Professional Documents
Culture Documents
Written by: Ben Stubbs, Faithful+Gould, Euston Tower, 286 Euston Road, London. NW1 3AT
Front cover photography: Voided Biaxial Slab, photo courtesy of Bubbledeck UK.
WRAP and Faithful+Gould believe the content of this report to be correct as at the date of writing. However, factors such as prices, levels of recycled content and
regulatory requirements are subject to change and users of the report should check with their suppliers to confirm the current situation. In addition, care should be taken
in using any of the cost information provided as it is based upon numerous project-specific assumptions (such as scale, location, tender context, etc.).
The report does not claim to be exhaustive, nor does it claim to cover all relevant products and specifications available on the market. While steps have been taken to
ensure accuracy, WRAP cannot accept responsibility or be held liable to any person for any loss or damage arising out of or in connection with this information being
inaccurate, incomplete or misleading. It is the responsibility of the potential user of a material or product to consult with the supplier or manufacturer and ascertain
whether a particular product will satisfy their specific requirements. The listing or featuring of a particular product or company does not constitute an endorsement by
WRAP and WRAP cannot guarantee the performance of individual products or materials. This material is copyrighted. It may be reproduced free of charge subject to the
material being accurate and not used in a misleading context. The source of the material must be identified and the copyright status acknowledged. This material must
not be used to endorse or used to suggest WRAP’s endorsement of a commercial product or service. For more detail, please refer to WRAP’s Terms & Conditions on its
web site: www.wrap.org.uk
Contents
1.0 Introduction ............................................................................................................................. 4
1.1 Background...........................................................................................................................4
1.2 Selection of design details......................................................................................................4
1.3 Assessment criteria................................................................................................................5
2.0 Design details........................................................................................................................... 8
2.1 Exposed ceilings ....................................................................................................................9
2.2 Rotary displacement piles .................................................................................................... 12
2.3 Castellated and cellular beams ............................................................................................. 12
2.4 Post tensioned floor slab ......................................................................................................12
2.5 Voided biaxial slab ............................................................................................................... 12
2.6 Flexible plumbing systems.................................................................................................... 12
2.7 Aerated concrete blocks with thin joint mortar....................................................................... 12
2.8 Polished concrete floor......................................................................................................... 12
2.9 Low waste door jamb .......................................................................................................... 12
2.10 Tile detailing ....................................................................................................................... 12
Version
Version Issue date Brief description
1 Nov 2009 Original issue
2 Aug 2010 Section 2.2 amended
Acknowledgements
For Atkins
Expert Panel
Armstrong Ceilings
Bachy Soletanche (Geotechnical Specialists)
Bubbledeck, UK (Voided Biaxial Slab)
Ecoflor (Polished Concrete Floors)
Hep2O (Flexible Plumbing)
Knauf (Plasterboard)
May Gurney (Piling Contractor)
ASD Westok (Castellated/Cellular Beams)
1.1 Background
Achieving the construction sector commitment target of halving construction waste to landfill by 2012 will require
construction designers to identify and act upon opportunities to improve materials resource efficiency (reduced
use of materials and waste creation) through planning and design of projects.
Work undertaken by WRAP (Waste & Resources Action Programme), Envirowise, AMEC and the BRE has shown
that reducing waste being created has a far greater positive impact on reducing waste to landfill compared with
improving on-site management of waste. It has also been shown that reducing waste is far more cost-effective.
The principles of Good and Best practice Site Waste Management Plans (SWMP) promote that the best
opportunities to improve materials resource efficiency occur by working at the earliest stages possible in the
construction process. Clearly, working with design teams to implement this through the design process is a critical
link in achieving the target.
Decisions made throughout the evolution of a design can have a major impact on the levels of materials used and
waste which arises during the physical construction, and future demolition, of a project. High-level decisions (for
example, the layout or form of a building) and more detailed-level decisions (for example, those that relate to the
design of specific elements of a building) can be equally influential. Often these decisions are made based on
considerations such as site constraints, client requirements for improved performance or finish, or compliance
with Building Regulations, but rarely include improving materials resource efficiency. WRAP is therefore working
with designers to build their knowledge and experience of materials resource efficiency, and provide the tools and
resources they need to implement it. Two key resource guides have been published by WRAP:
A further resource is a series of data sheets of design details which can provide improved materials resource
efficiency compared to standard design details commonly used in UK construction projects. The purpose of these
data sheets is to support design teams (architects, consultants, engineers) to consider and implement
opportunities for improving materials resource efficiency through the design process.
This document provides information on the development of ten data sheets. It presents the basis of the research
and the assumptions and underlying data used. The ten data sheets are available from
www.wrap.org.uk/construction and are:
Exposed ceiling;
Rotary displacement piles;
Castellated and cellular beams;
Post-tensioned floor slab;
Voided biaxial slab;
Flexible plumbing systems;
Aerated concrete blocks with thin joint mortar;
Polished concrete floor;
Low waste door jamb; and
Tile detailing.
The development of specific design detail sheets builds on previous research by WRAP on design detailing for
resource efficiency which resulted in a long list of potential details (Appendix 1). This list was assessed by the
expert panel and a resulting short list was then further refined in consultation with individual experts to ensure
that the selected options have the potential to deliver measurable benefits.
1
Available for download from www.wrap.org.uk/construction
2
Available for download from www.wrap.org.uk/construction from January 2010.
Where relevant, benefits have been quantified based on reliable, auditable data; however, this is subject to the
limitations of data availability and variations in the options available for each design detail. In addition,
appropriate measures are not available for all criteria (e.g. constructability, replicability). Quoted benefits
should therefore be treated as a guide only; actual benefits are likely to vary on a project-by-
project basis.
