Professional Documents
Culture Documents
TECHNICAL MANUAL
The following Technical Manual provides details of our Light Gauge Steel Framing system
specifically developed for the residential, hotel, care and student accommodation sectors.
The system has been fully assessed by the SCI and NHBC for structural designs up to 15 storeys
in accordance with BS EN 1993-1-3.
2.8 / Roofs 21
2.9 / Lifts 22 5. STANDARD DETAILS 39
2.9.1 / Lift Design Requirements 22
Detail Contents 39
2.10 / Stairs 23
Standard Details 40–74
2.10.1 / Basics 23–24
2.10.2/ Single Flight Arrangements 24
2.10.3 / Double Flight Arrangements 25
2.10.4 / Other Stair Arrangements 25
2.10.5 / Stair Attachment 26–27
2.10.6 / Hand Rails & Balustrades 27
MetStructures profiles are 1.2mm to Load bearing light gauge steel framing
3.2mm in gauge, roll formed from is based on balloon construction
pre-coated galvanised coil. Sections providing separate storey height
are factory assembled into load frames. Vertical gravity loads from
Wall
bearing wall panels consisting of a roof and floors span onto load
‘U’ base track and ‘C’ vertical studs bearing walls down to supporting
set at regular centres with ledgers foundations or podia. Lateral Floor/
at head to suit the application. The wind loads applied to the external Roof
MetStructures system can be used to envelope are taken by roofs and floors
form structures up to a maximum of using plate action, then into braced Wall
fifteen storeys in height dependent walls or cores down to the supporting
upon loading, geometry and usage. foundation or podium. Figure 1.
Principles
of Balloon
Construction
Once the floor has adequately cured, construction of The roof may also be formed from composite concrete
the next level begins and loading out of the floor decking but can alternatively employ timber or light steel
with plasterboard / bathroom pods, etc. takes place. frame trusses or joists. In all instances, floors and roofs are
to provide adequate diaphragmatic resistance to distribute
Where joisted cassette floors are used they are formed in the lateral loads back to the buttressing side wall bracing
factory from deeper ‘C’ sections at regular centres with ‘U’ systems.
profile end tracks and noggins as required to prevent twist
and lateral movement. A working platform of minimum
18mm OSB is provided. The joists are designed with pinned
end connections and effective lengths dependent
upon the restraints available from
finishes and noggins.
The system’s application is currently limited to an absolute When such items are to be built in a cold frame environment
maximum of fifteen storeys. Depending on the structural (uninsulated or exposed to possible water ingress), special
requirements and building type, lower limits may be considerations such as additional protective coatings may
applicable. Additionally, as a building product, elements of be required and the lifetime of the construction reduced
the framing system can be used for special constructions in accordance with the guidance given by the SCI P262
such as features, bulkheads and soffits. document (The Steel Construction Institute, 2009),
BS EN ISO 12944-2:1998 (BSI, 1998) and
BS EN ISO 9223:2012 (BSI, 2012).
External insulation
Figure 5.
Indicative warm frame wall build-up
06 | www.metstructures.uk.com | 0121 389 1603
1 | SYSTEM PRINCIPLES & ADVANTAGES
1.3.1 / The cold rolled sections in To achieve this and to keep the Where the steel is installed in a cold
Continued the stud and track system are frame warm as well as avoiding cold frame environment (low risk of water
galvanised with 20μm zinc bridging, insulation is applied to the ingress, some risk of condensation),
coating. Its intended use is external face of the steel. The amount this reduces to 50-60 years.
of insulation that is applied to the See extract on following page from
to be within a ‘warm frame
outside of the frame is dependent SCI Publication P262 (The Steel
environment’, i.e. the steel is to on the U-Value that is required to be Construction Institute, 2009).
always be fully enclosed within achieved and designed to avoid the
the warm envelope of the façade. risk of interstitial condensation (to
architect’s specification). Assuming
the steel is maintained within a warm
frame environment, current industry
guidance is that a design life of 250
years can be expected (The Steel
Construction Institute, 2009).
Walls and floors in warm frame applications No risk of water ingress or condensation 250 years
Warm internal environment
Non-load bearing stud partitions 250 years
and no risk of water ingress
Infill external walls in multi-storey buildings Warm frame and no risk of water ingress 250 years
Roof structures (insulated) Low risk of condensation 200 years
Suspended ground floors Low risk of water ingress;
100 years
(with over-site membrane) some risk of condensation
Roof structures (uninsulated) Some risk of condensation 100 years
Purlins and side rails Low risk of condensation;
60 years
supporting metal cladding some dust and pollution
Low risk of water ingress;
Sub-frames to over-cladding panels 60 years
some risk of condensation
Suspended ground floors Low risk of water ingress;
50 years
(without over-site membrane) higher risk of condensation
Note: All values are for Z275 Figure 6. Extract from P262
(total weight of zinc coating on both surface = 275g/m2) - Durability of Light Steel Framing
The BRE Report “Thermal Insulation: continue 150mm below the base may be required to ensure the
Avoiding Risks” (BRE REP 262, 2002) rail of the steel wall to minimize longevity of the steel.
