You are on page 1of 8

Natural Disaster Shelter Projects 2011–2012 A.

25

A.25 Philippines – 2011 – Cyclone


Overview:
Summary
In late 2011, over 39,000 houses were damaged and over 400,000
people were displaced by winds, floods and landslides following tropical
storm Washi (also known as Sendong). Collective centres were established
and non-food items were distributed in the first phase of the response.
After the emergency phase of response, transitional sites were
established and programming shifted to include reconstruction on newly
identified relocation sites (see A.27), transitional shelter programming in
existing urban areas (see A.26), and repair and rehabilitation of damaged
houses. After one year, 7,800 people remained in 38 different evacuation
centres.

Background After the cyclone established in northern Mindanao


The Philippines is a middle-in- Tropical storm Washi, (also by the Office of Civil Defence. It
come country, with a well-educated known as Sendong), hit the worked closely with international
population and engaged local and Mindanao region of the Philip- organisations, and established co-
national authorities. The Philippines pines from the 16th to the 18th of ordination groups for shelter, camp
regularly faces natural disasters December 2011. The storm brought management coordination and for
and the country has had previous strong winds and heavy rain that led non-food items.
experience of coordination with to flash floods, landslides and pro- Approximately three quarters
the cluster system. This helped to tracted flooding. 624,600 people of those people affected by the
manage the response efficiently. were affected, 430,000 people storm lived at or below the poverty
were displaced and 39,000 houses line with limited means for self-
Many low income families had
were damaged or destroyed. The recovery. Of the partially damaged
settled in particularly vulnerable
primary impacts were in Cagayan houses, nearly half had no struc-
locations on river banks and other
de Oro City and Iligan City. tural damage but needed to be
marginal land. In large parts of
Mindanao there had not been any In the immediate aftermath of cleaned before families could move
major disasters in recent memory. the storm, people found shelter back in.
in evacuation centres, with host Two months after the storm,
In rural areas, families commonly
families, in rented accommodation, moderate to heavy rains fell over
lived in amakan type shelters (with
in makeshift shelters at the site of parts of Mindanao and Visayas
woven bamboo walls) with frames
destroyed houses or in damaged islands, triggering some flooding
made from bamboo and other
houses. and landslides. Although no
varieties of wood.
The government immediate- flooding was reported in the areas
For urban areas, people living
ly mounted a major emergency affected by the tropical storm, the
at or below poverty line, lived in a
rescue, evacuation and response rain worsened the conditions in
mixture of raggedly constructed
operation. Coordination was rapidly temporary shelters.
shanties and semi-concrete houses.

Before the cyclone, many families were living in locations that were vulnerable to storms and flooding, but that had access
to livelihoods. The government declared that some of these were “no build” zones, and new sites had to be identified.
Photo: Wan Sophonpanich

www.ShelterCaseStudies.org 81
A.25   Natural Disaster

The government established a


reconstruction policy that included:
• the establishment of no build
zones
• permanent housing
• material supplies
• site upgrading for informal
settler families
• housing loans for families in
Heavy rain caused over 400,000 people to be displaced. Most people made formal settlement sites.
temporary repairs to their houses or moved in with host families.
In practice, the only no-build
Photos: Anna Pont
zones that were officially declared
Evacuation centres Host families were in Isla de Oro and Cala-cala.
A total of 119 evacuation Despite the early focus of relief These highly damaged settlements
centres were established, housing activities on collective centres and were directly in the path of the
100,000 people (20,000 families). the comparative ease of deliver- river. No official declaration was
Initial response mainly focussed ing large scale assistance to these made regarding other high risk and
on meeting the needs of people centralised sites, the majority of the medium risk areas.
in these often crowded evacuation affected population found accom-
centres. Camp management com- modation with host families. After Land
mittees were established in many of 2 months, 260,000 people were One of the major constraints
the sites. living with host families. The main in the provision of temporary and
support that these families received permanent shelter was the lack
By the end of 2012 many evacu- of available land. Identifying land
was through emergency distribu-
ation centres had closed, leaving and preparing transitional and
tion.
7,800 people (1,700 families) in 38 permanent relocation sites took
evacuation centres. Recovery many months.
An interagency shelter assess-
Tented camps
ment based on secondary data
Some tented camps were es-
sources was conducted within the
tablished to decongest some of
first month of the storm, but took
the most overcrowded evacuation
some time to be finally published. It
centres, and to provide shelter for
provided numbers of damaged and
people living in evacuation centres
destroyed houses that were used as
which needed to be returned to
planning figures.
their previous use (such as schools).
Following these results, the
Transitional sites and shelter organisations collectively
Relocation sites agreed to prioritise support to the
Where temporarily available most vulnerable 65 per cent of
land could be found, transitional people whose houses had been lost
sites were established as a more or damaged:
durable solution to camps (See
A.26). • families/occupants of the
13,850 structurally damaged Camps were established for people
When land for construction houses who were at or below living in closing or overcrowded
could be negotiated on a long evacuation centres.
the poverty line Some of the camps were very dense.
term basis, relocation sites were • families from all the 11,427 Photo: Anna Pont
established (See A.27). After four totally destroyed houses.
months, seven relocation projects
were underway, with a planned
capacity of nearly 6,000 houses for
households whose land was unsafe.
By the end of 2012, nine
permanent relocation sites had
been established by the local gov-
ernment working with NGOs.
3,147 shelters were complete,
2,943 of which were handed over.
Some transitional sites were established as
359 more permanent shelters were more durable solutions than camps.
being built. Photo: Anna Pont

