Professional Documents
Culture Documents
D. ELECTRICAL REQUIREMENTS................................................................................................................ 31
F. CIVIL REQUIREMENTS.......................................................................................................................... 51
I. PROJECT MANAGEMENT..................................................................................................................... 60
Steam Turbine shall be specified to be capable of continuously operating down to 25% of its
base load rating. This requirement is intended to ensure that the power plant can operate
throughout the load profile with maximum possible efficiency.
The plant shall comply with the grid code of Bangladesh and shall be capable of supplying
their rated output power at rated frequency and rated power factor for a voltage range of
+10% to – 20% from rated grid voltage. Each generator shall also be capable of supplying
its rated output at rated voltage and rated power factor at rated frequency which may vary
between 48.5 Hz and 51.5 Hz. The electrical generators shall be capable of continuous
operation without injurious effects with an output over the range 0.8 power factor lag to 0.95
power factor lead and capable of generating rated active power over the above power factor
range.
If there is any discrepancy between this document & Major Equipment suppliers’OEM
technical specifications, then Major Equipment suppliers’ OEM technical specifications
shall prevail in their respective working scope.
The Site area is shown on the Plant Layout drawings in Appendix [14]. Included in the
drawings is an indicative layout of the plant. The Contractor shall verify on site all
dimensions and levels shown on the drawings and shall inform the Employer of any
discrepancies. The final layout shall allow sufficient space for equipment accessibility and
laydown during maintenance activities.
The Contractor shall provide general arrangement drawings to illustrate any engine block,
crank shaft or the generator rotor withdrawal requirements. These areas are to be kept free
and clear with no installed piping or electrical equipment. The Contractor shall demonstrate
in the layout plan and the design of systems how these goals have been achieved, to the
Employer's satisfaction and agreement.
The Contractor shall carry out any air sampling necessary to determine the quality of the
ambient air and use this information in the design of the filtration system for the Engines
and elsewhere in the design of the plant as required.
The main power block consists of 6 x 18V48/60TS MAN Diesel & Turbo reciprocating
engine(s) and 1 x Steam Turbine and generators. Other plant buildings and structures
outside of the main power block include a water treatment plant, oily water treatment facility,
solid waste facilities, control room, store room, compressor room, maintenance facility,
Electrical Interconnection Facilities, oil storage facility, fuel treatment house, admin building
and other associated buildings and structures that may be required for the balance of the
Facility. The Facility shall be designed for a life of 30 years.
Generally, the main supply shall include, but not be limited to the following:
1) HFO run medium speed diesel engines, giving a total net plant output of 115MW to
attain the design Plant Availability of 90% for a life of 30 years at a plant factor of
80%.
2) Synchronous, 3 Phase, 50 Hz generators driven by the engines.
3) Heat Recovery Steam Generator (HRSG) to fulfill steam requirement of Steam
Turbine with ability to operate on even 2 HFO engine fully. HRSG design parameters
shall be complying to the technical parameters defined by the OEM of the engine;
8) All tanks necessary for the storage of HFO, Fresh lube oil, Used Lube oil, Diesel,
Raw water, Treated and demineralized water. Contractor should provide fuel oil
storage capacity not less than 20 days of operations at 100% plant factor.
9) Contractor to develop the fuel unloading station for all seasons along with access and
parking. Fuel unloading facility shall have provision of unloading HFO & LFO
including necessary hose with couplings and measuring flow meters. Any chemical
which has daily consumption over 20 liter /day, shall be provided permanent tanks
where tanks shall be topped up.
10) Contractor to provide Telephone and Internet connections within the plant boundary.
Client shall arrange necessary incoming connections to the junction box of the plant.
11) Waste oil will be pumped to the sludge storage tank, where it will be removed by road
tanker.
12) All waste water shall be treated before discharge for compliance of national
regulations like contamination treatment, control of discharge temperature etc.
2) Interconnection of the plant’s PABX and Internet shall be at a junction point provided
by the Contractor at site (to be defined during execution).
3) Discharge water connection point to external drainage system to be in accordance to
the Employer’s directive (within plant boundary).
4) Project internal roads network shall be designed and constructed by Contractor and
connected to the existing highway.
The codes, standard and specifications referenced in this Specification shall include
addenda and amendments in force at Notice to Proceed and shall govern in all cases where
references to them are made. Other equivalent international standards may only be used
with the written agreement of the Employer.
A.11 Fuel
Information regarding the HFO and High Speed Diesel to be consumed on Site is included
in Fuel Specification Appendix [4]. The Contractor shall provide proper and appropriate
treatment of the fuels to make them suitable for use with the Works.
A.15 Sewage
All sewage from the Works shall be directed by underground pipe work to an on-site septic
tank system. The Contractor shall be responsible for the design and installation of the
complete sewage system for the Works and shall provide any additional sewage handling
and/or treatment necessary during construction meeting environmental standard.
Engine shall be cooled by radiator. Steam turbine & BOPs shall be cooled by cooling water
with help of cooling tower, based on the cooling water quality, metallurgy shall be selected
& carbon steel shall not be used for open circuit cooling system.
A.19 Environmental
The Contractor shall design and construct the Works such that it meets the requirements of
the EIA. All practicable measures shall be taken to prevent and minimize harm to the
environment as a result of the construction and operation of the Works.