discusses aspects of insulations thermal bridging. Insulation with
relevant to external light steel frame an integral facing on one side only, Openings for windows, doors, flues,
walls. A vapour control layer should e.g. a foil facing, should have the vents, etc. are formed by design
be provided unless a condensation facing on the cavity side. The facing within the framed panels and the
risk analysis is carried out. This should not be used as the vapour weights, position and connections
should be fixed on the warm side control layer. Service pipes, conduits, are considered in the structural
of the wall insulation and should etc. within walls should be on the calculations and drawings.
cover the external wall including warm side of the insulation. Design
The system adheres to the principles
base rails, head rails, studs and lintel and specification of the wall build-
of Rapid Dry Envelope (RDE) where
and cill reveals. The vapour control up beyond the steel frame is the
the building is made watertight
layer should be of 500g polyethylene responsibility of the architect or other
quickly and to a high standard to
or vapour control plasterboard as nominated specialist. In applications
release works on site for internal
recommended in the NHBC 6.10 -D6 where the steel is not in a warm frame
trades.
(NHBC, 2018). Insulation should construction, special considerations
As cold formed steel members are non-combustible The requirements for fire protection vary by project
but have no significant inherent fire resistance they and by application of the system. The client team
are dependent on the through-wall components to must determine the requirements in line with
provide the structure’s fire protection. applicable regulations.
Fire resistance of light gauge steel resistance to relevant codes of to be fire protected to achieve the
systems is provided by single or practice. Typically, over 90 minutes’ required rating.
multiple layers of boarding fixed resistance may be achieved for each
to the flange of the studs or joists element using multiple layers of Cavity stopping systems should also
This may be either fixed directly 15mm boards. be employed as required by the
or via secondary resilient bars. relevant building regulations.
Manufacturers of such boarding Fire resistance of the composite
concrete deck floor is provided Further details may be sought from
systems have tested their boards
by reinforcing the concrete with SCI Technical Information Sheet
to protect light steel frame systems
adequate cover. Supporting channels ED016 (The Steel Construction
for insulation, integrity and load
at the head of the walls also need Institute, 2012).
Part E of the building regulations defines the Acoustic performance must additionally satisfy
minimum requirements for floors and walls that any regional guidance and suitability requirements
separate one dwelling from another, between which must be defined by the design team at the
internal walls and floors from another dwelling or start of the project.
communal space.
Approved •T
he use of ‘Robust Details’ (Robust Details Ltd, 2014)
This method relies on specific defined build-ups provided by Robust details to
document E
demonstrate compliance based on known combinations.
describes two
methods of •P
re-completion testing
This method tests elements of the building on site (such as separation of walls and
demonstrating floors) prior to handover of the building to demonstrate a test compliance against
compliance: target values.
The MetStructures Framing Framed construction relies on The desired acoustic level can be
System standard details have been boarding performance as well as attained via the addition of layers of
developed with the guidance of the structural isolation to achieve a good board as well as some bespoke layers
Robust Details in mind however it acoustic performance. Between designed to satisfy only acoustic
is envisaged that pre-completion dwellings, this may be achieved issues such as resilient bars to reduce
testing will be required on all by using twin skin walls or other sound transfer, acoustic matt or
schemes. Additionally, the project enhanced wall constructions. specialist backing boxes.
acoustician should review all
details for compliance in advance of
construction.
1.3.3 / Composite concrete decks may either be designed with At junctions between compartments, flanking insulation must
Continued adequate thickness to meet minimum mass requirements be provided to prevent sound transfer through the cavity.
or with a requirement for an acoustic floor build-up to be Insulation provided 600mm above and below floors, and at
provided on top depending on the project requirements. either side of walls is good practice.
Inter-stud
insulation
by others
External sheathing board
External
insulation
Bricktie channel
Brickwork
by others Figure 7.
Flanking detail
across party wall
Progressive collapse
tie by design
Fire stop to
supporting
channel
by others
Inter-stud insulation
by others (above and
below ceiling line)
C Stud
Internal lining board
to provide suitable fire
protection by others
Ceiling by others
The following is presented as guidance only, the build ups shown are indicative and should be checked
with boarding suppliers’ data on a project specific basis by the principal designer.
Load-bearing walls:
dB Rating Wall build-up
60dB 2 x 12.5mm gypsum-based lining board on separate metal frames with quilt in cavity (i.e. twin party wall)
Table 3. Indicative wall build-up acoustic performances. SCI Technical Information Sheet ED015 (The Steel Construction Institute, 2012).
