You are on page 1of 98

PLANNING, ANALYSIS, AND DESIGN OF HOSPITAL

BUILDING
Bonafide record of work done by

KAVIMUGAN B (17C112)
SASWATH S (17C128)
BALASUBRAMANI N (17C205)
GURU M (17C208)
SHRI RAGAV V S (17C222)

Dissertation (phase II) submitted in partial fulfilment of the requirements for


the degree of
BACHELOR OF ENGINEERING
Branch: CIVIL ENGINEERING
of Anna University

APRIL - 2021
DEPARTMENT OF CIVIL ENGINEERING
PSG COLLEGE OF TECHNOLOGY
(Autonomous Institution)
COIMBATORE – 641004
PSG COLLEGE OF TECHNOLOGY
(Autonomous Institution)
COIMBATORE – 641 004

PLANNING, ANALYSIS, AND DESIGN


OF HOSPITAL BUILDING

Bona fide record of work done by

KAVIMUGAN B (17C112)
SASWATH S (17C128)
BALASUBRAMANI N (17C205)
GURU M (17C208)
SHRI RAGAV V S (17C222)

Dissertation submitted in partial fulfilment of the requirements for


the degree of
BACHELOR OF ENGINEERING
Branch: CIVIL ENGINEERING
of Anna University
APRIL 2021

...……………………………. ……….…………..……………….
Mr. C G SIVA KUMAR Dr. M. PALANIKUMAR
Faculty guide Head of the Department

Certified that the candidate was examined in the viva-voce


examination held on ………………….

…………………….. …………………………..
(Internal Examiner) (External Examiner)

ACKNOWLEDGEMENT
The final outcome of this project required a lot of guidance and assistance from our
faculties and we are extremely privileged to have this all along the completion of our
project and we would not forget to thank them.

We are thankful to and fortunate enough to get constant encouragement, support


and guidance from all teaching staffs of civil engineering department and we heartily
thank our internal project guide Mr. C G Siva Kumar, assistant professor, department
of civil engineering for his constant guidance and suggestions throughout this project
work
CONTENTS

S. NO. TITLE Pg. No.

Abstract …………………………………………………………. 03
List of Figures ………………………………………………….. 04
List of Tables …………………………………………………… 06
1.0. Introduction ……………………………………………………………. 07
1.1. Objectives ……………………………………………………… 07
1.2. Outcome ……………………………………………………….. 08
2.0. Requirements …………………………………………………………. 09
2.1. Circulation area ……………………………………………….. 09
2.2. Floor Height …………………………………………………… 09
2.3. Pharmacy ……………………………………………………… 10
2.4. Clinics ………………………………………………………….. 10
2.5. Side laboratory ………………………………………………… 13
2.6. Injection room …………………………………………………. 13
2.7. Diagnostic services …………………………………………… 13
2.8. Dark room ……………………………………………………… 13
2.9. Blood bank ……………………………………………………... 14
2.10. Bleeding room …………………………………………………. 14
2.11. Intensive Care Unit ……………………………………………. 14
2.12. Operation Theatre …………………………………………….. 14
2.13. Hospital Kitchen ……………………………………………….. 15
2.14. Central Sterile and Supply Department …………………….. 15
2.15. Hospital Laundry ………………………………………………. 16
2.16. Medical and General stores ………………………………….. 17
2.17. Ventilation ……………………………………………………… 17
3.0. Planning of hospital building ……………………………………… 19
3.1. Area requirement per bed ……………………………………. 19
3.2. Calculation of area ……………………………………………. 20
3.3. Floor calculation ……………………………………………….. 21
4.0. Visit to ESIC Tirunelveli Hospital ………………………………… 22
5.0. Drawings and Nomenclatures …………………………………….. 24
5.1. Floor plans ……………………………………………………… 24
5.2. Structural elements layout ……………………………………. 32
5.3. Nomenclature …………………………………………………... 40
6.0. Analysis using STAAD.Pro ………………………………………… 42
6.1. Introduction to STAAD.Pro …………………………………… 42
6.2. Importing drawing from AutoCAD to STAAD ………………. 42
6.3. Assigning member properties ………………………………... 43
6.4. Assigning supports ……………………………………………. 43
6.5. Rendering of structure ………………………………………… 43
6.6. Load definitions ………………………………………………… 44
6.7. Analysis results ………………………………………………… 47

1
7.0. Design using STAAD.Pro ………………………………………….. 48
7.1. Material property definition …………………………………… 48
7.2. Design results ………………………………………………….. 48
7.3. Interactive design using STAAD …………………………….. 49
7.4. Foundation design …………………………………………….. 52
8.0. Manual design …………………………………………………………. 54
8.1. Design of one way slab ……………………………………….. 54
8.2. Design of two way slab ……………………………………….. 58
8.3. Design of beam ………………………………………………… 65
8.4. Design of columns …………………………………………….. 68
8.5. Design of footing ………………………………………………. 71
8.6. Design of staircase ……………………………………………. 76
9.0. Sewage treatment plant ……………………………………………. 79
9.1. Population Estimation ………………………………………… 79
9.2. Design of Inlet Chamber ……………………………………… 81
9.3. Design of Screen Chamber …………………………………… 82
9.4. Design of Grit Chamber ……………………………………….. 83
9.5. Design of Aeration tank ……………………………………….. 85
9.6. Design of Secondary Clarifier ………………………………… 88
9.7. Return sludge pump house …………………………………… 89
9.8. Design of sludge drying beds …………………………………. 90
9.9. Filtration pump house and sump ……………………………... 91
9.10. Design of rapid sand filters ……………………………………. 92
9.11. Design of activated carbon filters …………………………….. 95
10.0. Water supply …………………………………………………………. 96
10.1. Tank 1 – Exclusively for people ………………………………. 96
10.2. Tank 2 – Fire Safety …………………………………………… 97
10.3. Tank 3 – Gardening ……………………………………………. 97
11.0. Conclusion …………………………………………………………… 98
12.0. References ……………………………………………………………… 99

2
ABSTRACT

The main objective of this project was to plan, analyse and design a hospital
building by using various software techniques. Nowadays, the software approach
plays a vital role in the construction field to attain quick and better accuracy in
planning, analysis and design of a building, that is of any size or shape. This method
also helps speed-up the execution of the project and hence successfully complete it
in an efficient manner. The planning was done using the Indian standard (IS) codes
in order to achieve a systematic and an efficient structure. In this project, the
structure planned was a multi-speciality hospital building having G+3 floors. The
RCC structure has three blocks consisting of 90 beds overall and a total area of
24,954 sq m. The architectural and structural drawings were done using the
AutoCAD software, followed by analysis and design of the structure in STAAD.Pro
software. Furthermore, the manual design of slabs, beams, columns and footings
were done in MS Excel spreadsheet software. Finally, design and provisions were
made for a Sewage Treatment Plant (STP) and a water supply system which are the
prime requirements a hospital building.

