Professional Documents
Culture Documents
TEST PACKAGE
3. TEST PROJECT
The Test Project may include the following standalone modules designed to test the
skills of the Competitors:
• Module 1: Refrigeration System Installation & Commissioning
• Module 2: Air Conditioning System Installation & Commissioning
• Module 3: Fabrication and Brazing
• Module 4: Mechanical Component Replacement
4. ASSESSMENT
This section describes how the Experts will assess the Test Project/Modules. It also
specifies the assessment specifications and procedures and requirements for marking.
4.1 Assessment Criteria
This section defines the assessment criteria and the number of marks awarded.
The total number of marks for all assessment criteria must be 100.
Section Criterion Marks
Subjective Objective Total
A Refrigeration Pipework - 40 40
B Electrical Wiring - 14 14
C Component and System Positioning - 10 10
D Commissioning and Adjustment - 10 10
E Repair and Replacement - 5 5
F Refrigerant Recovery and Emission Control - 13 13
G Safety - 8 8
Total - 100 100
G – Safety
• Safe working practice
During the competition all competitors MUST follow the safety rules listed along with
Health safety requirements of the Host Region.
SHOES
• Fully enclosed work shoes or boots must be worn at all times.
CLOTHING
• Legs must be covered at all times, by either long work trousers or coverall.
• Upper body must be covered at all times
• Arms must be covered with long sleeves, when brazing and using refrigerant.
GLOVES
• Must be worn when brazing and using refrigerant
• All electrical work involving live testing will require wearing of approved gloves.
FACE MASK
• Must be worn when working with refrigerants.
• Must be worn when brazing/soldering
ELECTRICAL
• Competitors MUST NOT SWITCH ON (apply power) any electrical equipment
(Refrigeration and Airconditioning unit) until they receive permission from an expert,
except for power tools.
Any competitor that is identified for not wearing the PPE or is engaging in any unsafe practice
will be stopped and advised on the correct safety practice by an expert.
Furthermore, if unsafe working practice is repeated the expert may STOP the competitor and
report the issue to the Chief Expert. The competitor may not be allowed to continue until the
safety issue is resolved. The competitor will lose associated safety marks.
If the competitor continues to ignore the safe working practice they may be removed from the
competition area for a safety briefing for 10 mins. By the Host Region Health and Safety
Representative.
A.2 SUPPLIES/MATERIALS
Qty Unit Supplies Description Estimated Total Qty on
Unit Price site
2 cyl R410a (13.6kg/cyl) P10,200.00 P20,400.00 none
2 cyl R404a (13.6kg/cyl) P10,200.00 P20,400.00 none
2 rolls 2.0mm2 THHN wire/black. P3200.00 P6,400.00 none
12 Pcs. 3 pin/ C.O. combination of P300.00 P3,600.00 12 pcs
horizontal & vertical
50 Mtr. 5.5mm2 /3wires royal cord P150.00 P7,500.00 none
12 Pcs. Circuit bkr. /20 AT/1Ph With P500.00 P6,000.00 6pcs
enclosure
5 kg Wood nail/2 inch L P75.00 P375.00 ok
500 Pcs. Metal screw/ 1.5”L x ¼” dia. P5.00 P2,500.00 none
6 rolls ½” Copper pipe for inverter ACU P4,500.00 27, 000.00 none
50’/roll
6 rolls ¼” copper pipe for inverter ACU P2,500.00 15,000.00 none
50’/roll
15 pcs Rubber insulation 3/8” x 3/8” x 8’ 45.00 675.00 none
15 pcs Rubber insulation ¼” x 3/8” x 8’ 40.00 600.00 none
6 rolls Insulation tape 150.00 900.00 none
18 set Flare fittings 12.7mm, brass (union 400.00 7200.00 none
and nuts)
6 set Flare fittings 6.35mm, brass, (union 250 1500 none
and nuts)
6 pcs Copper elbow 12.7mm 150.00 900.00 none
6 pcs Copper T joint 12.7mm 80.00 480.00 none
6 pcs Copper reducing socket 12.7mm x 80.00 480.00 none
6.35mm
6 pcs PVC conduit ¾” Neltex 200.00 1,200.00 ok
20 Gal. white paint/boysen QDE P650..00 P13,000.00 none
10 Gal. Paint thinner P300.00 P3000.00 none
3 Pcs. Roller brush P200.00 P600.00 ok
6 Cyl Nitrogen Tank /REFILL P1,000.00 P6,000.00 none
6 cyl Oxygen Tank /REFILL P1000.00 P6,000.00 none
6 cyl Acetylene tank /REFILL P1,000.00 P6,000.00 none
50 pcs Plywood 4’ x 8’ x ¾” Marine P1,500.00 P75,000.00 none
12 pcs Square Tube B.I. 2mm x 2” x 20 ‘ P1500.00 P18,000.00 none
TOTAL P251,710.00
Below is the Marking Scale Summary for Trade Refrigeration and Air Conditioning, which must
be provided to all Competitors at the Information Session, conducted prior to the start of the
competition.