1.3.5 / CLADDING
All buildings are designed on a project-specific • Traditional Single Skin Facing Brick/Blockwork
basis for which detailed structural calculations and • Direct Applied and Cavity Insulated Render
drawings are produced. Systems
In all applications, the system is sheathed to the internal • Board Based Cladding Systems
face with plasterboard to the architect’s specification • Lightweight Metal Panels
and to the outside with factory applied sheathing board,
additional insulation boards are further site applied subject • Timber Cladding
to specification requirement. Façade treatments are • Insulated Panel Systems
considered and typically consist of but are not limited to: • Brick Slip Systems
The following details provide an illustration of the typical facade treatments which may be applied to the MetStructures
framing system. Further cladding finishes may be applied; for more information contact MetStructures.
Insulation
Concrete Floor
Intumescent
Cavity Fire Barrier
Blockwork
Lining boards
Brick tie
Insulation Insulation
Brickwork
Lining boards
& insulation
External Sheathing Board
Insulation
Intumescent Cavity
Fire Barrier
External Sheathing
Board
Fire Batt
External Sheathing
Board Lining Boards
& Insulation
Figure 12.
Breather Membrane Insulated Render
Ceiling Line
with Cavity
Insulation
Intumescent
Cavity Fire Barrier
Insulation
Intumescent Cavity
Fire Barrier
Lining Boards
& Insulation
Timber Cladding
Lining Boards
Insulation
Concrete Floor
Vertical Support Rail
Intumescent Cavity
Fire Barrier
Insulation
Lining Boards
& Insulation
Insulation
Lining Boards
Insulation
Concrete Floor
Vertical Support Rail
Intumescent Cavity
Fire Barrier
Lining Boards
Terracotta Cladding
Insulation
Concrete Floor
Vertical Support Rail
Intumescent Cavity
Fire Barrier
Insulation
Figure 17.
External Sheathing
Board Terracotta tile
Ceiling Line Rainscreen
Breather Membrane
• Student accommodation
• Light gauge steel frame with composite concrete and metal deck floor slabs
• Light gauge steel roof cassettes with OSB3 boarding
• Gross internal floor area 2740m2
Based on the architect’s drawings, Specific details can also be assessed stage to enable assessment of the
MetStructures will review the (e.g. architectural features) to develop groundworks requirements.
architectural intent for the building structural solutions which work with
and provide an indicative structural the system. The MetStructures team can attend
scheme to demonstrate how the design team meetings to assist with
building might be formed in the The scheme can then be quoted, the development of the frame design.
system. This will identify the required and the MetStructures site team can
load-bearing walls and column assess the logistics requirements.
locations etc and indicative sizing of Subject to agreement, foundation
key members. loads may be provided at this
Detailed design can commence once the architectural The construction issue intent drawings are then assessed
design has reached a frozen construction issue. At against any previous schemes to ensure any changes are
this point, the MetStructures team will allocate a captured and understood. A detailed engineering scheme is
dedicated project engineer and designer and a design then produced, and final foundation/podium gravity loads
commencement meeting to review the scheme and are calculated to enable the project engineer to complete
details should be arranged. This meeting should also be their designs. The MetStructures engineer will complete an
used to discuss phasing and build sequence. analysis for the scheme and design all structural members
in accordance with relevant design codes. Full calculations
are also produced which can be issued to building control or
It is critical to the success of the project to have nominated checking engineers. We will work with the design
adequate information to design the structure at team to ensure elements such as service routes, etc. are
accommodated where possible.
this stage – although the project may be weeks
from site, key decisions on the load paths and At the same time, the MetStructures design team begin work
structure of the building are made up-front producing an accurate and data-rich Building Information
which would be costly to change at later stages. Model (BIM). Once the engineer’s specifications have been
Information required includes sub-contractor included, general arrangement drawings are taken from the
packages such as the lift interfaces and curtain model and issued for design team approval.
wall support requirements. While the approval process is underway, the designers
continue to model all of the detailed connections of
each member and further enrich the model ready for
manufacture. Design team comments are then incorporated,
and construction GA’s are issued.
1.4.3 / MANUFACTURE
Working to the agreed build sequence wall panels, Each panel is thoroughly checked for dimensional accuracy,
accessories and any supplementary steelwork are correctness and quality before being signed off for delivery
manufactured and assembled within the MetStructures to the project site.
associated works.
1.4.4 / INSTALLATION
MetStructures work with the corner of the building. Wall panels are The walls are generally pre-boarded
main contractor’s site team placed, plumbed, temporary propped in the factory and therefore, by fitting
to ensure a successful build anchored into place and bolted to the windows, a weather-tight shell is
program. Tight site logistics can adjacent panels. Site fitted beams and provided to allow first fix of follow on
columns are bolted in to the adjacent trades while the upper floors are still
be catered for with just in time
columns and walls. Walls and beams being built.
deliveries, but it is preferable come pre-fitted with ledger angles for
to store panels and decking on the decking which is placed between The MetStructures engineer and
site. Craneage is required to lift elements and screwed into place. designer will visit site as required to
panels, beams, columns and Temporary propping is placed and ensure the structure is being built in
decking into place. fixed before reinforcement is then laid accordance with the design and any
as required. Once fully checked and site reports produced will be made
Once the slab has been checked to signed off, the slab can be poured. available to the client.
tolerance and handed over, the panel Once adequately cured, the next floor
erection begins with the perimeter can begin.
walls, generally working from one
1.4.5 / OPERATION & MAINTENANCE
The system requires minimal maintenance as Any damage to the frame should be reported to
long as it is enclosed within the warm frame of MetStructures immediately for structural assessment to
the building. ensure a safe structure. This includes fire damage.