3
List of Figures
Figure No. Title Pg. No.

3.1. Final Proposed design ……………………………….. 21

4.1. Air and Water purifier ………………………………… 22

4.2. Power supply ………………………………………….. 22

4.3. OT Complex ……………………………………………. 23

5.1. Ground floor layout …………………………………… 24

5.2. First floor layout ………………………………………. 26

5.3. Second floor layout …………………………………… 28

5.4. Third floor layout ……………………………………… 30

5.5. Column Layout ………………………………………… 32

5.6. Plinth beam layout ……………………………………… 33

5.7. First floor beam layout …………………………………. 34

5.8. Second floor beam layout ……………………………. 35

5.9. Third floor beam layout ………………………………. 36

5.10. First floor slab layout …………………………………. 37

5.11. Second floor slab layout ……………………………… 38

5.12. Third floor slab layout …………………………………. 39

5.13. Nomenclature ………………………………………….. 40

6.1. Final AutoCAD plan …………………………………… 42

6.2. Exported model to STAAD …………………………… 42

6.3. Sectional Properties …………………………………… 43

6.4. 3d Rendering of Structure ……………………………. 44

6.5. Seismic parameters …………………………………… 44

6.6. Live load application ………………………………….. 45

6.7. Shear force …………………………………………….. 47

6.8. Bending moment ………………………………………. 47

4
7.1. Beam results …………………………………………… 48

7.2. Column results ………………………………………… 49

7.3. Member formation …………………………………….. 50

7.4. Beam detailing ………………………………………… 50

7.5. Column calculations ………………………………….. 51

7.6. Column detailing ……………………………………… 51

7.7. Footing layout …………………………………………. 53

5
List of Tables
Table No. Title Pg. No.

2.1. Spaces to be ventilated in a hospital ………………. 18

3.1. Arear allotted for each services …………………….. 19

3.2. Area calculation ………………………………………. 20

5.1. Ground floor details ………………………………….. 25

5.2. First floor details ……………………………………… 27

5.3. Second floor details ………………………………….. 29

5.4. Third floor details …………………………………….. 31

6.1. Auto generated load combinations …………………. 45

9.1. Loading Parameters …………………………………. 80

6
INTRODUCTION CHAPTER !

CHAPTER 1

1.1 INTRODUCTION

A hospital is an establishment that specializes in healthcare for patients using


effective medical treatment. They consist of medical professionals such as doctors
and surgeons, whom with the assistance of nursing staff and medical equipment
provide diagnosis and relief to the patient. Generally, there are two types of patients
in a hospital. They are in-patients and out-patients respectively. A medical institution
is always well-equipped to handle large number of patients at any given time with a
sense of providing immediate diagnosis and relief. The hospital that takes care of
such urgency is normally a general hospital. It has an emergency section that takes
care of victims who undergo accidents due to fire, traffic, domestic incidents etc and
also sudden illnesses. For the care of in-patients there are various specialized wards
for the patients to rest and recover. There are also rooms for performing various
surgeries and operations. Hospitals are generally funded by the local government,
various health organizations and sometimes even private donations from
entrepreneurs. Sometimes, when there is a need for a single type of treatment or
specialization, there are various hospitals that provide these kinds of care.

They are generally categorized as:

i. Cardiac hospitals

ii. Oncology hospitals

iii. Women’s hospitals

iv. Children’s hospitals

v. Psychiatric hospitals

vi. Trauma centers

vii. Cancer treatment centers

All the above types of exclusive healthcare are found in multi-speciality hospitals.
They are mostly large in size and have a major patient flow daily.

1.2 OBJECTIVE

The main objectives of this project are:

0 To plan, design and analyze a hospital building.

1 To study the requirements in and around a hospital building.

2 To learn about the code provisions involved in designing a hospital building.

3 To study and understand the various components of hospital building.


7
INTRODUCTION CHAPTER !

4 To design various structural elements of the building manually by checking


several safety conditions.

5 To get hands on experience to use various design and analysis software.

1.3 OUTCOME

The various outcomes of this project are as follows:

6 The necessity of an efficient hospital building.

7 The modelling of building using structural and architectural software.

8 Efficient methods to use manpower, cost and time to complete a hospital


building.

9 Application of various theoretical knowledge gained to design a hospital


building.

8
REQUIREMENTS CHAPTER 2

CHAPTER 2

2.0. REQUIREMENTS OF VARIOUS ROOMS, UNITS AND DEPARTMENTS

The basic requirements and planning of a hospital building was taken from IS
12433-2(2001). This code gave the provisions for a hospital building having up to
100 beds.

2.1 CIRCULATION AREA

Circulation area are the spaces in a hospital building that is used by patients
and people for movement in and around the building. They give access to other parts
of the built environment and also passages leading outdoors. These spaces give a
means of orientation within the building. Visitors, patients and staffs can also find
their way by looking at the well-directed routes overhead that are illuminated using
lights. Circulation spaces include entrances, waiting areas, corridors, stairs, lifts,
landings, foyers etc. According to hospital codes, corridors having breadth less than
8 feet are undesirable. A protective corner beading must be provided in hospital
corridors for impact collisions and to reduce wear and tear on the wall.

Corridors facilitate horizontal circulation, whereas the vertical circulation is in


the form of structures such as stairs and lifts. In a hospital building there are some
spaces like operation theatres, laboratories etc which may be restricted to public
access. They are circulation spaces that can be used only by doctors and medical
staffs.

The circulation space area is determined by considerations such as:

i. The number of people using them


ii. The type of usage
iii. The direction of flow of traffic
iv. Crossing flows.

Open spaces include atriums, courtyards and in some cases verandahs that
may have several functions. The more the open space area there is in a hospital
building, there can be more accommodation for patients during emergency situations
and severe crises such as breakout of diseases.

2.2 FLOOR HEIGHT

The height of floors of every building varies with the client and standard codes
of different countries. According to IS codes, the floor height is generally measured
at any point from the floor surface to the lowest point of the slab or ceiling. It must
not be less than a height of 3 m. This includes the minimum head-room from the
bottom of beams. With the exception of doors, the minimum aggregate areas of

9
REQUIREMENTS CHAPTER 2

openings are kept at a minimum of 20% of the floor area. For rooms with appliances
such as fans and lights, the floor height is measured to be 2.5 m from the floor to the
appliance. HVAC system requirements are also taken into account while fixing the
height of the room.

2.3 PHARMACY OR DISPENSARY

A Dispensary is a small setup in a hospital that has medical supplies and


medical equipment. It is set-up by a pharmacist to give medications as per
prescriptions from a doctor.

10 Location: The dispensary must be located in an area that can be easily
accessed by all the clinics in the hospital.

11 Size: The size of the dispensary must be good enough to contain 5% of the
total clinical visits to the OPD in one session at a rate of 0.8 m² per patient.

Generally, for every 200 OPD patients daily, one dispensing counter is
provided. The dispensary and the compounding room have many dispensing
windows, compounding counters and shelves. The patterns of arranging these
shelves and counters depend on the size of the room.

Dispensaries in hospitals have standard procedures for activities such as


stocking, preventing stock out of important drugs, receiving, inspecting, handing
over, storage and retrieval of drugs, inventory management, storage of narcotic
drugs, checking of pilferage, date of expiry and pest and rodent control. A checklist is
often kept by a pharmacist for medicines and medical equipment, so that it is not
easy to lose track off.

Independent dispensaries are provided for the access of both in-patients and out-
patients in a hospital.

Recommended size of a dispensary:

12 In-Patient Dispensary – 2m x 1m

13 Out-Patient Dispensary – 3m x 3m

2.4 CLINICS

Clinics are healthcare facilities in a hospital that mainly focuses on the care of
out-patients that are run by multiple practitioners. A Clinic’s aims are to deliver
primary service in health education and also providing health care services.

A meagre number of small procedures like dressing and administering


injections are done in clinics. The treatment and dressing rooms have to be spacious
enough to accommodate a medicine chest, a work counter and pedal operated bins
for effectively disposing used cotton, bandages, plasters etc. Importantly, rooms for
treating infectious and communicable diseases are kept isolated from the rest of the
hospital at a remote corner.

10
REQUIREMENTS CHAPTER 2

A doctor’s consultation room must accommodate a maximum of 4-5 people.


All consultation rooms are to be provided with items such as examination table, X-
ray view box, screens and wash basin facilities with also having enough numbers of
wheelchairs and stretchers.

