INSPECTION REPORT

SPVD 2014/29/EU module C –internal production control

Notified Body 2287 File Nr: GNS-SP-C-TOB-01

PROJECT : Manufacturing of Air Tanks Ref (Project) : / IDD.TR.3389929.18.D11.Rev01


Applicant (BV Client) : Gensa Basinç Tanklari İmalat ve Bombe San.Tic.Ltd.Şti.
Manufacturer (Name and address): Ostim Osb Mah. 1208. Cad. No:8/A Yenimahalle/Ankara
Place and date of inspection : Gensa Workshop & 02/01/2019
Bureau Veritas local office: Istanbul

Quantity
Type and scope of inspection : SPVD Module C (conformity to type based on internal production 3
control)
-

TECHNICAL DOCUMENTS
TITLE Reference nr Rev. Date
Standard: EN 286-1 2009 28.04.2009
Welding qualifications: EN 9606-1 2017 18.12.2017
Other documents: EN 15614-1 2017 18.12.2017

CONCLUSIONS
The vessel(s) object of inspection on Air Tanks Model no: G10-10, G10-15, G10-16 is compliant with
applicable requirements.
NEXT VISIT SCHEDULED ON : 02.07.2019

Inspected by :

T.Oğulhan Bardakçı

Date : 02.01.2019

Diffusion : BV Local BV Office Client Total nb of pages

PV252-TR - C Inspection Report Rev0 1/4 September 2016


INSPECTION REPORT
SPVD 2014/29/EU module C –internal production control

Notified Body 2287 File Nr: GNS-SP-C-TOB-01

List of open points (inspection on vessel, documentary review).


Products / Tasks / Points / Operations / Examined documents and results
Date of Examination performed according to requirements listed in previous Decision (*)
report Numbering of finding
(****) (**) page
Cross out the closed findings, do not remove them

(*) Results :
C = Conform / NC = Not Conform (**)
ABS = absent (or incomplete)(**)(***)
NA = Not applicable

(**) Give details about the different findings


(***): Indicate clearly if some information is missing to conclude

PV252-TR - C Inspection Report Rev0 2/4 September 2016


INSPECTION REPORT
SPVD 2014/29/EU module C –internal production control

Notified Body 2287 File Nr: GNS-SP-C-TOB-01

A – Technical documentation of the manufacturer


Title of Document (****) Finding nr
Ref nr Rev./Date Decision (*)
(**)
WPQ, PQR (consistency with type approval)
PQR no: GEN- - C
PQR-005

PQR no: GEN-


PQR-003

PQR no: GEN-


PQR-004

PQR no: GEN-


PQR-006

PQR no: ANK-09-


B-016

PQR no: ANK-09-


B-017

PQR no: GNSA-


PQR-16-002

16-IS-0225-TAT-
17-WLD-0158

16-IS-0225-TAT-
17-WLD-0159

16-IS-0225-TAT-
17-WLD-0162

16-IS-0225-TAT-
17-WLD-0335

16-IS-0225-TAT-
17-WLD-0163

16-IS-0225-TAT-
16-WLD-0337

16-IS-0225-TAT-
16-WLD-0336
Main materials : Malzeme Boru-
- same grade than in type approval file - C
Sertifikası No:
- certificates 3.1 or 3.2
P265GH Sert No:
730/0534519

P265GH Sert No:


20170063463-00

incelendi
Filler materials (for welding): GEKA SG2: Cert no:
- same grade than in type approval file 08324681318,
- C
- certificates 2.2 18/381383170,
18/412047019
incelendi.

PV252-TR - C Inspection Report Rev0 3/4 September 2016


INSPECTION REPORT
SPVD 2014/29/EU module C –internal production control

Notified Body 2287 File Nr: GNS-SP-C-TOB-01

Report on examination and tests performed: Hidrostatik Test


-testing program is available and appropriate C
Raporu
-testing program has been respected
-exams and tests are dully recorded
-results are compliant with criteria İmalat Ölçü Kontrol
Formu incelendi

EU type examination is available SP – GNS01 – B – REV.0


- Vessels are included in the scope of the type AB – 19 – TUR C
approval

A document describing the manufacturing


processes which includes :
a) a description of the means of manufacture and İmalat Prosedürü REV.0 C
checking (review procedures, technical P.47
worksheets, organization notes, organogram…)
b) an inspection document describing the ITP No: GNS-ITP- REV.0 C
appropriate examinations and tests to be carried 001
out during manufacture (review new process,
sub-contracting…)
c) an undertaking to carry out the examinations Basinç Testi REV.0 C
and tests in accordance with the inspection Talimatı
document and to have a hydrostatic test (or T.44
pneumatic test if agreed by Member State)
The addresses of the places of manufacture
and storage are well defined C

Other documents submitted


Application form which includes the unicity of the
GNS-SPVD-001 C
request (no other NoBo can be requested)
Project of EU Declaration of conformity (check
SPVD Decleration C
NoBo name & address, scope) of Comformity
Instruction notice (review availability only)
Kullanma Klavuzu C
Manufacturing file (results of examination and tests +
Hidrostatik Test C
hydraulic test)
Review the list of serial numbers Raporu
Make sure the batch are made of max 300 vessels

İmalat Ölçü Kontrol


Formu
Mandate if any
N/A

This part shall be completed before the starting of production

PV252-TR - C Inspection Report Rev0 4/4 September 2016