In addition to these core criteria, a set of additional criteria were identified which may also have implications for
the efficiency of some of the design details throughout their life cycle. Where relevant, information on these
criteria is given below but is not included as separate categories on the design sheets.
The quantification of benefits under different assessment criteria for the design details involved the collection of
data from a wide variety of sources. This included product manufacturers and suppliers, cost consultants,
academic literature and construction professionals. All sources are referenced in the footnotes of relevant
sections.
CORE CRITERIA
The units of measurement for materials resource efficiency vary between different design details according to: a)
the most appropriate format to describe savings that can be achieved; and b) data availability. For most details
the metrics are volume, area or mass; however, length is also used in the case of piping for plumbing.
Whilst absolute numbers based on real examples have been provided where possible, reductions are actually best
described in percentage terms for most of the details because a range of sizes or configurations are available.
The main potential materials resource efficiency benefits also vary between different details. For some, the main
benefit is materials savings; for others it is reduced waste. Data is for whichever is most appropriate, or both
metrics where possible.
3
WRAP NetWaste Tool [www.wrap.org.uk/nwtool]
An assessment of potential cost savings which could be achieved by specifying each of the design details was
provided by Faithful+Gould and based on specific examples.
It should be noted that cost savings were not a prerequisite for inclusion of a design detail; in fact some options
may cost more to procure and install than standard options. However, the cost of individual design details should
be viewed in whole life terms; any extra costs may be offset by efficiencies which they can facilitate elsewhere in
the programme, or due to maintenance or operational savings.
Unless otherwise stated, all embodied carbon calculations were based on data contained within Bath University’s
‘Inventory of Carbon and Energy (ICE)’4. This is currently the most widely recognised source of such data
covering a wide range of construction materials. Where carbon factors are unavailable for specific materials,
calculations are based on the nearest equivalent.
1.3.6 Constructability
Issues which may influence the constructability of individual element, both positive and negative, have been
noted. It is particularly important for designers to be aware of any special considerations which should be taken
into account during the construction programme. Examples include any extra skills or tools which may be
required for installation compared to the standard option.
1.3.7 Replicability
The potential to replicate design details across a number of different types of project is important. Where
individual details are limited to certain types of project, this has been noted.
4
Bath University (2006) Inventory of Carbon and Energy (ICE)
1.3.12 Longevity
The expected design life of each of the design details is important in the consideration of life cycle materials
resource efficiency. Long term materials savings and reductions in waste to landfill may be no better than for
standard options if replacement intervals are much shorter or intensive maintenance is required.
1.3.13 Packaging
Packaging waste can be a major contributor to landfill waste; the construction industry is responsible for major
quantities of such waste. Where relevant, the likely extent of packaging waste has been assessed.
1.3.14 Standardisation
For many design details standardisation of sizes, installation or appearance is crucial to ensure adoption across a
range of building types and projects. Where relevant, the availability of standard options is noted; however, by
their nature, several of the details are bespoke for individual projects (e.g. beams, floor slabs)
1.3.16 Repairability
The ability to perform simple, cost effective repairs is essential for the long term viability of some design details.
This section assesses the opportunities for such repairs and any implications repair work may have on aesthetics
or structural integrity.
1.3.17 Deconstructability
The reuse of products and materials, without changing their form, is the most efficient waste management
option. Where it is possible to remove products or materials from buildings for reuse with minimal or no further
processing, this has been noted. However, some elements will always be difficult to reuse; for example, this may
be due to their bespoke nature, materials used, size or position within a building’s structure.
This section also includes any further important considerations or information for designers who are considering
specifying each of the options.
This section presents each of the selected design details, together with a detailed breakdown of the data
collected to demonstrate their benefits, both in terms of materials resource efficiency and other criteria described
above.
NBS reference
Description, including how it differs from standard practice
Type of projects it is relevant to
Design stage of implementation
Relevant standards5
Quantification of benefits in terms of resource efficiency (as outlined above)
Quantification of other relevant benefits
Further useful information
5
We have listed the main reference codes for each standard; it should be noted that some standards include a number of
versions (e.g. BS EN 12201, Plastic piping systems for water supply, includes separate versions for pipes, fittings, valves, fitness
for purpose etc.)
However, the installation of such systems can result in high levels of materials use and wastage.
Traditional mineral fibre tiles, for example, can be easily damaged, offcuts are discarded and there are
no opportunities for reuse. In addition, service life is often limited.
Exposure of the slab represents good passive design, allowing efficient exploitation of the thermal
mass of the building; it can reduce the need for mechanical heating and cooling.
Where completely exposed concrete isn’t an option, ‘canopy systems’ (clusters of ceiling tiles) can
result in substantially less materials use and waste compared to wall-to-wall coverage. It is also
possible to specify recycled content.
6
WRAP Case Study Data (Southwark School - currently unpublished)
7
Ibid
8
Ibid.
9
Atkins Data. Armstrong Dune Suspended ceiling @ £30/m2; also includes additional cost of fair-faced formwork to soffit plus
two coats of emulsion paint (optional) @ £12/m2.
10
Faithful+Gould Cost Consultancy
11
WRAP Case Study Data (Southwark School - currently unpublished)
Room acoustics can be controlled through diffusion or absorption by special surface finishes,
canopy systems, or other room finishes (e.g. carpets).
The thermal mass of exposed ceilings can be used effectively as part of a passive design to help
reduce mechanical heating and cooling requirements.
It is important to establish a design strategy for M&E service distributing at an early stage.
Concrete is not the only option for exposed ceilings; in situ steel shuttering or timber can also be
left exposed.
CO2
Quantity Quantity equivalents Embodied Waste
13
Product materials of waste Material CO2 CO2
Design
Totals 10.36 0.78
12
Based on Armstrong Dune Max Ceiling Tiles. WRAP Case Study Data (Southwark School - currently unpublished)
13
Bath University (2006) Inventory of Carbon and Energy (ICE)
14
Assumed equivalent of plasterboard.