Required spaces in clinics:

1. Reception

2. Waiting Lobby

3. Consultation rooms (or) Cubicles

4. ECG rooms

5. Toilets

Minimum area requirements of a clinic:

14 Reception and Waiting lobbies – 14 sq m

15 Consultation rooms – 14 sq m

16 ECG room – 10.5 sq m

17 Toilets – 3.5 sq m

2.4.1 OBSTETRIC AND GYNECOLOGICAL CLINIC

This clinic is headed by a doctor who specializes in women’s health. An


obstetrician-gynecologist is also known as an OB-GYN. The reception and
registration areas are separate. There is a waiting area near the reception and the
registration section. There are important rooms in this clinic such as rooms for
treatment, consulting-cum examination and a laboratory. This clinic is planned in
such a way that it provides easy access to in-patients, thus enabling them to use the
clinics for antenatal and postnatal care. There is also an additional provision of a
toilet-cum-changing room close to the treatment room.

For the purpose of out-patients, the clinic is conveniently placed near the
OPD. Patients in antenatal care have to undergo a small procedure before being
checked by the doctors. For this reason, a clinical laboratory is provided with a toilet-
cum-changing room attached to it.

Minimum room dimension required: 3m x 4m

Minimum area requirement:

 Consultation or examination room -15.40 sq m


 Examination and treatment room - 10.40 sq m

11
REQUIREMENTS CHAPTER 2

2.4.2 PEDIATRIC CLINIC

For children aged 12 years and below, a pediatric clinic provides them with
healthcare and medical treatment. The doctor that specializes in pediatrics is known
as a Pediatrician. Due to high risk of infection, this clinic is often placed at a safe
distance from the rest of the clinics in the hospital. A separate treatment room is
provided for immunization in a Pediatric clinic. A children’s play area is also provided
in the clinic.

Minimum dimension required: 3m x 4m

Minimum area requirement for the patient - 14 to 19 sq m

Minimum area for a cubicle with at least one wash basin for two beds - 19 to 24
sq m.

2.4.3 ORTHOPEDIC CLINIC

Orthopedic clinics mainly focus on the care of the skeletal structure and
system. The doctor who practices this type of medicine is known as an Orthopedist.
The skeletal system is majorly made up of muscles, bones and it also consists of
joints, ligaments and tendons. In this clinic, there are separate rooms for preparation
of plaster for mending fractures. The consultation cum-examination room is where
the doctor checks the patient and gives diagnosis. The X-ray equipments in the clinic
should be in close distance with the radiology department, emergency and accident.
This helps in making maximum use of equipment and decrease the amount of
energy used in travel.

Storage rooms are provided for storing materials like plasters, bandages,
splints and other aids of therapeutic nature. Treatment rooms for mending fractures
and sprains must have good space to accommodate a dressing stand and a mobile
X-ray unit. Finally, a recovery room next to the treatment room is vital so that
patients can rest for a while before being transferred to a ward or leave the hospital.

Minimum area requirement:

Doctor’s chamber - 13.5 sq m

Plastering room - 13.5 sq m

Plaster preparation room - 9 sq m

12
REQUIREMENTS CHAPTER 2

2.5 SIDE LABORATORY:

A side laboratory is generally used for fast detection of problems in blood and
urine of patients. The minimum area needed for a side laboratory is 36 sq m. The
test samples of the patients are taken in this room and many laboratory tests are
done on it. The data and test results of the patients are managed by a software.
These laboratories are to be located near the doctor’s room.

2.6 INJECTION ROOM:

A hospital consists of a main injection room that is provided next to the


dispensary. The main type of injection that is administered in separate rooms are
inoculation and immunization injections. There are certain side-effects that the
patient undergoes when the injection is administered. For this purpose, a stretcher is
kept in the injection room. In addition to this a pedal dustbin is kept in order to
dispose-off the used syringes and medical items. The minimum area required for this
room is 12 sq m.

2.7 DIAGNOSTIC SERVICES

The diagnostic services specifically give quick, economical and high-class


diagnostic care to patients in well-protected surroundings. Departments like
Radiology and Nuclear medicine form the backbone of such diagnostic services that
detect very complex diseases and conditions. The rooms having X-ray equipment
has a minimum dimension of 18 sq m. For radiation control in X-ray rooms, a 2 mm
lead sheet sandwiched between the partitioning or a 115 mm brick with 6 mm barium
plaster is used. This room should be attached to a waiting area with a toilet facility
and also a change room facility.

2.8 DARK ROOM (FILM DEVELOPING AND PROCESSING)

The dark room consists of equipment that is used for developing and
processing X-ray results. This comes under the radiography department. Accurate
processing of the X-ray films is vital in radiography to obtain effective results. The
usage of smart and quick methods makes this process less expensive. A skilled staff
is required in the dark room so that using their extensive knowledge, they can notice
pivotal details and eliminate the errors. The dark room should not have light entering
inside it and this is done by installing an airlock. Ventilation is, however required
inside the room which includes provision of exhaust fans. The minimum area
required for the dark room is 2.6m x 2m.

13
REQUIREMENTS CHAPTER 2

2.9 BLOOD BANK

The blood bank is a room in a hospital that collects and stores blood of
various donors and patients. They are arranged in terms of blood groups and are
catalogued. The blood bank also issues blood to patients needing the specific blood
group at a specific quantity. They are known as blood transfusions. The storage of
blood is done in refrigerators, which consists of several rows of shelves. The room
has a minimum area of 100 sq m and an extra area of 50 sq m is provided for the
preparation of blood products such as in centrifuges. The blood bank is attached with
a bleeding room that consists of blood groupings, a blood storage room and a
recovery room containing stretchers. A reception area is provided outside the blood
bank.

2.10 BLEEDING ROOM

This room is where the donors donate their blood. They consist of cubicles for
donor privacy. The bleeding room is attached to the blood bank for storing blood
groupings of donors and patients. This room is attached to a resting room exclusively
for donors and also a reception area. Since, the risk of infection is high, free flow of
people in this room is restricted. The appropriate size for the bleeding room is 3.6m x
3.6m. A washroom is provided near the resting room for the use of donors.

2.11 INTENSIVE CARE UNIT (ICU)

This unit specifically concentrates on patients with highly critical conditions


and require excellent medical help and good care. The number of patients in the
Intensive Care Unit varies daily. The operation theatre is always placed close to the
ICU, because, when the patient is in danger, the hospital staff can transfer the
patient immediately. Other important departments like the pathology and radiography
departments are near, so that when there is a decrease in medical staff, the staffs
can be shared. The ICU should have a minimum of 4 beds and a maximum of 12
beds. For free movement of staff and equipment, the area for each bed is restricted
to 10.5 sq m. The area for each bed is also devised based on the infection criteria.

2.12 OPERATION THEATER

An operation theater is a room where all kinds of surgeries and operations are
performed by highly skilled medical professionals. The medical procedures are
usually carried out in a clean or a sterile environment where all the people in the
room wear masks and protective suits to prevent spread of germs. This room usually
does not have a window and it uses air conditioners to maintain a controlled
atmosphere.

14
REQUIREMENTS CHAPTER 2

Various planning and factors are taken into consideration before placing an
operating room in a hospital building. They are generally placed in quiet
surroundings in the hospital and also most importantly the area must be free from
any contaminants. In addition to these considerations, the OT area must have
utmost shielding from sun light. They must be nearby and easy to access from other
units such as ICU, radiology, pathology, blood bank, CSSD and wards.

Operation theaters are divided into 3 zones:

18 Zone A – This zone is known as the protection zone where the medical
staffs who look after the patient cannot come inside this area.

19 Zone B –This zone is known as the clean zone that consists of rooms for
doctors for changing into medical gear, medical gear and equipment storage and an
induction room for administering anaesthesia to the patient.

20 Zone C – This zone is known as the sterile zone, which covers an area that
includes the operation theatre and the scrub-up room where the doctor cleans up.

21 Zone D – This zone is known as the disposable zone that is a separate area
having direct access to the operating room where all the unclean materials and used
medical equipments are disposed.