0 STRATEGIC
MetStructures operate a typical 12-14 week
DEFINITION preconstruction period, though lead times for
design, supply and installation vary from project
to project and are dependent on both size and
1 PREPARATION
AND BRIEF
complexity. The following programme example
based on the RIBA plan of work is given for
typical guidance only and should not be read
or used as a project specific programme.
2 CONCEPT
DESIGN
ARCHITECT
PROJECT ENGINEER
MAIN CONTRACTOR
3 DEVELOPED
DESIGN
Design Support
• Load Path Checks
Estimating
• Pricing
2–4
• Foundation Loads • Outline Programme
• Span Checks • Warranties WEEKS
4 TECHNICAL
DESIGN
• General Arrangements
• Lifts & Stairs
• Details
• Start on Site Dates
• Delivery Plan
• Panel Sequencing
8–12
• Sections • Follow on Trades
• Hot Rolled Steel WEEKS
• Structural Calculations
• CDM Compliance
• Approvals
5 CONSTRUCTION
Site Checks
• Foundation Checks VARIES
• Light Steel Framing Checks
6 HANDOVER
AND CLOSE
OUT O&M Manual
1–2
• Replacement
• Modification WEEKS
7 IN USE
2. SYSTEM OVERVIEW
DESIGN LIFE
2.1 / 2.2 / MAINTENANCE
With reference to the publication Maintenance of the framing system during
‘P262 Durability of Light Steel Framing in construction is possible with a visual inspection
Residential Building’ (The Steel Construction of the sections and it is highly recommended
Institute, 2009) and when the framing is fully that any water present on the sections during
insulated in a ‘Warm Frame Environment’, construction be fully removed before sheathing
the design life of the sections may be up to boards are applied.
250 years as long as water ingress is fully
Post construction inspections cannot normally be
prevented and the structure is correctly
done visually without damage to finishes and intrusive
maintained. inspections may not be appropriate during the life
The durability of zinc-based coatings is a function time of the building. However, it is recommended that
of duration of wetness and composition of the inspections of both the interior and exterior of the
atmosphere. When the structure is built to the building be made on an annual basis and as part of a
required standards, properly ventilated and wider building maintenance strategy with particular
maintained, moisture is not permitted to access the regard to any damage that may affect the integrity or
galvanised light gauge steel through either direct performance of the sections including but not limited to:
contact or humidity (interstitial condensation).
•C
racking of internal plasterboard or external finishes
The correct specification and application of
façade treatments, cavity ventilation/closing •D
amage to external finishes from impact that
products, vapour control and breather membranes, exposes the steel frame
plasterboards, insulation and thermal breaks mean •M
odifications to the building that expose or change
there should be no risk to the framing from contact the framing system
with any moisture that presents a risk to the integrity
of the zinc coating. •A
reas of water damage (particularly around gutters,
penetrations & down pipes)
• V isual staining
•E
vidence of rust
The steel framed structure can commence once If the accuracy of the ground floor slab or support
the foundation/podium slab is fully installed, the structure cannot be guaranteed within required
concrete has reached its required design strength, tolerances, then a ring beam should be installed
has been inspected and modified (if required) to an by others. See tolerance section 4.5.2.
acceptable line and level (refer to section 4.5) and
handed over by the slab design engineer.
2.6 / PANELS
The vertical studs are typically 100mm width, with Figure 18.
Panel erection
varying gauges depending upon loading conditions,
and placed at 300, 400 or 600mm centres.
Noggins at mid-span may also be a requirement to reduce
minor axis buckling. All the studs are tied together with
horizontal base and head members. Bracing straps are to be
fixed to certain wall panels to give racking resistance. Once
SSL
the ground floor walls have been positioned, plumbed,
propped and fixed, the flooring system can be installed and
will restrain the top of the walls.
Openings within the wall panels for windows and doors etc.
are formed by reinforcing the jamb studs as required (either
using stronger sections, ‘boxing’ with tracks or doubling up
on members) and providing stud and track arrangements
as lintels and cills.
FLOORS
2.7 /
2.8 / ROOFS
Typically, there are three types of roofing systems Once the top floor wall panels have been positioned,
used with the system – composite concrete deck, plumbed, propped and fixed the roof system can be
steel joisted and timber truss - each of which installed and will restrain the top of the walls. Where
are supported on internal and external walls design of roof trusses is provided by others, they must be
made aware that roof must provide a structural diaphragm
and/or beams.
between buttressing walls.
