Professional Documents
Culture Documents
Facilities Introduction
Ivan Puckett
1
Facilities Introduction
What is included in “Facilities” ?
2
Facilities Introduction
Products
Wellstream
To consumer(s)
Processing Facility or further
processing
Waste Streams
3
Facilities Introduction
“Facilities” & the Oil & Gas Industry Sectors
Upstream
Subsea gathering system Onshore gathering system
6
Facilities Introduction
Upstream
7
Facilities Introduction
Midstream
• Gas plants
• NGL fractionation facilities
• Gas/LPG storage facilities
• Gas, NGL and oil transportation pipelines
• Similar equipment & processes as Upstream, plus:
• Gas sweetening
• Sulfur recovery
• NGL recovery
• Liquid product treating
• NGL fractionation
• Nitrogen removal
• Crude oil dehydration, desalting, stabilization &
sweetening
8
Facilities Introduction
Midstream
Onshore turboexpander gas plant
9
Facilities Introduction
Downstream
• Refining
• Petrochemicals
• LNG regasification
• Gas and finished liquid product storage and
distribution
• Many of the same types of equipment as Upstream
and Downstream, but:
• Much more focus on reactive chemistry, ie. rearranging
molecules
• Higher temperatures (and often higher pressures)
• Located in more populated areas
• Additional safety, environmental and PR concerns
10
Facilities Introduction
Downstream
Typical oil refinery & process flow
diagram
11
Facilities Introduction
12
Facilities Introduction
14
Facilities Introduction
15
Facilities Introduction
16
Facilities Introduction
17
Facilities Introduction
18
Facilities Introduction
19
Facilities Introduction
20
Facilities Introduction
21
Facilities Introduction
200.0
150.0
100.0
50.0
0.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Pros Cons
• One project • Could be wrong (Hi or Low)
• One set of equipment • Way over sized at the beginning and
• Accelerates production the end
• Up front Capital intensive
23
Facilities Introduction
"Drill to Fill"
180.0
160.0
140.0
120.0
100.0
80.0
60.0
40.0
20.0
0.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Pros Cons
• One project • Could be wrong (Hi or Low)
• One set of equipment • Up front Capital intensive
• Accelerates initial production • Intentionally limits production peak
• Reduces Capital
24
Facilities Introduction
200.0
150.0
100.0
50.0
0.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Pros Cons
• Reduces Capital • Constant project execution mode
• Equipment reuse option • Still have to start projects well ahead of
• Adjust capacity as data requires production curve
• Will require SIMOPS
• Continuous funding
25
Questions?
26