1 SPL 1 MTR PEMASANGAN PIPA PPR 15 mm

1.000 Meter PPR 15 mm 35,000.00 35,000.00


0.250 Bh Assesories Pipa 35,000.00 8,750.00
0.150 o/hr Tukang 96,922.00 14,538.30
0.050 o/hr Mandor 110,768.00 5,538.40
Jumlah 63,826.70

K.2 SPL 1 MTR PEMASANGAN PIPA PPR 20 mm

1.000 Meter PPR 20 mm 43,780.00 43,780.00


0.250 Bh Assesories Pipa 35,000.00 8,750.00
0.150 o/hr Tukang 96,922.00 14,538.30
0.050 o/hr Mandor 110,768.00 5,538.40
Jumlah 72,606.70

K.3 SPL 1 MTR PEMASANGAN PIPA PPR 25 mm

1.000 Meter PPR 25 mm 57,310.00 57,310.00


0.250 Bh Assesories Pipa 35,000.00 8,750.00
0.150 o/hr Tukang 96,922.00 14,538.30
0.050 o/hr Mandor 110,768.00 5,538.40
Jumlah 86,136.70

K.4 SPL 1 MTR PEMASANGAN PIPA PPR 32 mm

1.000 Meter PPR 32 mm 92,180.00 92,180.00


0.250 Bh Assesories Pipa 35,000.00 8,750.00
0.150 o/hr Tukang 96,922.00 14,538.30
0.050 o/hr Mandor 110,768.00 5,538.40
Jumlah 121,006.70

K.5 SPL 1 MTR PEMASANGAN PIPA PPR 40 mm

1.000 Meter PPR 40 mm 146,080.00 146,080.00


0.250 Bh Assesories Pipa 35,000.00 8,750.00
0.150 o/hr Tukang 96,922.00 14,538.30
0.050 o/hr Mandor 110,768.00 5,538.40
Jumlah 174,906.70

K.6 SPL 1 MTR PEMASANGAN PIPA PPR 50 mm

1.000 Meter PPR 50 mm 226,600.00 226,600.00


0.250 Bh Assesories Pipa 35,000.00 8,750.00
0.150 o/hr Tukang 96,922.00 14,538.30
0.050 o/hr Mandor 110,768.00 5,538.40
Jumlah 255,426.70

K.7 SPL 1 MTR PEMASANGAN PIPA HDPE 40 mm

1.000 Meter HDPE 40 mm 22,700.00 22,700.00


0.250 Bh Assesories Pipa 35,000.00 8,750.00
0.150 o/hr Tukang 96,922.00 14,538.30
0.050 o/hr Mandor 110,768.00 5,538.40
Jumlah 51,526.70

K.8 SPL 1 MTR PEMASANGAN PIPA HDPE 50 mm

1.000 Meter HDPE 50 mm 35,200.00 35,200.00


0.250 Bh Assesories Pipa 35,000.00 8,750.00
0.150 o/hr Tukang 96,922.00 14,538.30
0.050 o/hr Mandor 110,768.00 5,538.40
Jumlah 64,026.70

K.9 SPL 1 MTR PEMASANGAN PIPA HDPE 65 mm

1.000 Meter HDPE 65 mm 55,650.00 55,650.00


0.250 Bh Assesories Pipa 35,000.00 8,750.00
0.150 o/hr Tukang 96,922.00 14,538.30
0.050 o/hr Mandor 110,768.00 5,538.40
Jumlah 84,476.70

K.10 SPL 1 MTR PEMASANGAN PIPA HDPE 100 mm

1.000 Meter HDPE 100 mm 150,950.00 150,950.00


0.250 Bh Assesories Pipa 35,000.00 8,750.00
0.150 o/hr Tukang 96,922.00 14,538.30
0.050 o/hr Mandor 110,768.00 5,538.40
Jumlah 179,776.70

K.11 SPL 1 MTR PEMASANGAN PIPA HDPE 15 mm

1.000 Meter HDPE 15 mm 6,500.00 6,500.00


0.250 Bh Assesories Pipa 35,000.00 8,750.00
0.150 o/hr Tukang 96,922.00 14,538.30
0.050 o/hr Mandor 110,768.00 5,538.40
Jumlah 35,326.70

K.12 SPL 1 MTR PEMASANGAN PIPA HDPE 25 mm

1.000 Meter HDPE 25 mm 9,000.00 9,000.00


0.250 Bh Assesories Pipa 35,000.00 8,750.00
0.150 o/hr Tukang 96,922.00 14,538.30
0.050 o/hr Mandor 110,768.00 5,538.40
Jumlah 37,826.70

K.13 SPL 1 MTR PEMASANGAN PIPA HDPE 32 mm

1.000 Meter HDPE 32 mm 14,700.00 14,700.00


0.250 Bh Assesories Pipa 35,000.00 8,750.00
0.150 o/hr Tukang 96,922.00 14,538.30
0.050 o/hr Mandor 110,768.00 5,538.40
Jumlah 43,526.70

K.14 SPL 1 MTR PEMASANGAN PIPA HDPE 80 mm

1.000 Meter HDPE 80 mm 150,950.00 150,950.00


0.250 Bh Assesories Pipa 35,000.00 8,750.00
0.150 o/hr Tukang 96,922.00 14,538.30
0.050 o/hr Mandor 110,768.00 5,538.40
Jumlah 179,776.70
A.4.7.2 HARGA SATUAN PEKERJAAN INSTALASI LISTRIK

Pemasangan 1 titik Lampu A.4.7.2.A


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Tukang Tebas L.02 OH 0.3000 86,043.00 25,812.90
Tukang L.02 OH 0.1500 96,922.00 14,538.30
Mandor L.04 OH 0.0150 110,768.00 1,661.52
JUMLAH TENAGA KERJA 42,012.72
B BAHAN
Kabel NYA (3x2,5) mm M1 12.000 10,500.00 126,000.00
Klem Kabel No. 10 Bh 6.000 1,500.00 9,000.00
Pipa PVC 5/8" M' 11.000 4,250.00 46,750.00
Inbow Dos Bh 3.000 5,000.00 15,000.00
Las Dop Bh 4.000 2,500.00 10,000.00
Isolasi Rol 0.330 10,000.00 3,300.00
T - Dos 5/8" Bh 3.000 7,500.00 22,500.00
Flexible pipe (Kabel ties) M' 1.000 8,000.00 8,000.00
JUMLAH HARGA BAHAN 240,550.00
C PERALATAN
Sewa alat 5% dari harga bahan Ls 1.000 12,027.50 12,027.50
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 282,562.72


E Overhead & Profit (Maksimum 15 %) 10% XD 28,256.27
F Harga Satuan Pekerjaaan (D+E) 310,818.99

Pemasangan 1 M' Kabel NYA 3 X 2,5 mm A.4.7.2.A1


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang L.01 OH 0.0500 86,043.00 4,302.15
Tukang listrik L.02 OH 0.0500 96,922.00 4,846.10
Mandor L.04 OH 0.0250 110,768.00 2,769.20
JUMLAH TENAGA KERJA 11,917.45
B BAHAN
Kabel NYA (3x2,5) mm M1 1.000 10,500.00 10,500.00
Flexible pipe (Kabel ties) M1 1.000 8,000.00 8,000.00
Pipa PVC 5/8" M' 1.000 4,250.00 4,250.00
Isolasi Rol 0.050 10,000.00 500.00
JUMLAH HARGA BAHAN 23,250.00
C PERALATAN
Sewa alat 5% dari harga bahan Ls 1.000 1,162.50 1,162.50
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 35,167.45


E Overhead & Profit (Maksimum 15 %) 10% XD 3,516.75
F Harga Satuan Pekerjaaan (D+E) 38,684.20

Pemasangan 1 titik stop kontak A.4.7.2.B


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.3000 86,043.00 25,812.90
Tukang listrik OH 0.1500 96,922.00 14,538.30
Mandor OH 0.0150 110,768.00 1,661.52
JUMLAH TENAGA KERJA 42,012.72
B BAHAN
Kabel NYA (3x2,5) mm M1 14.000 10,500.00 147,000.00
Klem Kabel No. 10 Bh 6.000 1,500.00 9,000.00
Pipa PVC 5/8" btg 13.000 4,250.00 55,250.00
Inbow Dos Bh 3.000 5,000.00 15,000.00
Las Dop Bh 4.000 2,500.00 10,000.00
Isolasi Rol 0.330 10,000.00 3,300.00
T - Dos 5/8" Bh 3.000 7,500.00 22,500.00
Flexible pipe (Kabel ties) M' 1.000 8,000.00 8,000.00
JUMLAH HARGA BAHAN 262,050.00
C PERALATAN
Sewa alat 5% dari harga bahan Ls 1.000 13,102.50 13,102.50
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 304,062.72


E Overhead & Profit (Maksimum 15 %) 10% XD 30,406.27
F Harga Satuan Pekerjaaan (D+E) 334,468.99

Pemasangan 1 Buah Saklar Tunggal A.4.7.2.C


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Saklar Tunggal Bh 1.000 16,400.00 16,400.00
JUMLAH HARGA BAHAN 16,400.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,230.16


E Overhead & Profit (Maksimum 15 %) 10% XD 2,223.02
F Harga Satuan Pekerjaaan (D+E) 24,453.17

Pemasangan 1 Buah Saklar Ganda A.4.7.2.D


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Saklar Ganda Bh 1.000 20,350.00 20,350.00
JUMLAH HARGA BAHAN 20,350.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 26,180.16


E Overhead & Profit (Maksimum 15 %) 10% XD 2,618.02
F Harga Satuan Pekerjaaan (D+E) 28,798.17

Pemasangan 1 Buah Stop Kontak A.4.7.2.E


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Stop kontak Bh 1.000 17,500.00 17,500.00
JUMLAH HARGA BAHAN 17,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 23,330.16