The Criteria Marks to be awarded for all four modules are listed below.
Skill Criteria Maximum Points
The above skills criteria are spread over Four (4) Modules listed below:
______________________________ _ __________
Expert’s Signature Over-Printed Name Date
Module 1 Module 2 Module 3 Module 4 Total
Section Criterion Sub-criterion
18 pts. 9 pts. 13 pts. -- 40 pts.
A Refrigeration Pipe work 13
• Pipe branch 4 1.5
• Dimension accuracy 2 0.5
• Flare and swage joint quality 2 1
• Silver brazing 2 1
• Strength pressure and leak test 4 2
• Brazing alloy penetration 2 1.5
• Suction and liquid lines to standards 2 1.5
Total 18 9 13 40
The competitor is required to position the supplied No-Frost Refrigeration Equipment according to the
schematic pipe work diagram that will be supplied.
The competitor is required to commission the system within the time limit. When you have finished
commissioning the system, you are required to record the operational setting on a System Data Sheet
that will be provided to each competitor.
The competitor must ask an Expert to check their own commissioning records and obtain an Expert
signature in the space provided in the commissioning sheet.
The Specifications for the Freezer Cabinet are:
Refrigerant = R404a/R134A
Ambient Temperature = 30 ®C Db
Condensing temperature difference = 12 K
Cabinet temperature = 5®C - 10®C
Evaporation temperature difference = 7K
Suction line Pressure Drop = 1K
a. Low Pressure Controller Cut-off the system 10 K lower than design Saturated Suction
Temperature (SST) and cut-in (Start) the system when SST reaches -8®C.
b. High Pressure Cut-out the system when the condensing temperature reaches 10 K above the
design condensing pressure.
c. Temperature Controller cut-off the solenoid valves and must maintain the average room
temperature at return air within 1 K.
d. Defrost controller cuts off the system every 6 hours a day with 30 minute of defrost duration.
e. Defrost termination temperature at 10®C with 5 min fan delay for water draining.
REGION :
The Competitor must ask an Expert to check their refrigeration unit and initial the box after the
following items occur;
1. Pressure Test
Under the supervision of an Expert, carry out a staged pressure test of the refrigeration system in
accordance to manufacturer’s equipment instructions.
The pressure test point should not drop from the starting point in the fifteen (15) minutes after
the pressure test is isolated from the Nitrogen Cylinder.
If the pressure test has not been achieved, the competitor can continue to fix the leak and
achieve the pressure test; however the full mark for Pressure Test will be lost.
Expert’s Initials:
2. Evacuation
• Under the supervision of an Expert, evacuate the refrigeration system in accordance with
manufacturer’s instructions using the Deep Vacuum Methodto hold a vacuum of at least 1000
microns (29.88 In. Hg) of mercury.
The evacuation point should not rise more than 20% of the starting point in the Ten (10) minutes after
the vacuum pump is isolated from the system under test.
If the evacuation below 1000 microns of mercury has not been reached within 1/2 hour, the competitor
can continue to achieve the evacuation; however the full mark for Evacuation will be lost.
Or
Evacuation Achieved Outside ½ Hour: Competitor’s Initials:
Expert’s Initials:
3. Determine and Adjust the Cut-in & Cut-out Temperature
• Determine the settings of the controller to comply with the system specification.