Revisions to the data were provided by Roger Bullivant Ltd in July 2010. The previous text is indicated with a
strikethrough, and new/updated text in red. The data sheet has been updated and reissued accordingly.
Packaging N/A
Standardisation Uses standard machinery. Depth of pile can be varied according to requirements.
15
Based on CFA Pile of 18m x 450mm and RDP of 7.5m X 450mm
16
Concrete Centre [Correspondence]
17
Faithful+Gould Cost Consulting. Based on rotary bored piles instead of CFA piles. CFA pile; 450mm diameter; 18m deep vs.
Rotary displacement pile; 450mm diameter; 7½m deep. (Raw data: May Gurney, Piling Contractor)
18
Ibid.
19
Bachy Soletanche ‘Rotary Displacement Piling: Screwsol. BAe Broughton Fire Station’.
(http://www.bacsol.co.uk/downloads/case_studies/Rotary%20Displacement%20Piling/A404%20-
%20BAe%20Broughton%20Fire%20Station.pdf)
Table 2.2.5 Comparison of embodied carbon in concrete20: CFA and rotary displacement piles
(volume of steel reinforcement is the same for both options)
20
Dimensions provided by Atkins Cost Consulting
21
ICE/Bath University Data. Assumed high strength concrete @ 0.211kgCO2/kg (steel reinforcement not included)
Standard I-beams have an ‘I’ or ‘H‘-shaped cross section with a solid web (vertical section) (Fig 2.3.1).
Usually made of structural steel, British and European standards refer to them as Universal Beams
(UBs).
I-beams provide effective structural support. However, since the strength of the beam is more closely
related to its depth rather than the volume of steel, they often have a strength far exceeding the
engineering requirement and so in many applications other resource efficient solutions may be
suitable.
Figure 2.3.1
Standard I-beam
Castellated beams are created by forming ‘web openings’ in a standard universal beam section. This
involves cutting along the length of the section in a ‘wave form’ and welding the two pieces together
to form a deeper section with hexagonal openings (Fig 2.3.2a). Precision cutting techniques with
laser technology can alternatively produce circular or oval openings, the position of which can be more
easily planned. These are cellular beams (Fig 2.3.2b).
Castellated and cellular beams also offer designers a number of opportunities for bespoke sizes and
sections; for example, this includes varying the depth of the beam or creating tapered sections.
Castellated beams are particularly suited to long span applications with light to moderate loadings
such as roofs.
Figure 2.3.2b
Cellular beam
Cost Cost savings will be directly related to the amount of steel Average savings of £38/metre
implications saved – this varies between individual beams. (around 10%) for castellated steel
For some castellated beams, costs of production may be close beams26.
to those of standard beams due to extra work involved in
cutting and welding.
Cost savings for cellular beams are also reduced due to more
complex manufacture.
The relatively light weight of castellated beams may allow
transportation and on-site cost savings.
Further savings are possible due to lighter supporting
structure.
Integrating services into the beam can may result in M&E cost
savings.
Time Long spans and light weight allow omission of some Time savings will depend on exact
implications supporting structure leading to quicker construction. nature of overall structure.
Light weight and manoeuvrability may allow some time
savings on site, although this is unlikely to be significant.
Carbon Reductions in steel use whilst achieving the same structural Steel embodied carbon savings of
reduction strength result in significant embodied carbon reductions. 41 kg CO2e/metre can be expected 27.
Reduced volume/weight of materials can reduce transport
emissions.
Recycling Steel is 100% recyclable.
implications Most steel produced in the UK contains recycled content;
levels can be specified.
Manufacturing waste is recycled.
Construct- The light weight of castellated beams means that they can be
ability easier to assemble than solid I-beams.
Bolted sections are easy to disassemble.
Some M&E services can pass through openings in the beam.
Replicability Castellated beams are proven across a range of buildings and
are produced using standard procedures in factory conditions.
Beams are usually bespoke for individual projects – laser
precision cutting ensures efficient manufacturing process.
Particularly suitable for longer spans such as stadia, car parks
and bridges.
Procurement issues Castellated and cellular beams are widely available and produced by specialist
manufacturers.
Off-site construction/ Castellated beams are produced offsite under factory conditions.
modularisation
Longevity 60+ years
Packaging N/A
22
ASD Westok Ltd [Telephone Interview]
23
Ibid.
24
Ibid.
25
Ibid.
26
Faithful+Gould Cost Consultancy. Based on castellated steel beams instead of BS4 steel beams. 305 x 305mm UC x 240kg/m
~ beam for 7.5m span.
27
ICE Bath Data: Based on steel carbon factor of 1.82kg CO2/kg; see section 2.1.5 for assumed weights. Includes steel
manufacture only; does not include cutting and welding.
28
ICE Bath Data: Based on steel carbon factor of 1.82kg CO2/kg. Includes steel manufacture only; does not include cutting and
welding.
Slabs can be either prefabricated or poured in situ; prefabricated units are manufactured in factories
to the required shape/dimension and transported to site, whilst in situ slabs are poured onsite using
temporary or permanent formwork. The resulting concrete slab is solid concrete with steel reinforcing
mesh encased within.
Post-tensioned slabs have been widely and successfully used in the USA and Australia for several
decades and are now becoming increasingly popular in the UK. They are significantly thinner than
ordinary reinforced slabs, minimising the weight of a building as well as reducing its overall height (it
may be possible to incorporate an extra storey on a ten storey building). Materials resource efficiency
is achieved not only by reducing materials in the slab itself, but also in columns, walls and foundations
which have less weight to support. Enhanced strength means that it also possible to achieve greater
spans between columns or walls.