E Overhead & Profit (Maksimum 15 %) 10% XD 2,333.02
F Harga Satuan Pekerjaaan (D+E) 25,663.17

Pemasangan 1 Buah Lampu TL 2 X 18 Watt A.4.7.2.F


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Lampu TL 2 X 18 watt Bh 1.000 315,000.00 315,000.00
JUMLAH HARGA BAHAN 315,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 320,830.16


E Overhead & Profit (Maksimum 15 %) 10% XD 32,083.02
F Harga Satuan Pekerjaaan (D+E) 352,913.17

Pemasangan 1 Buah Downlight 9 Watt A.4.7.2.G


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Lampu Downlight 9 Watt Bh 1.000 128,000.00 128,000.00
JUMLAH HARGA BAHAN 128,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 133,830.16


E Overhead & Profit (Maksimum 15 %) 10% XD 13,383.02
F Harga Satuan Pekerjaaan (D+E) 147,213.17

Pemasangan 1 Buah Downlight 5 Watt A.4.7.2.H


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Lampu Downlight 5 Watt Bh 1.000 82,000.00 82,000.00
JUMLAH HARGA BAHAN 82,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 87,830.16


E Overhead & Profit (Maksimum 15 %) 10% XD 8,783.02
F Harga Satuan Pekerjaaan (D+E) 96,613.17

Pemasangan 1 Buah Downlight 13 Watt A.4.7.2.I


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Lampu Downlight 13 Watt Bh 1.000 172,500.00 172,500.00
JUMLAH HARGA BAHAN 172,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 178,330.16


E Overhead & Profit (Maksimum 15 %) 10% XD 17,833.02
F Harga Satuan Pekerjaaan (D+E) 196,163.17

Pemasangan 1 Buah Lampu SL 10 Watt A.4.7.2.J


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Lampu SL10 Watt Bh 1.000 36,800.00 36,800.00
JUMLAH HARGA BAHAN 36,800.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 42,630.16


E Overhead & Profit (Maksimum 15 %) 10% XD 4,263.02
F Harga Satuan Pekerjaaan (D+E) 46,893.17

Pemasangan 1 Buah Lampu SL 20 Watt A.4.7.2.K


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Lampu SL 20 Watt Bh 1.000 41,975.00 41,975.00
JUMLAH HARGA BAHAN 41,975.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 47,805.16


E Overhead & Profit (Maksimum 15 %) 10% XD 4,780.52
F Harga Satuan Pekerjaaan (D+E) 52,585.67

Pemasangan 1 Buah Lampu Baret LED 20 Watt A.4.7.2.L


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Lampu Baret LED Phllips Bh 1.000 724,500.00 724,500.00
JUMLAH HARGA BAHAN 724,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 730,330.16


E Overhead & Profit (Maksimum 15 %) 10% XD 73,033.02
F Harga Satuan Pekerjaaan (D+E) 803,363.17

Pemasangan 1 Buah Downlight 8 Watt A.4.7.2.G1


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Lampu Downlight 8 Watt Bh 1.000 90,000.00 90,000.00
JUMLAH HARGA BAHAN 90,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 95,830.16


E Overhead & Profit (Maksimum 15 %) 10% XD 9,583.02
F Harga Satuan Pekerjaaan (D+E) 105,413.17

Pemasangan 1 Buah Downlight 13 Watt Outbow A.4.7.2.G1


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Lampu Downlight 13 Watt outbow Bh 1.000 185,000.00 185,000.00
JUMLAH HARGA BAHAN 185,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 190,830.16


E Overhead & Profit (Maksimum 15 %) 10% XD 19,083.02
F Harga Satuan Pekerjaaan (D+E) 209,913.17

Pemasangan 1 Buah Titik Power 1 Phasa A.4.7.2.N


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Pipa listrik 5/8” Btg 1.2500 4,050.00 5,062.50
Kabel NYY 3 x 2,5 (metal Kabel) m 20.000 10,350.00 207,000.00
Tduz Bh 1.000 6,750.00 6,750.00
JUMLAH HARGA BAHAN 218,812.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 224,642.66


E Overhead & Profit (Maksimum 15 %) 10% XD 22,464.27
F Harga Satuan Pekerjaaan (D+E) 247,106.92

Pemasangan 1 Unit Exhaust A.4.7.2.O


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Exhoust Bh 1.000 350,000.00 350,000.00
Perlengkapan % 30.000 105,000.00 105,000.00

JUMLAH HARGA BAHAN 455,000.00


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 460,830.16


E Overhead & Profit (Maksimum 15 %) 10% XD 46,083.02
F Harga Satuan Pekerjaaan (D+E) 506,913.17
Pemasangan 1 M2 Railling Stainless Steel A.4.2.1.10a
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.350 86,043.00 30,115.05
Tukang L.02 OH 0.350 96,922.00 33,922.70
Kepala Tukang L.03 OH 0.035 128,570.00 4,499.95
Mandor L.04 OH 0.018 110,768.00 1,993.82
JUMLAH TENAGA KERJA 70,531.52
B BAHAN
Stainless Steel Dia 5 cm M1 1.100 58,500.00 64,350.00
Pemasangan Besi Plat 6 mm Kg 0.319 10,000.00 3,187.50
Baut fisher Bh 4.000 1,500.00 6,000.00
Assesoris (perkuatan, las dll) Ls 1.000 30,000.00 30,000.00

JUMLAH HARGA BAHAN 103,537.50


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 174,069.02


E Overhead & Profit (Maksimum 15 %) 10% XD 17,406.90
F Harga Satuan Pekerjaaan (D+E) 191,475.93

Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 1 lapis cat mutakhir A.4.7.1.19
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0600 86,043.00 5,162.58
Tukang L.02 OH 0.0600 96,922.00 5,815.32
Kepala Tukang L.03 OH 0.0120 128,570.00 1,542.84
Mandor L.04 OH 0.0030 110,768.00 332.30
JUMLAH TENAGA KERJA 12,853.04
B BAHAN
Cat Kg 0.0800 207,900.00 16,632.00
Kuas Bh 0.0100 32,950.00 329.50
Pengencer Liter 0.0100 12,000.00 120.00
JUMLAH HARGA BAHAN 17,081.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 29,934.54


E Overhead & Profit (Maksimum 15 %) 10% X D 2,993.45
F Harga Satuan Pekerjaaan (D+E) 32,928.00

Pemasangan 1 buah urinoir A.5.1.1 4


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja OH 1.0000 86,043.00 86,043.00
Tukang Batu OH 1.0000 96,922.00 96,922.00
Kepala Tukang OH 0.1000 128,570.00 12,857.00
Mandor OH 0.0500 110,768.00 5,538.40
JUMLAH TENAGA KERJA 201,360.40
B BAHAN
Urinoir Unit 1.000 1,100,000.00 1,100,000.00
Semen @ 40 Kg Kg 6.000 1,000.00 6,000.00
Pasir pasang M3 0.010 155.00 1.55
Perlengkapan 30 % harga urinoir % 0.300 1,100,000.00 330,000.00
JUMLAH HARGA BAHAN 1,436,001.55
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,637,361.95


E Overhead & Profit (Maksimum 15 %) 10% XD 163,736.20
F Harga Satuan Pekerjaaan (D+E) 1,801,098.15
Pemasangan 1 Buah Lampu TL 2 X 18 Watt (V-shape) A.4.7.2.F
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 86,043.00 430.22
Tukang listrik OH 0.0500 96,922.00 4,846.10
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 5,830.16
B BAHAN
Lampu TL 2 X 18 watt (V-shape) Bh 1.000 395,000.00 395,000.00
JUMLAH HARGA BAHAN 395,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 400,830.16


E Overhead & Profit (Maksimum 15 %) 10% XD 40,083.02
F Harga Satuan Pekerjaaan (D+E) 440,913.17

Pekerjaan 1 M2 floor Hardener A.4.4.3.30


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja OH 0.120 86,043.000 10,325.160
Tukang Batu OH 0.120 96,922.000 11,630.640
Kepala Tukang OH 0.012 128,570.000 1,542.840
Mandor OH 0.006 110,768.000 664.608
JUMLAH TENAGA KERJA 24,163.248
B BAHAN
Drymix Floor Hardener @25 kg Kg 1.000 90,000.00 90,000.000
JUMLAH HARGA BAHAN 90,000.000
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 114,163.248


E Overhead & Profit (Maksimum 15 %) 10% X D 11,416.325
F Harga Satuan Pekerjaaan (D+E) 125,579.573

Pemasangan 1 Buah Lampu Taman ED 40 W A.4.7.2.G1


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pembantu tukang OH 0.0050 96,922.00 484.61
Tukang listrik OH 0.0500 128,570.00 6,428.50
Mandor OH 0.0050 110,768.00 553.84
JUMLAH TENAGA KERJA 7,466.95
B BAHAN
Lampu Taman ED 40 W Bh 1.000 130,000.00 130,000.00
JUMLAH HARGA BAHAN 130,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 137,466.95


E Overhead & Profit (Maksimum 15 %) 10% XD 13,746.70
F Harga Satuan Pekerjaaan (D+E) 151,213.65

Pemasangan 1 m’ pipa PVC tipe AW diameter


A.5.1.1 19
1/2”
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja OH 0.0360 86,043.00 3,097.55
Tukang Batu OH 0.0600 96,922.00 5,815.32
Kepala Tukang OH 0.0060 128,570.00 771.42
Mandor OH 0.0020 110,768.00 221.54
JUMLAH TENAGA KERJA 9,905.82
B BAHAN
Pipa PVC Ø 1/2" Kualitas AWE (United) M 1.200 6,300.00 7,560.00
Perlengkapan Ls 0.350 6,300.00 2,205.00
JUMLAH HARGA BAHAN 7,560.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 17,465.82


E Overhead & Profit (Maksimum 15 %) 10% 1,746.58
F Harga Satuan Pekerjaaan (D+E) 19,212.41