82
Natural Disaster Shelter Projects 2011–2012 A.26

A.26 Philippines – 2012 – Cyclone


Case Study:

Country: Project timeline


The Philippines
12 months – –– 1,823 t-shelters
Project location: completed
Mindanao
Disaster:
6 months – –– 675 t-shelters in
Tropical Storm Washi (Sendong)
relocation sites,
Disaster date: –– 194 on-site
December 16th 2011
Number of houses damaged /
destroyed:
39,000 3 months – –– 8,000 cash for
work days worked
Number of people displaced:
30 per cent of the 600,000
population of Cagayan de Oro
City 2 months – –– First transitional
settlement centres
Project outputs:
occupied
30 transitional settlement sites
with services Philippines –– Provided water to
1,823 t-shelters 10,000 people in
evacuation centres,
Occupancy rate on handover:
distributed over
92 per cent Mindanao 2,000 WASH kits
Shelter size:
18m2 for family of five 3 weeks – –– Project start
Materials cost per shelter:
US$ 410 for relocation sites 16th December
US$ 550 for on-site 2011 – –– Disaster date
construction.

Project description
The organisation implemented an urban transitional settlement programme building 1,823 transitional
shelters. Many complex issues arose, including land and property rights, zoning issues, high-risk settlements and
providing shelter solutions to those without land rights. This programme demonstrated the importance of and
challenges to acquiring land for transitional settlements.

Strengths and weaknesses on-site shelter support. Additional targeting criteria


99 The transitional shelter (t-shelter) design cost and stricter decision-making timeframes would have
US$ 410, including labour. This was cheaper than improved beneficiary selection.
emergency tents (US$ 800-1,000, including airfreight). 88 The project was unable to support some of the
99 The t-shelter design and was inspired by the local most vulnerable affected populations, notably people
vernacular architecture. Shelters could be maintained in ‘high-risk zones’ (due to official objections) and
and materials could be re-used. people with ambiguous land tenure.
99 The integration of WASH and shelter was 88 An alternative shelter design for people with
emphasised from the beginning of the program. disabilities should have been developed.
99 The agency put a great deal of effort into persuading -- An ill-defined ‘no-build zone’ policy created
land owners to release their land. challenges. A number of landowners remained in
99 The agency successfully negotiated the free ‘limbo’ because their homes were within no-build
installation and use of water and electricity for two zones, and new land was not allocated.
months for 7 relocation sites. -- Different stakeholders, such as the church and local
88 There were questions around how disaster-resistant government, had different approaches to beneficiary
the t-shelter design was. selection and prioritisation.
88 The organisation would have benefitted from hiring -- Some affected households refused to move into
a liaison officer to better understand the political a transitional settlement because they thought this
system and accelerate the project. would impact on their right to promised permanent
88 There were difficulties in verifying beneficiaries for housing.