Procurement issues There are a number of specialists who can install post tensioned slabs. It is
recommended that suppliers are CARES approved36
29
Ibid.
30
Concrete Centre [Correspondence]
31
Stevenson, A. M. Post-Tensioned Concrete Floors in Multi-Storey Buildings. British Cement Association.
32
Minson, A Post-tensioned suspended floors gain favour. Concrete Centre [Available at:
http://www.concretecentre.org/main.asp?page=1089]
33
Faithful+Gould Cost Consultancy. Post tensioned concrete slab instead of insitu reinforced concrete slab.
34
WRAP Case Study (Colchester Magistrates Court - currently unpublished) – Comparison between ribbed solid concrete slab
and post-tensioned slab. Includes cladding savings due to thinner slab consequent floor heights.
35
Ibid.
36
www.post-tensioning.co.uk
Active thermal mass systems can be designed to pump air at low velocity or water through slabs
to activate more of the mass.
Reducing slab thickness may affect sound insulation. Take care to avoid the need for increased
ceiling structure to compensate, particularly in residential properties.
37
Concrete Centre [Correspondence]
38
Stevenson, A. M. Post-Tensioned Concrete Floors in Multi-Storey Buildings. British Cement Association. Steel weight can be
reduced by up to 50% (Comparison is with 410mm solid concrete slab incorporating 42kg steel/m2).
39
Bath University (2006), Inventory of Carbon and Energy (ICE) (Concrete = 0.163kgCO2e/kg; Steel wire = 2.83kgCO2e/kg)
Not all of the concrete slab contributes to its structural strength - the middle of the slab is ‘non-
working’ dead load. But, the specification of supporting foundations, columns and walls must all take
into account the total weight of the solid slab.
Several VBS technologies have been introduced during the last decades, primarily to reduce the
weight of buildings, and designs now have comparable strength to solid concrete slabs.
Typical systems use hollow plastic spheres placed in a precise modular grid; these can be fixed in
place using only reinforcement mesh. Solid concrete above and below the voids ensures greater
strength at the points of highest stress. Semi pre-cast systems offer faster, straightforward
construction.
VBS systems offer excellent freedom in architectural design, by allowing a variety of building shapes,
large spans and few supporting points. As a result they allow the construction of flexible and easily
changeable buildings.
The light, strong slabs can also allow materials savings throughout the building structure, including in
supporting beams, columns and foundations.
Cost Modest cost savings or slight increase in cost for the Manufacturer estimates suggest 5-15%
implications slab itself. However, this is offset when the frame and cost savings for the building carcass46.
substructure are included; a light slab and large spans
allow materials cost savings for other structural Savings of £8/m2 for 450mm VBS instead
elements (beams, columns, foundations etc). of 900mm solid slab47. This equates to
Reduced weight can result in lower transport costs. 4%.
Less powerful lifting equipment is required.
Potential reduction of downstand beams and load
bearing walls contributes to cost reductions.
Time Semi-precast systems incorporate permanent Time savings of up to 40% have been
implications formwork with factory production and finish which achieved (semi-precast systems)48
simplifies finishing work on site.
The potential to eliminate downstand beams and some
load bearing walls allows fast construction times.
Subsequent installation of services is also fast.
Some fully finished VBS elements can be used for
certain applications (e.g. balconies; staircases)
Low concrete volume can allow for short drying/curing
times.
Carbon Embodied carbon emissions are reduced in Potential embodied carbon reductions of
reductions correspondence with low concrete use. around 90kgCO2e/m2 are achievable,
Enables simple placement of installations like ducts based on 340mm VBS.49 (See table 2.5.5)
and heating/cooling systems directly in the slab;
thermal heating/cooling slabs can substantially reduce
energy consumption.
The thermal mass of the slab can be exploited through
passive or active means to reduce heating or cooling
for buildings in operation.
Reduced volume/weight of materials can result in
reduced transport emissions.
Recycling Consider specifying concrete with recycled content.
implications Recycled HDPE spheres are used in some systems.
Specifying VBS systems has no negative impact on the
recyclability of the slab.50
Constructability Problems associated with reduced resistance to shear,
local punching and fire in older VBS systems have
been reduced. However, it may be necessary to omit
voids near columns and walls where the shear stress is
high.
The reduced weight of the slab can allow long spans Up to 50% increase in span between
between columns, or alternatively reduced deck columns can be achieved
thickness for equivalent span.
Subsequent installation of services can be simplified
due to flat soffits with no obstructing beams. It is
40
Bubbledeck (http://www.bubbledeck.co.uk/) and Cobiax (http://www.cobiax.ch/html/english/cobiax_big5/big5_benefits.html)
41
WRAP – Waste Minimisation Design Review (University of Bristol – currently unpublished)
42
Bubbledeck (http://www.bubbledeck.co.uk/)
43
Ibid.
44
http://www.cobiax.ch/html/english/cobiax_big5/big5_benefits.html
45
WRAP – Waste Minimisation Design Review (University of Bristol – currently unpublished)
46
http://www.bubbledeck.co.uk/
47
Faithful+Gould cost consultancy
48
http://www.cobiax.ch/downloads/english/press/New_Concrete_06_06.pdf
49
See table 2.5.5. Data supplied by Bubbledeck ‘Bubbledeck-v-Solid Slab Comparisons’ (February 2009)
50
Bubbledeck (http://www.bubbledeck.co.uk/)
Embodied carbon reduction (slab only) using VBS = 91kgCO2/m2 (approx 41%)
51
BRE ‘Green Guide to Specification’ (http://www.thegreenguide.org.uk/)
52
Data supplied by Bubbledeck ‘Bubbledeck-v-Solid Slab Comparisons’ (February 2009)
53
Solid slab must be thicker for the same span.
