Excavation for dry condition 150 Tue, 07-Sep-21 Mon, 28-Feb-22

201(4)d Backfill 115 Thu, 10-Feb-22 Thu, 23-Jun-22

104(1) Subgrade Preparation (Common Material) 24 Wed, 01-Jun-22 Tue, 28-Jun-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 150 Tue, 07-Sep-21 Mon, 28-Feb-22
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 119 Mon, 21-Jun-21 Fri, 05-Nov-21

103(1)c Embankment for At grade section for Depot 96 Sat, 06-Nov-21 Fri, 25-Feb-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 180 Wed, 06-Oct-21 Tue, 03-May-22
(Common Material)

205(1) Cement Mixed Approach Block for internal 170 Wed, 06-Oct-21 Thu, 21-Apr-22
bridge

205(2) Geogrid, 37.5KN/m 170 Wed, 06-Oct-21 Thu, 21-Apr-22

205(3) Geogrid, 75.0KN/m 170 Tue, 12-Oct-21 Wed, 27-Apr-22

205(5) Gravel Bag filled with Crushed Stone 160 Mon, 20-Sep-21 Thu, 24-Mar-22

Surface Cource (Part C)


107(1) Sub-ballast 20 Mon, 04-Jul-22 Tue, 26-Jul-22

Structura Works (Part D) Sat, 25-Sep-21 Fri, 13-May-22


207(1)c Reinforcing Steel, Grade 60 for Structure in 172 Sat, 25-Sep-21 Wed, 13-Apr-22
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Mon, 21-Mar-22
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Tue, 10-May-22 Wed, 11-May-22
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Fri, 13-May-22
Integral Bridge
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

Revised Detailed Schedule April May June July


Bill No. Item Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA) Tue, 07-Sep-21 Tue, 03-May-22


102(1) Unsuitable Excavation for dry condition 150 Tue, 07-Sep-21 Mon, 28-Feb-22

201(4)d Backfill 115 Thu, 10-Feb-22 Thu, 23-Jun-22

104(1) Subgrade Preparation (Common Material) 24 Wed, 01-Jun-22 Tue, 28-Jun-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 150 Tue, 07-Sep-21 Mon, 28-Feb-22
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 119 Mon, 21-Jun-21 Fri, 05-Nov-21

103(1)c Embankment for At grade section for Depot 96 Sat, 06-Nov-21 Fri, 25-Feb-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 180 Wed, 06-Oct-21 Tue, 03-May-22
(Common Material)

205(1) Cement Mixed Approach Block for internal 170 Wed, 06-Oct-21 Thu, 21-Apr-22
bridge

205(2) Geogrid, 37.5KN/m 170 Wed, 06-Oct-21 Thu, 21-Apr-22

205(3) Geogrid, 75.0KN/m 170 Tue, 12-Oct-21 Wed, 27-Apr-22

205(5) Gravel Bag filled with Crushed Stone 160 Mon, 20-Sep-21 Thu, 24-Mar-22

Surface Cource (Part C)


107(1) Sub-ballast 20 Mon, 04-Jul-22 Tue, 26-Jul-22

Structura Works (Part D) Sat, 25-Sep-21 Fri, 13-May-22


207(1)c Reinforcing Steel, Grade 60 for Structure in 172 Sat, 25-Sep-21 Wed, 13-Apr-22
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Mon, 21-Mar-22
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Tue, 10-May-22 Wed, 11-May-22
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Fri, 13-May-22
Integral Bridge
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

Revised Detailed Schedule January February March April May


Bill No. Structural Cast Item
in Situ Concrete, 40 MPa for
Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Fri, 17-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Sat, 09-Apr-22
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Mon, 14-Mar-22
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Mon, 06-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Sat, 09-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Tue, 01-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 26-Mar-22
Assemblies

Miscellaneous Structures (Part E) 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 53 Wed, 19-Jan-22 Sat, 02-Apr-22

Thu, 12-Aug-21 Thu, 10-Mar-22


Structural Earth Works 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

Revised Detailed Schedule June July August September October


Bill No. Structural Cast Item
in Situ Concrete, 40 MPa for
Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Fri, 17-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Sat, 09-Apr-22
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Mon, 14-Mar-22
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Mon, 06-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Sat, 09-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)   0% 0% 0%

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Tue, 01-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 26-Mar-22
Assemblies

Miscellaneous Structures (Part E) 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 53 Wed, 19-Jan-22 Sat, 02-Apr-22

Thu, 12-Aug-21 Thu, 10-Mar-22


Structural Earth Works 87 Thu, 12-Aug-21 Sat, 11-Dec-21
1% 1% 1% 8% 1% 1% 1%

Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

Revised Detailed Schedule November December January February March


Bill No. Structural Cast Item
in Situ Concrete, 40 MPa for
Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Fri, 17-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Sat, 09-Apr-22
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Mon, 14-Mar-22
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Mon, 06-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Sat, 09-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Tue, 01-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 26-Mar-22
Assemblies

