Professional Documents
Culture Documents
A
B B
D C C D
• The weight the central building horizontal truss 1 is 8.3 • The weight the central building horizontal truss 1 is 3.5
tons tons
STEPS OF THE CONSTRUCTION PROCESS :
1. STEP 1 3. STEP 3
2. STEP 2
Steel columns hoisting checking The above figure shows the partition of the main truss and the sub truss
The section of the concrete columns below 16.28m
under the elevated mezzanine is P1600x35, the section
of the steel columns above 16.28m is P1400x35, This project uses the main truss station on both sides of the 2 sets of 400 ton
according to the characteristics of the distribution of crawler crane tower hoisting condition. The transverse main and secondary
steel columns and the performance of the crane, trusses are divided into 7 sections, in which the 66m trusses are divided into 3
divided the column into two parts, the divided point is sections and 2 segments on both sides.
18.5m.
STEPS OF THE CONSTRUCTION PROCESS :
6. STEP 6 Simulation of stress and deformation in construction
process