54
Embodied carbon factors based on ICE/Bath Data. Steel Bar = 1.72kgCO2/kg ; Concrete Slab = 0.163kgCO2/kg; Recycled
HDPE = 1.44kgCO2/kg (assumed 20% less than virgin HDPE figure)
Flexible pipes are supplied on long rolls, creating less waste than rigid lengths by reducing the number
of offcuts. Fewer joints and fittings are required and most systems enable these to be easily
demountable and reusable.
Construct- Long pipe lengths means few joints/fittings may be required. Plastic piping is round ¼ the weight
ability The light weight and flexibility of plastic pipes can result in of rigid copper pipe.
easy handling and installation.
Safer and fast electrical installation is possible, reducing the
need for earthing.
Pipework can be ‘threaded’ through complex routes – flooring
can be installed before pipes.
Many flexible pipe fittings can be rotated in situ, even under
pressure.
Repairs can be made without emptying pipes.
Long runs are possible resulting in few joints (support
spacings may need to be adjusted).
Fittings are designed to connect to standard copper pipes
where necessary.
Replicability Standard pipe sizes and fittings ensure full replicability
between projects.
55
Based on Hep2O Performance Data: 0.75kg/m for Hep2O; 2.81kg/m for copper
(http://content.wavin.com/WAXHW.NSF/pages/PDF_HEP2OTHB_PERFDATAEN/$FILE/THPerformanceData.pdf)
56
Faithful+Gould. Copper pipework with end feed capillary joints (weightings 50%:15mm, 30%:22mm, 20%:20mm) vs. Hep2O
pipework with proprietary joints (weightings 50%:15mm, 30%:22mm, 20%:20mm)
57
See table 2.5.5
Deconstructability Most flexible plumbing fittings are fully demountable and reusable (e.g. ‘push-fit’
fittings)
Table 2.6.5 Embodied carbon of copper vs. plastic pipe (15mm diameter)
Total embodied carbon reduction by substituting 15mm copper pipe for 15mm polybutylene (or
HDPE) pipe = 88%.
58
Hep2O Performance Data
[http://content.wavin.com/WAXHW.NSF/pages/PDF_HEP2OTHB_PERFDATAEN/$FILE/THPerformanceData.pdf]
59
Bath University (2006), Inventory of Carbon and Energy (ICE) (NB: No carbon factor available for polybutylene. Assumed
equivalent to HDPE)
Subject Aerated concrete blocks (aerated autoclaved concrete - AAC) with thin
joint mortar
NBS reference NBS F10 (Brick/Block Walling)
Type of projects Wide variety of domestic and commercial building types.
covered
Design stage of RIBA Stage D/E (Design Development/Technical Design)
implementation
Relevant standards BS EN 771-4, Specification for masonry units. Autoclaved aerated
concrete masonry units.
BS 8110, Structural use of concrete
Eurocode 2, Design of concrete structures
These types of blocks are usually bonded with sand/cement mortar (proportions depending on
required strength), 10 mm thick.
Modern large format AAC blocks are manufactured to exacting dimensional tolerances and can be
easily cut where necessary. Major materials resource efficiency savings come from the light weight of
the blocks (around 25% of the weight of conventional concrete on average) and lower mortar
requirements. In addition most AAC blocks include recycled content, in the form of pulverised fuel
ash (PFA).
A high level of design flexibility is possible allowing for a variety of plan forms, awkward sites and
bespoke projects.
The autoclaving process involves the use of high-temperature, high-pressure steams to ensure
strength, rigidity and dimensional stability. It can produce in a matter of hours concrete strengths
equal to those obtained in a concrete moist-cured for 28 days at 70° F (21°C).
Thin joint mortar is a cement-based product that only requires the addition of water and allows joints
of 3mm or less, although thickness can be varied to allow perfect levelling. Applied to the blocks with
a serrated applicator, it is quick-setting allowing rapid construction progress. Movement control mesh
compensates for the strength of the mortar and distributes any movement stresses that may build up
within the blockwork.60
60
Thin Joint Technology [http://www.thinjoint.com/basic-frame.html?main=basic.html]
Recycling PFA, a by-product from coal fired power stations, is used as an Aerated concrete contains 85% PFA,
implications ingredient. a waste product from coal power
100% of aerated concrete blocks can be recycled or reused at stations.70
the end of a building’s life.
No implications from use of thin joint mortar.
Construct- Modern aerated blocks are manufactured to exacting Thin joint mortar sets within 20
ability dimensional tolerances. minutes.71
Blocks are lightweight and easy to handle.
A range of face sizes, thicknesses and strengths are available A typical 100mm block weighs
to match individual applications. approx 1/3 of the 20kg health and
Low mortar requirements mean less onsite storage is required safety guideline.72
(i.e. bulk sand and cement)
Thin joint technology allows easy laying and levelling of 70% lighter than standard concrete
blocks; simple training can be provided through builders blocks.
merchants or onsite.
Dimensional accuracy helps to improve construction quality by
61
Greenspec (http://www.greenspec.co.uk/) gives strengths of 2.8 to 8.4 N/mm2 for AAC Blocks.
62
Tarmac (Durox System) [http://www.tarmac.co.uk/topblock/DuroxSystemproduct.aspx]
63
Aircrete [www.aircrete.co.uk]
64
Faithful+Gould Cost Consultancy. 100mm Thermalite Turboblock wall with 10mm clm 1:2:9 mortar joints vs. 100mm Durox
‘Supabloc’ wall with 3mm joints.
65
WRAP Case Study (Queenshill Court – currently unpublished) – replacement of traditional brick & block internal and external
walls with Thermoplan terracotta blocks with an external render finish.
66
Ibid.