A.25 Noise
The Contractor shall design the Works such that the specified noise criteria shall comply
with guarantee figure Appendix [1] at Plant Boundary.
A.26 Aesthetics
The layout, building colors, architectural design, landscaping and finishing of the Works
shall be to the approval of the Employer.
The Works shall be capable of withstanding without damage, undue heat, strain, vibration,
noise, corrosion or other operating difficulties, all stresses which may be experienced during
normal operation, cyclic load operation, part loading, over speed, sudden load swings and
under all specified test conditions.
All materials, plant and other supplies to be incorporated in the works shall be new and of a
standard proven design. The Contractor shall not propose nor provide equipment from any
manufacturer, which the manufacturer proposes, for the duration of this Contract, to be
superseded or outdated by a later generation of equipment. The Contractor shall not
propose to provide equipment which is not in regular commercial use and service in
installations of scope and magnitude similar to this contract or for which local support and/or
services in Bangladesh are not currently available. Any Israeli origin equipment/materials
shall not be provided on the entire project.
The Works shall be designed so that no single fault of auxiliary plant (except Plant Outgoing
Line Feeder, Plant LV Common bus supply / station transformer failure, fuel feeder pump,
fuel booster pump, UPS) shall cause the shutdown of the whole plant. Generally, bypasses
shall be installed so that instrumentation, equipment and critical control valves can be
repaired on-line.
All equipment and systems shall have sufficient margin to cater for equipment and system
wear and tear and deterioration. The Contractor shall identify and justify all margins during
engineering submission – including margins for sizing/design of cooling water pumps, heat
exchangers, HVAC systems, fire protection systems, transformer ratings, safety features,
phase bus rating, generator breaker rating, battery and UPS systems and the emergency
diesel generator.
All electrical and control and instrumentation (C&I) equipment (e.g. the power center, motor
control center, UPS and DC systems, DCS/SCADA, wiring cabinets, balance of plant MCCs
and PLCs etc. shall be housed in air-conditioned/ ventilated rooms or cubicles.
The Works shall be designed so that, in the event of a trip, it and its associated systems
shall shutdown in a safe manner without damage to equipment. All equipment shall be
designed to permit safe shutdown on loss of electrical power supply or on loss of control
system.
The detailed design of all buildings shall include consideration of energy efficiency. The
architectural treatment shall be consistent with the overall site landscape plan.
The Contractor shall provide all the Hardware and Licensed Software required for
programming DCS/SCADA, all control systems, PLCs and HMIs .The Contractor shall
develop and provide any custom software needed to adapt or customize the control and
monitoring systems being provided by the Contractor to perform the various tasks and
provide the various functions required. Customized software shall be menu driven with
multi-window capabilities to the maximum extent possible, and shall utilize other guidance
routines to permit personnel not trained as programmers to conveniently alter or
supplement the contents of the various routines. The reservations as to the use of custom
software, and the backup and documentation for such software shall be as described for
standard software.
Software licenses for unrestricted use by the Owner shall be provided upon completion of
defect liability period for all systems supplied as part of the Works and shall apply to all
software required for the operation, diagnostics of these systems unless otherwise
recommended by OEM.
It shall be possible to complete maintenance of specified plant items, or items not essential
for maintaining continuous operation of the plant, (e.g. pumps, thermocouples, sensors)
without reducing output from full load. All such maintenance activities must be planned by
the Contractor to be in accordance with safety requirements and Applicable Laws and
standards, and described in the maintenance manuals.
Access ways, walkways etc. shall be free from cable ways, conduits, pipework etc. which
could cause tripping hazards or impede the normal progress of operations and maintenance
staff around the Works.
B.6 Insulation
The insulation will be in accordance with the related standards, general recognized rules
and practices and approved PIDs. The insulation will be made of insulation blankets or
prefabricated insulation blocks. Complete heat insulation, setting materials and suitable
supports will be supplied for all parts of the unit. The insulation will be suitable for all
expected operating temperatures and the insulation will be of sufficient thickness to conform
to present-day standards. All the heat carrying systems as per process requirements will be
insulated, including their drains and vents up to their first shut-off valves. Drain and vent
lines after the shut-off valves and outlet pipes of the blow-off piping will only be insulated for
personnel protection whereas operating and maintenance people may have accidental
contact. Drain systems having an operating duty of continuous drainage will entirely be
insulated with associated equipment such as steam traps, valves and headers.
An exterior metal covering will be provided to protect all insulated header, pipes, tubes and
connecting pipes external to the steam boiler. Flanges, valves and other equipment
requiring regular maintenance will be provided with insulating boxes. These will be fitted
with hinges and clamp fasteners and will be lined with an insulation of the required
thickness, which will be secured to the box.
Cladding shall be not less than 0.7mm (22 SWG) in thickness and shall be adequately
supported to prevent sagging or excessive deflection. In the case of exterior surfaces, it
shall be designed to resist wind loadings.
Pipework insulation shall be terminated at a distance equal to the length of the flange bolts
from the flange in the case of flanged joints or at point which permits preparation of the pipe
end for welding without disturbing the insulation in the case of welded-in valves. The joint or
valve shall be insulated independently of the pipe by preformed blocks or blanket type
material of thickness at least equal to that of the adjacent pipe insulation. Valves shall be
insulated up to and including the bonnet but not the bonnet joints.