Cut-in Temperature ®C ®F =
Cut-out Temperature ®C ®F =
• Under the supervision of an Expert, adjust the control switch settings, in accordance with
acceptable trade practices.
• Determine the settings for the Dual Pressure Control to ensure its safe and effective operation.
Show all pressure settings below.
• Under the supervision of an expert, adjust the Pressure Control settings, in accordance with
acceptable trade practices.
5. Charge the System with Refrigerant
• Under the supervision of an Expert, Charge the refrigeration system with the required weight of
refrigerant to ensure operation according to beverage cabinet specification above, and in
accordance with acceptable trade & environment practices.
• Under the supervision of an Expert, check and adjust if necessary, the Thermostatic Expansion
Valve superheat setting, to ensure the system’s efficient and effective operation.
• Temperature TXV Superheat K ®C =
When you have completed commissioning the system so that it operates efficiently and
effectively, under the supervision of an Expert record the operating conditions listed below.
Show all working out.
Refrigerant Type =
Ambient Temperature ®C ®F =
The Final Beverage Cabinet Temperature when the Competitor hands over the test project
The competitor will be issued with a split type inverter air conditioning system that includes
R410a refrigerant charge. The competitor will be required to position, install and commission the Indoor
unit and Outdoor unit, pipe work and associated wiring onto a supplied framework. The installation of a
Condensate drain is also required.
The test module requires the installed pipe work to be Pressure tested and Evacuation tested
within the time limit. You are then to commission the system according to the specifications provided.
The competitor is required to commission the system within the time limit.
When you have finished commissioning the system; you are required to record the operational settings
on a System Data Sheet that will be supplied to you.
The competitor must ask an expert to check their own commissioning records and obtain an
expert signature in the space provided on the commissioning sheet.
Cooling Mode
Room temperature setting at = +21 Degree C
Fan speed setting at = High Speed
Louver Setting = Fixed Open
The Competitor must ask an Expert to observe their air conditioning unit operation and set up and
obtain an Expert initial in the box provided.
Refrigerant Type =
Ambient Temperature ®C ®F =
This module involves the marking out, cutting, flaring, swaging and silver brazing to a high standard and
cleaning the finished job.
The component will be pressure tested and the silver brazed joints and flare joints will be inspected and
marked according to the marking scale.
Pressure Test
Under the supervision of an Expert, pressure test the components to 1,050kpa (150 psig) in accordance
with manufacturer’s instruction and skill standards.
Using specialized and selected refrigeration tools, the Competitor is required to remove and replace a
component and re-commission the system.
The system must be returned to correct operation within the 3 hour time limit.
There will be any number of component replacement tasks available and each individual task will be
kept secret in its own envelope until the time of this competition module.
The task Description will be announced at the start of the module test by the Chief Expert or the
delegated representative.
The module is designated to test the Competitors ability to recover refrigerant in an environmentally
safe way.
REGION:
Pipe supports must be fitted with some form of protection to the insulation so as not
tocompress or deform the insulation. Where pipe temperatures operate below zero
Centigrade insulation must be vapour sealed to the pipe work using appropriate adhesive.
The sensing bulb is to be fastened to the suction line as close to the evaporator pipe
workoutlet as is possible. The expansion valve may be installed within the evaporator
housing orwithin the refrigerated space adjacent to the evaporator. Externally equalised
expansion valvesmust have the pressure equalising line connected to the suction line
immediately after thebulb. The bulb is to be located on a horizontal section of the suction line
immediately after theevaporator, in a position corresponding to between 12 o’clock and 8 or 4
o’clock positions.
To ensure compliance with health & safety and reduction of emissions, the high pressure
sensing point must be installed to ensure the pressure sensing point cannot be isolated.
Schrader fittings cannot be used to connect high pressure switches.
The high pressure sensing point may either be at the compressor discharge or in the high
pressure liquid line. Where no service fittings are present, the sensing point must be located
in the discharge line between the compressor and the condenser.
The low pressure sensing point must be made at the compressor suction service valve or
crankcase pressure fitting. Where suction service valves are not available; the low pressure
sensing point must be made by flame brazing a ¼’’ (6mm) Shrader fitting into the suction
pipe work entering the compressor.