67
Tarmac (Durox System) [http://www.tarmac.co.uk/topblock/DuroxSystemproduct.aspx]
68
Ibid
69
See section 2.7.5
70
Aircrete [www.aircrete.co.uk]
71
Ibid
72
Aircrete [www.aircrete.co.uk ]
Longevity Aerated concrete blocks have very good durability in use and are virtually unaffected by
insect attack, sulphates, frost or water.
60+ years
Packaging Usually packaged on reusable wooden pallets and shrink wrapped.
Standardisation High levels of dimensional accuracy from precision factory cutting.
AAC blocks come in a variety of sizes including 215mm course height to match standard
blocks.
Dimensional coordination Available in a number of standard sizes compatible with standard blocks.
Deconstructability The concrete is 100% recyclable; however, blocks are easily damaged during
deconstruction and may be difficult to reuse.
As well as reducing materials use, thin joint techniques can also improve air tightness, thermal bridging and
sound insulation.
Excellent thermal efficiency allows cost-effective solutions to meet current Part L Building Regulations.
Can be used in load-bearing walls up to 5 storeys.
AAC is a relatively soft material and chipping or denting is possible. However, damaged ends can be trimmed
and thin joint mortar can be used to ‘glue’ broken pieces.
Table 2.7.5 Embodied carbon of AAC blocks compared to standard concrete blocks
73
Bath University (2006), Inventory of Carbon & Energy
74
HHCelcon http://www.hhcelcon.co.uk/c/document_library/get_file?folderId=54610&name=DLFE-2802.pdf
75
Concrete Block Association http://www.cba-blocks.org.uk/
Both new and existing concrete can be ground and polished to a high shine for attractive flooring
which needs no coating or waxing. Polished concrete looks like polished stone and is highly durable.
It is decorative, practical and economical.
The use of ‘dry shake’ finishes gives the option of different colours and textures and helps ensure a
more homogenous surface. It is also possible to use additional ‘toppings’ on existing surfaces to
achieve the desired finish.
76
WRAP – Netwaste Tool
77
Faithful+Gould Cost Consultancy. Polished concrete floor instead of terrazzo tiles. Based on 300 x 300 x 28mm Terrazzo tiles
laid in semi-dry screed vs. power float unset concrete & apply surface hardener.
It is important to consider the acoustic implications of omitting soft floor finishes. The addition of
a resilient layer below the screed can help limit sound impacts in residential properties.
Slip resistance requirements should also be taken into account and the exposed finish adapted
appropriately. However, if kept clean and dry a polished concrete floor is no more slippery than
regular concrete.
Installation may be affected by weather conditions, for both internal and external applications.
Table 2.8.5 Embodied carbon of terrazzo tiles and separate screed layer
78
Bath University (2006) Inventory of Carbon and Energy (ICE)
79
Kengate Terrazzo [http://www.kengate-terrazzo.co.uk/tech-testdata.htm]
Plasterboard has one of the highest wastage rates for construction materials. Every year around one
million tonnes of waste plasterboard is created from construction, refurbishment and demolition
activities, with resulting environmental impacts and waste management costs.80 The construction of
door openings can make a major contribution to this waste.
Traditional methods for constructing door openings involve positioning a plasterboard sheet half way
or fully over the door position and then simply cutting out the required opening (Fig. 2.9.1). This
results in large off cuts.
80
WRAP (2006) Review of plasterboard material flows and barriers to greater use of recycled plasterboard.
[http://www.wrap.org.uk/downloads/PBD0004_Plasterboard_material_flows_report1.7f70e4d4.2424.pdf]
Further material efficiencies can be achieved by taping and skimming over joints rather than applying
a plaster skim to the entire wall.
As an alternative, for lighter doors it may be possible to eliminate the secondary strengthening studs
at each side of a door opening to reduce metal use instead of plasterboard. However, this is only
possible with standard plasterboard arrangements.
Procurement issues None. Proprietary systems are widely available and independent, bespoke versions can
be put together by installers.
Off-site construction/ Factory produced proprietary systems are available.
modularisation
Salvaged components N/A
81
Knauf [Online] Knauf Drywall Anti-waste initiatives generate big savings.
[http://www.knaufdrywall.co.uk/news/page_175.html]
82
Ibid.
83
Ibid. Based on reduction of plasterboard wastage rate from 16% to 12%
84
Faithful+Gould Cost Consulting. Based on plasterboard discarded per door opening (traditional method vs Knauf Eco door
jamb method)
85
See section 2.6.5 for calculations.
86
Ecology Action [Online] Green Buildings Materials Guide
[http://www.ecoact.org/Programs/Green_Building/green_Materials/gypsum.htm]
The biggest source of plasterboard waste is the offcuts resulting from dimensional specifications
which do not correspond with sheet sizes. Wherever possible, design to standard sheet sizes.
Chipping plasterboard waste saves storage space and reduces the overall volume of waste to be
managed.
For projects with larger plasterboard requirements (i.e. >10,000m2), it may be cost effective to
specify bespoke sheet sizes. However, accurate estimates of quantities will be necessary to
maximise waste reduction potential.
As an alternative to this plasterboard detail, for lighter doors it may be possible to eliminate the
secondary strengthening studs at each side of a door opening to reduce metal use instead of
plasterboard. However, this is only possible with standard plasterboard arrangements.
Table 2.9.5 Embodied carbon reduction from use of low waste door jamb.
87
Bath University (2006) Inventory of Carbon and Energy (ICE)
88
Knauf Drywall. Based on Knauf standard wallboard.
Wall and floor tiles can be responsible for significant amounts of construction waste at the fit-out
stage: typically between 8 and 10%89 is wasted.
However, when using larger sized tiles this rate can be significantly higher due to the increased
offcuts produced and higher damage rates, particularly when working around smaller details or in
awkward spaces (Fig 2.10.1). Whilst some offcuts can be reused, in practice most end up as waste.