Miscellaneous Structures (Part E) 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 53 Wed, 19-Jan-22 Sat, 02-Apr-22

Thu, 12-Aug-21 Thu, 10-Mar-22


Structural Earth Works 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

Revised Detailed Schedule April May June July


Bill No. Structural Cast Item
in Situ Concrete, 40 MPa for
Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Fri, 17-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Sat, 09-Apr-22
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Mon, 14-Mar-22
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Mon, 06-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Sat, 09-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Tue, 01-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 26-Mar-22
Assemblies

Miscellaneous Structures (Part E) 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 53 Wed, 19-Jan-22 Sat, 02-Apr-22

Thu, 12-Aug-21 Thu, 10-Mar-22


Structural Earth Works 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

Revised Detailed Schedule January February March April May


Bill No. Item Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4

STRUCTURAL WORKS 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR


DOLORES 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER 0% 0% 0% 0%

N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend: 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 1.1% 1.1% 1.1% 1.1%
BidDocs Schedule 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 2% 3% 4%
Currrent Schedule
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.06% 0.06% 0.06% 0.06%
Revised Schedule 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.06% 0.13% 0.19% 0.25%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

Revised Detailed Schedule June July August September October


Bill No. Item Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4

STRUCTURAL WORKS 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR


DOLORES 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER 0% 0% 0% 0% 0% 0% 0% 0%

N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend: 1.1% 1.1% 1.2% 1.2% 1.2% 1.2% 1.2% 1.2% 0.1% 0.1% 0.2% 0.2% 0.3% 0.3% 0.4% 0.4% 1.6% 1.9% 1.9% 3.1%
BidDocs Schedule 5% 6% 8% 9% 10% 11% 12% 13% 14% 14% 14% 14% 14% 15% 15% 15% 17% 19% 21% 24%
Currrent Schedule
0.06% 0.06% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.03% 0.03% 0.79% 0.79% 0.89% 7.74% 0.89% 0.89% 0.89% 0.00% 0.00% 0.00%
Revised Schedule 0.31% 0.38% 0.47% 0.56% 0.66% 0.75% 0.84% 0.93% 0.96% 0.99% 1.79% 2.58% 3.46% 11.20% 12.09% 12.98% 13.88% 13.88% 13.88% 13.88%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

Revised Detailed Schedule November December January February March


Bill No. Item Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4

STRUCTURAL WORKS 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR


DOLORES 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER

N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend: 3.7% 3.8% 3.8% 3.9% 3.9% 4.4% 3.9% 3.9% 4.6% 4.2% 4.4% 2.5% 2.9% 2.5% 2.5% 2.5% 2.4% 2.7% 2.0% 2.0%
BidDocs Schedule 27% 31% 35% 39% 43% 47% 51% 55% 60% 64% 68% 71% 74% 76% 79% 81% 83% 86% 88% 90%
Currrent Schedule
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Revised Schedule 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

Revised Detailed Schedule April May June July


Bill No. Item Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4

STRUCTURAL WORKS 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR


DOLORES 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER

N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend: 2.0% 1.8% 2.1% 0.5% 0.2% 0.1% 0.1% 0.0% 0.1% 0.1% 0.1% 0.0% 0.7% 0.7% 0.7% 0.7%
BidDocs Schedule 92% 94% 96% 96% 97% 97% 97% 97% 97% 97% 97% 97% 98% 99% 99% 100%
Currrent Schedule
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Revised Schedule 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88% 13.88%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February
RL. WT.
Duration
Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 0.465%

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 12 0.470%

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22 16 0.141%

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7 1.487%
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4 1.997%

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22 8 7.694%
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 6 4.154%
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 20.468%
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 7 8.374%

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 7 8.832%

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 4 0.253%

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 15 2.848%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule March April May


Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


May June July August
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule August September October No


Bill No. Item Description Duration Start End Duration Start End Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105 0.00105

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 0.00143 0.00143 0.00143 0.00143 0.00143
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 0.00758 0.00758 0.00758 0.00758 0.00758
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 0.0031 0.0031 0.0031 0.0031 0.0031

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 0.00327 0.00327 0.00327 0.00327

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule November December January


Bill No. Item Description Duration Start End Duration Start End Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062 0.00062
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22 0.00769 0.00769 0.00769 0.00769 0.00769 0.00769 0.00769 0.00769 0.00769 0.00769
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule February March April


Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 0.00019 0.00019 0.00019 0.00019

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 0.00062 0.00062 0.00062 0.00062
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143 0.00143
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758 0.00758
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327 0.00327