Pemasangan 1 m’ pipa PVC tipe AW diameter


A.5.1.1 19
2”
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja OH 0.0360 86,043.00 3,097.55
Tukang Batu OH 0.0600 96,922.00 5,815.32
Kepala Tukang OH 0.0060 128,570.00 771.42
Mandor OH 0.0020 110,768.00 221.54
JUMLAH TENAGA KERJA 9,905.82
B BAHAN
Pipa PVC Ø 2" M 1.200 25,000.00 30,000.00
Perlengkapan Ls 0.350 25,000.00 8,750.00
JUMLAH HARGA BAHAN 30,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 39,905.82


E Overhead & Profit (Maksimum 15 %) 10% 3,990.58
F Harga Satuan Pekerjaaan (D+E) 43,896.41
V2 AP Pekerjaan Ventilasi V2
0.0800 M1 Rangka aluminium 4" x 1 3/4" @ Rp. 163,169.05 Rp 13,053.52
0.0500 M1 Bingkai Ventilasi Aluminium @ Rp. 73,574.05 Rp 3,678.70
Total Rp 16,732.23

Pekerjaan Aluminium Strip 80 mm


0.0800 M1 Rangka aluminium 4" x 1 3/4" @ Rp. 163,169.05 Rp 13,053.52
1.0000 m2 Aluminium Strip 80 mm @ Rp. 60,500.00 Rp 60,500.00
Total Rp 73,553.52

P4 AP 1 Bh Pekerjaan pintu
5.3000 M1 Rangka aluminium 4" x 1 3/4" @ Rp. 149,196.85 Rp 790,743.31
0.2060 M1 Bingkai Ventilasi aluminium @ Rp. 69,180.10 Rp 14,251.10
0.1600 M2 Kaca bening 5 mm (ventilasi) @ Rp. 209,120.45 Rp 33,459.27
4.0000 Bh Engsel Pintu @ Rp. 64,555.70 Rp 258,222.80
1.0000 Bh Kunci tanam 2x slag @ Rp. 265,595.00 Rp 265,595.00
1.0000 Bh Grendel pintu tanam @ Rp. 138,303.00 Rp 138,303.00
1.0000 Set pegangan pintu @ Rp. 94,500.00 Rp 94,500.00
Total Rp 1,595,074.48
Analisa : A. 2.2.1.9
Item : Pembersihan lapangan dan perataan
Satuan : m2

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.075 Rp. 86,043.00 Rp. 6,453.23
Mandor L.04 OH 0.008 Rp. 110,768.00 Rp. 830.76
Jumlah Tenaga Kerja (A) Rp. 7,283.99
B BAHAN
Kerosen / Minyak Tanah (Industri) Hr 0.010 Rp. 15,375.00 Rp. 153.75

Jumlah Harga Bahan (B) Rp. 153.75


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 7,437.74
E Overhead & Profit 10% x D Rp. 743.77
F Harga Satuan Pekerjaan ( D + E ) Rp. 8,181.51
G Dibulatkan Rp. 8,181.00
Analisa :
Item : Galian Tanah Biasa
Satuan : m3

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.563 Rp. 86,043.00 Rp. 48,442.21
Mandor L.04 OH 0.056 Rp. 110,768.00 Rp. 6,236.24
Jumlah Tenaga Kerja (A) Rp. 54,678.45
B BAHAN

Jumlah Harga Bahan (B) Rp -


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 54,678.45
E Overhead & Profit 10% x D Rp. 5,467.84
F Harga Satuan Pekerjaan ( D + E ) Rp. 60,146.29
G Dibulatkan Rp. 60,146.00
Analisa :
Item : Mobilisasi dan demobilisasi
Satuan : Ls

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A Mobilisasi
Excavator Jam 4.000 Rp. 278,000.00 Rp. 1,112,000.00
Dump Truck Jam 5.000 Rp. 205,000.00 Rp. 1,025,000.00
Peralatan Lain Ls 6.000 Rp. 150,000.00 Rp. 900,000.00

Jumlah Mobilisasi (A) Rp. 3,037,000.00


B Demobiliasi
Excavator Jam 4.000 Rp. 278,000.00 Rp. 1,112,000.00
Dump Truck Jam 8.000 Rp. 205,000.00 Rp. 1,640,000.00
Peralatan Lain Ls 1.000 Rp. 150,000.00 Rp. 150,000.00

Jumlah Demoblisasi (B) Rp. 2,902,000.00


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 5,939,000.00
E Overhead & Profit 10% x D Rp. 593,900.00
F Harga Satuan Pekerjaan ( D + E ) Rp. 6,532,900.00
G Dibulatkan Rp. 6,532,900.00
Analisa :
Item : Galian Tanah Menggunakan Alat
Satuan : m3

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.218 Rp. 86,043.00 Rp. 18,740.17
Mandor L.04 OH 0.022 Rp. 110,768.00 Rp. 2,414.74
Jumlah Tenaga Kerja (A) Rp. 21,154.91
B BAHAN

Jumlah Harga Bahan (B) Rp -


C PERALATAN
Excavator Bh 0.036 Rp. 258,000.00 Rp 9,365.40

Jumlah Harga Alat (C) Rp. 9,365.40


D Jumlah ( A + B + C ) Rp. 30,520.31
E Overhead & Profit 10% x D Rp. 3,052.03
F Harga Satuan Pekerjaan ( D + E ) Rp. 33,572.34
G Dibulatkan Rp. 33,572.00
Analisa :
Item : Pekerjaan Pasangan batu kosong Ø0.05-0.10 m
Satuan : M3

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A Tenaga
Pekerja L.01 OH 1.000 Rp. 86,043.00 Rp. 86,043.00
Tukang L.02 OH 0.500 Rp. 96,922.00 Rp. 48,461.00
Kepala Tukang L.03 OH 0.050 Rp. 128,570.00 Rp. 6,428.50
Mandor L.04 OH 0.100 Rp. 110,768.00 Rp. 11,076.80

Jumlah Tenaga Kerja (A) Rp. 152,009.30


B Bahan
Batu Kali / Batu Belah (Sungai / Gunung) M3 1.200 Rp. 165,000.00 Rp. 198,000.00

Jumlah Harga Bahan (B) Rp. 198,000.00


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 350,009.30
E Overhead & Profit 10% x D Rp. 35,000.93
F Harga Satuan Pekerjaan ( D + E ) Rp. 385,010.23
G Dibulatkan Rp. 385,010.23
Analisa :
Item : Pekerjaan Plesteran Drainase 1PC:3PP tebl 15 mm
Satuan : m2

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A Tenaga
Pekerja L.01 OH 0.300 Rp. 86,043.00 Rp. 25,812.90
Tukang L.02 OH 0.150 Rp. 96,922.00 Rp. 14,538.30
Kepala Tukang L.03 OH 0.015 Rp. 128,570.00 Rp. 1,928.55
Mandor L.04 OH 0.015 Rp. 110,768.00 Rp. 1,661.52

Jumlah Tenaga Kerja (A) Rp. 43,941.27


B Bahan
Pasir Pasang (1400 kg/m3) M3 0.030 Rp. 217,000.00 Rp. 6,510.00
Semen @ 50 Kg Kg 7.78 Rp. 3,000.00 Rp. 23,328.00

Jumlah Harga Bahan (B) Rp. 29,838.00


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 73,779.27
E Overhead & Profit 10% x D Rp. 7,377.93
F Harga Satuan Pekerjaan ( D + E ) Rp. 81,157.20
G Dibulatkan Rp. 81,157.20
Analisa : AHSP A.4.1.1.3
Item : Membuat Beton Mutu f'c = 12.2 MPa (K-150), Slump (12 ± 2 ) cm, w/c = 0.72
Satuan : m3

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.650 Rp. 86,043.00 Rp. 141,970.95
Tukang L.02 OH 0.275 Rp. 96,922.00 Rp. 26,653.55
Kepala Tukang L.03 OH 0.028 Rp. 128,570.00 Rp. 3,599.96
Mandor L.04 OH 0.083 Rp. 110,768.00 Rp. 9,138.36
Jumlah Tenaga Kerja (A) Rp. 181,362.82
B BAHAN
Semen @ 40 Kg Kg 299.000 Rp. 1,000.00 Rp. 299,000.00
Pasir Beton (1400 kg/m3) Kg 799.000 Rp. 107.14 Rp. 85,607.14
Kerikil (1350 kg/m3) Kg 1,017.000 Rp. 107.41 Rp. 109,233.33
Air Liter 215.000 Rp. 65.00 Rp. 13,975.00

Jumlah Harga Bahan (B) Rp. 507,815.48


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 689,178.30
E Overhead & Profit 10% x D Rp. 68,917.83
F Harga Satuan Pekerjaan ( D + E ) Rp. 758,096.13
G Dibulatkan Rp. 758,096.13
AHSP A.4.1.1. HARGA SATUAN PEKERJAAN BETON

Analisa : AHSP A.4.1.1.1


Item : Membuat Beton Mutu f'c = 7.4 MPa (K-100), Slump (12 ± 2 ) cm, w/c = 0.87
Satuan : m3

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.650 Rp. 86,043.00 Rp. 141,970.95
Tukang L.02 OH 0.275 Rp. 96,922.00 Rp. 26,653.55
Kepala Tukang L.03 OH 0.028 Rp. 128,570.00 Rp. 3,599.96
Mandor L.04 OH 0.083 Rp. 110,768.00 Rp. 9,193.74
Jumlah Tenaga Kerja (A) Rp. 181,418.20
B BAHAN
Semen @ 40 Kg Kg 247.000 Rp. 1,000.00 Rp. 247,000.00
Pasir Beton (1400 kg/m3) Kg 869.000 Rp. 107.14 Rp. 93,107.14
Kerikil (1350 kg/m3) Kg 999.000 Rp. 107.41 Rp. 107,300.00
Air Liter 215.000 Rp. 65.00 Rp. 13,975.00