An operation theatre has a minimum size of 6.5m x 6.5m, with the corridor
width of minimum 2.85m. The wall corners should be curved to stop dust from
staying on the corner surface. Importantly, the movement of patients and medical
equipment is in one direction. When there are multiple operation theatres present,
the pre-operative, post-operative and a scrub-up room is provided for common use.
The minimum dimensions of the additional rooms largely depend on the number of
operation theatres that makes use of these rooms. In a hospital the number of beds
to be provided should be a minimum of 35-50% of the total bed count.

2.13 HOSPITAL KITCHEN / CANTEEN

Generally, in a hospital, huge crowds come on a daily basis. It is the duty of


the hospital to provide food to the people visiting there and also to the medical staffs
inside. For this reason, a canteen attached to a kitchen is provided in hospital
buildings. The planning of space in the canteen is vital in the view of crowd control
as there is always a huge risk of spread of infections and pathogens. The control of
noise and odour is sentient as this may cause distress to patients admitted in the
hospital and also disrupt its functioning. Proper ventilation and natural lighting are
provided in addition to the artificial lighting already present. Since, patients need to
be given food at a specific time, the canteen is made easily accessible for this
purpose. This is in the form of a ward pantry that serves food to the patients. Despite
this, the most preferred option is to have the canteen in a separate area. In the
hospital kitchen, proper space is given for wash areas and separate areas are
provided for a storeroom and cooking section. The space between these units is
planned in accordance with the easy flow of kitchen staff. The food requirement for a
hospital is very large, so, the storage facility is to be big enough to accommodate

15
REQUIREMENTS CHAPTER 2

them. For this purpose, a different entry is provided for the storage room. The
entrance of the kitchen must have a minimum clearance of 1.2m x 1.2m in order to
avoid collision of doors with other rooms next to it.

2.14 CENTRAL STERILE & SUPPLY DEPARTMENT (CSSD)

The Central Sterile and Supply Department has the function of storing and
supplying sterile equipment to departments like the operation theatre, clinics etc.
They sterlize the instruments thoroughly by various effective sterlization methods
and store them in ultra-violet ray cabinets. The CSSD is kept accessible to all the
other departments in the hospital. Since, the operation theatre facility uses sterile
instruments and equipment very often, the CSSD is placed near the operation
theatre. This unit is restricted to the public and only the medical staff is allowed to
access it. Importantly, this facility must be heavily protected from any external
agents. The control of contaminants in this unit is necessary. This unit should have a
floor space of 10 sq m per bed. The CSSD is divided into 3 zones which are the
soiled zone, clean zone and sterile zone. A barrier is provided between the soiled
and the clean zones.

The medical equipment stored in the CSSD is classified into:

22 Operation theater use – These equipments are only for the use in the
operation theater and no other departments can use this. Surgical equipments such
as gloves, cutting and dissecting instruments, forceps, clamps etc are primarily
supplied to the operating room.

23 Other departments use – These equipments are only for the purpose of
clinical areas in the hospital and are not supplied to the operation theatre. Syringes
and thermometer are such medical equipments.

24 Both OT and other departments use – These equipments are supplied to
both the operation theater and other departments. Oxygen cylinder is one such
equipment.

2.15 HOSPITAL LAUNDRY

The hospital laundry is a service provided by the hospital to give clean and
odourless linen to all the patients. The hospital linen consists of all the cloth used in
the hospital. This includes the pillow covers, blankets, mattress, patient clothes
provided by the hospital, bed sheets, towels, table cloth etc. There are two primary
obligations taken by the laundry service, which are cleanliness and disinfection of
cloth. The washing of linen used for the operation theatre is very important as it
should be thoroughly sterilized before use and there must not be any signs
contaminants. For this purpose, a separate laundry is provided only for the OT.
Laundries are run manually or electrically and they are provided with units for
processes like drying, pressing and storage of dirty and cleaned linens. Most
importantly, the change of air in the laundry area is done about 10 times an hour.
Specific methods are used for removing specific stains on the linen. The storage of
Ready To Use (RTU) cleaning chemicals such as abrasives, acids, alkalies,

16
REQUIREMENTS CHAPTER 2

bleaches, detergent and sanitizers are also considered while considering the floor
area.

Requirements:

Minimum area: 1 m²/bed

Layout: U-shaped or Rectangular shaped

Designing the laundry space: Space is mainly provided for heavy machines like the
washing machine and squeezer. In addition, there is provision for supply of water and
power. They are designed in such a way that it should help with the main processes
like sorting, washing, hydro-extraction, drying, ironing, folding and packing. There are
separate spaces provided for sewing the linens. A barrier is provided between
sorting, washing and hydro extraction areas and the clean linen processing area.

Floors and Ceiling: The floor should be rust non-slippery, free from rust, easily
washable and have sufficient slope to provide easy flow of water. The ceiling should
be easily washable, non-slippery, moisture proof, and finally, sound proof. The floor to
ceiling height is not less than 3.5 m.

Lighting: Provisions for access to daylight is given so as to increase the productivity


and efficiency of laundering.

2.16 MEDICAL AND GENERAL STORE

The hospital stores consist of various stores that helps in the effective
functioning of the hospital. The space for each store is used to the maximum by
providing built-in shelves at various heights based on the type of store. Proper
ventilation and security arrangement is provided in every store. Fire extinguishers
and other fire retarding instruments are provided for the stores. For the medical store
or the pharmacy, the layout and the facilities provided are very important, since the
requirement from this store is humongous. The hospital pharmacy deals with
obtaining, storing, compounding, dispensing, testing and distribution of medicines.
They also provide the hospital with medical equipments needed for surgeries and
operations. While designing a medical store one needs to look at the space
requirements of both the the people working there and the customers. The layout of
the drug store must be pleasing to the eye, by having different colours for each
department and easy navigation.

Floor area requirement:  The pharmacy requires a space not less than 24 sq m for


a hospital of any size. The basic requirements for a 100 bedded hospital are 0.93 sq
m per bed.

17
REQUIREMENTS CHAPTER 2

2.17 VENTILATION

Ventilation of hospital buildings is vital and it is done either by natural supply


and natural exhaust of air or natural supply, mechanical supply and mechanical
exhaust of air. Proper ventilation and indoor air quality are to be maintained to have
excellent infection control and importantly, patient safety. Major factors are taken into
account while providing ventilation for hospitals, such as the lack of directional
control of airflow that may have a potential to cause transmission of diseases. The
general standards for ventilation in a hospital building is given based on
maintenance of required oxygen, carbon-dioxide and other air quality levels. This is
mainly for controlling the body odours in the air, when no products of combustion,
other contaminants and anaesthesia gases are present in the air which may be
highly dangerous.

Table 2.1 Spaces to be ventilated in a hospital

Space to be Ventilated Air Changes Per Hour

Bathrooms/toilets 6-12

Wards 8-12

Kitchens 6-9

Operation theatres 15-20

Other air-conditioned spaces 8-10

18
PLANNING CHAPTER 3

CHAPTER 3

3.0.. PLANNING OF HOSPITAL BUILDING:-

3.1 AREA REQUIRED PER BED


Table 3.1 Area allotted for each services

Particulars Area Per Bed (m2)

Entrance area 4.20

ambulatory 9.31

Diagnostic service 5.95

Intermediate care area 15.75

Intensive care area 1.96

Critical care area 4.69

Therapeutic services 8.75

Hospital services 7.0

Engineering services 3.92

Administrative/Ancillary services 4.48

66.01

Add 40 percent for circulation 26.4

Space including corridors 92.41

19
PLANNING CHAPTER 3

3.2 CALCULATION OF AREA

Assumption for number of beds

Table 3.2 Area calculation

Departments No. of beds

Ophthalmology 5

ENT 5

Obstetrics & Gynaecology 15

Pediatric 10

Orthopedic 15

ICU 10

Total number of beds 60

Operation theatre(50% of total) 30

Final number of beds 90

Approximate area per IS 12433 (part2):2001=66.01 m 2 per bed

 Total area to be provided for beds =90*66.01 =5941 m 2


 Add 40% for circulation area = 1.4*5941 =8318 m 2

The total carpet area to be provided including all amenities = 8318 m 2

20
PLANNING CHAPTER 3

3.3 FLOOR CALCULATION

FLOOR DESIGN

Based on trial and error process, the following plan was developed and the size of
each block was fixed to be 37m x 20m

Figure 3.1 Final proposed design

Area of one block per floor = 37x20 = 740 m2

Total number of blocks = 3

Total area per floor = 3*740 = 2220 m2

Number of floors needed = (Total area needed)/(Total area per floor)

= 8318 / 2220

= 3.75

= 4

Hence the final design proposed is given in Fig 1.Each block is provided with a size
of 37m x 20m. 3 such blocks are provided in each floor and 4 such floors are
provided.