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05 9.73E-05

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


April May June July
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026 0.00026

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22 0.00035 0.00035 0.00035 0.00035

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22 0.00143 0.00143
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22 0.00327

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 0.00712 0.00712
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule July


Bill No. Item Description Duration Start End Duration Start End Week 3 Week 4
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 115 Thu, 10-Feb-22 Thu, 23-Jun-22

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Wed, 01-Jun-22 Tue, 28-Jun-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 96 Sat, 06-Nov-21 Fri, 25-Feb-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 180 Wed, 06-Oct-21 Tue, 03-May-22
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 170 Wed, 06-Oct-21 Thu, 21-Apr-22

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 170 Tue, 12-Oct-21 Wed, 27-Apr-22

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 160 Mon, 20-Sep-21 Thu, 24-Mar-22

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Tue, 26-Jul-22 0.00712 0.00712
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February
RL. WT.
Duration
Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22 5 2.280%
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22 6 0.195%
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22 13 0.014%
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22 5 0.736%
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22 12 0.019%

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22 3 1.363%
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22 2 1.170%
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21 6 0.009%
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21 5 0.015%
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22 10 0.249%
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7 0.001%
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22 7 2.632%
Assemblies

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4 1.241%

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5 2.484%
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule March April May


Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22
Assemblies

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


May June July August
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22
Assemblies

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule August September October No


Bill No. Item Description Duration Start End Duration Start End Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22
Depot
0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081
206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22
Integral Bridge
0.00092
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22
Integral Bridge
0.00059 0.00059 0.00059
206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)
3E-05
206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  
5E-05 5E-05 5E-05
206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22
Assemblies
0.00439
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22
0.00103 0.00103
Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule November December January


Bill No. Item Description Duration Start End Duration Start End Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22
Depot
0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081
206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22
GRS
0.00022 0.00022 0.00022
206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22
Integral Bridge
0.00092 0.00092
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22
(include waterstop at construction joint)
0.00091 0.00091 0.00091 0.00091 0.00091 0.00091 0.00091
205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22
Integral Bridge
0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059 0.00059
206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)
3E-05 3E-05
206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
0.001%
209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22
Assemblies
0.00439 0.00439
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22
0.00103 0.00103 0.00103 0.00103 0.00103 0.00103 0.00103 0.00103 0.00103 0.00103
Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22
0.00226 0.00226
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule February March April


Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22
Depot
0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081 0.00081
206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22
GRS
0.00022 0.00022 0.00022 0.00022 0.00022 0.00022
206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22
Integral Bridge
0.00092 0.00092 0.00092
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22
(include waterstop at construction joint)
0.00091 0.00091 0.00091 0.00091 0.00091 0.00091 0.00091 0.00091
205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22
Integral Bridge
0.00059 0.00059 0.00059 0.00059 0.00059 0.00059
206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)
0.0005 0.0005 0.0005 0.0005 0.0005
206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22
Assemblies
0.00439 0.00439 0.00439
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22
0.00226 0.00226 0.00226 0.00226 0.00226 0.00226 0.00226 0.00226 0.00226
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


April May June July
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22
Electrical Manhole
0.014%
206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22
Integral Bridge
0.00092 0.00092
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22

9.5E-05 9.5E-05
206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22
Assemblies

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule July


Bill No. Item Description Duration Start End Duration Start End Week 3 Week 4
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 172 Sat, 25-Sep-21 Wed, 13-Apr-22
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Mon, 21-Mar-22
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Tue, 10-May-22 Wed, 11-May-22
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Fri, 13-May-22
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Fri, 17-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Sat, 09-Apr-22
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Mon, 14-Mar-22
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Mon, 06-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Sat, 09-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Tue, 01-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 26-Mar-22
Assemblies

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February
RL. WT.
Duration
Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3 1.125%

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2 2.419%

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2 0.657%

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2 0.471%

RIVER BANK PROTECTION WORKS FOR -3 25.630%


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0 0.041%

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.066%

100.000%
Legend: Accomplishment 0% 0% 0% 0% 0% 0% 0% 0%
Notes / Remarks
BidDocs Schedule -Slack Time Commulative Accomplishment 0% 0% 0% 0% 0% 0% 0% 0%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule March April May


Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER 0.01068 0.01068 0.01068
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend: 0% 0% 0% 0% 0% 0% 0% 0% 1% 1% 1%
Notes / Remarks
BidDocs Schedule -Slack Time 0% 0% 0% 0% 0% 0% 0% 0% 1% 2% 3%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


May June July August
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend: 1% 1% 1% 1% 1% 1% 1% 1% 1% 0% 0%
Notes / Remarks
BidDocs Schedule -Slack Time 4% 5% 6% 8% 9% 10% 11% 12% 13% 14% 14%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule August September October No