www.ShelterCaseStudies.org 83
A.26   Natural Disaster

Before the cyclone


(See overview A.25 for back-
ground.)
Until 2011, there had been no
major floods in the area since the
1950s. The population of Cagayan
de Oro had spread along risk
areas, such as river banks and delta
areas. In Macasandig, one of the
most affected areas, there was a
mix of commercial and residential
buildings. Residents ranged from
poor in shanty areas to middle-class
in apartment buildings.
Despite the well-developed local
administration, the complexities
of addressing housing, land and Emergency shelters such as schools and gymnasiums quickly became
property issues in an urban transi- overcrowded in the aftermath of the storm.
tional response presented real chal- Photo: CRS/S.Hirano
lenges in supporting the most vul-
nerable. risk of flooding or landslide Selection of beneficiaries
• access to roads Relocation
After the cyclone • access to water (either There were only two organisa-
The flash floods caused by groundwater or pipe tions who responded with transi-
Tropical Storm Washi destroyed a connection) and electricity tional shelter projects in the Phil-
large portion of the city centre of • costs of travelling into the ippines. As a result, there was
Cagayan de Oro. Macasandig and city from the site were not considerable pressure from gov-
Isla de Oro were the worst affected prohibitively expensive for ernment officials, church leaders,
urban barangays (the smallest ad- beneficiaries camp managers and other NGOs to
ministrative boundary, equivalent • the proximity of public facilities prioritise certain evacuation centres
to a village). such as schools, health centers or specific beneficiaries.
Poor families residing in and markets.
The government prioritised
makeshift shelters by the river Different types of agreement closing evacuation centers and tent
banks suffered the most. Many were required with different land- cities before assisting community-
middle-class households who owners. In most sites, there was based IDPs as the evacuation centres
rented or owned apartments were a guarantee that land would be were costly and water and sanitation
also affected. returned to owner. Overall 30 sites services were over-stretched.
As the emergency response were established. Meanwhile, organisations working
unfolded, the government on education issues advocated
The types of agreement are
launched their permanent housing for emptying schools to address
summarised in the table below.
programme. The agency proposed protection concerns associated with
a two-tier transitional shelter owner type of agreement endorsed having displaced people living on
programme to plug the gap by school grounds. 
between emergency shelter and City Verbal agreement for Mayor
temporary use. Other Families who wanted to return
permanent housing. conditions included to their places of origin were given
requests for certain lowest priority on the permanent
Land Acquisition shelter recipients or, in
one case, early closure housing waiting list.
The following criteria were used
of the site in order for
to verify the suitability of land: the land to be used for The organisation faced the chal-
permanent shelter. lenges of determining whether
• clarity of land ownership
Private Written MoA between Landowner informal settlers had really lost
• land is donated rent-free for up the Archdiocese of their homes in the storm. There
to 2 years Cagayan de Oro and the
landowner with terms were some cases of ‘opportunists’
• land owner clearly understands
and conditions. trying to use the system to receive
the purpose and the nature of
Church Verbal agreement after Archbishop a shelter although their home
transitional settlements request of Archbishop. remained intact.
• land is well drained and is not at

84
Natural Disaster Shelter Projects 2011–2012 A.26

Transitional shelters could be placed


Transitional shelters could be relocated. on available plots of land.
Photo: Charisse Mae Borja / CRS Photo: Seki Hirano / CRS

The organisation aimed to retain Implementation DRR components


community social structures as far To address the range of needs Drainage, sewage channels and
as possible when relocating benefi- the agency offered two transitional other essential infrastructure were
ciaries in the most affected areas. shelter options: construction on provided where necessary. This was
This was not always possible due either the original site or in one of to ensure the protection of both
to variations in site location, timing 15 relocation sites. the people living on the land and
of response, and the number of the land itself.
shelters available on each site. Transitional shelter design
Transitional shelters erected On-site transitional shelters
On site Construction on relocation sites needed to were constructed using a reinforced
Affected households whose be moveable and make minimal concrete foundation enabling the
houses had been totally destroyed, impact on the land. shelter to be securely anchored,
and who lived in low to medium preventing it from being upturned
risk zones, were offered flood- The agency worked with a local
by flood or strong winds.
resistant transitional shelters sited architect and local engineers to
in their original neighbourhood. design an adaptation of the tradi- The design featured a raised
Water and Sanitation facilities tional Amakan (bamboo or palm floor to provide flood protection,
were organised within community leaf weave) house. facilitate ventilation and to keep
groups and elevated septic tanks out vermin.
Amakan houses have been built
were constructed. for centuries and are well adapted Logistics
Informal settlers were often to the tropical climate of the Phil- Drying timber and limited road
without official land or house ippines. They can also easily be access were the biggest logistical
tenure papers. This meant it was repaired or rebuilt. The design used issues, affecting delivery time and
difficult to confirm whether they locally available amakan (palm was costs. One truck could carry enough
had lost their home during Washi used) for the walls and coco lumber, timber for 28 transitional shelters,
or if they had lived elsewhere. which is durable and inexpensive, meaning that over 75 truckloads of
for the structural frames. timber were required for the whole
To identify households for
The design was based on the project.
on-site rebuilding, the organisation
conducted a community mapping following design criteria: Materials list
process. This involved visiting • Culturally appropriate: Provides Materials Quantity
former housing locations, verifying privacy, uses local materials and Portland cement(40kg) 5 bags
the damage to houses, verifying the provides protection from rain Mixed gravel 1 bags
lack of shelter, interviewing neigh- 10mmx6.0m re-bar 12m
and heat 8mmx6.0m re-bar 3m
bours and verifying lists of names • Relocatable: Can be carried by Coco Lumber 4”x4”x12’ 64 ft.
with ward leaders and community 20 persons or easily dismantled Coco Lumber 2”x3”x12’ 128 ft.
leaders. This ward specific approach Coco Lumber 2”x4”x8’ 128 ft.
• Speed of construction: Can be Coco Lumber 2”x2”x8’ 75 ft.
was taken helped to retain the built in 2-3 days Coco Lumber 2”x4”x8’ 32 ft.
community structure. • Economical 2” umbrella nails 1kg
Bamboo slats 3 bundle
It was challenging to identify • Flexible: Design can be adjusted Nails 9kg
those most in need. As time passed, for relocated families or those Plywood ¾”x4”x8” 6 sheets
returning to original sites Plywood 3/16”x4’x8’ 6 sheets
a number of people had begun re- Amakan 4’x8’ 13 sheets
building, making it difficult to verify • Upgradeable: Can be upgraded Sealant 1 pint
the original level of damage. to a permanent home.