21
SITE VISIT CHAPTER 4

CHAPTER 4

4.0. SITE VISIT: VISIT TO TIRUNELVELI ESIC HOSPITAL

The following features of the hospital were noted.

Figure 4.1 Air and water purifier

Figure 4.2 Power supply

22
DRAWINGS & NOMENCLATURE CHAPTER 5

CHAPTER 5

5.0. DRAWINGS AND NOMENCLATURE

5.1. FLOOR PLANS:-

5.1.1 GROUND FLOOR:-

Figure 5.1 Ground floor layout

23
DRAWINGS & NOMENCLATURE CHAPTER 5

Table 5.1 Ground floor details

Rooms Dimensions(mm)

Reception and Billing 10000 x 10000

Pharmacy and storage 10000 x 10000

AHU 4000 x 3000

Power room 4000 x 3000

Toilet 5000 x 5000

OTS 5000 x 8300

Help desk 8000 x 3000

Scan 1 & 2 8000 x 8000

Emergency Ward 7000 x 10000

Dining 20000 x 5000

Kitchen 20000 x 5000

Laundry 5000 x 5000

X Ray room 8000 x 8000

UPS room 2000 X 3000

Cable room 18000 x 7000

Manifold 7000 x7000

24
DRAWINGS & NOMENCLATURE CHAPTER 5

5.1.2 FIRST FLOOR:-

Figure 5.2. First floor layout

25
DRAWINGS & NOMENCLATURE CHAPTER 5

Table 5.2 First floor details

Rooms Dimensions(mm)

OTS 5000 X 8300

ENT 1 5000 x 3000

ENT 2 5000 X 4000

OPTHALMOLOGY 1 5000 x 4000

OPTHALMOLOGY 2 4000 x 3000

Library 4000 x 3000

Conference hall 4000 x 7230

Head nurse room 4000 x 3000

MS room 4000 x 3000

AHU 3000 x 4000

Power room 3000 x 4000

Toilet 5000 x 5000

OP ward 1,2,3,4 5000 x 4087

OP ward 5,7,8,9,10 5000 x 4205

Power room 3000 x 3000

Nurse station 4000 x 4000

General ward 25230 x 5000

OP ward 5000 x 4000

Lab 5000 x 7540

Lab collection 5000 x 4000

26
DRAWINGS & NOMENCLATURE CHAPTER 5

Blood bank 5000 x 5000

5.1.3 SECOND FLOOR:-

Figure 5.3 Second floor layout

27
DRAWINGS & NOMENCLATURE CHAPTER 5

Table 5.3 Second floor details

Rooms Dimensions(mm)

General ward 35000 x 5000

OTS 5000 x 8300

Power room 3000 x 4000

AHU 3000 x 4000

Toilet 5000 x 5000

General ward 1 35000 x 5000

General ward 2 25230 x 5000

Nurse station 4000 x 4000

ICU 25230 x 5000

5.1.4 THIRD FLOOR:-

28
DRAWINGS & NOMENCLATURE CHAPTER 5

Figure 5.4 Third floor layout

29
DRAWINGS & NOMENCLATURE CHAPTER 5

Table 5.4 Third floor details

Rooms Dimensions(mm)

Waiting area 10000 x 10000

AHU 4000 x 3000

Toilet 5000 x 5000

Pre op area 15000 x 5000

Post op area 20000 x 5000

CSSD 5000 x 5000

Stores 5000 x 4000

Power room 4000 x 3000

Waste segregation 5000 x 5000

Scrub up area 5000 x 5000

OT complex 1 &2 25230 x 6000

5.2. STRUCTUAL ELEMENT LAYOUT PLAN

5.2.1. COLUMN LAYOUT:-

30
DRAWINGS & NOMENCLATURE CHAPTER 5

Figure 5.5 Column layout

Total number of columns = 86

5.2.2. BEAM LAYOUT:-

31
DRAWINGS & NOMENCLATURE CHAPTER 5

Figure 5.6 Plinth beam layout

Total number of beams = 236

32
DRAWINGS & NOMENCLATURE CHAPTER 5

Total number of beams = 299

33
DRAWINGS & NOMENCLATURE CHAPTER 5

Figure 5.8 Second floor beam layout


Total number of beams = 299

34
DRAWINGS & NOMENCLATURE CHAPTER 5

Figure 5.9 Third floor beam layout

Total number of beams = 290

35
DRAWINGS & NOMENCLATURE CHAPTER 5

5.2.3 SLAB LAYOUT:-

Total number of slabs = 93

One way slabs = 24

Two way slabs = 69

36
DRAWINGS & NOMENCLATURE CHAPTER 5

Figure 5.11 Second floor slab layout

Total number of slabs = 96

One way slabs = 24

Two way slabs = 72

37
DRAWINGS & NOMENCLATURE CHAPTER 5

Total number of slabs = 90

One way slabs = 17

Two way slabs =73

38
DRAWINGS & NOMENCLATURE CHAPTER 5

5.3. NOMENCLATURE

Figure 5.13 Nomenclature of beams and slabs

BEAMS:-

Beam name: 3X1

where,

3 – Floor number

X – Represents the direction of the beam (x or y)

1 - Beam number

SLABS:-

Slab name: 3S1

where,

3 – Floor number

S – Alphabet to represent slab

1 – Slab number

39
DRAWINGS & NOMENCLATURE CHAPTER 5

Note:-

 The numbering should be started from the left top corner of the plan.
 Once the numbering of beam is completed in horizontal direction, numbering
should be continued in vertical direction from top to bottom

40
ANALYSIS IN STAAD.Pro CHAPTER 6

Chapter 6

6.1. Introduction to Staad.Pro


STAAD.Pro also called STAAD is a structural analysis and design software
programme created by Research Engineers International in 1997. Later in 2005, it
came under the control of Bently systems as they bought Research Engineers
International. Similar to Etabs, it is one among the most popular structural analysis
and design software. It’s popularity arises from the fact that it can support 90
different international coadal provision for concrete, steel, timber and aluminium. A
variety of analysis method including the static and dynamic analysis methods has
been embedded making it one of the most versatile software for analysis and design.
In addition to the basic physical and analytical modelling tab, STAAD provides a
range of specialized tabs, which includes STAAD Building planner, Steel Auto
drafter, STAAD.Beva, Advanced concrete design, Foundation design, Advanced slab
design and Earthquake mode, which can be used exclusively when a particular
variety of design is required. Staad is interoperable with other engineering analysis
and design software making it user friendly.
6.2. Importing drawing from AutoCad to STAAD
After finalizing the plan, a new STAAD project is created and the AutoCad drawing
can be imported to that project. When importing, care should be taken such that
each and every member are described individually. Another approach is that the
entire plan can be drawn manually in STAAD.