Insulation and lagging over all flanges and valves shall be easily removable and
replaceable without disturbing the surrounding insulation. The separate portion of the
lagging shall extend sufficiently far along the pipe to allow the joint bolts and nuts to be
withdrawn without disturbing the lagging on the pipe.
The casing over flanges shall have a drain hole to indicate the presence of a leak.
Insulation shall be continuous through floors, walls, pipe supports, anchors, guides and
hangers. The insulation shall be sealed at all interruptions due to hangers etc. and the
cladding shall be flashed and sealed to make it weather tight. Insulation shall be installed
only after the completion of any hydrostatic testing of the pipework system or equipment
has been completed.
B.7 Chemicals
Chemical storage areas and facilities shall be sized to store up to one month’s supply of
chemicals assuming the plant operates at full load. All such storage facilities shall comply
with statutory requirements and relevant Codes and Standards. Eyewashes and emergency
showers using potable water shall be provided wherever chemicals are to be handled.
The flooring in areas where chemicals are in use, handled or stored shall be suitably
prepared/coated to protect them in the event of a spill. Where any supporting slab or
platform may be subject to contamination by any corrosive agent or wetness due to liquid
spillage, the Contractor shall provide appropriate surface protection by means of chemical
resisting coating/tiles or anti-slip coating/tiles, to be agreed by the Owner.
B.8 Buildings
The Engines, Steam Turbine, generators and associated auxiliary equipment shall be
located indoors and shall include an overhead crane system. The arrangement of the major
equipment within the building shall allow free access for the overhead crane for
maintenance.
B.9 Signage
Wall mounted signs shall be provided at all floors, platforms, etc. to indicate reduced
headroom clearance, hazardous areas, warning signs and others as required by the
design , , Codes and Standards.
All motors, valves etc. which must be operated during start-up, shutdown, normal,
emergency or special operations of the plant and auxiliaries shall be automatically /
remotely operable (as per design) by the control system, with the sequences initiated from
the central control room. Notwithstanding this, it shall also be possible for the operator to
interrupt the automatic, programmed sequences and control the plant manually from the
locally or central control room.
The degree of automation provided shall ensure the plant can be safely and reliably started,
shut down, controlled and monitored locally or remotely from the control room location
except for engine, steam turbine, exhaust gas boiler & substation which must be safely and
reliably started, shutdown, controlled and monitored from control room location.The degree
of automation provided shall ensure the plant can be safely and reliably started, shut down,
controlled and monitored from locally or a remote control room location.
The lay-down areas shall be arranged and located to permit X and Y horizontal movement,
in addition to vertical access by the overhead crane hooks. The need to pass major
components over operating units shall be minimized.
Prohibited materials
The Works shall not incorporate:
o Asbestos or asbestos-containing materials;
o Cast iron for any oil service
o PCBs
o CFC’s or other ozone depleting substances except (with Owner’s consent in writing) in
applications where their use cannot reasonably be avoided, and is generally accepted for
the specific application;
o Carcinogenic materials; and
o Any other materials generally known in the construction industry at the time of use to be
deleterious to health if used or incorporated in such projects the Works.
The Contractor shall provide following drawings/documents but not limited to;
- Project schedule indicating the critical path
- Heat Balance Diagram shall be prepared for the entire operating range of the
equipment being supplied. The diagrams shall be updated as design progress to use
actual turbine data, air cooled condenser data, HRSG data, etc.
- Water Balance Diagram
- Piping and Instrumentation Diagram
- Electrical Single Line Diagram
- SCADA Control Architecture
- Plot Plan and General Arrangement Drawings
- Piping Isometric Drawing
- Facility description, system description and system operating instruction
- Equipment list
- Pipeline list
- Valve list
- Cable list
-
- Instrument list
- Lubricant list
- Consumable list
- Recommended 2 year operational spare part list
- Final soil investigation report
- Civil and structural design criteria based upon the Contractor’s Geotechnical
investigation.
- Equipment and Material Specification/ Vendor Manuals/Prints
- Engineering analysis and calculation .
- Drawings Issued for Construction
- WPS
- Operation and Maintenance Manual
B.13 Labeling
Each item of plant including, field devices and drives shall be durably and legibly labelled,
indicating the purpose, plant identification number and where necessary any operating
position functions. Each shall have its unique plant identification system number.
This new engine type is a development for power plant applications, based on the well-
proven 48/60 engine. The engine is equipped with a sequential, two stage turbo-charging
system to provide a new dimension in engine performance, operational flexibility and
reduced NOx-emissions.
Engines 18V48/60TS, mounted on steel foundation frame, suitable for operation on heavy
fuel oil, as per following details. The engine is rigidly mounted on a steel foundation frame
which is resiliently seated on the foundation. The steel foundation frame is used as lube oil
service tank.
Engine attached lube oil pump(s) including pressure control valve and connecting pipe
between pumps.
Engine attached HT and LT cooling water pump.
Lube oil module mounted on a frame with corresponding fittings completely piped and
wired.
Lube oil replenishing and flow rate measuring device.
HP / LP steam and condensate shall have totally separate system from each other, shall
not be mixed anywhere in the whole water and steam cycle yet there will be provisions for
converting HP to LP steam only if there a necessity of more LP steam.
The feed water tank, used to secure the feed water reserve for the exhaust gas boiler
system. Water in the tank consists of condensate and fresh make-up water. The LP and HP
steam shall be separated.