Jumlah Harga Bahan (B) Rp. 461,382.14


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 642,800.35
E Overhead & Profit 10% x D Rp. 64,280.03
F Harga Satuan Pekerjaan ( D + E ) Rp. 707,080.38
G Dibulatkan Rp. 707,080.38
Analisa : AHSP A.4.1.1.17.a
Item : Pembesian 10 Kg Dengan Besi Beton Polos/Ulir
Satuan : Kg

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.700 Rp. 86,043.00 Rp. 60,230.10
Tukang L.02 OH 0.700 Rp. 96,922.00 Rp. 67,845.40
Kepala Tukang L.03 OH 0.070 Rp. 128,570.00 Rp. 8,999.90
Mandor L.04 OH 0.070 Rp. 110,768.00 Rp. 7,753.76
Jumlah Tenaga Kerja (A) Rp. 144,829.16
B BAHAN
Besi Beton Ulir Kg 10.500 Rp. 14,000.00 Rp. 147,000.00
Kawat Beton Kg 1.500 Rp. 9,500.00 Rp. 14,250.00

Jumlah Harga Bahan (B) Rp. 161,250.00


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 306,079.16
E Overhead & Profit 10% x D Rp. 30,607.92
F Harga Satuan Pekerjaan ( D + E ) Rp. 336,687.08
G Harga Satuan Pekerjaan Besi Untuk 1 Kg F / 10 Rp. 33,668.71
H Dibulatkan Rp. 33,668.71
Analisa : AHSP A.4.1.1.23
Item : Pemasangan Bekesting Untuk Balok
Satuan : m2

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.660 Rp. 86,043.00 Rp. 56,788.38
Tukang L.02 OH 0.330 Rp. 96,922.00 Rp. 31,984.26
Kepala Tukang L.03 OH 0.033 Rp. 128,570.00 Rp. 4,242.81
Mandor L.04 OH 0.033 Rp. 110,768.00 Rp. 3,655.34
Jumlah Tenaga Kerja (A) Rp. 96,670.79
B BAHAN
Kayu Kelas III (Borneo/dll) M3 0.040 Rp. 4,500,000.00 Rp. 180,000.00
Paku Biasa 5 cm - 10 cm Kg 0.400 Rp. 20,000.00 Rp. 8,000.00
Minyak Bekesting Liter 0.200 Rp. 6,500.00 Rp. 1,300.00
Kayu Kelas II (Kamper/Kruing/dll) M3 0.018 Rp. 5,500,000.00 Rp. 99,000.00
Multipleks 9 mm Lembar 0.350 Rp. 135,000.00 Rp. 47,250.00
Kayu Dolken Ø 8-10/400 cm Batang 2.000 Rp. 17,000.00 Rp. 34,000.00
Jumlah Harga Bahan (B) Rp. 369,550.00
C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 466,220.79
E Overhead & Profit 10% x D Rp. 46,622.08
F Harga Satuan Pekerjaan ( D + E ) Rp. 512,842.87
G Untuk 2x Pemakaian Rp. 256,421.44
H Dibulatkan Rp. 256,421.44
Analisa : AHSP A.2.2.1.9
Item : Pembersihan Lapangan dan Perataan
Satuan : m2

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 Rp. 86,043.00 Rp. 8,604.30
Tukang Kayu L.02 OH - Rp. 96,922.00 Rp -
Kepala Tukang L.03 OH - Rp. 128,570.00 Rp -
Mandor L.04 OH 0.050 Rp. 110,768.00 Rp. 5,538.40
Jumlah Tenaga Kerja (A) Rp. 14,142.70
B BAHAN

Jumlah Harga Bahan (B) Rp -


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 14,142.70
E Overhead & Profit 10% x D Rp. 1,414.27
F Harga Satuan Pekerjaan ( D + E ) Rp. 15,556.97
G Dibulatkan Rp. 15,556.00
Analisa :
Item : Pekerjaan Timbunan dan pemadatan
Satuan : m3

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A Tenaga
Pekerja L.01 OH 0.330 Rp. 86,043.00 Rp. 28,394.19
Mandor L.04 OH 0.033 Rp. 110,768.00 Rp. 3,655.34

Jumlah Tenaga Kerja (A) Rp. 32,049.53


B Bahan

Jumlah Harga Bahan (B) Rp -


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 32,049.53
E Overhead & Profit 10% x D Rp. 3,204.95
F Harga Satuan Pekerjaan ( D + E ) Rp. 35,254.49
G Dibulatkan Rp. 35,254.49
Analisa : AHSP A.4.1.1.7
Item : Membuat Beton Mutu f'c = 19.3 MPa (K-225), Slump (12 ± 2 ) cm, w/c = 0.58
Satuan : m3

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.650 Rp. 86,043.00 Rp. 141,970.95
Tukang L.02 OH 0.275 Rp. 96,922.00 Rp. 26,653.55
Kepala Tukang L.03 OH 0.028 Rp. 128,570.00 Rp. 3,599.96
Mandor L.04 OH 0.083 Rp. 110,768.00 Rp. 9,193.74
Jumlah Tenaga Kerja (A) Rp. 181,418.20
B BAHAN
Semen @ 40 Kg Kg 371.000 Rp. 1,000.00 Rp. 371,000.00
Pasir Beton (1400 kg/m3) M3 698.000 Rp. 107.14 Rp. 74,785.71
Batu pecah 2-3 cm Kg 1,047.000 Rp. 111.11 Rp. 116,333.33
Air Liter 215.000 Rp. 65.00 Rp. 13,975.00

Jumlah Harga Bahan (B) Rp. 576,094.05


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 757,512.25
E Overhead & Profit 10% x D Rp. 75,751.23
F Harga Satuan Pekerjaan ( D + E ) Rp. 833,263.48
G Dibulatkan Rp. 833,263.48
Analisa :
Item : Pemasangan Pintu Air
Satuan : Bh

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A Tenaga
Pekerja L.01 OH 2.300 Rp. 86,043.00 Rp. 197,898.90
Tukang L.02 OH 1.330 Rp. 96,922.00 Rp. 128,906.26
Kepala Tukang L.03 OH 2.330 Rp. 128,570.00 Rp. 299,568.10
Mandor L.04 OH 0.033 Rp. 110,768.00 Rp. 3,655.34

Jumlah Tenaga Kerja (A) Rp. 630,028.60


B Bahan
Besi Beton Polos Kg 6.90 Rp. 4,000.00 Rp. 27,600.00
Kawat Las Kg 1.53 Rp. 9,700.00 Rp. 14,841.00
Campuran Beton m3 0.07 Rp. 707,080.38 Rp. 48,788.55
Pasangan Bata m3 0.14 Rp. 1,397,296.52 Rp. 192,826.92

Jumlah Harga Bahan (B) Rp. 284,056.47


C PERALATAN
Pintu air T.2000x B 800mm Buah 1.00 Rp. 7,000,000.00 Rp. 7,000,000.00
Tackle/tripod tinggi 4 - 5 m Sewa/Hr 0.35 Rp. 25,000.00 Rp. 8,625.00
Mesin Las Sewa/Hr 0.35 Rp. 100,000.00 Rp. 34,500.00

Jumlah Harga Alat (C) Rp. 7,043,125.00


D Jumlah ( A + B + C ) Rp. 7,957,210.07
E Overhead & Profit 0% x D Rp -
F Harga Satuan Pekerjaan ( D + E ) Rp. 7,957,210.07
G Dibulatkan Rp. 7,957,210.07
Analisa :
Item : Analisa Keamanan dan K3
Satuan : Ls

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A Penyiapan RKK
Pembuatan Dokumen Rencana Keselamatan
#N/A #N/A 1.000 Rp. 500,000.00 Rp. 500,000.00
Konstruksi

Jumlah Tenaga Kerja (A) Rp. 500,000.00


B Sosialisasi, Promosi dan Pelatihan
Spanduk #N/A 2.00 Rp. 200,000.00 Rp. 400,000.00

Jumlah Harga Bahan (B) Rp. 400,000.00


C Alat Pelindung Kerja dan pelindung diri
Biaya Alat Pelindung Diri (APD)
Topi Pelindung #N/A 30.00 Rp. 50,000.00 Rp. 1,500,000.00
Sarung Tangan #N/A 30.00 Rp. 25,000.00 Rp. 750,000.00
Sepatu Safety #N/A 30.00 Rp. 350,000.00 Rp. 10,500,000.00
Masker #N/A 10.00 Rp. 15,000.00 Rp. 150,000.00
Hand sanitizer #N/A 5.00 Rp. 25,000.00 Rp. 125,000.00

Jumlah Harga Alat (C) Rp. 13,025,000.00


D Asuransi dan Perizinan
Asuransi/BPJS Ketenagakerjaan #N/A 1.00 Rp - Rp -

Jumlah Harga Bahan (D) Rp -


E Biaya Personil K3 Konstruksi
Biaya Petugas K3 #N/A 6.00 Rp. 2,500,000.00 Rp. 15,000,000.00

Jumlah Harga Bahan (E) Rp. 15,000,000.00


F Biaya Fasilitas, Sarana dan Prasarana Kesehatan
Peralatan P3K #N/A 1.00 Rp. 500,000.00 Rp. 500,000.00

Jumlah Harga Bahan (F) Rp. 250,000.00


D Jumlah ( A + B + C ) Rp. 29,300,000.00
E Overhead & Profit 0% x D Rp -
F Harga Satuan Pekerjaan ( D + E ) Rp. 29,300,000.00
G Dibulatkan Rp. 29,300,000.00
Analisa :
Item : Kist dam pasir/ tanah
Satuan : Bh

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A Tenaga
Pekerja L.01 OH 0.040 Rp. 86,043.00 Rp. 3,441.72
Mandor L.04 OH 0.004 Rp. 110,768.00 Rp. 443.07