Figure 6.1 Final AutoCad plan

6.3. Assigning member


properties
After defining the
members,
member properties can be assigned. Different member
properties can be assigned for different members or the
same property Figure 6.2 Exported model to STAAD
can be assigned to the entire structure. However, when the
same property is assigned to the entire structure, economy
of the structure has to be compromised. In addition to
defining member properties, material property can also be

41
ANALYSIS IN STAAD.Pro CHAPTER 6

defined. M30 grade concrete and Fe500 steel are defined as concrete properties.
Moreover, the following section properties were assigned
For slabs, plate thickness is defined as 175mm (1)
For beams, R1 is rectangular beam of dimension 230mm x 345mm (2)
R2 is rectangular beam of dimension 300mm x 450mm (4)
For columns, C1 is rectangular column of dimension 400mm x 400mm(3)
C2 is rectangular column of dimension 400mm x 480mm(5)

6.4. Assigning support


Support condition for the structure can be selected from a range of predefined
support condition or can be defined based on requirement. For this structure, fixed
support condition has been assigned throughout the structure.
6.5. Rendering of structure
After assigning all the properties, the three dimensional view of the structure can be
rendered via STAAD. This feature can be used to apply eccentricity to beams to
make the beam coplanar with the column. This is done to improve the architectural
beauty of the structure. In addition to that, there is a possibility that the slab panels
may be supported at different levels as the cross sectional properties of the beam
vary within floors. Moreover, slabs may not rest over beam and may be positioned at
a lower level. Carrying out analysis and design with such mistakes must be avoided
as the beams and columns may be under designed leading to failure of members
under practical conditions.

Figure 6.4 3d Rendering of structure

6.6. Load Definitions


6.6.1. Earthquake load
The earthquake load for the structure has been
assigned in accordance with IS 1893 – 2005 which
is in-buit in STAAD. Based on these inputs, the load
values are generated and assigned to the entire
structure in staad. The following were the
assumptions made while assigning earthquake
loads.
 The structure is assumed to be located in
zone III with a zone factor value of 0.16.
 The structure is assumed to be OMRF.

42

Figure 6.5 Seismic parameters


ANALYSIS IN STAAD.Pro CHAPTER 6

 The soil is assumed to be a medium soil with soil factor as 2.


 The damping ratio is assumed as 0.05.
 Based on codal formula, the period in x direction is calculated as 5 seconds
and the period in z direction is calculated as 0.024 seconds.
Also, dead load of every member and 50% of live load has been defined as the
seismic weight of the structure.
6.6.2. Dead load
Based on IS 875 (Part 1) – 1987, the dead load of concrete has been assumed as
25 kN/m^3. As soon as this value is given as an input and the self-weight factor is
defined as 1, the deal load will be assigned for entire structure.

6.6.3. Live Load


Based on IS 875 (Part 2) – 1987, the live load of the structure has been applied. The
live load has been assumed as 3.5 kN/m^2. Care should be taken to differentiate
between one way and two way load distribution as staad considers every slab as a
two way slab. X, Y and Z range values can be mentioned and one way and two way
distribution can also be specified to apply live loads accurately to each and every
slab.

Figure 6.6 Live load application

6.6.4. Auto generated load combinations


Based on the defined load case details, STAAD generated auto load combinations
which includes ultimate load cases and serviceability load cases. The following table
shows the various factors generated for various loads to arrive at different load
combinations.
Table 6.1 Auto generated load combinations

Earthquake X Earthquake Y DL LL

Combination 5 1.5 1.5

Combination 6 1.2 1.2

Combination 7 1.2 1.2 1.2

43
ANALYSIS IN STAAD.Pro CHAPTER 6

Combination 8 1.2 1.2 1.2

Combination 9 -1.2 1.2 1.2

Combination -1.2 1.2 1.2


10

Combination 1.5
11

Combination 1.5 1.5


12

Combination 1.5 1.5


13

Combination -1.5 1.5


14

Combination -1.5 1.5


15

Combination 1.5 0.9


16

Combination 1.5 0.9


17

Combination -1.5 0.9


18

Combination 1.5 0.9


19

6.7. Analysis results

44
ANALYSIS IN STAAD.Pro CHAPTER 6

Once the load combinations are defined, the structure can be analysed. In case of
incorrect details, STAAD issues a error message and it has to corrected. Upon
successful completion of analysis, the shear force, bending moment and deflection
of various structural elements can be viewed.

Figure 6.7 Shear force

Figure 6.8 Bending moment

45
DESIGN IN STAAD.Pro CHAPTER 7

Chapter 7

STAAD also provides design for various structural elements. Though the
design of beam and column can be obtained from STAAD according to Indian
Standards, it doesn’t provide design for slab.

7.1. Material property definition

The code for design has to be specified followed by material properties has to
be assigned before carrying out design process. For this structure, IS 456 is defined
as the code and the following were the inputs for material properties

 Grade of concrete : M30


 Fy for main reinforcement : 500 mPa
 Fy for secondary reinforcement : 500 mPa
 Clear cover for beam : 25 mm
 Clear cover for column : 30 mm

After assigning the above properties, the structure can be analysed again. In case a
member fails in design stage, STAAD will issue a warning message stating the
reason for failure of member. Accordingly, the sectional property of that particular
member can be changed. This process is to be repeated until all the members are
designed and the analysis is completed without warning messages.

7.2. Design results

Once completed, the design results for beam and column can be viewed by
double clicking on that particular member. In addition to that, information regarding
the steel area required and provided can be viewed.

46
Figure 7.1 Beam results
DESIGN IN STAAD.Pro CHAPTER 7

Figure 7.2 Column results

7.3. Interactive design using STAAD

Generally, STAAD designs each and every member as an individual member.


For instance, columns which are positioned one above the other will have different
reinforcement details which may not be practically possible. Interactive design
overcomes these cons by grouping elements to members and designing as a whole.

7.3.1. Inputs

The first step in the interactive design tab involves creation of members by
grouping elements. Any number of colinear elements can be grouped together to
form members. This is followed by grouping of members to form design groups.
They can be broadly classified as beams and columns. In addition to this, the design
code and the material property has to be specified once again in this tab. Once the
above mentioned steps are completed, the structure can be designed again.

47
DESIGN IN STAAD.Pro CHAPTER 7

7.3.2. Results

In the post design tab, the hogging, sagging and also the displacement of the
member can be viewed. In addition to that, the Ast required and provided can also
be viewed. Moreover, by double clicking on any particular member, the detailing of
that member can be seen and the same can be imported to AutoCad. For columns,
the shear force with the main reinforcement detail and shear reinforcement detail can
be viewed. There is a possibility of a member being undesigned and under such
circumstances, the sectional properties of that member has to be changed in the
analytical modelling tab and it will automatically be reflected in interactive design tab.

Figure 7.3 Member formation

Figure 7.4 Beam detailing

48
Figure 7.5 Column calculations
DESIGN IN STAAD.Pro CHAPTER 7

Figure 7.6 Column detailing

7.4. Foundation design

Once the design of super structure is completed, the design of sub structure
can be initiated. STAAD provides design of footing in a different software named
STAAD foundation. It offers a variety of footing designs. It includes designing footing
as isolated, combined and mat footings.

10.4.1. Design parameters

For the purpose of footing design, the following inputs were given

 Type of footing : Combined


 Grade of concrete : M30
 Yield strength of steel : 500 mPa
 Minimum bar diameter : 12 mm
 Clear cover : 50mm
 Unit weight of soil : 22 kN/m^3
 SBC : 250 kN/m^2
 Depth of water table : 10m below ground level

49
DESIGN IN STAAD.Pro CHAPTER 7

7.4.2. Result

With the above inputs, it was found that some footings overlapped with one
another. And hence such footings were identified and designed as combined
footings. The results obtained in the STAAD format was exported to AutoCad
drawing.