The recent trend towards the use of larger tiles, particularly for wall finishes, can therefore have a
potentially increased impact on the resource efficiency of a project unless carefully planned.
Fig. 2.10.1 The use of larger tiles resulting in higher volume of offcuts.
89
WRAP Netwaste Tool.
Careful coordination of the type and size of tiles with the space in which they are to be used can have
a major impact on the amount of materials used and waste created.
Larger tiles may be appropriate for large, uninterrupted wall areas where minimal detailing is required.
However, using smaller or mixed-size tiles, particularly for smaller or less regular spaces, and around
furniture and fittings (e.g. basins, toilets etc) can result in a significant reduction of tile wastage (Fig.
2.10.2).
Tile sheets can also offer improved workability and even the smallest offcuts can be easily reused.
Longevity 60+ years. Ceramic tiles have extremely long lives and are generally replaced for
aesthetic reasons rather than due to wear and tear.
Packaging Tiles are necessarily supplied in protective packaging. This is usually cardboard and
can be recycled assuming it is not contaminated.
Standardisation Wall and floor tiles are available in a range of standard sizes
Dimensional coordination Tiles should be carefully selected to match the size of room.
For hand made/bespoke tiles, lower tolerances can be accommodated
Repairability Broken tiles must be replaced. Matching may be problematic if spares are not
available.
Deconstructability Tiles rarely survive intact when removed from walls or floors. Opportunities for reuse
are therefore very limited.
90
Faithful+Gould. Based on 100mm x 100mm tiles instead of 400mm x 400mm.
91
Johnson Tiles [http://www.johnson-ceramics.com]
Ceramic tiles are extremely durable. Consider refreshing rather than replacing on existing
buildings.
Broken tiles may be used in mosaics to provide an attractive and distinctive finish.
As sub-base
Coordination between other phase 2 builds – for material sharing
Rubble for thermal heat stores
Recycled aggregate in concrete mix
Furniture and equipment - Reuse for charity
Recycle through supply survey
Timber flooring materials
Roof tiles (depending on condition check) - Clay tiles from Seacole (in poor condition) - local
reclamation centre required
External lighting (flood lights)
Structural steel (gets recycled, no plan to use on-site)
Reclaimed benches
Retention of reclaimed materials for the purposes of education in the new school
Re-use (retention) of existing brick boundary wall on Donegal St as a retaining wall, other
boundary walls will be demolished. (being considered seriously)
Improving specifications of materials on site, technical compost
Use of existing material from adjacent building sites (Dependent on the level of contamination)
Some slate is being excavated and could either used on site for walls, landscaping or drainage.
There may be quality issues with this
Bubbledeck or similar alternative could be used to reduce the quantity of concrete in floor slabs
of first floor
Concrete could be specified to contain a recycled content or PFA
Sports hall will have a sprung timber floor – could a second hand floor be found?
The front of the gym will have to be removed to provide a large window to allow light in – this
could be used as fill or sub base
Demolition of existing plant room and changing rooms will provide fill or sub base
Outbuilding, repair existing; spares. Slate roofs and LS bricks (reuse in haha wall).
Car park tarmac – base material
Hedges – compost on site
Haha being dug out, reuse in landscaping?
Children’s playground being moved
Interface, take away carpet
Reuse old metal safe doors – architectural salvage
A tarmac public footpath runs across part of the site. An application to divert this has been
submitted and a decision is awaited. The tarmac could be left in place or reused elsewhere on
site
Carpets in classrooms could be carpet tiles to reduce off-cuts and reduce waste when repairs are
required
Could a water tank be sourced from one of the existing schools?
Could soil be remediated and used on another part of the MoD site? Cost likely to make this
unviable
Wall protection could also be moveable – so only protecting the area being worked above
There is the opportunity to excavate additional slate for these uses
Recycled materials could be specified for landscaping
Concrete paving/ blocks already specified for paths around classrooms as are better than pre-
cast in terms of embodied energy – this could be extended down to the sports fields
Rotary Piling suggested for foundations to reduce excavation – may cause stability problems with
the listed wall
Software modelling noted above but with the input and coordination of the subcontractor
Off site cladding panels – reuse waste in factory, reduced weight and therefore materials in
construction /
foundations
Off Site
Prefabricated stairs
Prefab stair wells
Thermo deck off site pre cast concrete structure
Modular design
2.
Gym roof lights to be translucent panels that can’t be cut to size so roof tiles will be removed to
fit. Tiles are thought to be clay and could be reused BUT won’t be available until the end of the
project. May be too late, could be used in access ramps?
Gym floor to be replaced – could use a second hand sprung floor
External lifts are already being considered instead of ramps which will require a lot of concrete
Piling not strips
Steel frame (Kit set – recycle off cuts)
Reinforced concrete pad (reused substrate)
Cladding, prefer OSM to bricks
Masonry would be local LS
Plasterboard, replace with: Fermacell – more expensive, but less wastage. More fit for purpose?
Stairs
Doors (off the peg)
Windows, component / on site assembly
OSC, form finding software approach to vinyl flooring
Pod/OSC of operating theatres
Pre-cast / minimise variants of stairs
Floor build ups – void formers to reduce in-situ concrete requirement e.g. BubbleDeck
Two classrooms need to be 10m2 larger than the others, currently these are wider but they could
be longer instead. This would make the toilets and two classrooms a standard layout with an
additional length which would be easier for off site manufacture of components
Building steel framed – driven by contractor - grid at 4.735 centres – not standard – could grid
be changed?
Floor slabs are planned to be cast in situ – most of them could be pre-cast. Ground floors will all
have under-floor heating
Pool plant could be bought as a package – access may restrict this
Lift
Can the 12 classrooms be made identical and be made as pods off site?
Off-site construction and manufacture already an integral part of the method of working.