Schrader copper pipe fittings must not be cut down. The maximum inserted pipe depth to be
no more than 5mm into the pipe work.
The standard of joint must be completely filled all around and have no raised marks or
depressions around the circumference.
This standard has been developed for the sole purpose of ensuring both safe working
practice and system integrity (avoid system rupture) during the Regional Skills refrigeration
and air conditioning test project competition.
This standard covers testing of high side and low side equipment and includes fabricated
pipe workassemblies that have been insulated but before the joints and ends are sealed.
4.1. Procedures
Pressure testing must not exceed the maximum test pressure of the nameplate on the
manufactured equipment.
High and low side test pressures may require isolation of certain components.
Competitor must ensure all valves are open for the pipe work section under test.
Oxygen Free Nitrogen (OFN) is connected to the pipe work assembly using test
hoses suitable to handle the maximum regulator pressure plus 20%.
The Nitrogen pressure test must be carried out according to the temperatures that
are equivalent to the standard air temperature reference for the pipe work section
under pressure e.g.
The system test pressure as indicated on the regulator will be recorded by the competitor.
The competition area is not expected to suffer a difference in temperature. Therefore the
pressure test will be regarded as failed if the test pressure drops over a 15 minute time
period.
If pressure does not hold, it is the responsibility of the competitor to solve the problem
without the assistance from an expert.
On completion of the test, the Nitrogen must be released in a slow and controlled manner so
that it does not endanger themselves, spectators, experts or others in the area.
The Nitrogen cylinder and regulator must be disconnected from the system after the test.
5. EVACUATION STANDARDS
Evacuation of the refrigeration system will be required after pressure testing is performed to
the standard. The purpose of evacuation is to ensure the complete removal of any moisture
and any other non condensable fluids that may affect efficient and reliable system
operation.
The Test Project will only require the deep evacuation method described as follows:
Using a suitable vacuum pump, the system pressure will be reduced to a vacuum of 130 Pascal
Absolute (1,000 microns of mercury) and left to stand isolated from the vacuum pump for a
period of ten minutes. A vacuum gauge must be fitted to a remote part of the system to
ensure the complete system vacuum is achieved.
The system evacuation will not be accepted if the vacuum has raised more than 20% of the
starting vacuum position. For example: a 1000micron vacuum test that rises to above 1200
microns will fail the test.
To ensure the refrigeration system integrity, and minimise the risk of environmental damage
from emission of Fluorinated gases, the following two methods will be the accepted
standard for leak testing.
When the appropriate test pressure for the device being tested is achieved, the competitor
must use an industry approved leak detection solution. Where soap and water solution is
used the competitor must prove the solution mixture will ‘bubble up’ at the maximum test
pressure.
Electronic leak detectors must be used to test for refrigerant leaks during charging
process and when the system is operating at design conditions. In addition, the
refrigeration system must be leak tested when the complete system is switched off and
system pressures have equalised. Electronic leak detectors must be suitable to measure
at least 5 grams of Refrigerant gas per year.
7. REFRIGERANT HANDLING
HFC pure or blended refrigerants must be liquid charged and weighed into the system being
charged. A record of the type and weight of refrigerant added and/or removed from the
system must be attached to the refrigeration system.
The loss of refrigerant to atmosphere must be kept to a minimum. The following examples
describe where unavoidable losses may occur:
7.3.1 Loss of refrigerant from leaking seals, joints, gaskets and cracked pipes. The leak(s)
must be located and completely eliminated.
7.3.2 Loss of refrigerant from relief valves, bursting discs and fusible plugs discharging to the
atmosphere to protect against dangerous pressure levels. Where possible these safety
devices should be vented back into the system or to another working system.
7.3.3 Loss of refrigerant dissolved in oil, this should be minimised during the normal process
ofrefrigerant recovery.
7.3.4 Loss of small quantities of refrigerant from charging hoses and pipes which occurs in
the normal process of connecting and disconnecting. Charging hoses and pipes should be
sealed at each end when not in use.
The primary objective is to ensure the safety of competitors, technical experts and others
involved in the refrigeration Test Project, plus visitors in the vicinity and close proximity of
the test area.