50
MANUAL DESIGN CHAPTER 8

Chapter 8

8.0. Manual Design

8.1. Design of One way Slab

One way slab : 2S6

lx = 2000 mm

ly = 5115 mm

Iy/Ix = 2.558

Since Iy/Ix > 2, it is a one-way slab

Effective depth and overall depth

Shorter span, I = 2000mm

fck = 30 N/mm²

fy = 500 N/mm²

fs = 0.58fy(area of steel required/area of steel provided)

Therefore ,

fs = 290 N/mm²

Assuming the percentage of tension reinforcement as 0.6%

Hence the modification factor is 1(from fig 4 of IS 456 2000)

D = I/(Basic value x modification factor)

d = 100 mm

Take, d = 155 mm

Diameter of bar = 10 mm

Effective cover = 15 mm

D = 175mm

51
MANUAL DESIGN CHAPTER 8

Effective length

Thickness of wall = 230mm

Iex = Least of (lx + d)and(lx + thk / 2 + thk / 2)

ley = Least of (ly + d)and(ly + thk / 2 + thk / 2)

lex = Least of (2155 , 2230)

ley = Least of ( 5270 ,5345)

Therefore, lex = 2155mm

Therefore, ley = 5270mm

Loads

DL : Self weight = 4.375 KN/m²

: Wall load = 1.09 KN/m²

LL = 3.5 KN/m²

FF = 1 KN/m²

Total load = 9.965 KN/m²

Total Factored load, w = 14.9475 KN/m²

Bending moment

Maximum BM = w*(lex)² / B

= 8.68 kNm

Check for moment safety

Maximum moment = 8.68 kNm

Md = 0.36fck*Xumax*b(d-0.42Xumax)

Xumax = 0.46d(for Fe 500 and M30)

Solving for d;

drequired = 46.537 mm

52
MANUAL DESIGN CHAPTER 8

dprovided = 155 mm

Since, dreq < dprov

Safe

Calculation of reinforcement

Ast = 0.5 * (fck/fy) (1-(4.6M/fck*bd^2))^1/2)*bd

= 159 mm²

Spacing : least of (area of 1 bar) / (ast req) * 1000 = 494mm

3d = 465mm

300mm = 300mm

Spacing of main bars = 300 mm

No of bars = lex / spacing = 7.183

= 8 bars

Therefore, provide 8 #10bars @ 300c/c

Astmin = 0.12%bD

= 210 mm²

Therefore, Astmin < Astprov

Safe

Distributors

Area of distributors = Astmin = 210mm²

Spacing : least of (area of 1 bar)/(Astmin) * 1000 = 239 mm

5d = 775 mm

450 mm

Spacing of distributors = 235 mm

Number of bars = ley / spacing = 22.050

= 23 bars

53
MANUAL DESIGN CHAPTER 8

Therefore, provide 23# 8bars @ 235 c/c

Check for shear (CI 40.2.1.1)

In x direction

Shear force, Vu : w*lx/2 = 16.11 KN

Nominal shear stress, ζv : Vu/b*dx = 0.10 N/mm2

Pt% in x direction = 100*Ast/b*D = 0.09%

There is a reduction of Pt% at the supports by 50%

Pt% = 0.045%

From table 19 of IS 456 2000

For M30 grade, ζc = 0.29 N/mm²

For a slab depth of 175mm : k = 1.25

Kζc = 0.36 N/mm²

Since, ζv < kζc

Safe

Check for deflection(CI 22.2.1)

fs = 0.58 fy (area of steel requirement / area of steel provided)

= 290 N/mm²

Pt% in x direction = 0.09%

From fig 4 of IS 45:2000,

Modification factor = 1.6

D = Span / Basic Value * Modification factor = 159.84 mm

Dprov = 175 mm

Since, Dprov > D

Safe

Check for development length

54
MANUAL DESIGN CHAPTER 8

(M/V)+Lo>Ld (Cl 26.2.3b)

From Cl 26.2.1,

Ld = ɸ(0.87fy) / 4 * ζbd

ζbd for M30 grade = 1.5 N/mm² (CI 26.2.1.1)

For deformed bars there is an increase by 60%

ζbd = 2.4 N/mm²

Ld = 453.125 mm

(M/V)+Lo = 538.80+ Lo mm

Since 538.80+Lo >Ld

Safe

8.2. Design of two way slab

Two way slab : 2S1

lx = 5115 mm

ly = 5230 mm

ly/lx = 1.022

Since lx/ly < 2, it is a two way slab

Overall depth and effective depth

Shorter span, l = 5115 mm

fck = 30 N/mm²

fy = 500 N/mm²

fs = 0.58 fy (area of steel required/area of steel provided)

Therefore, fs = 290 N/mm²

Assuming the percentage of tension reinforcement as 0.2%

Hence the modification factor is 1.5 (from fig 4 of IS 456 2000)

55
MANUAL DESIGN CHAPTER 8

D = I / (Basic value x modification factor)

D = 170.5 mm

Take, D = 175 mm

Effective cover = 15 mm

Diameter of bar = 10 mm

dx = 155 mm

dy = 150 mm

Effective length

Thickness of wall = 230 mm

lex = least of (lx + dx) and (lx + thk/2 + thk/2)

lex = least of (5270 , 5345)

Therefore, lex = 5270 mm

ley = least of (ly + dy) and (ly + thk/2 + thk/2)

ley = least of (5380 , 5460)

Therefore, ley = 5380 mm

Loads

DL : Self weight = 4.375 kN/m²

: Wall load = 1.09 kN/m²

LL = 3.5 kN/m²

FF = 1 kN/m²

Total load = 9.965 kN/m

Total factored load, w = 14.948 kN/m²

56
MANUAL DESIGN CHAPTER 8

Bending moments

Iy/Ix = 1.022

From table 26 of IS 456:2000

Conditions 4 interpolating,

αx (negative) = 0.0482

αx (positive) = 0.036

αy (negative) = 0.047

αy (positive) = 0.035

Mx = αx*w*(Ix)^2 : Mx (negative) = 20.010 kNm

: Mx (positive) = 14.945 kNm


My = αy*w*(ly)^2 : My (negative) = 19.511 kNm

: My (positive) = 14.530 kNm

Check for moment safety

Maximum moment = 20.01 kNm

Md = 0.36 fck * Xumax * b (d - 0.42 Xumax)

Xumax = 0.46 d (for Fe 500 and M30)

Solving for d;

drequired = 70.656 mm

dprovided = 155 mm

Since, dreq < dprov

Safe

Calculation of reinforcement

Ast = 0.5 * (fck/fy) (1-(1-(4.6M/fck*bd²))^1/2) * bd

Ast x (negative) = 307 mm²

Ast x (positive) = 227 mm²

57
MANUAL DESIGN CHAPTER 8

Greatest : Ast x = 307 mm²

Spacing : (area of 1 bar/Ast req)*1000 = 256 mm

3d = 465 mm

300 mm

Spacing of main bars in x direction = 250 mm

Number of bars = lex / spacing = 21 bars

Therefore, provide 21#10bars @ 250c/c

Ast y (negative) = 310 mm²

Ast y(positive) = 229 mm²

Greatest : Ast y = 310 mm²

Spacing : (area of 1 bar/Astreq) * 1000 = 253 mm

3d = 450 mm

300 mm

Spacing of main bars in x direction = 250 mm

Number of bars = lex / spacing = 22 bars

Therefore, provide 22#10bars @ 250c/c

Torsion reinforcement (D-1.8)

Asttorsion = 0.75 * Area required for mid-span moment of slab


= 171.75 mm²

Size of mesh in x direction = lex / 5

= 1054 mm

Size of mesh in y direction = lex / 5

= 1076 mm

Diameter of mesh bar = 8 mm

Spacing = (area of 1 mesh / Asttorsion) * 1000

58
MANUAL DESIGN CHAPTER 8

Astmin = 0.12%bD

= 210 mm²

Number of bars for the edge strip in x and y direction

Astmin / Area of 1 mesh bar = 5bars

Therefore, provide 5#8 bars @ 290c/c

Since, Ast min<Astxprov and Astyprov

Safe

Check for shear (CI 40.2.1.1)