1100
frame will provide the shaft and lifting beam / lifting
Lift shafts are formed using standard load-bearing wall
slab (if applicable) and connection points for the
panels spanning floor to floor. On the door side(s), an
guide rail mechanisms. Fire protective boarding can opening for the door is provided which may include a PFC
Note: Toe board by 450
be factory applied locally behind the connection at head to provide a fixing point for the lift door mechanism.
others as required SSL
points for the guide rails.
Fire Mastic
P1001-B3 Unistrut
or similar approved
All designs for lift shafts rely • Setting out of and loading applied to guide rail attachment points
on early receipt of the lift • Setting out of and loading applied to lifting connections
manufacturer’s requirements.
• Required clear opening dimensions of the shaft
For standard counter-
balanced traction lifts, the key • Setting out of the door openings and door connection points
information required is: • Any requirements for the door threshold (cutting back of screed etc)
• Confirmation of deflection limit (onerous deflection requirements may be
accommodated)
For other types of lift, the requirements may vary and early dialogue between the
lift designer and MetStructures design team is critical.
In order to set out the studs, confirmation of the boarding requirements to the
inside of the shaft is also required from the architect.
2.10 / STAIRS
2.10.1 / BASICS
MetStructures can supply and fit steel, precast or timber stair units, Stairs may be in a variety of configurations
designed and supplied by specialists. The frame design will allow including single flight, double-flights
provision for stairs by means of clear openings and supporting with half landings or more complex
beams where required. arrangements with quarter landings etc.
Figure 22.
Typical stair
arrangements
Figure 23.
Wall stiffeners adjacent
to voids
Where stairs are supplied by others, the stair stair prior to pouring the slab may be preferable
designer must provide details of the loading which and should be discussed with the initial phasing
the stairs will apply back to the primary frame. requirements.
Detailing to avoid the requirement to install the
Figure 24.
Single flight stair
support arrangement
Support at
head and
base of flight
Support for
integral half
landing
Floor build up as
Fixing method for stair to trimmer specified by architect
beam to be confirmed by
stair manufacturer
Joisted cassette
by MetStructures
Figure 27.
Stair to joisted landing
Figure 28.
Stair to concrete landing
Inter-stud insulation
by others
Composite structural decking
with fibre reinforced concrete
Progressive collapse
tie by design
Profiled fire stop required Fire Reinforcement
& progressive collapse
50
required (by design)
Support by MetStructures
Fire stop to supporting bolted to flange of studs
channel
Note: Teks cut off by
others to allow fitting
of boards
150 (min)
If not within the MetStructures supply package, the contracted stair designer must
provide details of the loading which the stairs will apply back to the primary frame.
Beam
Studs
Beam
Post
Partial depth beam
connection
Beam
Connection by design
Figure 30.
Typical base detail for
pre-panelised column
The column should also be tied in to the floor, normally by use of the connection to
the supported beam.
Figure 32.
Beam with TOS = SSL
Where no finishes are available to Indicative beam depths can be provided as part of the design approval process in
hide the exposed elements, beams order to ensure adequate space for services. Where absolutely essential, service
may be lowered by 50mm in order slots may be able to be designed into the beam webs to allow passing of services
to run the concrete over. however this is a costly option and should be avoided if at all possible.
Where beams or columns are required outside of the lined zones, specific fire protection detailing may be required.
This may be achieved by either boarding or intumescent painting the hot-rolled steel elements.
2.12 / FINISHES
Once the structural frame, boarding, roof finishes, cedar, insulated panels and brick slip among others.
windows and doors have been installed the Masonry finishes are generally supported at podium or
envelope will be water-tight, so the services and foundation level and the frame provides lateral restraint
internal and external finishes can begin. only however, in certain instances, masonry may be
supported by project-specific agreement and design.
This removes the external cladding from the critical path.
A variety of external claddings can be applied to the Further information on finishes can be found in
system including masonry, render, terracotta rainscreen, section 1.3.4/ Cladding.
2.13 / SERVICES
The system can accommodate Joisted floors/roofs
service penetrations
Holes in the joist webs can be punched up to 60% of the joist depth.
throughout. General Vertical holes through floor panels can be trimmed out during the design process.
guidance on the size of such
penetrations is provided Wall Panels
below however each project’s Holes in the stud webs can be punched up to 60% of the web depth.
requirements are assessed at Penetrations for vent pipes etc. through wall panels can be accommodated early on in
the design stage. the design stage so the studs can be positioned to miss the penetrations.
F
D
3. STANDARD
COMPONENTS
3.1 / STANDARD COLD ROLLED SECTIONS
All MetStructures sections are manufactured using pre-hot dipped
galvanised steel strip S450 to BS EN 10346:2015 (BSI, 2009)with a
Z275 galvanised coating. Sections sizes vary and can be rolled to suit
customers’ requirements.
