P.T.

P.T. REKAYASA Submission Rev A CLIENT COMMENT Submission Rev B CLIENT COMMENT Submission Rev 0 CLIENT COMMENT Submission Rev 1 Submission Rev 2 CLIENT COMMENT
INDUSTRI
REK Submission Date Submission Date Submission Date Submission Date Submission Date

Transmittal

Transmittal

Transmittal

Transmittal

Transmittal

Transmittal

Transmittal

Transmittal

Transmittal
NO. Document No. DESCRIPTION SIZE UNIT QTY DISC Weight

Weight

Weight

Weight
ENGINEERING
AYA &

Item

Item

Item

Item

Item

Item

Item

Item

Item
CONSTRUCTION Plan Actual Status Date Status Plan Actual Status Date Status Plan Actual Status Date Status Actual Status Actual Status Date Status
J SA
AKARTA - INDON
E INDU
SIA
STRIDRAWING 14 14 7.368% 13 10 3.947% 4 2 0.789% 0 0 0
43 SNG-L2-PPD-011 Key Plan Production Line (SNG-M2A to SNG-M1A) A3 Set 1 PPL 1.316% 1 DC-006 28-Apr-21 26-Apr-21 IFR 1 0.526% - - - 1 DC-062 12-May-21 23-Aug-21 IFA 0.000% 26-May-21 0.000%
ENGIN
44 SNG-L2-PPD-012 Piping Plan SNG-M1A Area A3 Set 1 PPL 1.316% 1 DC-021 28-Apr-21 28-May-21 IFR 1 0.526% TR-004 3-Jun-21 PPD 1 DC-061 12-May-21 18-Aug-21 IFA 1 0.395% TR-014 26-Aug-21 PPD 1 DC-072 26-May-21 9-Sep-21 AFC 1 0.395% TR-018 15-Sep-21 PPD
TR-017, Rev 0 PPD comment EERIN
45 SNG-L2-PPD-013 Piping Plan SNG-M2A Area A3 Set 1 PPL 1.316% 1 DC-028 28-Apr-21 8-Jun-21 IFR 1 0.526% TR-007 29-Jun-21 PPD 1 DC-054 12-May-21 2-Aug-21 IFA 1 0.395% TR-013 16-Aug-21 PPD 1 DC-058, 073 26-May-21 9-Sep-21 AFC 1 0.395% TR-017 14-Sep-21 PPD
G46& SNG-L2-IMD-008 Alignment Sheet SNG M2A to SNG M1A A3 Set 1 PPL 1.316% 1 DC-014 5-May-21 7-May-21 IFR 1 0.526% - - - 1 DC-041 19-May-21 29-Jun-21 IFA 1 0.395% TR-008 7-Jul-21 PPD 1 DC-063 2-Jun-21 23-Aug-21 AFC 0.000%
CONST
47 SNG-L2-IMD-010 Isometric Drawing (SNG M1A Area) A3 Set 1 PPL 1.316% 1 DC-043 5-May-21 1-Jul-21 IFR 1 0.526% - - - 19-May-21 0.000% 2-Jun-21 0.000%
RUCTI
ON 48 SNG-L2-IMD-011 Isometric Drawing (SNG M2A Area) A3 Set 1 PPL 1.316% 1 DC-037 5-May-21 24-Jun-21 IFR 1 0.526% - - - 1 DC-054 19-May-21 2-Aug-21 IFA 1 0.395% - - - 1 DC-058 2-Jun-21 12-Aug-21 AFC 0.000%
TR-014, Rev B PPD comment J 49
A K A SNG-L2-DTD-020 Pipe Manifold Drawing (SNG M1A Area) A3 Set 1 PPL 1.316% 1 DC-037 12-May-21 24-Jun-21 IFR 1 0.526% - - - 1 DC-060 26-May-21 16-Aug-21 IFA 1 0.395% TR-014 26-Aug-21 PPD 9-Jun-21 0.000%
TR-013, Rev B PPD comment R50 T A - SNG-L2-DTD-021 Pipe Manifold Drawing (SNG M2A Area) A3 Set 1 PPL 1.316% 1 DC-031 12-May-21 15-Jun-21 IFR 1 0.526% - - - 1 DC-057 26-May-21 8-Aug-21 IFA 1 0.395% TR-013 16-Aug-21 PPD 9-Jun-21 0.000%
TR-017, Rev B PPD comment I51N D SNG-L2-DTD-022 Road Crossing Drawing A3 Set 1 PPL 1.316% 1 DC-022 12-May-21 30-May-21 IFR 1 0.526% TR-005 11-Jun-21 PPD 1 DC-065 26-May-21 25-Aug-21 IFA 1 0.395% TR-017 14-Sep-21 PPD 9-Jun-21 0.000%
TR-018, Rev B PPD comment O52 N E S SNG-L2-DTD-023 Detail Tie In Drawing (SNG M1A Area) A3 Set 1 PPL 1.316% 1 DC-033 12-May-21 17-Jun-21 IFR 1 0.526% TR-008 7-Jul-21 PPD 1 DC-071 26-May-21 3-Sep-21 IFA 1 0.395% TR-018 15-Sep-21 PPD 9-Jun-21 0.000%
IA
53 SNG-L2-DTD-024 Detail Tie In Drawing (SNG M2A Area) A3 Set 1 PPL 1.316% 1 DC-031 12-May-21 15-Jun-21 IFR 1 0.526% TR-008 7-Jul-21 PPD 1 DC-058 26-May-21 12-Aug-21 IFA 0.000% 9-Jun-21 0.000%
54 SNG-L2-DTD-025 Typical Pipeline Crossing (SNG-M2A to SNG-M1A) A3 Set 1 PPL 1.316% 1 DC-034 12-May-21 21-Jun-21 IFR 1 0.526% TR-008 7-Jul-21 PPD 1 DC-074 26-May-21 15-Sep-21 IFA 0.000% 9-Jun-21 0.000%
TR-015, Rev B PPD comment 55 SNG-L2-DTD-026 Canal Crossing Drawing A3 Set 1 PPL 1.316% 1 DC-036 12-May-21 23-Jun-21 IFR 1 0.526% TR-011 30-Jul-21 PPD 1 DC-067 26-May-21 30-Aug-21 IFA 1 0.395% TR-015 2-Sep-21 PPD 9-Jun-21 0.000%
TR-018, Rev B PPD comment 56 SNG-L2-DTD-027 Weight Concrete Detail Drawing (SNG-M2A to SNG-M1A) A3 Set 1 PPL 1.316% 1 DC-049 14-Jul-21 21-Jul-21 IFR 1 0.526% TR-012 12-Aug-21 PPD 1 DC-070 28-Jul-21 2-Sep-21 IFA 1 0.395% TR-018 15-Sep-21 PPD 11-Aug-21 0.000%

DRAWING 12 12 6.316% 9 7 2.763% 4 3 1.184% 0 0 0


TR-017, Rev 0 PPD comment 63 SNG-C2-DTD-019 Foundation Pig Launcher (L-701) A3 Set 1 CIV 1.316% 1 DC-036 12-May-21 23-Jun-21 IFR 1 0.526% TR-011 30-Jul-21 PPD 1 DC-064 26-May-21 24-Aug-21 IFA 1 0.395% TR-014 26-Aug-21 PPD 1 DC-068 9-Jun-21 31-Aug-21 AFC 1 0.395% TR-017 14-Sep-21 PPD
TR-017 & 018, Rev 0 PPD comment64 SNG-C2-DTD-020 Foundation Pig Receiver (R-701) A3 Set 1 CIV 1.316% 1 DC-036 12-May-21 23-Jun-21 IFR 1 0.526% TR-011 30-Jul-21 PPD 1 DC-064 26-May-21 24-Aug-21 IFA 1 0.395% TR-014 26-Aug-21 PPD 1 DC-068, 070 9-Jun-21 2-Sep-21 AFC 1 0.395% TR-017, 018 15-Sep-21 PPD
SNG-C2-DTD-021 Anchor Block Plan and Detail Drawing
TR-013, Rev B PPD comment 65 SNG-C2-DTD-022 Typical Ditch Detail Drawing A3 Set 1 CIV 1.316% 1 DC-039 12-May-21 28-Jun-21 IFR 1 0.526% TR-008 7-Jul-21 PPD 1 DC-056 26-May-21 5-Aug-21 IFA 1 0.395% TR-013 16-Aug-21 PPD 9-Jun-21 0.000%
TR-015, Rev A PPD comment 66 SNG-C2-DTD-023 Land Filling and Compacting (SNG M1A area) A3 Set 1 CIV 1.316% 1 DC-057 11-Aug-21 8-Aug-21 IFR 1 0.526% TR-015 2-Sep-21 PPD 25-Aug-21 0.000% 8-Sep-21 0.000%
67 SNG-C4-GAL-003 Pipe Support Layout Foundation Layout A3 Set 1 CIV 1.316% 1 DC-039 12-May-21 28-Jun-21 IFR 1 0.526% TR-008 7-Jul-21 PPD 1 DC-062 26-May-21 23-Aug-21 IFA 0.000% 9-Jun-21 0.000%
TR-018, Rev B PPD comment 68 SNG-C4-PSD-006 Pipe Support Drawing A3 Set 1 CIV 1.316% 1 DC-039 12-May-21 28-Jun-21 IFR 1 0.526% TR-008 7-Jul-21 PPD 1 DC-071 26-May-21 3-Sep-21 IFA 1 0.395% TR-018 15-Sep-21 PPD 9-Jun-21 0.000%
TR-011, Rev A PPD comment 69 SNG-C6-DTD-006 Sewer Manifold Drawing (SNG M1A Area) A3 Set 1 CIV 1.316% 1 DC-036 12-May-21 23-Jun-21 IFR 1 0.526% TR-011 30-Jul-21 PPD 26-May-21 0.000% 9-Jun-21 0.000%
TR-011, Rev A PPD comment 70 SNG-C6-DTD-007 Sewer Manifold Drawing (SNG M2A Area) A3 Set 1 CIV 1.316% 1 DC-036 12-May-21 23-Jun-21 IFR 1 0.526% TR-011 30-Jul-21 PPD 26-May-21 0.000% 9-Jun-21 0.000%
TR-016, Rev B PPD comment 71 SNG-C6-DTD-008 Control Box Detail Drawing (Segment 7) A3 Set 1 CIV 1.316% 1 DC-048 12-May-21 14-Jul-21 IFR 1 0.526% TR-012 12-Aug-21 PPD 1 DC-066 26-May-21 25-Aug-21 IFA 1 0.395% TR-016 9-Sep-21 PPD 9-Jun-21 0.000%
72 SNG-C7-STD-006 Pipe Marker & Sign Marker A3 Set 1 CIV 1.316% 1 DC-035 12-May-21 22-Jun-21 IFR 1 0.526% TR-008 7-Jul-21 PPD 1 DC-056 26-May-21 5-Aug-21 IFA 1 0.395% - - - 1 DC-066, 071 9-Jun-21 3-Sep-21 AFC 1 0.395% TR-016, 018 15-Sep-21 PPD
73 SNG-C7-DTD-005 Gate & Fencing Drawing (SNG M1A Area) A3 Set 1 CIV 1.316% 1 DC-036 12-May-21 23-Jun-21 IFR 1 0.526% TR-011 30-Jul-21 PPD 1 DC-064 26-May-21 24-Aug-21 IFA 1 0.395% TR-014 26-Aug-21 PPD 1 DC-071 9-Jun-21 3-Sep-21 AFC 0.000%
74 SNG-C7-DTD-006 Gate & Fencing Drawing (SNG M2A Area) A3 Set 1 CIV 1.316% 1 DC-035 12-May-21 22-Jun-21 IFR 1 0.526% TR-008 7-Jul-21 PPD 1 DC-064 26-May-21 24-Aug-21 IFA 0.000% 9-Jun-21 0.000%

76 100% 76 76 40.000% out of 40% 68 59 23.289% out of 30% 43 27 10.658% out of 30% 6 3 3

Based on EMP comment arrival Rev A Belum Submit 0 Rev B Belum Submit -8 Rev 0 Belum Submit -33

PROGRESS REV A : 40.00% out of 40% Total Submitted A 100%


PROGRESS REV B : 23.29% out of 30% by Exatra B 89.5% 9
PROGRESS REV 0 : 10.66% out of 30% 0 56.6% - 9 -
TOTAL PROGRESS : 73.95% Total 83.8%