Stairs shall be provided on one side of each WHRB to drum level or single common
platform for all HRSG shall be provided.
Nitrogen shall be used for blanketing during extended outages. Nitrogen preservation
system should be as specified. Bottle and nitrogen gas will be provided by Owner.
Steam System shall be designed as per ASME B31.1 and ASME TDP-1
30% capacity of steam turbine bypass system shall be provided. The bypass system shall
provide stable pressure control of upstream of the valve in case of steam turbine trip, load
Steam Turbine Load Run back test during Engine Trip/ Bypass condition shall be carried
out.
It shall be possible to isolate any compressor for maintenance, with the adjacent
compressor(s) running. The air receivers shall be of the cylindrical type, designed and
constructed in accordance with relevant standards and Codes and complete with the
following connections and fittings:
o Air inlet from compressors
o Air outlet to diesel engine
o Drain
o Safety/relief valve
o Automatic water drain trap
o Pressure gauge
o Inspection cover.
The control system for the compressors shall be arranged so that the receiver is
automatically maintained at the set pressure by the electric motor driven air compressor.
The compressor stop pressure switch setting shall be such as to prevent excessive cycling
of the compressor.
Fuel receiving, handling and transportation from the intake point (near railway station/jetty in
case of river transportation) shall be the responsibility of EPV Thakurgaon Ltd. Required
necessary arrangement in railway station/construction of jetty and necessary arrangement
in case of river transportation, pipe line from the intake point up to EPV Thakurgaon Ltd.
storage facility including fuel measuring system, internal fuel supply system, fuel heating
and purification/treatment system as per requirement of the offered plant shall be installed
by EPV Thakurgaon Ltd. at its own cost and responsibility.
The Contractor shall design and provide a complete fuel oil system to the engines at
appropriate supply conditions and quantity with redundancy. Scope of supply consist the
following but not limited to
1) All tanks necessary for the storage of HFO, lube oil (new and used/sludge), diesel and
raw, treated and demin water shall be provided by Contractor. Contractor should
provide fuel oil storage capacity not less than 20 days of operations and the site for the
fuel yard shall be the existing fuel yard. The tanks shall be designed to API 650 and
shall be complete with stairs, handrails, external coatings, instrumentation, vents,
manholes, drains, filling, over flow and any other equipment necessary for the safe
operation of the fuel oil system.
2) Contractor shall develop the fuel unloading station along with access road from Plant
gate.
Workshops, fuel treatment room, stores, battery rooms and other infrequently manned
spaces may be forced or naturally ventilated. Warehouse shall have a separate
temperature-controlled storage room for specific storage items. Control rooms, LV & MV
switchgear room shall be air conditioned Ventilation and Air Conditioning shall be provided
in all areas where necessary. Control Room shall have 3x50% redundancy of air
conditioning equipment to maintain specified rated operating temperature.
The HVAC system shall be designed in accordance with all relevant codes and standards.
The Contractor shall consider the health and welfare of all personnel and the requirements
of the relevant equipment across all plant loading conditions and the full range of external
ambient conditions. The design of the HVAC system shall also consider the requirement to
provide air pressurization for smoke control, adequate ventilation of hazardous gases and
fumes and to control the spread of hot gases and smoke.
The impulse voltage levels for all equipment connected shall be in line with the
requirements IEC, IEEE or equivalent standard. 132 kV equipment fault level shall be 40kA
for 1 sec. Contractor shall be responsible for ensuring that all electrical equipment in the
power station shall have a fault capability adequate for the system to which it is connected.
All plant and equipment shall be designed to ensure satisfactory operation under such
sudden variations of load and voltage as may be met under working conditions, including
those due to starting loads, transient short circuit, internal and external fault conditions
within limit.
Protective relays and systems shall be provided to detect all credible faults on each item of
plant and equipment and their primary interconnections. Each protective scheme shall be
designed so that it does not cause incorrect tripping of a circuit breaker if a fault occurs
outside the zone of protection covered by the scheme. Fault clearance times shall be
according to relevant codes and standards and with the relevant carried out studies.
Protection relays shall be based on latest and proven technology of renowned manufacturer
programmable microprocessor type incorporating with fault, event and transient
measurement memories, programmable logic , matrices for programming tripping
sequence, oscillography, auxiliary relays and integration with DCS/SCADA.
LV and MV systems related to the steam turbine shall be configured such a way that in
case of failure of single auxiliary transformer shall not cause un-operatable of steam
turbine.
D.4 Switchgear
Each switchboard shall be readily extensible and space shall be provided to allow the future
installation of two circuit breaker cubicles at both ends of each switchboard. A clear side
access space of one meter shall be provided at each end of the fully extended switchboard.
Maximum 10% spare as a redundancy shall be of critical outgoing feeder / starter of most
common sizes (for items quantity are greater than 5 nos, & rating below 630A).
The switchgear rating shall be of as required based on plant running auxiliaries at normal
condition + maximum 10% design margin for future load & shall be of non-redundant.
The total batteries shall be rated for a period of 2 hours when supplying 125% of the
maximum continuous load of its associated equipment. Equally the total batteries shall be
rated for a period of 10 hours (5 hours + 5 hours) when supplying 100% of the maximum
continuous load of its associated equipment without the voltage collapsing below 80% of its
rating. The total batteries shall be of two sets i.e. 2 x 50% and each of the battery set shall
be connected to each charger.