MC PROFILE RANGE
Flange
Web
Section Mass Web Flange Lip Gauge Section Mass Web Flange Lip Gauge
Reference (kg/m) (mm) (mm) (mm) Reference (kg/m) (mm) (mm) (mm)
Flange Web
Gauge Dim A
COLD ROLLED PARTS
MU OVERBENT
PROFILE RANGE
Flange
<9
00
<9
00
Web
Section Reference Web (mm) Flange (mm) Dim A Gauge Internal Radius
MU-10512 105 60 100 1.2 1
MA PROFILE RANGE
Web
MA-16012 2.62 161.2 90 40 1.2
MA-18012 2.62 181.2 70 40 1.2
MA-10032 5.37 102 90 40 3.2
MA-12032 5.37 122 70 40 3.2
Gauge
MA-16032 6.88 163.2 90 40 3.2
MA-18032 6.88 183.2 70 40 3.2
Flange A
An
gl
gl
An
e
Flange
Depth
e
An
gl
gl
An
Gauge
Section Reference Mass (kg/m) Web Flange (mm) Leg (mm) Gauge Depth
MT-15012 5.15 105 153.2 70 1.2 152
MT-16012 5.3 105 161.2 70 1.2 160
MT-18012 5.67 105 181.2 70 1.2 180
MT-20012 6.09 105 203.2 70 1.2 202
MT-25012 7.03 105 253.2 70 1.2 252
MT-15032 13.83 115 155.2 70 3.2 152
MT-16032 14.23 115 163.2 70 3.2 160
MT-18032 15.23 115 183.2 70 3.2 180
MT-20032 16.34 115 205.2 70 3.2 202
MT-25032 18.85 115 255.2 70 3.2 252
An accurate starting point is required for the the base track using galvanised steel shim packs for levelling
commencement of the frame. The acceptable purposes which may be subject to additional costs. The
tolerance for the foundation/podium (in the absence following guidance should be observed:
of further contractual agreement) shall be: •G
aps up to 10mm, steel shim packs should be used under
• F oundation level tolerance is +0mm / -6mm. each loadbearing stud.
• F or gaps between 10 - 20mm, steel shim packs installed
It is important that the foundation level, podium or ground under each stud as well as grouting with a high strength
beams are accurately measured before commencing non-shrink grout under the entire length of the base
installation of wall frames. This should be carried out by the channel.
client’s site engineer prior to handover and any deviation
in tolerance above the shimming levels agreed must be • F or gaps greater than 20mm, advice should be sought
remediated by the contractor by either ‘scabbling’ down the from the design engineer and remedial works to the base/
high points or grouting up the lows (to client’s engineer’s substructure will be required.
specification). Where hot rolled columns are connected to the slab, a
To accommodate the remaining site tolerances and avoid nominal 15mm under-height tolerance may be included to
excessive site cutting, wall panels can be packed underneath be fully shimmed and grouted by the contractor.
Installation tolerances are to be agreed with the main contractor prior to commencing
on site. The National Structural Steel Specification (BCSA, 2007) can be used as a
guidance but note this is written for hot rolled beam and column steel frames.
5. STANDARD
DETAILS
The following drawings give an abridged selection of the standard MetStructures
construction details. A full and comprehensive pack of standard details can be
obtained from MetStructures upon request.
DETAIL CONTENTS
MET-001 Base Connection Detail C Stud to U Track MET-030 Brick Support Detail
MET-002 Head Connection Detail C Stud to U Track MET-031 Internal Wall Built off Concrete Single & Twin
MET-005 Parapet Detail Concrete Roof MET-035 Twin Internal Wall to Joisted Cassette Floor
MET-006 Parapet Detail Joisted Cassette Roof MET-036 Partition Wall Tie Detail
MET-007 Cill/Lintel Connection Details 1.2mm Gauge MET-037 Internal Wall Door Head & Jamb Details
MET-008 Cill/Lintel Connection Details 2.0mm Gauge MET-038 Internal Door Recessed Cill Detail
MET-009 Cill/Lintel Connection Details Compound Lintel MET-039 Single Internal Wall to Timber Truss Roof
MET-010 Base Connection Detail Hot Rolled to U Track MET-040 Twin Partition Wall to Timber Truss Roof
MET-011 Braced Wall Fixing Detail MET-041 Single Internal Wall to Joisted Cassette Roof
MET-012 External Wall Built off Concrete Slab MET-042 Internal Wall Built off Beam
MET-013 External Wall Built off Podium Slab Threshold & Barrier Details for Lift Shaft
MET-043
& Other CDM Openings
MET-014 External Wall Built off Beam
MET-044 Lift Shaft Guide Rail Connection Detail
MET-015 External Wall Lintel Detail
MET-045 Lift Wall Base to Pit
MET-016 External Wall Cill Detail
MET-046 Lifting Beam / Tie in Slab
External Wall to Concrete Floor
MET-017 MET-047 Typical Stair Plan Detail Half Landing
Load Bearing Detail
External Wall to Concrete Floor MET-048 Typical Stair Plan Detail Quarter Landing
MET-018
Non Load Bearing Detail Typical Stair Trimmer Beam Detail