Jumlah Tenaga Kerja (A) Rp. 3,884.79


B Bahan
Karung Plastik bh 1.00 Rp. 2,800.00 Rp. 2,800.00
Tali Rapia m 2.00 Rp. 500.00 Rp. 1,000.00
Sewa Pasir m3 0.12 Rp. 280,000.00 Rp. 33,600.00

Jumlah Harga Bahan (B) Rp. 37,400.00


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 41,284.79
E Overhead & Profit 0% x D Rp -
F Harga Satuan Pekerjaan ( D + E ) Rp. 41,284.79
G Dibulatkan Rp. 41,284.79
Analisa : AHSP A.3.2.1.10
Item : Pemasangan Pondasi Siklop, 60% Beton Campuran 1 SP : 2 PB : 3 Kr dan 40% Batu Belah
Satuan : m3

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 3.400 Rp. 86,043.00 Rp. 292,546.20
Tukang Batu L.02 OH 0.850 Rp. 96,922.00 Rp. 82,383.70
Kepala Tukang L.03 OH 0.085 Rp. 128,570.00 Rp. 10,928.45
Mandor L.04 OH 0.170 Rp. 110,768.00 Rp. 18,830.56
Jumlah Tenaga Kerja (A) Rp. 404,688.91
B BAHAN
Batu Kali / Batu Belah (Sungai / Gunung) M3 0.480 Rp. 165,000.00 Rp. 79,200.00
Semen @ 40 Kg Kg 194.000 Rp. 1,000.00 Rp. 194,000.00
Pasir Beton (1400 kg/m3) M3 0.312 Rp. 150,000.00 Rp. 46,800.00
Kerikil (1350 kg/m3) M3 0.468 Rp. 145,000.00 Rp. 67,860.00
Besi Beton Polos Kg 126.000 Rp. 4,000.00 Rp. 504,000.00
Kawat Beton Kg 1.800 Rp. 9,500.00 Rp. 17,100.00

Jumlah Harga Bahan (B) Rp. 908,960.00


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 1,313,648.91
E Overhead & Profit 10% x D Rp. 131,364.89
F Harga Satuan Pekerjaan ( D + E ) Rp. 1,445,013.80
G Dibulatkan Rp. 1,445,013.00
AHSP A.4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

Analisa : AHSP A.4.2.1.1


Item : Pemasangan Besi profil
Satuan : Kg

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.060 Rp. 86,043.00 Rp. 5,162.58
Tukang L.02 OH 0.060 Rp. 96,922.00 Rp. 5,815.32
Kepala Tukang L.03 OH 0.006 Rp. 128,570.00 Rp. 771.42
Mandor L.04 OH 0.003 Rp. 110,768.00 Rp. 332.30
Jumlah Tenaga Kerja (A) Rp. 12,081.62
B BAHAN
Besi Profil Kg 1.150 Rp. 16,700.00 Rp. 19,205.00

Jumlah Harga Bahan (B) Rp. 19,205.00


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 31,286.62
E Overhead & Profit 10% x D Rp. 3,128.66
F Harga Satuan Pekerjaan ( D + E ) Rp. 34,415.29
G Dibulatkan Rp. 34,415.00
Analisa :
Item : Pasangan Batu Kali dengan campuran Mortar 1PC:3PP
Satuan : M3

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A Tenaga
Pekerja L.01 OH 2.700 Rp. 86,043.00 Rp. 232,316.10
Tukang L.02 OH 0.900 Rp. 96,922.00 Rp. 87,229.80
Kepala Tukang L.03 OH 0.090 Rp. 128,570.00 Rp. 11,571.30
Mandor L.04 OH 0.270 Rp. 110,768.00 Rp. 29,907.36

Jumlah Tenaga Kerja (A) Rp. 361,024.56


B Bahan
Batu Kali / Batu Belah (Sungai / Gunung) M3 1.200 Rp. 165,000.00 Rp. 198,000.00
Pasir Pasang (1400 kg/m3) M3 0.485 Rp. 217,000.00 Rp. 105,245.00
Semen @ 50 Kg Kg 202 Rp. 3,000.00 Rp. 606,000.00

Jumlah Harga Bahan (B) Rp. 909,245.00


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 1,270,269.56
E Overhead & Profit 10% x D Rp. 127,026.96
F Harga Satuan Pekerjaan ( D + E ) Rp. 1,397,296.52
G Dibulatkan Rp. 1,397,296.52
Analisa : AHSP A.4.1.1.23
Item : Balok Beton Biasa
Satuan : m3

Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.360 Rp. 86,043.00 Rp. 30,975.48
Tukang L.02 OH 0.180 Rp. 96,922.00 Rp. 17,445.96
Kepala Tukang L.03 OH 0.018 Rp. 128,570.00 Rp. 2,314.26
Mandor L.04 OH 0.036 Rp. 110,768.00 Rp. 3,987.65
Jumlah Tenaga Kerja (A) Rp. 54,723.35
B BAHAN
Kayu Kelas II (Kamper/Kruing/dll) M3 0.014 Rp. 5,500,000.00 Rp. 77,000.00
Paku Biasa 5 cm - 10 cm Kg 0.008 Rp. 20,000.00 Rp. 160.00
Minyak Bekesting Liter 0.300 Rp. 6,500.00 Rp. 1,950.00
Kayu 5 x 7, Kayu Kelas II M3 0.200 Rp. 6,765,000.00 Rp. 1,353,000.00

Jumlah Harga Bahan (B) Rp. 1,432,110.00


C PERALATAN

Jumlah Harga Alat (C) Rp -


D Jumlah ( A + B + C ) Rp. 1,486,833.35
E Overhead & Profit 10% x D Rp. 148,683.33
F Harga Satuan Pekerjaan ( D + E ) Rp. 1,635,516.68
G Untuk 2x Pemakaian Rp. 817,758.34
H Dibulatkan Rp. 817,758.34
HARGA DASAR SATUAN BAHAN
Harga Satuan
No. Tenaga Kerja Satuan Keterangan
(Rp.)

1 Air Liter Rp. 65.00


2 Alluminium Foil DS m2 Rp. 16,000.00
3 Atap Aspal Bitumen CT3 Lembar Rp. 172,000.00
4 Underlayment Anti Bocor Atap m2 Rp. 64,000.00
5 Bambu Batang Rp. 123,000.00
6 Batu Bata Buah Rp. 700.00
7 Bata Ringan Tebal 7.5 cm Bh Rp. 9,000.00
8 Bata Ringan Tebal 10 cm Bh Rp. 12,000.00
9 Batu Kali / Batu Belah (Sungai / Gunung) M3 Rp. 165,000.00
10 Batang Kelapa Batang Rp. 307,500.00
11 Batu pecah 2-3 cm (1350 Kg/m3) M3 Rp. 150,000.00
12 Batu pecah 2-3 cm Kg Rp. 111.11
13 Batu Granit Kg Rp. 16,000.00
14 Batu Tempel Bh Rp. 16,500.00
15 Baut Kap Ø 1/2 - 8 Buah Rp. 5,535.00
16 Bensin (Industri) Liter Rp. 12,300.00
17 Besi Beton Polos Kg Rp. 4,000.00
18 Besi Beton Ulir Kg Rp. 14,000.00
19 Besi Hollow 40.40.2 mm m Rp. 22,000.00
20 Besi Profil Kg Rp. 16,700.00
21 Besi Siku L 30.30.3 Kg Rp. 12,500.00
22 Beton Rooster / Kerawang Buah Rp. 4,000.00
23 Bubungan Atap Aspal Bitumen M' Rp. 51,950.00
24 Cat Dasar Kg Rp. 28,000.00
25 Cat Kayu Mengkilat Kg Rp. 71,340.00
26 Cat Menie Kg Rp. 30,750.00
27 Cat Penutup Exterior Setara Jotun Kg Rp. 35,000.00
28 Cat Penutup Interior Setara Jotun Kg Rp. 65,000.00
29 Dempul Kg Rp. 30,750.00
30 Floor Drain Setara Toto Buah Rp. 280,000.00
31 Gypsum ( 120 x 240 cm ) Lembar Rp. 116,850.00
32 Gravel M3 Rp. 160,000.00
33 Granit Uk. 60 x 60 cm Polished Bh Rp. 86,400.00
34 Granit Uk. 60 x 60 cm Unpolished Bh Rp. 115,200.00
35 Granit Uk. 40 x 40 cm Bh Rp. 56,000.00
36 Granit Uk. 60 x 120 cm Bh Rp. 380,000.00
37 Ijuk Kg Rp. 12,300.00
38 Ijuk m3 Rp. 400,000.00
39 Kawat Beton Kg Rp. 9,500.00
40 Kawat Las Kg Rp. 9,700.00
41 Kayu Kelas I (Seumantok/Ulin/dll) M3 Rp. 6,765,000.00
42 Kayu Kelas II (Kamper/Kruing/dll) M3 Rp. 5,500,000.00
HARGA DASAR SATUAN BAHAN
Harga Satuan
No. Tenaga Kerja Satuan Keterangan
(Rp.)

43 Kayu Kelas III (Borneo/dll) M3 Rp. 4,500,000.00


44 Kayu Kelas IV (Sengon/dll) M3 Rp. 3,500,000.00
HARGA DASAR SATUAN BAHAN
Harga Satuan
No. Tenaga Kerja Satuan Keterangan
(Rp.)