D.7 Motors
Motors shall be of the energy efficient type and comply with the requirements of IEC60034.
Motor enclosures shall be suitable IP rating as per the relevant IEC standard. Motor Service
factors shall be as per standard.
MV motors and LV motors required to operate outdoors or motors that may be at standstill
for relatively long periods, shall be fitted with anti-condensation heaters of appropriate
rating.
The cable installation shall be compatible with relevant IEC/VDE/BS or equivalent standard
and comprised of complete cable terminations & fittings, cable trays, cable ladder racks,
junction boxes, GI and flexible conduits, glands, ferrules, lugs, numbered ferrules, fixed
fade-free and dirt resistant identification label / cable markers, clips , all fixings, fittings,
brackets and accessories etc.
− Insulation class F
− Mounting design IM1001 or IM7201
− Protection class alternator IP23
− Protection class terminal box IP54
− Cooling method IC0A1 (Air cooled)
− Operation S1, continuous
− Operation mode Grid parallel
− Applicable standard IEC 60034
The generator shall be capable of supplying its rated real power output at nominal voltage
and at a power factor between the following limits: 0.8 power factor lagging and 0.95 power
factor leading. The generator shall be of open air-cooled inlet filtered type. The outlet air of
the generator shall preferably be ducted from the powerhouse. The stator end windings
shall be designed to last the design life of the generator without failure.
Generators shall have a minimum short circuit ratio of not less than 0.5
Three phase synchronous alternator shall be of rigid stator frame, welded steel structure
construction. The stator core is built of thin electric sheet steel laminations which are
insulated on both sides with heat-resistant inorganic resin. The radial cooling ducts in the
stator core ensure uniform and effective cooling of the stator. The rotor consists of a forged
steel shaft, a hub and sheet steel poles fixed on the hub. The pole laminations are pressed
together with steel bars fixed to the end plates. The windings, epoxy resin impregnated, are
provided with very strong bracing which withstand all expected mechanical and electrical
shocks and vibrations. The alternator is self-ventilated and needs no external forced air
flow. The surrounding air is used for cooling. The cooling air is drawn in through air filters
and blown out to the surrounding environment.
Generator Protection System shall include but not limited to the following
o Stator Differential
o Loss of excitation/ over excitation
o Over/under voltage
o Over/ under frequency
o Directional power
o Stator earth fault (100% cover)
o Over-current
o Rate of change of frequency
o Over-fluxing
o Stator winding temperature alarm and trip
o Synchro-check
These shall be wired back to the control room and shall alarm on high temperature.
A suitable neutral earthing system shall be provided for the generator may be resistors or
neutral grounding transformer.
The alternator is painted and Final series test report according to manufacturer's standard
is included.
The connections between the generator and the generator circuit breaker shall comprise of
suitably rated sized medium voltage TR-XLPE cable / bus duct.
Power Transformer shall be suitable for outdoor installation, On-load tap changer, oil as a
cooling medium and ONAN /ONAF cooling rate equipped with effective control to
changeover from ONAN to ONAF with increasing load. The capacity of any cooling system
shall be such that the transformer can be operated at rated load. The maximum hot spot
temperature under all Site and operational conditions shall be 98 oC. The transformer shall
have an on-load tap changer with the tapping range selected to meet the voltage and
reactive power requirements of the network. Tap position shall be shown in the control
room. The tap changer shall be provided with both automatic and manual control facilities.
The tap changer shall be fitted with a position indicator and an operation counter that can
be read at the transformer.
The Facility shall include three of medium voltage buses where 2 nos generators shall be
connected to each bus, and 1 nos turbine generator shall be connected to one of the three
buses. Output from each bus shall include a main three phase transformer for each
generator, together with all protection, busbars and disconnectors where required. These
main transformers shall be type for stepping up the voltage from 11 KV to 132 KV &
equipped with on-load tap changers and shall be of ONAN or ONAF type rated for the full
continuous net output of the generators with sufficient margin.
The transformer quantity shall be three and ONAF rating shall be of based on power
available for export of each transformer + maximum 15% design margin at Minimum Heat
Rate Mode (The mode at Engine Heat Rate will be minimum when the Engine Power
Output will be18.522MW) or + maximum 5% design margin at Maximum Output Mode (The
mode at Engine Power Output will be maximum i.e. 20.683MW). ONAN rating shall be of
minimum 20-25% less of ONAF rating.
The transformers shall be of non-redundant and none of the transformer shall run in parallel
operation and rating to be calculated in a condition so that maximum of two engine
generators shall be connected to each of the transformer, in addition with the two engine
generators, one steam turbine generator shall be connected to one (pre-defined)
transformer to limit allowable system fault level.
As a minimum requirement, the transformer shall be provided with the following auxiliary
equipment:
o Buchholz Relays alarm and protection trips;
o Oil level and Temperature indicator and alarm;
o Pressure relief device(s) for main tank and Tap-changer tank if separate to the main
tank;
o Winding temperature indicators, alarms and protection trips;
o On-line condition monitoring equipment - Oil & Winding temperature (local monitoring),
Alarm & Trip signal, Buchholz Alarm & Trip signal, Oil level low, Pressure relief device
operated
o Oil sampling valves;
o Differential, Restricted Earth fault , Standby earth fault, over flux protections shall be
included
o with other protections;
o HV and LV bushings;
o Dehydrating breather for Main Tank and OLTC tank;
o Marshaling and control cubicle;
o Lifting , Jacking lugs;
o Earthing Terminals;
o Rating and terminal marking plates.
o Transformer vector group preferably YNd1
Dry type transformers shall be of the vacuum cast resin distribution transformer type with at
least Class F insulation mounted in vertical cubicles for use indoors in clean dry areas with
all safety interlocking and protections.