MET-049
External Wall to Joisted Cassette Floor Concrete Floor
MET-019
Load Bearing Detail Typical Stair Trimmer Beam Detail
MET-050
External Wall to Joisted Cassette Floor Joisted Cassette Floor
MET-020
Non Load Bearing Detail MET-051 Half Landing Support Detail
MET-021 Propped Balcony Detail MET-052 Single Internal Wall to External Wall
MET-022 Cantilever Balcony Detail MET-053 Twin Internal Wall to External Wall
MET-023 External Wall Parapet MET-054 External Corner Outward
MET-024 External Wall to Concrete Roof MET-055 External Corner Inward
MET-025 External Wall to Timber Truss Roof MET-056 External Corner non-90 Degree
MET-026 External Wall to Timber Truss Gable MET-057 Internal Wall Junction Plan Details
MET-027 External Wall to Joisted Cassette Roof MET-058 External Jamb Details
MET-028 Factory Punching Capabilities MET-059 Panel to Panel Junction Details
MET-029 Scaffold Tie Detail MET-060 Brick Movement Joint Detail
C Stud
U Track
U Track
C Stud
U Track
Asymmetric
Ledger Angle
M12 Countersunk
M12 Countersunk
bolt set bolt set
with locking
withnut
locking
or nut or
equivalent
equivalent
rivet rivet
Double sided
Double sided
ledger angle
ledger angle
U Track
Short flange to
prevent overspill @ SSL
Asymmetric
ledger angle
U Track
Cassette Joist
C Stud
35
equivalent rivet
2
U Track 1.2mm
35 35
2 35 35
U Track 1.2mm
42
40
C Stud
C Stud C Stud
C Stud C Stud
35 35
35 35
M12 Countersunk
M12 Countersunk
bolt set bolt set
withM12
locking
with
nutlocking
or nut or
M12 Countersunk bolt set bolt set
Countersunk
35 35
35 35
42 42
42 42
equivalent equivalent
rivet
with locking rivet
nut or
with locking nut or
equivalent
equivalent rivet rivet
7 7
35 35
35 35 U Track 2mm
U Track 2mm
7 7
35 35
35 35 U Track 2mm
U Track 2mm
7 735 35
35 35 U Track 2mm
U Track 2mm
7 7 35 35
35 35 U Track 2mm
U Track 2mm
42 42
42 42
35 35
35 35
M12 Countersunk
M12 Countersunk
bolt bolt
set with locking
set with
M12 nutlocking
or
Countersunk nut or
bolt
M12 Countersunk
equivalent bolt
equivalent
rivet rivet
set with
set with locking nutlocking
or nut or
35 35
35 35
equivalentequivalent
rivet rivet
C Stud C Stud
C Stud C Stud
35 35
U Track 2mm
35
M12 Countersunk bolt set
with locking nut or
equivalent rivet
35
7
2no Tek Screws at every stud
to fix U track to horizontal C
C Stud
U Track 2mm
Angle fixed into junction of lintel and jamb - 2no fixings through each leg
Base Plate
Base Plate
Base Plate
U Track
150 min
Insulation to C Stud
specification by others External sheathing board
Weep hole by others U Track
Floor finishes to Architects details
Cavity insulation by others
M12 Countersunk bolt set with
Cavity barrier by others locking nut or equivalent rivet
Brickwork by others
Brickwork by others
C Stud
Aperture by others
Brickwork by others
C Stud
Aperture by others
MET-020 / External Wall to Joisted Cassette Floor Non Load Bearing Detail
Thermal isolation
pad by agreement
Thermal isolation
pad by others
Inter-stud insulation by
others (Min 600mm below
ceiling line & 600 above SSL) Fixings by design
50
(by design)
Fire stop to supporting
channel by others Note: Teks cut off by others
150 (min)
to allow fitting of boards
Brickwork by others
Bricktie channel by others
External sheathing board
Insulation to
specification by others Non fire rated ceiling by others
Inter-stud insulation by
others (Min 600mm below
ceiling line & 600 above SSL)
MetStructures wall
Weep hole
by others
External sheathing board
Window by others
Fixings by design
Insulation to specification
by others
Bricktie channel
by others External sheathing board
Inter-stud insulation
by others (Min 600mm
MetStructures wall system
below ceiling line &
600 above SSL)
Internal lining board to
provide suitable fire protection
to primary frame by others
Brickwork by others
C 100 B
FACTORY FORMED SERVICE HOLES
C 100 B
C 100 B
=
40
= = =
40 40
= =
FACTORY35FORMED PUNCHES
35
35 CF Ø14 Ø18
=
70/100
70/100
CF Ø18
35 = = 35 = = =
Ø14
CF Ø14 Ø18
70/100
70/100
70/100
70/100
50mm
100-500
100-500
= 50mmmin35
100-500
100-500
50mm
100-500
100-500
= = = = = = minmin
70/100
70/100
70/100
= =
B C E C B
B C E C B
B C E C B
A
D
A A
F F
D
D
Floor finishes to
Architects details
External sheathing board
Fixings by design
U Track
M12 Countersunk bolt
Insulation made good set with locking nut
around bracket on site Factory fitted
22mm OSB3
Scaffold tie and
bar by others
Tapes by MetStructures
(Site applied)
Sacrificial connector
left in place by others
Site set out by others