www.ShelterCaseStudies.org 85
A.27   Natural Disaster

A.27 Philippines – 2012 – Cyclone


Case Study: Keywords: Resettlement, Household NFIs, Construction materials, Core housing construction,
Housing repair and retrofitting, Site planning, Infrastructure, Training.

Country: Project timeline


The Philippines
Project location:
Mindanao
Disaster:
11 months– –– 70 per cent of
Tropical Storm Washi (Sendong) planned 6,000
Disaster date: houses completed
16th December 2011
Number of houses damaged /
destroyed:
39,000
Project outputs:
5,000 emergency shelter kits
6,000 permanent core houses
(90 per cent complete)
Occupancy rate on handover:
70 per cent occupancy
Shelter size:
21m2 - permanent core house 4 months – –– First 500 perma-
Philippines nent core houses
Materials cost per shelter: constructed
US$ 50: emergency shelter kit Mindanao
US$ 2,750: permanent core
house 1 month – –– Distribution of non-
food items starts
Project cost per shelter: 2 weeks – (5000 HH)
US$ 3,100
16th December
2011 – –– Disaster date

Project description
The organisation distributed 5,000 shelter repair kits and built 6,000 housing units for displaced families. It
built the houses with services on new relocation sites using contractors, volunteers and working with partners.
It deployed three construction mobilisation units for the repair and restoration of houses and communities
damaged by the storm.

Strengths and weaknesses negative impact in the project and the local economy.
99 Good relations were established with local 88 Relocation introduced the need to develop new
authorities. As a result, land for relocation sites and networks and community relations among the
resources for site development were readily available relocated population. These activities had very little
from the authorities. funding support from the project.
99 Quick development of family selection criteria and 88 Delays among other organisations providing
process. As a result, displaced families could be offered infrastrcuture and services to the sites meant that only
a clear path to recovery in a relatively short time. 70 per cent of the houses were occupied by the end
99 Good management of construction activities in of 2012.
multiple sites with a variety of contractors contributing -- Strong coordination with other organisations
to a steady delivery of permanent shelter. through national coordination and local interagency
99 The project has allowed the development of block- group meetings was needed to avoid duplication of
making, welding and carpentry skills among the material distributions. Several organisations provided
affected populations. similar products, such as repair kits.
88 Due to limited availability of local construction -- At the end of 2012, Typhoon Bopha (Pablo) hit
materials and high prices, advance scouting became Mindanao. Previously, Mindanao was seldom hit by
necessary to order from suppliers. This created some cyclones and typhoons, as a result preparedness was
backlog in implementation. lower than elsewhere.
88 Price hikes of 30 per cent and more created a

86
Natural Disaster Shelter Projects 2011–2012 A.27

The organisation rapidly completed 70 per cent of a planned 6,000 houses within 11 months of the storm on safer
permanent relocation sites.
Photo: Mikel Flamm