Three of station auxiliary transformers shall be ONAN cooled if located outside, or resin
type design if situated inside the buildings. Nominal no load ratio of delta star connection
shall be 11 KV to 0.415 KV. The connection shall be arrangement in vector symbol Dyn11
according to IEC 764 and neutral of star connected low tension winding shall be earthed
solidly.
The off load tap changer shall be provided on the high tension winding, and their ratio shall
be as follows: 11 kV ± 2.50 % with 4 step 0.415 kV Output.
The transformer quantity shall be three and rating shall be of as required based on
plant running auxiliaries at normal conditions + maximum 10% design margin for
future load & shall be of non-redundant.
Manual synchronizing facilities, with such check facilities shall be provided as a minimum
for all circuits except for station/service transformer circuits.
The Facility shall be provided with a central on-site control room (CCR) so that operators
can control the generators and perform switching and load dispatch duties.
Indoor medium voltage switchgear shall be rated maximum short circuit fault level 50kA for
1 sec which will be confirmed after final fault level study considering none of the Power
Transformer or Auxiliaries Transformer parallel operation and maximum two engine
generators connected to each power transformer / bus, System gird fault level shall be
considered 31.5kA for 1 sec during the study.
Outdoor high voltage switchgear shall be rated maximum short circuit fault level 40kA for 1
sec.
The Company shall provide the following tele-control facilities required at the
LDC:
- Control of the 132 kV circuit switches.
- Indications of 132 kV switches and trip relays activated.
- Measurement of 132 kV circuit MW, MVAR, and voltage quantities.
- Alarm facilities in the event of any 132 kV circuit tripping and protection-operated and
communication equipment failure.
The Metering System to be installed at the Facility shall include one set tariff metering and
indicative metering.
The measurements, which are used for calculation of the main tariff metered energy, are
taken at the high voltage side of the plant net power outgoing point. This accurately reflects
the actual energy transmitted from the Facility power plant to the BPDB grid. The tariff will
measure the net energy production of the plant/facility. Back-Up Metering System shall also
be of the same type and identical to the Metering System.
Sufficient indicative metering facilities will be installed to allow efficient normal operating
and maintenance procedures and automatic control functions to be conducted at the
Facility. The metering shall be logged by the Facility‟s DCS/SCADA.
D.18 Switchyard
Provision and installation of all control and signal cables between the switchyard and the
Facility shall be responsibility of the Contractor. An interface panel shall be provided within
the switchyard control facility for receiving the signals from PGCB grid control. It shall be
responsibility of the Contractor to lay and terminate these cables at the interface panel.
All 132kV circuit breakers and disconnect switches shall be capable of being electrically
controlled from the three control positions as follows:
The Contractor shall provide all the necessary control-selector switches, position indicating
contacts, and interposing relays.
The controllers shall communicate with each other and the Human Machine Interface (HMI)
part of the SCADA to send/receive data, command and feedback. Provision for necessary
communication with NLDC / PGCB shall be provided as per requirements.
The SCADA HMI shall be located in the CCR and shall provide a fully integrated control,
monitoring and alarm facility to the plant operator with a view to optimize the visibility and
controllability of the process and minimize operator manning levels.
The high level plant management sub-systems of the SCADA such as the plant historian
and condition/performance monitoring systems shall interface with the SCADA
communication network to extract the plant data. These sub-systems shall communicate
with the SCADA in such a way that the real time operation of the SCADA is unaffected.
External third party control systems (e.g. substation monitoring system) shall be interfaced
The HMI workstations shall be based on an Operating System (OS) which is rugged, user-
friendly and has been field-proven for continuous use in industrial applications. All CCR
The HMI application software shall be fully developed when installed at site and tested
rigorously during plant commissioning. This shall include graphic displays, function group
sequence displays, tabular displays, diagnostic displays, databases, alarms, trends and
reports to operate and manage the power plant in a safe and efficient manner. Software
licenses for unrestricted use by the Owner shall be supplied upon completion of defect
liability period for the HMI operating system, its application software and associated tools.
The main or highest level DCS/SCADA screen (mimic) shall represent, in as simple a
manner as possible, the entire plant and give the operator the main control parameters,
such as power out, fuel flow, fuel pressure, terminal volts, etc. It shall be possible to reach
any sub-system screen from the main screen by following as few links as possible. The
navigation facility provided shall be simple and unambiguous to the plant operator.
There shall be several levels of priority assignable to the plant and system generated
alarms. All alarms shall be displayed on the alarm screen of the HMI, logged in
chronological order and stored for future analysis. . The occurrence of an alarm shall initiate
a visual and audible warning on the operator workstation. Alarms shall be printed on
demand.
E.11 Reports
The DCS/SCADA shall be programmed before hand-over to produce reports on the
operation and performance of the plant for use by the Owner management ..