Floor finishes to
Architects details
Fixings by design
U Track
M12 Countersunk
Insulation made good bolt set with locking nut
around bracket on site
Sacrificial connector
left in place by others Load Bearing
Deck Support
Site set out by others
C Stud
EXTERNAL WALL SCAFFOLD TIE - INTO DECK
Floor finishes to
Inter-stud insulation by Architects details
others (Min 600mm below
ceiling line & 600 above SSL) C Stud
Insulation to
specification by others
Insulation to
specification by others
Progressive collapse
tie by design
Fire stop to
supporting
channel
by others
Inter-stud insulation
by others (above and
below ceiling line)
C Stud
Internal lining board
to provide suitable fire
protection by others
Ceiling by others
Progressive collapse
tie by design
Cavity barrier Fire Reinforcement
by others Floor finishes to & progressive collapse
Architects details required (by design)
Fire stop to
supporting
channel
by others
Inter-stud insulation
by others (above and C Stud
below ceiling line)
LOAD BEARING SIDE NON LOAD BEARING SIDE
Fixings by design
Factory fitted
22mm OSB3
Insulation by others
(Specification subject to
performance requirements
by others)
Inter-stud insulation
by others (Min 600mm
below ceiling line &
600 above SSL)
Fixings by design
Ceiling by others
C Stud
Fixings by design
Floor finishes to
Architects details M12 Countersunk
bolt set with
locking nut
Inter-stud insulation
by others (Min 600mm
below ceiling line &
600 above SSL)
Fixings by design
Fire lining boards
to underside of joists
Partition wall tie
by others
Fixings by design
C Stud
A B
30
A B
Fixings by design
U Track
Deck Support
Ceiling by others
Section A-A
U Track
Deck Support
Ceiling by others
Section B-B
Internal Jamb
10
Fixings by design
MetStructures wall
Internal lining board to provide construction
suitable fire protection to primary
frame by others
LOAD BEARING SIDE NON LOAD BEARING SIDE
Inter-stud insulation
by others (Min 600mm
below ceiling line &
600 above SSL)
U track
M12 Countersunk
Internal lining board
bolt set with
to provide suitable
locking nut or
fire protection to
equivalent rivet
primary frame
by others
Factory fitted
MET-043 / Threshold & Barrier Details for Lift Shaft & Other CDM Openings
Steel spacer
P1001-B3 Unistrut
or similar approved
MetStructures
wall construction
41
MetStructures
wall construction
LG
Lifting beam by
MetStructures
Lifting eye installed and
tested by lift installer
Height to U/S of
lifting eye as per lift
manufacturer details
Additional studs to
support lifting beam
RSA or similar by
MetStructures to
support landing slab RSA or similar by
MetStructures to
support stair half
landings
Half landing slab
Stairwell
Stairwell
10mm Gap between stringer 10mm Gap between stringer 10mm Gap between stringer 10mm Gap between stringer
and plaster boards and plaster boards and plaster boards and plaster boards
Landing by Landing by
Stair Supplier Stair Supplier
Stairwell
Floor build up as
Fixing method for stair to trimmer specified by architect
beam to be confirmed by
stair manufacturer
Joisted cassette
by MetStructures
Inter-stud insulation
by others
Composite structural decking
with fibre reinforced concrete
Progressive collapse
tie by design
Support by MetStructures
Fire stop to supporting bolted to flange of studs
channel
Inter-stud
insulation
by others
External
insulation
Bricktie channel
Brickwork
by others
C Stud
Insulation to
specification by others
Brickwork by others
C Stud
Insulation to
specification
by others
Cavity barrier External sheathing board
by others
Bricktie channel
by others
Brickwork by others
Additional stud to
carry cavity
Brickwork by others barrier by
agreement only
C Stud
Inter-stud insulation
by others
Brickwork by others
100
Brick-tie channel
by others accessibility
subject to cavity closure
width by others
120 max.
Additional
stud max
225mm from
225 max opening
Insulation to
specification
by others External
sheathing
board
Window system
by others
Brickwork by others
C Stud
M12 Grade 8.8 bolt
complete with locking
M12(Top
nut and washers Grade 8.8 bolt
& bottom)
complete with locking
nut and washers (Top & bottom)
Insulation by others
Insulation by others
Brickwork by others
Brickwork by others
C Stud
C Stud
M12 Grade 8.8 bolt complete with locking
nut and washers (Top & bottom)
M12 Grade 8.8 bolt complete with locking
nut and washers (Top & bottom)
C Stud
External
Insulation to sheathing
specification board
by others
Bricktie
channel
by others
Brickwork
by others