Before the cyclone The government issued a decree Implementation


See Section A.25 for back- to prevent re-settlement and recon- The organisation distributed
ground. struction of houses in some high 5,000 emergency shelter kits con-
risk areas. As a result, families were taining construction materials
Families were settled along the
displaced into camps set up by the (timber, corrugated galvanised
river banks of the Cagayan de Oro
local authorities and international sheets, nails, etc.) and basic tools
river and other minor streams in
humanitarian organisations. to support emergency repairs on
northern Mindanao. The locations
The Government of the Philip- damaged homes.
are extremely hazardous and in
high-risk for flash floods. While pines made an early decision after Staff made an initial damage
being high risk areas, these locations the disaster to relocate affected assessment in affected neighbour-
were well located economically, families who had been living in the hoods and issued vouchers. The
being near the cities’ commercial river banks of the Cagayan de Oro distribution was made out of a
districts where most families found river. Their homes were completely centrally located warehouse.
support for their livelihoods. washed away by the floods.
In coordination with local and
After the cyclone Local government entities national authorities, the organi-
Rain from the severe tropical provided land for temporary sation conducted assessments
storm Washi (Sendong) created camps in the outskirts of cities, and planned to construct 6,000
flash floods. Most houses located to accommodate the displaced permanent shelters in 10 relocation
by the river banks were completely until permanent shelter could be sites in Cagayan de Oro City and
destroyed. Homes in safer locations secured. Iligan.
were damaged by high winds. Government agencies provided
land from pre-existing land banks
and facilitated planning resources
and heavy machinery for site devel-
opment. The organisation was put
in charge of overall programme co-
ordination and the construction of
the permanent shelters.

Selection of beneficiaries
The Philippines’ natioanl Depart-
ment of Social Welfare and Develop-
ment, conducted a thorough survey
and census of affected families.
It used this to determine eligibility
for assistance and shelter support.
Families prevented from resettling
in high risk areas were placed in
tented camps and selected for re-
location to the nearest site where
permanent shelter was being built.

New relocation sites were planned in locations with lower cyclone risk.
Photo: Mikel Flamm

www.ShelterCaseStudies.org 87
A.27   Natural Disaster

Non-food items and housing repair kits were Construction was implemented using contractors, vol-
distributed to 5,000 households. unteers and by working with partner organisations.
Photo: Leonilo Escalada Photo: Mikel Flamm

Implementation The permanent core houses were


The organisation used 22 small structurally designed by engineers, “At the beginning, we were
construction groups as external incorporating strapping and rein- doubtful we could be in a
contractors. These worked in com- forcements and were approved by permanent house so soon
bination with its own staff, volun- the relevant authorities. The sites after Washi. We are happy
teers and implementing partneror- were provided with drainage infra-
that we could move out of
ganisations. structure and roads, and walkways
were built to manage erosion. the tent into a permanent
Family participation in project house.”
activities was limited to unskilled Before families moved into
tasks and attendance to skills de- their new homes, as part of the
velopment training (carpentry, induction to the new settlements,
welding, and concrete block-mak- they received an initial training
ing). induction on disaster preparedness. A new housholder at the
This was coordinated with the local Calaanan site, Cagayan de
Coordination emergency management agency. Oro City
From the beginning of the
response, it became clear that Technical solutions
there would be a division of labour The core house was built from Logistics
between humanitarian organisa- concrete blocks, with a reinforced On account of its scale, the
tions responding to the disaster. masonry design. There were steel project presented many logistical
reinforcement bars, both verti- hurdles related to the supply of
While some organisations
cally and horizontally. The roof construction materials.
invested efforts in tents and transi-
structure was made of metal trusses
tional shelter in camp settings, this The organisation purchased
and purlins, with a cover of zinc/
organisation was keen to embark cement, reinforcement bar and
aluminium sheeting. Doors and
on a permanent shelter construc- other materials in bulk to minimize
windows used metal frames, and
tion programme to allow for the the price rises following the disaster.
the floor was covered with ceramic
next stage in the recovery. Coordi- These materials were then distribut-
tiles.
nation was key in helping to clearly ed to contractors as required by the
define these roles, and to provide a Each shelter unit had a multiple progress of construction.
pathway to permanent shelter for purpose room, an attached sanitary
affected families. unit (toilet and bath area) and a The project benefitted from
small kitchen area. The height of skilled and experienced manage-
DRR components the buildings allowed a mezzanine rial staff coming from the organi-
The different relocation sites level to be built by occupants to sation’s central office in Manila, as
were located in low-risk areas, with create a raised sleeping area. This well as newly hired staff.
reduced natural threats. These relo- could potentially increase the living
cation sites were safer than families’ space from 21m2 to 36m2.
original plots by the river.

88

You might also like