The control, monitoring and protection systems of the engine and generator shall be
interfaced to the DCS/SCADA via data communication links. This interface shall allow the
DCS/SCADA HMI to carry out high level control and supervision of the engine and
generator systems remotely from the CCR which is the normal point of control.
The power supply for the C&I systems shall be from a secure source (dedicated UPS ac
system or battery dc system).
E.14 Metering
Fuel and electrical power metering shall be provided to monitor the performance of the
power plant. Fuel metering shall include fuel flow to each engine (flow meter preferred) and
the total flow to the station for each type of fuel and shall include instantaneous and
cumulative values.
E.17 Instrumentation
All transmitters shall have internals and fittings of a corrosion resistant material suitable for
the medium being measured.
The Contractor shall include in his scope of supply a typical system with sufficient initial
installed capacity for a similar power station. The system supplied shall be expandable in
the future to increase the capacity by 25% as a minimum.
The PABX system shall be powered by a UPS or battery system with a stand-alone
capacity of at least 4 hours when the exchange has been fully extended. When a battery
system is used to power the PABX, the dc power supply shall consist of two independent
battery chargers.
Administration LAN
A Local Area Network (LAN) for the administrative functions of the power plant shall be
provided by the Contractor. For this purpose, cabling suitable for a fast Ethernet computer
network shall be provided to cover all offices.
Individually screened pairs or overall screened multicore cables shall be provided where it
is necessary to provide immunity from electro-magnetic interference. The screened cable
shall be of without armor. No conductor smaller than 1 mm2 shall be used for
interconnecting cabling except in the case of telephone type cables where conductors of
section not less than 0.6 mm2 may be used. . C&I cables of less than 1 mm2 cross-section
shall be subject to approval by the Owner or approval will be waived if recommends by
OEM.
Where twin or quad make-up is required in any cable, the cores shall be uniformly twisted
and the lays arranged such that cross-talk is reduced to a minimum. Cable cores, twins,
quads and individually screened multi-pairs shall be color coded. Each core of a multi-core
cable shall be readily identified by a number impressed into the insulation every 5000 mm.
All multi-core control cables (over 2 cores) shall have approximately 5% spare. Multi-core
pilot cables shall have copper/aluminum conductors, thermoplastic insulation, thermoplastic
inner sheath, armor and thermoplastic sheath overall.
Foundation for the rotating or reciprocating plant shall be designed to ensure that the elastic
strains within the plant shall be uniform within the limits prescribed by the plant
manufacturers.
All the structures shall be designed to facilitate erection according to the Contractor’s
proposed erection sequences and they shall also be designed to remain stable at all stages
during erection. If necessary, suitable temporary bracings or supports shall be designed
and provided. The dimension of the building shall provide adequate space for the safe
installation and proper operation and maintenance of all plant and equipment.
The design shall take account of the function of the works, the local environment, high
humidity conditions. Measure shall be included in the design to minimize the effects of the
aggressive conditions, and durable material shall be used to ensure a safe functional and
durable facility. All elements shall be designed to minimize maintenance and the design
shall facilitate the repair, maintenance and replacement of elements when necessary.
Building members shall provide a continuous path to earth and the reinforcement within
concrete sections shall be linked together to form a continuous path and ground to the
station earthing system.
All buildings shall be designed to ensure that noise, vibration and temperature levels are
kept within the stipulated limits as applicable following OSHA standard. Building envelopes,
window and doors shall be designed to be waterproof and give adequate protection from
solar gain and glare and to minimize the entry of dust. Where necessary window and door
shall be provided with fly screens.
Rooms containing hazardous or electrical equipment shall be fitted with two access door.
One doorway should be suitable for moving the largest item of equipment in and out of the
room, the other shall comprise an alternative means of escape via emergency exit doors
fitted with emergency exit devices inoperable from the outside. Emergency exit door shall
open outwards. All room area and compounds containing equipment liable to fire or
explosion shall be designed to safeguard personnel and minimize the effects.
The building wall cladding shall be installed above a RCC/Brick wall approximately one to
three meter high.
An intermediate operating floor, raised above ground floor level shall be provided to give
access to the steam turbine. Overhead travelling crane(s) shall be provided to facilitate the
servicing of each turbine and engine. Access into engine/steam turbine hall shall be through
doorways of sufficient size to conduct maintenance work and for general activity.
Around the transformer base a containment basin laid to falls and filled with single mixed
pebbles shall be designed to collect oil spillage, rainwater and the firefighting flows.
Table 1
(a) For the purposes of this Schedule, Start Up of the Facility is classified as follows:
(i) “Hot Start” - A start following a continuous shutdown of engine for a period of 8
hours or less and the engine is in Stand-by mode, the engine is preheated and pre
lubricated as per MAN guideline, auxiliary boiler will provide steam for engine
auxiliaries.
(ii) “Cold Start” - A start following a continuous shutdown of engine for a period more
than 48 hours, max standstill time for engine without slow turn <12 hr and auxiliary
boiler will provide steam for the engine and auxiliaries.
(b) The notice required to synchronize the engine generator for a Hot Start shall
apply provided the previous shutdown was not the result of a trip.
(c) For the purpose of this Schedule, a Start-Up shall be deemed to have occurred
upon synchronization of each engine generator to the Grid System.
(a) Facility load percentages in this Schedule refer to the load as a percentage of
Dependable Capacity.