Bill No. Item Description Duration Start End Duration Start End Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21
0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007
Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER 0.01068 0.01068
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.0001

Legend: 0% 0% 0% 0% 0% 0% 2% 2% 2% 3% 4%
Notes / Remarks
BidDocs Schedule -Slack Time 14% 14% 14% 15% 15% 15% 17% 19% 21% 24% 27%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule November December January


Bill No. Item Description Duration Start End Duration Start End Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21
0.0007 0.0007 0.0007 0.0007 0.0007
Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22
0.00242 0.00242 0.00242 0.00242
STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22
0.00066 0.00066 0.00066 0.00066 0.00066 0.00066 0.00066 0.00066
Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22
0.00052 0.00052 0.00052 0.00052
RIVER BANK PROTECTION WORKS FOR
DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068 0.01068
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22 0.0001 0.0001 0.0001

Legend: 4% 4% 4% 4% 4% 4% 4% 5% 4% 4% 2%
Notes / Remarks
BidDocs Schedule -Slack Time 31% 35% 39% 43% 47% 51% 55% 60% 64% 68% 71%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule February March April


Bill No. Item Description Duration Start End Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22
0.00242 0.00242 0.00242 0.00242 0.00242 0.00242
STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22
0.00066 0.00066
Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22
0.00052 0.00052 0.00052 0.00052 0.00052
RIVER BANK PROTECTION WORKS FOR
DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend: 3% 3% 2% 2% 2% 3% 2% 2% 2% 2% 2%
Notes / Remarks
BidDocs Schedule -Slack Time 74% 76% 79% 81% 83% 86% 88% 90% 92% 94% 96%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


April May June July
Bill No. Item Description Duration Start End Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

0.00016 0.00016

Legend: 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 1%
Notes / Remarks
BidDocs Schedule -Slack Time 96% 97% 97% 97% 97% 97% 97% 97% 97% 98% 99%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: Jan 23, 2021 (Saturday)
Project Finish: Mar 15, 2022 (Tuesday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule July


Bill No. Item Description Duration Start End Duration Start End Week 3 Week 4
Structural Earth Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

0.00016 0.00016

Legend: 1% 1%
Notes / Remarks
BidDocs Schedule -Slack Time 99% 100%

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule Offset Start


Duration
Bill No. Item Description Duration Start End
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Tue, 07-Sep-21 Tue, 28-Sep-21 7

201(4)d Backfill 89 Fri, 05-Nov-21 Wed, 09-Mar-22 9

104(1) Subgrade Preparation (Common Material) 24 Mon, 21-Mar-22 Thu, 21-Apr-22 13

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 49 Tue, 07-Sep-21 Fri, 12-Nov-21 7
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 70 Fri, 27-Aug-21 Thu, 02-Dec-21 6

103(1)c Embankment for At grade section for Depot 74 Mon, 11-Oct-21 Thu, 20-Jan-22 7
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 118 Wed, 06-Oct-21 Fri, 18-Mar-22 6
(Common Material)

205(1) Cement Mixed Approach Block for internal 108 Wed, 06-Oct-21 Fri, 04-Mar-22 7
bridge

205(2) Geogrid, 37.5KN/m 108 Wed, 06-Oct-21 Fri, 04-Mar-22 7

205(3) Geogrid, 75.0KN/m 108 Tue, 12-Oct-21 Thu, 10-Mar-22 7

205(5) Gravel Bag filled with Crushed Stone 88 Mon, 20-Sep-21 Wed, 19-Jan-22 4

Surface Cource (Part C)


107(1) Sub-ballast 20 Mon, 04-Jul-22 Fri, 29-Jul-22 15
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule Offset Start


Duration
Bill No. Item Description Duration Start End
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 195 Sat, 25-Sep-21 Sat, 25-Jun-22 5
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Sat, 16-Apr-22 6
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 10-May-21 Tue, 11-May-21 1
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Tue, 21-Jun-22 5
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Tue, 21-Jun-22 12

206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Thu, 05-May-22 3
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Thu, 14-Apr-22 2
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Wed, 15-Dec-21 6
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Tue, 12-Oct-21 5
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Mon, 07-Mar-22 10
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 23-Apr-22 7
Assemblies

Miscellaneous Structures (Part E) 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4

Plumbing & Sanitary Works (Part F) 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5


Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule Offset Start


Duration
Bill No. Item Description Duration Start End
Structural Earth Works Works 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3

Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2

STRUCTURAL WORKS 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2

Drainage Work 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2

RIVER BANK PROTECTION WORKS FOR -3


DOLORES 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend: Notes /
BidDocs Schedule Remarks

Revised Schedule Revised Schedule