You are on page 1of 4

ĐỀ THI CUỐI KỲ (cho thi trực tuyến)

FINAL EXAM PAPER (for online examination)


Học kỳ/Quarter: 4 - Năm học/Academic year: 2020 – 2021
Khoa/School: Quản Trị Kinh Doanh/Becamex Business School

Mã môn thi: BUS 359 Mã đề thi: 02


Course code Exam code
Tên môn thi: OPERATIONS AND SUPPLY CHAIN Thời gian làm bài: 60 minutes
MANAGEMENT Duration
Course name
Ngày thi: 09/09/2021 Tổng điểm: 100
Exam date Maximum mark

Hướng dẫn/ Instructions:


- Đề thi mở. Sinh viên được sử dụng tài liệu khi làm bài
This is an open book exam that allows students to refer to materials while answering the questions.
- Bài thi khi nộp bằng email phải được đặt tên theo cấu trúc: Ngày thi_Mã môn học_Mã số sinh viên_Họ tên sinh
viên. Ví dụ: 30.06.2021_ECE 203_0000000001_Nguyễn Văn A
The answer sheets should be named in the following format when submit by email: Exam date_Course
code_Student ID_Student name. For example: 30.06.2021_ECE 203_0000000001_Nguyễn Văn A

NOTE: please pay attention to plagiarism issues when doing the exam:
1. Copying information from the course’s material or the Internet for your answer will
receive a ZERO mark.
2. Copying between students will be treated as cheating, and ZERO marks will be applied
to any parties involved.

Question 1 (10 marks): There are 8 types of waste in Lean. Choose TWO out of 8 wastes and
discuss the causal relationship between them.

Question 2 (20 marks): What are the four critical things you learned from this course? Why do
you think they are important?

Trang/ Page: 1
Question 3 (25 marks): EIU Company is preparing an aggregate production plan for washers for
the next six months. The company’s expected monthly demand is given below in the chart. The
company has 1,500 washers at the beginning of the first month and want to maintain that number
at the end of the period. Below are other critical data:

Production cost per unit $200


Inventory carrying cost per month per unit
(based on ending monthly inventory) $20
Hiring cost per worker $700
Firing cost per worker $1,500
Beginning number of workers 30 people
Productivity per month 100 units

Month Demand Regular Ending Workers Hire Fire


Production Inventory required

1 5,000

2 7,000

3 6,000

4 3,000

5 8,000

6 7,000

Total 36,000

a. Complete the level strategy and calculate the total cost.


b. Complete the chase strategy and calculate the total cost.
c. If the total cost is the most important criterion for selection, which strategy should we use?

Trang/ Page: 2
Question 4 (45 marks): Given the BOM and MPS for item A.

Item A B C D E F
Lot size rule L4L L4L FOQ = 200 FOQ = 450 L4L FOQ = 250
Beginning Inventory 0 800 900 2000 0 200

MPS

Item 1 2 3 4 5 6 7 8
A 160 140 100 240 200 140 160 80

a. Complete the MRP schedule for item B.

Item: B

Week 1 2 3 4 5 6 7 8
Gross Requirements
On-Hand Inventory …
Scheduled Receipts
Net Requirements
Planned Order Release

b. Complete the MRP schedule for item C.

Item: C

Week 1 2 3 4 5 6 7 8
Gross Requirements
On-Hand Inventory …
Scheduled Receipts
Net Requirements
Planned Order Release

Trang/ Page: 3
c. Complete the MRP schedule for item D. Knowing that staff already placed two orders and
will receive 400 units in week 2 and 600 units in week 3.

Item: D

Week 1 2 3 4 5 6 7 8
Gross Requirements
On-Hand Inventory …
Scheduled Receipts
Net Requirements
Planned Order Release

d. Recently, the company changed to a new supplier because it offered the lot size rule as Lot-
4-Lot. Complete the MRP schedule for item D with this new supplier. Knowing that staff already
placed an order and will receive 1,600 units in week 1.

Item: D

Week 1 2 3 4 5 6 7 8
Gross Requirements
On-Hand Inventory …
Scheduled Receipts
Net Requirements
Planned Order Release

------ Hết/End ------

Giảng viên ra đề Duyệt của Chủ nhiệm bộ môn Duyệt của Trưởng/Phó Khoa
Lecturer’s signature Approval of Approval of
Department Head Dean/Vice Dean of School

(Đã ký/Signed) (Đã ký/Signed) (Đã ký/Signed

ThS Ninh Trần Thuỳ Dương TS Huỳnh Công Minh ThS Nguyễn Trường Sơn

Trang/ Page: 4

You might also like