Safety clothing must be worn when handling refrigerant fluids. The Host may request specific
work wear or materials in addition to the following list of work wear.
Sustainability is one of the competition values. The purpose of this standard is to ensure that
wherever possible and practical to do so, competitors take care of the quality of the oils they
are using.
Refrigeration and Vacuum pump oil containers must remain sealed when not in use.
9. ELECTRICAL SAFETY
There must be no working on live (energised) equipment. For example using an insulated
screw driver to tighten a live electrical terminal is not allowed.
Electrical safety gloves must be worn at all times when testing live (energised) electrical
components. The gloves must meet the Host safety standards.
All connections will be terminated securely and with the use of ferrule terminals. No bare
conductors can be on show when viewed from ninety degree (90o) angle to the terminal.
The installed electrical system must be checked by an expert prior to the competitor
performing the electrical installation tests.
The competitor must ensure the test instrument is tested and set correctly prior to electrical
testing of the system.
Experts are responsible for the supervision of electrical testing and must sign the appropriate
test box on the competitor’s work sheet.
Polarity test ensures live and neutral are not crossed in the circuit.
Safety switches must be in the made position to enable this test.
This test ensures the power cables are not conductive to earth.
Care must be taken to ensure the system is not in vacuum state, and electronic components
are isolated before the test can be performed by the competitor.
Where any test fails to pass the standard, the competitor is required to solve the problem
without guidance from an expert.
The Test Project will be selected to use a refrigerant that ensures positive pressure for all
operational controls.
The high pressure cut-out safety switch setting of air conditioning is to be determined and set
at 0.9 x maximum allowable pressure (MAP).
The setting of Air conditioning system must be at 30 psig cut-out with 40 psig pressure
difference to cut-in.
To prevent harm to the compressor system from loss of refrigerant or to achieve a suitable
pump down, the switch should be set to stop the compressor above 0 Barg but no more than
0.1 Barg.
Compliance with local health and safety standards must prevail at all times.
A risk management assessment must be carried out each day prior to the start of competition.
Any hazards identified during these risk assessments must be isolated and rectified
immediately.
There must be an evacuation procedure, along with the host institution’s health & safety
requirements posted within easy access of each work area.
The nominated safety officer along with first aid station and first aid equipment should be
clearly defined.
Fire extinguishers suitable for the type of risks must be clearly identified and located.
Any injuries sustained by either experts or candidates must be recorded in the first aid register
regardless of the degree of injury.
Competitors must use the appropriate personal protective equipment (PPE) as and when
required.
1. Equipment
2. Supplies/Materials
Qty Unit Supplies Description
6 cyl R410a (13.6kg/cyl)
6 cyl R404a (13.6kg/cyl)
2 rolls 2.0mm2 THHN wire/black.
12 Pcs. 3 pin/ C.O.combination of horizontal & vertical
50 Mtr. 5.5mm2 /3wires royal cord
12 Pcs. Circuit bkr. /20 AT/1Ph With enclosure
5 kg Wood nail/2 inch L
1 Gal. Red oxide Primer paint
1 Gal. White paint/Automotive enamel
1 gal Lacquer thinner
15 Pcs. #220 sand paper
500 Pcs. Metal screw/ 1.5”L x ¼” dia.
6 rolls ½” Copper pipe for inverter ACU 50’/roll
6 rolls ¼” copper pipe for inverter ACU 50’/roll
15 pcs Rubber insulation 3/8” x 3/8” x 8’
15 pcs Rubber insulation ¼” x 3/8” x 8’
6 rolls Insulation tape
18 set Flare fittings 12.7mm, brass (union and nuts)
6 set Flare fittings 6.35mm, brass, (union and nuts)
6 pcs Copper elbow 12.7mm
6 pcs Copper T joint 12.7mm
6 pcs Copper reducing socket 12.7mm x 6.35mm
6 pcs PVC conduit ¾” Neltex
6 Cyl Nitrogen Tank /REFILL
6 cyl Oxygen Tank /REFILL
6 cyl Acetylene tank /REFILL
20 Gal. white paint/boysen QDE
10 Gal. Paint thinner
3 Pcs. Roller brush
3. Venue