Long Span Beam: Casestudy

LONG SPAN STRUCTURE


Group-B3 Shubham kambli|Amey deshmukh |Vivek patil
Pillai Hoc Coa, Rasayani
ABOUT THE STRUCTURE:
1.The steel truss structure of the house face of
the central station of Shenyang South Railway
Station is 286.5m long,

2.And the roof truss is 21m+66m+21m in the


north and south, and the 8.0m is suspended
on both sides.

3.The basic 10.5m X 21.5m, 10.5m X 1 24m.


The structure elevation of the elevated layer
is 8.745m,

4.The sandwich structure is 16.400m, and the


roof structure is 29.91 to 37.51m
ELEMENTS:

A
B B
D C C D

• The weight the central building horizontal truss 1 is


11.7 tons

• The central building 8~15 m axis column span of 66m,


the total weight of component 31.7t, top plane truss
arch of the overall rate of about 9.45m.
C

• The weight the central building horizontal truss 1 is


10.7 tons

• The weight the central building horizontal truss 1 is 8.3 • The weight the central building horizontal truss 1 is 3.5
tons tons
STEPS OF THE CONSTRUCTION PROCESS :
1. STEP 1 3. STEP 3

Checking the plan and implementation of the central


steel roof truss

2. STEP 2

Steel columns hoisting checking The above figure shows the partition of the main truss and the sub truss
The section of the concrete columns below 16.28m
under the elevated mezzanine is P1600x35, the section
of the steel columns above 16.28m is P1400x35, This project uses the main truss station on both sides of the 2 sets of 400 ton
according to the characteristics of the distribution of crawler crane tower hoisting condition. The transverse main and secondary
steel columns and the performance of the crane, trusses are divided into 7 sections, in which the 66m trusses are divided into 3
divided the column into two parts, the divided point is sections and 2 segments on both sides.
18.5m.
STEPS OF THE CONSTRUCTION PROCESS :
6. STEP 6 Simulation of stress and deformation in construction
process

The installation process of steel structures is a cumulative


process in which the force and boundary conditions of the
structure vary according to time.
Therefore, the maximum internal force state or final state of the
component and the results of the overall structural analysis in
the design will vary greatly from the different construction
processes or sequences.
In order to ensure the safety of the construction process and
the construction of the steel roof, it is necessary to carry out the
simulation analysis of the construction process. The construction
process analysis is carried out by the software, and the internal
force and deformation of the steel structure during the
construction process are obtained.

Hoisting of the third sub section and its performance analysis is


been done to check.
STEPS OF THE CONSTRUCTION PROCESS :