(b) Step changes in Dispatch load are allowable, provided that the Facility load is greater
than 30% of Dependable Capacity as adjusted to Reference Conditions, but in no case
can such step change result in operation of the Facility below 30% of Dependable
Capacity. After such a step change the Facility load must be held constant for at least
30 minutes for stabilization purposes. Load ramping rates for such step changes in
Dispatch load shall follow the manufactures recommended load ramping rate(s).
(c) The Facility minimum continuous loading shall be the 3 0 % of the Facility‟s
Dependable Capacity, when the Facility is in operation. Beyond that the load of the
Facility may be reduce to zero in accordance with the Dispatch Instruction received
from the Control Center. The Facility shall be capable of automatic operation and
control from the Dependable Capacity to 30% of the Dependable Capacity and
frequent start and stop.
The Facility shall be equipped with black start capabilities.
For the purposes of this Schedule, Start Up of the steam turbine Facility is classified as
follows:
(i) “Hot Start” - A start following a continuous shutdown of steam turbine for a period of 12
hours or less and engines are running on 100% load.
(ii) “Cold Start” - A start following a continuous shutdown of steam turbine for a period more
than 12 hours and engines are running on 100% load.
Note: Stream Turbine shall be shut down if plant load factor is less than 30%
Figure 1 show that the maximum continuous engine output is ensured at a mains grid
frequency exceeding up to max. +4%, whereas at a frequency drop to max. -5%, the power
output is continuously reduced to 96% MCR. We permit operation of the engines up to +5%
frequency fluctuations for maximum 120 seconds. In any case, the maximum permissible
mains grid frequency deviation is ±5%. In grid parallel operation, the frequency of the grid
varies according to the current consumer load and the input from power suppliers.
H.1.1 Cranes
An overhead travelling crane shall be provided in order to lift and transfer major items of
plant within power house building. The crane shall be designed to lift the heaviest
component required to be lifted during maintenance (Engine hall cranes capacity shall be
as per MAN advice), including for major maintenance and overhaul activities on the engines
and generators. The crane shall be provided with an auxiliary hoist. The Contractor shall
give consideration to the requirement to lift and remove all pumps, compressors, motors,
major valves and other associated equipment, which may require removal for maintenance
and shall design and install suitable means for doing so. An overhead travelling crane of not
less than two tons capacity shall be provided in the workshop building.
All cranes shall comply with the requirements of ANSI or BS/EN, or other international
standards, and shall be tested and certified prior to being put into service. All cranes shall
be controlled with wire /wireless pendant push button unit. Each crane's hoist and controller
shall have two speeds. The trolleys shall have three speeds: creep, slow, and medium.
Speeds shall be in each direction. All crane motors shall have reverse phase protection,
jogging and plugging controls for precision work and soft start/soft stop capability.
Miscellaneous
Contractor to provide following items for ease of plant operation:
1) Workshop with Equipment (as per Appendix-2 & Appendix-3)
2) Tools for General & Special Maintenance (as per Appendix-2 & Appendix-3)
3) Chemical Lab testing equipment.
4) Cleaning bay
5) Fuel Unloading Shed (open type)
Adequate escape routes shall be provided for all personnel working in buildings; in
accordance with NFPA. The escape routes shall be clearly marked and provided with
All area where fire wall required should meet the NFPA requirement. All firefighting power
and control cables shall be laid in separate cable trays and shall be fire retardant.
The Contractor shall provide the drawings depicting Evacuation Routes/Escape Routes and
Fire Exit Doors, emergency exit door for all areas, all floors and all buildings supplied under
the Contract. .
The fire detector system elements and the associated sockets will be provided with sturdy,
corrosion-proof plastic housings and are to remain fully effective at 59% relative humidity,
40°C ambient temperature and severe dust conditions. The smoke/heat detectors, manual
call points/pull stations and fire alarm horns/bells shall be of the addressable type and
suitable for the specific areas where they are installed. The health of the detectors, panels
and other field devices shall be checked at regular intervals. The design of the system shall
be such that a malfunction in any of the zones or loops does not affect the normal operation
of the rest of the system.
The fire detection and alarm system shall be interfaced to the DCS/SCADA to enable the
summary alarms and system status information to be displayed on the operator
workstations.
The firefighting system shall be interfaced to allow automatic shut down of the forced
ventilation in the event of a fire. Operation of a manual alarm call point or activation of an
automatic detector shall cause an evacuation alarm in the building of origin. An early
warning smoke detection system shall be provided to cover the engine building, CCR,
control and electrical equipment rooms as a minimum requirement. Offices, workshops,
stores and other such areas shall be protected by firefighting system as per BNBC code.
Hydrants shall be spaced near roadways at 200 to 300 feet intervals, as per NFPA 850.
Multiple flow paths shall be provided in the loop piping so that if one pipe fails, another pipe
can supply sufficient firewater to other outlets. Sectionalizing post indicator valves shall
enable isolation of any failed section. Hose connections at hydrants shall be compatible
with the local fire department's firefighting equipment.
I. Project Management
The management of the project shall be under the direction of the Project Manager who
shall be in charge of all aspects of the project. The Project Manager shall be in direct
contact with Owner and shall report to the Contractor's corporate management. His or her
responsibility and authority for the project shall be limited only by terms of the Agreement,
by company policies, and by directives from management. The principal functions of the
Project Manager throughout the course of the project can be summarized as follows: