CUMULATIVE PROGRESS AS ON DATE

CKT 1

PRIORITY 2 PEGASUS SS - INFOSYS SS PRIORITY 3 INFOSYS SS - HINJ P1 SS

SN Item L1 L2 L3 L4 L5 L6 L7 L8 L9 L10 L11 L12 L13 L14 L15 L16 L17 L18 Total

Target date for


1 9/15/2021 10/5/2021
charging

2 Route length 414 411 450 421 431 391 411 406 426 426 406 412 462 466 431 531 541 491 7,927

3 Cable Length 1,296 1,260 1,377 1,290 1,320 1,200 1,260 1,245 1,305 1,305 1,245 1,290 1,440 1,425 1,320 1,620 1,650 1,620 24,468

Excavation, including
3 414 411 - - - 460 440 450 185 213 406 360 - - - - - 232 3,571
HDD

4 Sand Bedding - - - - - - - - - - -

a 100 mm 414 411 - - - 391 411 406 - - 400 - - - - - - - 2,433

b 400 mm 414 411 391 411 406 2,033

5 Cable placement 1,296 1,260 - - - 1,200 1,260 1,245 - - - - - - - - - - 6,261

6 Tile placement 414 411 - - - 391 411 406 - - - - - - - - - - 2,033

7 Backfilling 414 411 - - - 391 411 406 - - - - - - - - - - 2,033

8 Jointing

CKT 2

PRIORITY 1 PEGASUS SS - HINJ P2 SS PRIORITY 4 HINJ P2 SS - HINJ P1 SS

SN Item L1 L2 L3 L4 L5 L6 L7 L8 L9 L10 L11 L12 L13 L14 L15 L16 L17 L18 Total

Target date for


1 8/10/2021 10/31/2021
charging

a Route length 440 441 437 421 431 441 441 451 462 572 551 561 561 566 546 516 536 501 8,875

Cable Length 1,374 1,350 1,338 1,290 1,320 1,350 1,350 1,380 1,440 1,770 1,680 1,710 1,710 1,725 1,665 1,575 1,635 1,650 27,312

Excavation, including
3 440 441 435 370 - 441 441 451 185 213 406 360 - - - - - 232 4,415
HDD

4 Sand Bedding -

a 100 mm 440 441 - - - 441 441 451 - - 400 - - - - - - - 2,614

b 400 mm 440 441 441 441 451 2,214

5 Cable placement 1,374 1,350 - - - 1,350 1,350 1,380 - - - - - - - - - - 6,804

6 Tile placement 440 441 - - - 441 441 451 - - - - - - - - - - 2,214


7 Backfilling 440 441 - - - 441 441 451 - - - - - - - - - - 2,214

8 Jointing
DAILY PROGRESS REPORT Date: 02/10/2021

PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune

Location: Pune Metro Line -3 -Shivaji Nagar to Hinjewadi


Construction Agency : M/S Rahul Cable Pvt. Ltd.
FILE REF :
A - Meetings
Sr No Location Dept. Name & Officials Action Point Remarks

1 N.A N.A N.A N.A

B - Tender preparation for Phase – II

Sr No Document Received Under Preparation Tender under preparation Finalization of Tender document for publish

1 PML3_US_EHLV02 N.A Tender Documents already submitted to PICMRL

2 PML3_US_EHWDS01 N.A. N.A Tender Documents already submitted to PICMRL

C - Status of Invoice
Sr No Received to PMC Name of Contractors Observation Remarks

1 N.A N.A N.A N.A

TUV SUD / Pune Metro -PMC Daily Progress Report / 001 Ver 0.0 /dt.01-02-2021
DAILY PROGRESS REPORT Date: 02/10/2021

PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune

Location: Pune Metro Line -3 -Shivaji Nagar to Hinjewadi


Construction Agency : M/S Rahul Cable Pvt. Ltd.
FILE REF :
A - Meetings
Sr No Location Dept. Name & Officials Action Point Remarks

D - Daily Site Progress


Sr. No Particulars of Work Total Scope Today's Progress (Meter) Executed Quantity (in Km)Till Date
2.4 Package A4 - Civil -
1) Trench Work
Trench Excavation in
a) all types of Soil ( in 8.80 0
Kms)

100 mm Sand Bedding


b) 8.80 Section L11 - 400 mtrs (Phase -2 SS JB-2/5 CKT-1/2)
(KM)
220kV Cable Laid Included in Cumulative sheet
c) 51.10 0
(KM)
400mm Sand Bedding
d) 8.80 0
(KM)
e) RCC Tiles laying 8.80 0
f) Backfilling 8.80 Section L8, SS JB-5/2 CKT-1/2 - 60 meter

12) HDD Work

a) Phase - 1 0.00

Section L10 - While doing 24 inches of reamer, reamer got


b) Phase - 2 0.00 Sectio L10 - 16 inches reamer is in progress
stuck in hardrock . Now 16 inches reamer is in progress

c) Phase - 3 0.00 -

3) Joint Bay
a) JB-08 CKT-2 cleaning work in progress at L1 section b)
JB-11 CKT - 1 cleaning work completed
-
-
4) MDN Tower

Curing on Concrete for Stubs in progress / Curing for


foundation is in progress./ Raft foundation and stub
No work at site curing,site cleaning done /Back filling with excavated
material under progress./Back filling under progress and
material procurement for cable trench under progress

TUV SUD / Pune Metro -PMC Daily Progress Report / 001 Ver 0.0 /dt.01-02-2021
DAILY PROGRESS REPORT Date: 02/10/2021

PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune

Location: Pune Metro Line -3 -Shivaji Nagar to Hinjewadi


Construction Agency : M/S Rahul Cable Pvt. Ltd.
FILE REF :
A - Meetings
Sr No Location Dept. Name & Officials Action Point Remarks

E - Daily Site Observations


Sr No Area / Location Work Description Observation on Quality of Work Photo

1 Hinjewadi Phase 2 Trench Dressing work L11 section near Infosys gate 6, trench dressing work is in progress.

Near Jupiter house, Housekeeping ( scattered sand, RCC tiles etc.)


2 Hinjewadi Phase 2 Housekeeping work is in progress at road side / Near Infosys gate 6, Housekeeping
work is in progress at road side

3 Hinjewadi Phase 2 Earthing rod fixing Near DLF park, Earthing rode fixing work is in progress.

Near Infosys gate 6, HDPE pipe has been layed in front of Infosys gate
4 Hinjewadi Phase 2 HDPE Pipe laid
and also backfilling done.

6 Hinjewadi Phase 2 Trench Backfilling Near Jupiter house, Trench backfilling work started

TUV SUD / Pune Metro -PMC Daily Progress Report / 001 Ver 0.0 /dt.01-02-2021
DAILY PROGRESS REPORT Date: 02/10/2021

PROJECT : Project Management Consultant (PMC) for Utility shifting for Pune Metro, Pune

Location: Pune Metro Line -3 -Shivaji Nagar to Hinjewadi


Construction Agency : M/S Rahul Cable Pvt. Ltd.
FILE REF :
A - Meetings
Sr No Location Dept. Name & Officials Action Point Remarks

7 Hinjewadi Phase 2 Excavation work L12 section, Excavation work is in progress

TUV SUD / Pune Metro -PMC Daily Progress Report / 001 Ver 0.0 /dt.01-02-2021