45 Kayu Dolken Ø 8-10/400 cm Batang Rp. 17,000.00


46 Kayu 5 x 7, Kayu Kelas II M3 Rp. 6,765,000.00
47 Kayu Reng, Kayu Kelas II M3 Rp. 6,765,000.00
48 Keramik Uk. 20 x 20 cm (Polished) Bh Rp. 2,853.60
49 Keramik Uk. 30 x 30 cm (Polished) Bh Rp. 6,642.00
50 Keramik Uk. 33 x 33 cm (Polished) Bh Rp. 8,036.82
51 Keramik Uk. 40 x 40 cm (Polished) Bh Rp. 12,792.00
52 Keramik Uk. 20 x 20 cm (Unpolished) Bh Rp. 3,198.00
53 Keramik Uk. 30 x 30 cm (Unpolished) Bh Rp. 7,195.50
54 Keramik Uk. 33 x 33 cm (Unpolished) Bh Rp. 8,706.56
55 Keramik Uk. 40 x 40 cm (Unpolished) Bh Rp. 12,792.00
56 Kerosen / Minyak Tanah (Industri) Liter Rp. 15,375.00
57 Kerosen / Minyak Tanah (Subsidi) Liter Rp. 11,070.00
58 Kertas Amplas Lembar Rp. 6,150.00
59 Kerikil (1350 kg/m3) M3 Rp. 145,000.00
60 Kerikil Kg Rp. 160.74
61 Kloset Duduk Keramik Buah Rp. 3,280,000.00
62 Kloset Jongkok Keramik Buah Rp. 860,000.00
63 Koral Beton M3 Rp. 140,000.00
64 Kran Air Dia. 1/2" - 3/4" Bh Rp. 75,000.00
65 Minyak Cat Liter Rp. 30,000.00
66 Minyak Bekesting Liter Rp. 6,500.00
67 Minyak Pelumas Liter Rp. 12,400.00
68 Mortar Siap Pakai (MSP) Kg Rp. 6,000.00
69 Mortar Utama 380 ( 40 kg ) Zak Rp. 28,000.00
70 Multipleks 3 mm Lembar Rp. 55,350.00
71 Multipleks 4 mm Lembar Rp. 79,950.00
72 Multipleks 6 mm Lembar Rp. 104,550.00
73 Multipleks 9 mm Lembar Rp. 135,000.00
74 Paku Tripleks Kg Rp. 22,140.00
75 Paku Beton 8" Kotak Rp. 18,400.00
76 Paku Beton 4" Kotak Rp. 24,000.00
77 Paku 12 cm Bh Rp. 150.00
78 Paku Kayu 2" - 3" Kg Rp. 20,000.00
79 Paku Biasa 1/2" - 1" Kg Rp. 20,000.00
80 Paku Biasa 5 cm - 10 cm Kg Rp. 20,000.00
81 Paku Biasa 5 cm - 12 cm Kg Rp. 20,000.00
82 Paku Kayu Kg Rp. 20,000.00
83 Paku Reng Kg Rp. 15,498.00
84 Paku Seng Kg Rp. 18,450.00
85 Paku skrup 10 cm Kg Rp. 35,000.00
86 Papan Kayu Kelas I m3 Rp. 6,400,000.00
HARGA DASAR SATUAN BAHAN
Harga Satuan
No. Tenaga Kerja Satuan Keterangan
(Rp.)

87 Papan Kayu Kelas II m3 Rp. 5,500,000.00


88 Papan Kayu Kelas III m3 Rp. 4,000,000.00
89 Papan Kayu Plafond Kelas II m3 Rp. 5,640,000.00
90 Pasir Batu (Sirtu) M3 Rp. 280,000.00
91 Pasir Beton (1400 kg/m3) M3 Rp. 150,000.00
92 Pasir Beton Kg Rp. 107.14
93 Pasir Pasang (1400 kg/m3) M3 Rp. 217,000.00
94 Pasir Pasang Kg Rp. 155.00
95 Pasir Urug M3 Rp. 124,000.00
96 Paving Block M2 Rp. 98,400.00
97 Penjaga Jarak Bekesting (Spacer) bh Rp. 25,000.00
98 Pipa Leiding Ø 1" Galvanis Tebal 3.2 mm m' Rp. 50,225.00
99 Pipa Leiding Ø 3/4" Galvanis Tebal 3.2 mm m' Rp. 38,333.33
100 Pipa Leiding Ø 1/2" Galvanis Tebal 3.2 mm m' Rp. 30,750.00
101 Pipa Leiding Ø 1 1/2" Galvanis Tebal 3.2 mm m' Rp. 69,700.00
102 Pipa Leiding Ø 2" Galvanis Tebal 3.2 mm m' Rp. 88,150.00
103 Pipa Leiding Ø 3" Galvanis Tebal 3.2 mm m' Rp. 112,750.00
104 Pipa Leiding Ø 4" Galvanis Tebal 3.2 mm m' Rp. 176,300.00
105 Pipa Leiding Ø 6" Galvanis Tebal 3.2 mm m' Rp. 291,100.00
106 Pipa PVC Ø 1" m' Rp. 11,200.00
107 Pipa PVC Ø 1/2" Kualitas AWE (United) m' Rp. 6,300.00
108 Pipa PVC Ø 1 1/2" m' Rp. 19,500.00
109 Pipa PVC Ø 2" m' Rp. 25,000.00
110 Pipa PVC Ø 2 1/2" m' Rp. 36,500.00
111 Pipa PVC Ø 3" m' Rp. 50,000.00
112 Pipa PVC Ø 3/4" m' Rp. 8,300.00
113 Pipa PVC Ø 4" m' Rp. 66,000.00
114 Plamur Kg Rp. 22,000.00
115 Plint Keramik Granit 10 x 40 Bh Rp. 8,600.00
116 Plint Keramik Granit 10 x 60 Bh Rp. 12,800.00
117 Plywood 4 mm ( Ukuran 90 x 220 cm ) Lembar Rp. 78,000.00
118 Plywood 6 mm Lembar Rp. 86,000.00
119 Plywood 9 mm Lembar Rp. 135,000.00
120 Ramset Buah Rp. 350.00
121 Rangka Baja Ringan C75 kg Rp. 12,000.00
122 Rangka Baja Ringan C125 m' Rp. 122,000.00
123 Residu Kg Rp. 8,500.00
124 Roof Light Fibreglass 90 x 180 cm Lbr Rp. 260,000.00
125 Seal Tape Bh Rp. 3,500.00
126 Seng BJLS 0.20 Lbr Rp. 34,000.00
127 Semen @ 40 Kg Zak Rp. 40,000.00
128 Semen @ 40 Kg Kg Rp. 1,000.00
HARGA DASAR SATUAN BAHAN
Harga Satuan
No. Tenaga Kerja Satuan Keterangan
(Rp.)

129 Semen @ 50 Kg Zak Rp. 150,000.00


130 Semen @ 50 Kg Kg Rp. 3,000.00
131 Semen Warna @ 50 Kg Zak Rp. 150,000.00
132 Semen Warna @ 50 Kg Kg Rp. 3,000.00
HARGA DASAR SATUAN BAHAN
Harga Satuan
No. Tenaga Kerja Satuan Keterangan
(Rp.)

133 Sirap Kayu Bh Rp. 12,000.00


134 Skrup Fixer Bh Rp. 200.00
135 Solar (Industri) Liter Rp. 9,000.00
136 Stop Kontak + Instalasi Titik Rp. 73,800.00
137 Storox - 100 Kg Rp. 120,000.00
138 Stut Werk M3 Rp. 2,890,500.00
139 Tanah Liat M3 Rp. 40,000.00
140 Tanah Timbun M3 Rp. 70,000.00
141 Tanah Timbun Pilihan - Material Jalan M3 Rp. 140,000.00
142 Wastafel Bh Rp. 380,000.00
143 Waterdrain Bh Rp. 45,000.00
144 Waterstop PVC Lebar 150 mm m Rp. 24,500.00
145 Waterstop PVC Lebar 200 mm m Rp. 30,500.00
146 Waterstop Lebar 230 mm - 320 mm m Rp. 38,500.00
147 Wiremesh (Ulir) Dia. 5.0 Kg Rp. 10,000.00
148 Wiremesh (Ulir) Dia. 6.0 Kg Rp. 10,450.00
149 Besi Strip tebal 5 mm Kg Rp. 12,500.00
150 Seng Plat 3 x kk bjls 30 Lbr Rp. 84,000.00
150 Atap Apandek 0.30 mm M2 Rp. 70,000.00
151 Paku skrup + Mur bh Rp. 1,000.00
151 Borehole m Rp. 150,000.00
152 Kawat Bronjong 8/10 Kg Rp. 85,000.00
153 Batu Tempel Hitam Buah Rp. 90,000.00
154 Waterpass Hr Rp. 140,000.00
155 Thedolite Hr Rp. 490,000.00
156 Alat Bantu Ls Rp. 15,000.00
157 Jendela naco Buah Rp. 18,810.00
158 Kaca polos M2 Rp. 150,975.00
159 Kunci tanam Buah Rp. 173,250.00
160 Plywood 4 mm Lbr Rp. 58,500.00
161 Seng Gelombang Lbr Rp. 7,500.00
162 BBM Non Subsidi Liter Rp. 9,400.00
163 Jack Hammer Sewa/Hr Rp. 600,000.00
164 Pipa Baja Diameter 4 Kg Rp. 15,189.22
165 Pipa Baja Diameter 5 Kg Rp. 13,783.60
166 Pemasangan Besi Plat 6 mm Kg Rp. 10,000.00
167 Pemasangan Besi Plat 8 mm Kg Rp. 10,053.48
168 Pemasangan Besi Plat 10 mm Kg Rp. 10,072.87
169 Pemasangan Besi Plat 12 mm Kg Rp. 10,267.86
170 Pemasangan Besi Plat 16 mm Kg Rp. 10,460.86
171 Bout HTB M10, Bh Rp. 5,600.00
172 Bout HTB M16, Bh Rp. 7,100.00
HARGA DASAR SATUAN BAHAN
Harga Satuan
No. Tenaga Kerja Satuan Keterangan
(Rp.)

