Module Facing True south
Space available More then 1500 Sq.Ft./KW (Approx)
Type of Roof RCC / Tin Shed / Ground
Solar Unit Generation per day (4.0 - Yearly average) 3 to 5.5 Unit/Per KW / Perday
Proposed Technology
The Proposed solar photovoltaic power plant shall be consisting of crystalline solar
module with fixed tilt Angle mounting systems and the Solar Inverter shall be grid tied.
Poly Crystalline
1 Solar PV Module Modules (Nos 330W/24V Suncity Solar
confirming to relevant Module (25 Years 45
IEC standards) Performance Warranty )
Inverter with associated
control and protection
devices integrated to Luminous On grid Inverter
2 Solar Inverter 1 NOS
convert DC Power into with GPS 15 KW
3Phase AC voltages,
along with on grid
synchronizing facility.
Aluminum and GI (80
Module As per Design
Microns). All structures
3 Mounting Structure APOLLO
are designed for local
Structure 50mmX50mm and
wind (150Km/hr
40mmX40mm
maximum speeds) and
weather conditions.
MCCB/MCB
Cost and Viability of Complete Roof Top Solar Power 15 KW Plant (Suncity)
Total Cost in Rs. INR 6,43,524/-
GST ( 5%) 32,176/-
Grand Total with GST 6,75,700/-
1 Electricity Saving 1600 Units Per Year 24,000 Unit Per year 6,00,000
CO² Emission
2 Reduce 1.825 Ton Per Year 27.375 ton Per Year 684.375 Ton
3 Trees Saving 7 Trees Save per Year 105 trees per year 2625 Trees
(Manoj Purohit)
General Manager
Terms & Conditions
1 Payment Terms 40% against release of order 60% before Dispatch of Material
PV Modules -25 years Warranty on power Output (90% of the rated power is
guaranteed over a period of 10 years and 80% of the rated power is guaranteed
2 Warranty over a period of 25 years ). (Degradation 0.5% to 1% per year)
Inverter --5 Year System warranty except natural calamities.
Deleivery & Installation 30-45 Days from the Date of Receipt of technically & Commercially clear order
3
Schedule and Advance Payment
4 Validity of Offer 15 Days from the date of offer. After this period a confirmation has to be taken.
A. Cost of Super Structure (High Rise ) as per customer choice (If any ) shall be
borne by customer.
6 Exclusion B. This offer is valid for normal side conditions.
C. Any extra length of cable (If more than 90 feet)
D. Transportation cost will be extra if more than 30 KM of Jodhpur city radius.
If at any stage during the period of contract the performance of any obligations
under the contract is prevented or delayed whollaly or partaly be reasons of war,
hostility,fire,floods,lightning,epidemics,sabotages, guarantee,restrictions or other
acts of God ,Government or Law (herin after referred to as eventuates ) then a
notice of the happening of any such eventuality will be given with in 7 days from
7 Force Majeure
the Date of occurence of any such eventuality in such case neither party nor shall
any claim to be made for damages against the order in respect of such non
performance or delay and the performance and deleveries of the contract will be
resumed as soon as practicable after such eventualityhas come to an end or
ceased to exit.