Pre-fabricated services sections for all heating, electrical, ICT, phone, fire alarm, sprinklers
systems
Modular plant rooms
Modular form work (not PCC) and grid dimensions to minimize in-situ concrete slabs
Tea-point stations
Bespoke science and DT desks
Off-site staircases (x4)
Toilet pods
Toilet services modules
Sports changing rooms – toilets & showering services modules
Standardisation of bedroom and bathroom units (Plug-ins)
Theatres to be manufactured as modular units
Offices for administration to be manufactured as modular units
Façade modular panels
Panelock
Post-tension flat slabs to minimise slab depth, flat soffit, partitions and formwork. Also
implications for deconstruction.
Piles foundations – rotary system to reduce the amount of spoil to be reduced
Modular shuttering for concrete
Pre-cut wall elements and delivered with doors and clip into place (A-B)
Prefabricated core with M&E openings
Pre-cut wall elements and delivered with doors and clip into place (A-B)
Create module for walls and windows to reduce cut offs especially in dry walls
Consider construction / manufacturing procedures to eliminate/reduce waste
Revisit model to schedule plasterboard, insulation
Revisit model to check for pipe lengths, clasps
Time construction and delivery through 3D model and locate and plan storage for exact
quantities
Design for material optimisation
Building form and layout, especially grouping of individual units and amount of external walling
Regular / orthogonal spaces (may already be occurring)
Planning of sheet flooring to minimise cuts and coordinate with coving
Modification of building form and layout (BB highlighted risk liability problems here)
Perimeter fencing (concern that standardised fencing not appropriate because of varied site
levels)
Dimensional co-ordination - plasterboard
Reduce the amount of excavation – screw piles
Standardisation
Windows would need to be standardised to co-ordinate with the panel systems of steel and
cladding. All could be standardised to 1200mm. It is expected that changing the windows to
1200mm would be cheaper than specifying the panellised cladding to match the windows
Working to a 1200mm frame and panel system could allow ceilings and floors to be co-ordinated
If the slope on the pool floor is graded over a shorter distance then there would be less off-cuts
of tiles
Ceiling tiles and flooring tiles could be chosen instead of sheet/ rolls to reduce off-cuts
Sirtex is specified as insulation – could this be replaced with a panel system? Or replace with
recycled materials? Sirtex is very efficient as an insulator and allows very thin walls but does
generate a lot of waste and is hard to recycle
Ceiling tiles are specified but have high wastage. An open ceiling with baffles is planned for the
sports hall but ceiling tiles in the classrooms would provide the acoustic buffering to keep
classroom noise down and prevent excessive noise from rain on the metal roofs. Potential to
make a feature of areas of exposed ceiling to prevent the need for cutting ceiling tiles
Specification review – e.g. double or single board
Specifying recycled content in materials
Coordination of planning grids with materials throughout the building
Full door height or doors with fanlights versus overboard
Rationalisation of partition layouts with suspended ceiling
Find an alternative to black tarmac (slate with resin?)
Recycled content – recycled slate / demolition in concrete or screed (need for on-site mixing
plant)
Smaller plasterboards as easier to handle – need for discussion with specialist subcontractors
Unitised cladding systems, manufactured off site
Reuse of demolition as fill or landscape
Reuse aggregate in concrete from this or other sites in Bristol
Modular services – off site assembly into packages
Shuttering with regular modules – e.g. 45 degree rotations between beams
Volumetric WCs and other areas, e.g. staircases
Standard ceiling grids (in labs) resulting in less cuts but a need for a higher level of M&E
coordination
Engage University – do they have any materials for reuse on site (prefab building on site being
dismantled)?
Solar re-heating collector
Resin on top of concrete or screed in Maths lecture theatres in basement – less waste due to
pouring
Maths building: Finishes – carpet tiles review – must be Omni-directional
Salvage assessments of site
Walkways (bridges) – steel prefabricated already
Match skirting boards with off-cuts
Modular and Volumetric Lab benches plug and play, made off site
Client Furniture strategy – consistent & flexible – long term impact
Packaging – parallel with consumer purchasing – begin dialogue with suppliers
Burning packaging waste on site and use heat – adjacent to hospital – no biomass boiler
Method statements from contractors to reduce waste on site and for correct installation of fragile
materials
Dialogue with plasterboard manufacturer
Architects to specify responsibly sourced materials (A-B)
Client buy in when it comes to their construction input, e.g. ATOS/SERCO, involve third parties
M&E on time
Efficient standards and systems already operated
Meet environmental standards in Islington procurement code
BB have policy on specifying reduced packaging from suppliers
BB’s policies on ordering from suppliers - Minimise over ordering
Take-back schemes for certain materials, such as plasterboard off-cuts
SWMP and monitoring of quantities
Good site storage facilities / JIT delivery
Specify increased recycled content (not a direct waste saving but reduces waste sent to landfill)
Simplify specification
Early supply chain involvement
Specification writing, added flexibility in the contract
Appropriate procurement and incentives
4.
Take-back systems could be specified for plasterboard and ceiling tiles off-cuts
Take-back systems could be specified for plasterboard and ceiling tiles off-cuts
Precast basements
No basements - no excavation so no internal fill
Use of natural materials – long term durability so less maintenance and replacement
Steel frame
Volumetric systems for offices / labs (pods)
Standard University construction type / grid
Modular / demountable partition systems
Recyclable / Deconstructable partition systems
Modular structure, series of facets rather than circle. Only circular part is outer panel cladding.
All beams are radial. Cantilevered flat slab.
Precast concrete frame rather than in situ pouring
No ceilings to non-lab areas
the specification. This is being implemented as a zoning system so that certain sections of the
school can be zoned off for use.
Wired & wireless ICT system – exists as back-up, future/existing use
Identify any future adaptations or extensions to the school, such as possible final link building,
where dismantling to facilitate additions.