173 Anchor Bolt M19, Pj. 40 cm Bh Rp. 34,250.00


174 Flashing Genteng m Rp. 37,500.00
175 kaca laminated 2x5 mm sky light m2 Rp. 123,250.00
176 Lem kayu Kg Rp. 45,000.00
177 Lem kaca Kg Rp. 65,500.00
178 Rangka aluminium 4" x 1 3/4" m Rp. 163,169.05
179 Bingkai Ventilasi Aluminium m Rp. 73,574.05
180 Kalsiboard 6 mm Lbr Rp. 57,000.00
181 List Plafond Lbr Rp. 19,000.00
182 Paku Scrub 3 mm Kg Rp. 30,000.00
183 Sika waterproofing mortar Kg Rp. 159,000.00
184 Cat penutup ex. No drop Kg Rp. 29,000.00
185 Kuas 4" Bh Rp. 20,000.00
186 Aluminium Strip 80 mm m2 Rp. 60,500.00
187 Engsel Tanam Bh Rp. 37,500.00
188 Kunci Tanam Bh Rp. 110,650.00
189 Handle Pintu Bh Rp. 209,000.00
190 Door Stop Bh Rp. 19,000.00
191 Kaca Bening 8 mm m2 Rp. 320,000.00
192 Plamuur Kg Rp. 62,100.00
193 Cat penutup Kg Rp. 37,300.00
194 Kuas Bh Rp. 32,950.00
195 Pengencer Kg Rp. 12,000.00
196 Ampelas Lbr Rp. 16,400.00
197 Dempul Kayu Kg Rp. 34,000.00
198 Hand shower lengkap dengan aksesories Set Rp. 479,000.00
199 Tempat Tissu Bh Rp. 85,000.00
200 Robe Hook/Gantungan Bh Rp. 150,000.00
201 Roof Drain Stainlees 4" Bh Rp. 94,500.00
202 Kabel NYA (3x2,5) mm M1 Rp. 10,500.00
203 Klem Kabel No. 10 Bh Rp. 1,500.00
204 Pipa PVC 5/8" M' Rp. 4,250.00
205 Inbow Dos Bh Rp. 5,000.00
206 Las Dop Bh Rp. 2,500.00
207 Isolasi Rol Rp. 10,000.00
208 T - Dos 5/8" Bh Rp. 7,500.00
209 Flexible pipe (Kabel ties) M' Rp. 8,000.00
210 Saklar Tunggal Bh Rp. 16,400.00
211 Saklar Ganda Bh Rp. 20,350.00
212 Stop kontak Bh Rp. 17,500.00
213 Lampu TL 2 X 18 watt Bh Rp. 315,000.00
214 Lampu Downlight 9 Watt Bh Rp. 128,000.00
HARGA DASAR SATUAN BAHAN
Harga Satuan
No. Tenaga Kerja Satuan Keterangan
(Rp.)

215 Lampu Downlight 5 Watt Bh Rp. 82,000.00


216 Lampu Downlight 13 Watt Bh Rp. 172,500.00
217 Lampu SL10 Watt Bh Rp. 36,800.00
218 Lampu SL 20 Watt Bh Rp. 41,975.00
219 Lampu Baret LED Phllips Bh Rp. 724,500.00
220 Lampu Downlight 8 Watt Bh Rp. 90,000.00
221 Lampu Downlight 13 Watt outbow Bh Rp. 185,000.00
222 Pipa listrik 5/8” Btg Rp. 4,050.00
223 Kabel NYY 3 x 2,5 (metal Kabel) m Rp. 10,350.00
224 Tduz Bh Rp. 6,750.00
225 Wall Speaker Bh Rp. 400,000.00
226 Horn Speaker Bh Rp. 590,000.00
227 TBSS Bh Rp. 35,000.00
228 Volume Control Bh Rp. 125,000.00
229 Exhoust Bh Rp. 350,000.00
230 Wall Fan diameter 400 mm Unit Rp. 5,250,000.00
Pipa air bersih (PPR PN 16, incl. accessories) Rp -
231 PPR 15 mm m Rp. 35,000.00
232 PPR 20 mm m Rp. 43,780.00
233 PPR 25 mm m Rp. 57,310.00
234 PPR 32 mm m Rp. 92,180.00
235 PPR 40 mm m Rp. 146,080.00
236 PPR 50 mm m Rp. 226,600.00
237 Assesories Pipa Bh Rp. 35,000.00
238 Gate Valve Dia 1/2 Inch Bh Rp. 49,300.00
239 Pipa PVC Ø 6" m' Rp. 85,000.00
240 Bout HTB M10, Bh Rp. 10,500.00
241 Anchor Bolt M22, Pj. 40 cm Bh Rp. 36,500.00
242 Pemasangan Besi Plat 22 mm Kg Rp. 12,360.86
243 Pemasangan Besi Plat 25 mm Kg Rp. 14,661.86
244 Stainless Steel Dia 5 cm M1 Rp. 58,500.00
245 Baut fisher Bh Rp. 1,500.00
246 Door Closer Bh Rp. 50,000.00
247 Kaca Bening 6 mm m2 Rp. 250,000.00
248 Cat Kg Rp. 207,900.00
249 Urinoir Bh Rp. 1,100,000.00
250 Partisi Urinoir Bh Rp. 750,000.00
251 Lampu TL 2 X 18 watt (V-shape) Bh Rp. 395,000.00
252 Fire extinguiser Unit Rp. 525,000.00
253 kitchen zinc Unit Rp. 1,350,000.00
254 Slot Tanam Bh Rp. 75,000.00
255 Engsel Jendela Bh Rp. 37,500.00
HARGA DASAR SATUAN BAHAN
Harga Satuan
No. Tenaga Kerja Satuan Keterangan
(Rp.)

256 spring knip Bh Rp. 20,000.00


257 rambuncis Bh Rp. 18,500.00
258 Lampu Gantung Unit Rp. 249,500.00
259 Drymix Floor Hardener @25 kg Kg Rp. 90,000.00
260 Genset Kap. 65 kVA Set Rp. 210,000,000.00
261 Fuel Storage Tank Cap. 1000 liter Set Rp. 7,500,000.00
262 Electric Fuel Transfer Pump Cap. 70 LPM Unit Rp. 8,465,000.00
263 Fuel Hand Pump Cap. 20 LPM Unit Rp. 525,000.00
264 Fuel Flow Meter Unit Rp. 750,000.00
265 Fuel Water Sparator Unit Rp. 2,300,000.00
266 BBM Solar Ltr Rp. 9,400.00
267 Lampu Taman ED 40 W Bh Rp. 130,000.00
268 Roof tank FRP kap. 2x3 m3 m3 Rp. 3,350,000.00
269 HDPE 40 mm m Rp. 22,700.00
270 HDPE 50 mm m Rp. 35,200.00
271 HDPE 65 mm m Rp. 55,650.00
272 HDPE 100 mm m Rp. 150,950.00
273 Gate Valve 40 mm Bh Rp. 35,234.00
274 Gate Valve 65 mm Bh Rp. 55,674.00
275 Water meter 50 mm Unit Rp. 1,850,000.00
276 Water meter 80 mm Unit Rp. 6,750,000.00
277 HDPE 80 mm m Rp. 150,950.00
278 HDPE 15 mm m Rp. 6,500.00
279 HDPE 25 mm m Rp. 9,000.00
280 HDPE 32 mm m Rp. 14,700.00
281 Paving Block Natural Tebal 6 cm m2 Rp. 80,000.00
282 Batu Koral Kg Rp. 15,000.00
283 Kait Angin Bh Rp. 15,000.00
284 Kunci Slot Bh Rp. 55,000.00
285 Door Holder Bh Rp. 172,000.00
286 Kaca Cermin 5 mm m2 Rp. 72,500.00
287 Kaca Cermin 8 mm m2 Rp. 135,000.00
288 Wireglassed Tebal 5 mm m2 Rp. 210,000.00
289 Batu Kosong m3 Rp. 207,400.00
290 perlengkapan Ls Rp. 500,000.00
291 Bekisting m2 Rp. 156,923.18
292 Karung Plastik bh Rp. 2,800.00
293 Tali Rapia m Rp. 500.00
294 Sewa Pasir m3 Rp. 280,000.00
295 campuran Beton m3 Rp. 707,080.38
296 Pasangan Bata m3 Rp. 1,397,296.52
297 Mesin Las Sewa/Hr Rp. 100,000.00
HARGA DASAR SATUAN BAHAN
Harga Satuan
No. Tenaga Kerja Satuan Keterangan
(Rp.)

298 Pintu air T.2000x B 800mm Buah Rp. 7,000,000.00


299 Tackle/tripod tinggi 4 - 5 m Sewa/Hr Rp. 25,000.00
300 Excavator Jam Rp. 278,000.00
301 Dump Truck Jam Rp. 205,000.00
302 Peralatan Lain Ls Rp. 150,000.00
HARGA DASAR SATUAN UPAH

Harga Satuan (Rp.)


No. Tenaga Kerja Kode Satuan Keterangan
Jam Hari

1 Pekerja L.01 OH Rp. 10,700.00 Rp. 86,043.00


2 Tukang L.02 OH Rp. 12,100.00 Rp. 96,922.00
3 Tukang Gali L.02 OH Rp. 10,700.00 Rp. 86,043.00
4 Tukang Batu L.02 OH Rp. 12,100.00 Rp. 96,922.00
5 Tukang Kayu L.02 OH Rp. 12,100.00 Rp. 96,922.00
6 Tukang Besi L.02 OH Rp. 12,100.00 Rp. 96,922.00
7 Tukang Cat / Pelitur L.02 OH Rp. 12,100.00 Rp. 96,922.00
8 Tukang Pipa / Operator Pompa L.02 OH Rp. 12,100.00 Rp. 96,922.00
9 Tukang Pengayam Bronjong L.02 OH Rp. 12,100.00 Rp. 96,922.00
10 Tukang Tebas L.02 OH Rp. 10,700.00 Rp. 86,043.00
11 Kepala Tukang L.03 OH Rp. 16,000.00 Rp. 128,570.00
12 Mandor L.04 OH Rp. 13,800.00 Rp. 110,768.00
13 Juru Ukur L.05 OH Rp. 13,100.00 Rp. 105,031.80
14 Pembantu Juru Ukur L.06 OH Rp. 13,100.00 Rp. 105,031.80
15 Ahli Alat Berat ( Mekanik ) L.07 OH Rp. 13,100.00 Rp. 105,031.80
16 Operator L.08 OH Rp. 16,000.00 Rp. 128,570.00
17 Pembantu Operator L.09 OH Rp. 13,100.00 Rp. 105,031.80
18 Sopir Truck L.10 OH Rp. 13,100.00 Rp. 105,031.80
19 Kenek Truk L.11 OH Rp. 13,100.00 Rp. 105,031.80
20 Penjaga Malam L.12 OH Rp. 13,100.00 Rp. 105,031.80
21 Juru Gambar (Drafter) L.13 OH Rp. 13,100.00 Rp. 105,031.80
22 Design Engineer L.15 OH Rp. 13,100.00 Rp. 105,031.80
23 Operator Printer/Plotter L.16 OH Rp. 13,100.00 Rp. 105,031.80
REKAPITULASI
PEKERJAAN : REHABILITASI JARINGAN IRIGASI DAN BENDUNG D.I. KALENGKERE
LOKASI : DESA LIMAPOCCOE KEC. CENRANA
TAHUN ANGGARAN
: 2021

No. JENIS PEKERJAAN

I PERSIAPAN Rp 36,832,900.00
II FISIK
A PEKERJAAN SALURAN Rp 37,696,150.15
B PEKERJAAN BENDUNG Rp 2,044,295,087.35
C PEKERJAAN BANGUNAN PENGARAH Rp 61,920,228.26
III LAIN - LAIN Rp 3,280,000.00

TOTAL NILAI : Rp 2,184,024,365.77


PPN 10% : Rp 218,402,436.58
TOTAL TERMASUK PPN 10% : Rp 2,402,426,802.34
DI BULATKAN : Rp 2,402,426,800.00
DUA MILYAR EMPAT RATUS DUA JUTA EMPAT RATUS DUA PULUH ENAM RIBU
Terbilang :
DELAPANRATUS RUPIAH

Makassar, 20 Agustus 2021


CV. FAJRIN PRATAMA

MUH. FAJRIN AL.ISLAMI AKBAR


Direktur
PEKERJAAN : REHABILITASI JARINGAN IRIGASI DAN BENDUNG D.I. KALENGKERE
LOKASI : DESA LIMAPOCCOE KEC. CENRANA
TAHUN ANGGARAN : 2021

NO URAIAN SATUAN VOLUME HARGA SATUAN TOTAL HARGA


I. Persiapan
1 Papan Nama Bh 1.00 Rp 1,000,000.00 Rp 1,000,000.00
2 Mobilisasi dan Demobilisasi Ls 1.00 Rp 6,532,900.00 Rp 6,532,900.00
3 Penyelenggaraan Manajemen Keselamatan Konstruksi Ls 1.00 Rp 29,300,000.00 Rp 29,300,000.00
SUB TOTAL I Rp 36,832,900.00
II FISIK
A PEKERJAAN SALURAN
1 Pekerjaan Galian Tanah M3 38.00 Rp 60,146.00 Rp 2,285,548.00
2 Pekerjaan Pasangan Batu 1 : 4 M3 41.04 Rp 385,010.23 Rp 15,958,828.04
3 Pekerjaan Plesteran 1 : 4 (Tebal 15 mm) M2 87.40 Rp 81,157.20 Rp 7,235,001.80
4 Lantai Saluran (Beton mutu, f'c = 12,2 Mpa (K150)) M3 4.56 Rp 758,096.13 Rp 3,560,625.88
5 Pekerjaan Plat Injak
- Beton M3 0.07 Rp 707,080.38 Rp 49,495.63
- Tulangan Kg 14.52 Rp 33,668.71 Rp 488,869.63
- Bekisting M2 0.62 Rp 256,421.44 Rp 160,571.10
6 Pengadaan Dan Pemasangan Pintu Air Bh 1.00 Rp 7,957,210.07 Rp 7,957,210.07
SUB TOTAL A Rp 37,696,150.15
B PEKERJAAN BENDUNG
1 Pekerjaan Pembersihan Lokasi M2 48.00 Rp 15,556.00 Rp 746,688.00
2 Pek. Dewatering (Kisdam) Bh 190.00 Rp 41,284.79 Rp 7,844,110.48
3 Pekerjaan Galian Menggunakan Alat M3 982.51 Rp 33,572.00 Rp 33,314,673.98
4 Pekerjaan Timbunan Kembali M3 190.00 Rp 35,254.49 Rp 6,832,319.66
5 Pekerjaan Pasangan Batu Siklob M3 1,122.24 Rp 1,445,013.00 Rp 1,621,651,389.12
6 Pekerjaan Pasangan Batu 1 : 4 M3 358.50 Rp 385,010.23 Rp 138,026,167.46
7 Pekerjaan Plesteran 1 : 4 (Tebal 15 mm) M3 713.76 Rp 81,157.20 Rp 57,926,760.93
8 Pekerjaan Lantai Bendung (Beton K-225) M3 212.32 Rp 833,263.48 Rp 176,918,501.39
9 Pekerjaan Besi Siku Skot Balok 100.100.10 M' 12.00 Rp 34,415.00 Rp 412,980.00
10 Pekerjaan Skot Balok M3 0.76 Rp 817,758.34 Rp 621,496.34
SUB TOTAL B Rp 2,044,295,087.35
C PEKERJAAN BANGUNAN PENGARAH
1 Pekerjaan Galian Menggunakan Alat M3 49.82 Rp 33,572.00 Rp 1,672,557.04
2 Pekerjaan Pasangan Batu 1 : 4 M3 67.87 Rp 385,010.23 Rp 26,130,644.31
3 Pekerjaan Plesteran 1 : 4 (Tebal 15 mm) M3 135.06 Rp 81,157.20 Rp 10,961,091.03
4 Pekerjaan Lantai Beton K-225 M3 18.24 Rp 833,263.48 Rp 15,198,725.82
5 Pengadaan Dan Pemasangan Pintu Air Bh 1.00 Rp 7,957,210.07 Rp 7,957,210.07
SUB TOTAL C Rp 61,920,228.26
SUB TOTAL II Rp 2,143,911,465.77
III LAIN - LAIN
AS Built Drawing Set 1.00 Rp 2,500,000.00 Rp 2,500,000.00
Dokumentasi Paket 1.00 Rp 780,000.00 Rp 780,000.00
SUB TOTAL III Rp 3,280,000.00
JUMLAH TOTAL Rp 2,184,024,365.77
SCHEDULE PELAKSANAN PEKERJAAN ( KURVA S)

PHO DAN MASA PEMELIHARAAN SESUAI YANG DITENTUKAN


BOBOT
WAKTU PELAKSANAAN 90 ( SEMBILAN PULUH HARI KALENDER )
NO URAIAN PEKERJAAN JUMLAH HARGA BULAN I BULAN II BULAN III KET
% 1 2 3 4 5Chart Title
6 7 8 9 10 11 12
120.00

100.00
I PERSIAPAN 36,832,900.00 1.69 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14
80.00
II PEKERJAAN SALURAN 37,696,150.15 1.73 0.29 0.29 0.29 0.29 0.29 0.29
60.00
III PEKERJAAN BENDUNG 2,044,295,087.35 93.60 9.36 9.36 9.36 9.36 9.36 9.36 9.36 9.36 9.36 9.36
40.00
IV PEKERJAAN BANGUNAN PENGARAH 61,920,228.26 2.84 0.71 0.71 0.71 0.71
20.00
V LAIN - LAIN 3,280,000.00 0.15 0.03 0.03 0.03 0.03 0.03
-
1 2 3 4 5 6 7 8 9 10 11 12 13

JUMLAH 2,184,024,365.77 100.00

PROGRESS RENCANA MINGGUAN 0.43 0.43 9.79 9.79 10.50 10.50 10.21 10.24 9.53 9.53 9.53 9.53

KUMULATIF PROGRESS RENCANA MINGGUAN - 0.43 0.86 10.64 20.43 30.93 41.43 51.64 61.88 71.41 80.94 90.47 100.00

Makassar, 20 Agustus 2021


CV. FAJRIN PRATAMA

MUH. FAJRIN AL.ISLAMI AKBAR


Direktur
REKAPITULASI PERHITUNGAN TINGKAT KOMPONEN DALAM NEGERI (TKDN)
REHABILITASI JARINGAN IRIGASI DAN BENDUNG D.I. KALENGKERE

TOTAL
URAIAN DN LN BARANG / JASA GABUNGAN
Ribu Rp. % KDN
1 2 3 4 5 6 7

A BARANG
I Material Langsung
( bahan baku ) 70.00 0.00 1,528,817.06 70.00 70.00 70.00
II Peralatan ( Barang Jadi ) 5.00 0.00 109,201.22 5.00 5.00 5.00
Sub Total Barang 75.00 0.00 1,638,018.27 75.00 75.00 75.00

B JASA
III Manajemen Proyek dan Perekayasa
I Alat kerja / Fasilitas Kerja 5.00 109,201.22 5.00 5.00 5.00
II Konstruksi dan Fabrikasi 10.00 218,402.44 10.00 10.00 10.00
III Jasa Umum 10.00 218,402.44 10.00 10.00 10.00
Sub Total Jasa 25.00 0.00 546,006.09 25.00 25.00 25.00

C Total Biaya ( A+B ) 100.00 - 2,184,024.37 100.00 100.00 100.00

Formulasi Perhitungan : 1,638,018.27 + 546,006.09


% TKDN (Gabungan = 2,184,024.37 2,184,024.37
Barang dan Jasa
= 75.00 + 25.00 = 100.00 %

Makassar, 20 Agustus 2021


CV. FAJRIN PRATAMA

MUH. FAJRIN AL.ISLAMI AKBAR


Direktur