In x direction

Shear force, Vu : w * lx/2 = 38.23 KN

Nominal shear stress, ζv : Vu/b*dx = 0.25 N/mm²

Pt% in x direction = 100*Astx/b*D = 0.18%

There is a reduction of Pt% at the support by 50%

pt% = 0.09%

From table 19 of IS 456:2000,

For M30 grade : ζc = 0.29 N/mm²

For a slab depth of 175mm: k = 1.25

: kζc = 0.36 N/mm²

Since, ζv < kζc

Safe

In y direction,

Shear force, Vu : w*ly/2 = 39.09 KN

Nominal shear stress, ζv: Vu/b*dy = 0.26 N/mm²

Pt% in y direction = 100*Asty/b*D = 0.18%

There is a reduction of Pt% at the support by 50%

59
MANUAL DESIGN CHAPTER 8

pt% = 0.09%

From table 19 of IS 456:2000

For 30 grade : ζc = 0.29 N/mm²

For a slab depth of 175 mm : k = 1.25

kζc = 0.36 N/mm²

Since, ζv < kζc

Safe

Check for deflection (CI 22.2.1)

fs = 0.58 fy (area of steel required/area of steel provided)

Therefore,

fs = 290 N/mm²

In x direction,

Pt% = 0.18%

From fig 4 of IS 456:2000

Modification factor = 1.5

Dreq = span/basic value * modification factor = 170.5 mm

Dprov = 175 mm

Since, Dprov>Dreq

Safe

In y direction

Pt% = 0.18%

From fig 4 of IS 456:2000

Modification factor = 1.5

Dreq = span/basic value * modification factor = 174.3 mm

Dprov = 175 mm

60
MANUAL DESIGN CHAPTER 8

Since, Dprov > Dreq

Safe

Check for development length

In x direction

(M/V)+Lo > Ld (CI 26.2.3..3b)

From CI 26.2.1

Ld = ɸ(0.87fy)/4*ζbd

ζbd for M30 grade = 1.5 N/mm² (CI 26.2.1.1)

For deformed bars there is an increase by 60%

ζbd = 2.4 N/mm²

Ld = 453.125 mm

(M/V)+Lo = 527.54+Lo mm

Since 527.54+ Lo >Ld

Safe

In y direction

(M/V)+Lo>Ld From CI 26.2.1

Ld = ɸ(0.87fy)/4*ζbd

ζbd for M30 grade = 1.5 N/mm²

For deformed bars there is an increase by 60%

ζbd = 2.4 N/mm²

Ld = 453.125 mm

(M/V)+Lo = 499.13+Lo mm

Since 499.513+ Lo >Ld

Safe

61
MANUAL DESIGN CHAPTER 8

8.3 Design of beam

Beam number : 2935

Beam design as per IS 456:2000

Density of concrete = 25 kN/m3

fck = 30 N/mm2

fy = 500 N/mm2

Span of beam, l = 5.115 m

Assume, D = 400 mm

b = 350 mm

Self weight of beam, u1 = 3.5 kN/m

Wall load, u2 = 15.89 kN/m

Total udl, w = u1+u2 = 19.39 kN/m

Wall length = 5.115 m

Wall height = 3.6 m

Width of wall = 0.23 m

Bending moment

M1 = wl2 / 24 = 21.46 kNm

M1u = 31.72 kNm

Bending moment for support

M2 = wl2 / 12 = 42.29 kNm

M2u = 63.44 kNm

62
MANUAL DESIGN CHAPTER 8

For support

Check 1 : Type of beam (balanced / under reinforced / over reinforced)

M2u = 63.44 kNm

Pt = 50 * (fck/fy) * (1-(1-4.6Mu/fck*b*d^2)^0.5)

= 0.32%

Ast = 458.323 mm2

0.36fck*Xu*b = 0.87 * fy * Ast

Limiting neutral axis depth

Xumax / d = 0.46

Limiting moment co-efficient

Mulim/fck*b*d2 = 0.133

Modification factor for tension reinforcement

From figure 4 of IS 456:2000

Xu / d = 2.42 * (fy / fck) * (ast / bd) = 0.132

Xumax = 0.46 (for Fe 500)

As Xu/d < Xumax/d, hence section is under reinforced section

Check 2 : Singly reinforced / Doubly reinforced

M2u = 63.44 kNm

Mulim = 0.133 fck * b * d2 = 188.093 kNm

Modification factor for compression reinforcement = 1.08

M2u < Mulim . Hence , singly reinforced beam.

63
MANUAL DESIGN CHAPTER 8

Check 3 : Check for deflection

Modification for tension reinforcement

Area of tension reinforcement required

Astreq = 458.323 mm2

%Ptreq = 0.327 %

Astprov = 339.12 mm2

%Ptprov= 0.264 %

Modification factor, M1 = 0.98

Modification for compression reinforcement

Pccomp = 339.12 mm2

%Pc = 0.264 %

Modification factor, M2 = 1.08

Basic L / d for simply supported beam = 20

d = 255.75 mm

d after modification = (d * M1 * M2) = 270.486 mm

Overall depth, D = 305.486 mm

Depth assumed, D assumed = 400 mm

As Dassumed > Dobtained

Safe for deflection

64
MANUAL DESIGN CHAPTER 8

8.4. Design of column

Column Biaxially loaded : element 612

Unsupported length, l = 3600 mm

fck = 30 N/mm²

Breadth, b = 400 mm

fy = 500 N/mm²

Depth, D = 400 mm

Effective cover, d' = 40 mm

Load, Pu = 389.549 KN

Moment about x direction, Mux = 19.513 kNm

Moment about y direction, Muy = 19.302 kNm

Check for type of column

As per table 28 of IS 456:2000

The recommended value of effective length = 0.65l

Lex and ley = 2340 mm

Lex/b = 5.85 < 12

Ley/D = 5.85 < 12

Hence, this column is a short column.

Minimum Eccentricity

exmin = greatest of (lex / 500) + (b / 30) or 20mm = 20 mm

eymin = greatest of (ley / 500) + (D / 30) or 20mm = 20 mm

ex = Mux / Pu = 50.1 mm

ey = Muy / Pu = 49.5 mm

65
MANUAL DESIGN CHAPTER 8

Hence, ex > exmin and ey > eymin

To find P/fck

Assume pt% = 0.8%Ag (since min pt% is 0.8% of Ag)

Asc = 1280 mm²

Therefore, provide 12 # of 12-T bars on all four sides

Ascprov = 1357 mm²

P = 100*Asc/bD = 0.85

So, p/fck = 0.028

To find Mux1 and Muy1

P/fck = 0.028

Pu/fckbD = 0.08

d'/D = 0.1

From chart 48 of SP-16

Mux1/fckbD² = 0.07

Therefore, Mux1 = 134.4 kNm

d'/b = 0.1

From chart 48 of SP-16

Muy1/fckbD² = 0.07

Therefore, Muy1 = 134.4 kNm

To find Pu / Puz

Pt% = 0.8%

fck = 30 N/mm²

fy = 500 N/mm²

From chart 63 of SP-16

66
MANUAL DESIGN CHAPTER 8

Puz/Ag = 17

Therefore, Puz = 2720 kN

So, Pu/Puz = 0.14

To find Muy/Muy1

Mux/Mux1 = 0.15

Pu/Puz = 0.14

From chart 64 of SP-16

Muy/Muy1 = 0.85

Muy/Muy1(calc) = 0.14

Since, Muy/Muy1 > Muy/Muy1(Calc)

Safe

Transverse reinforcement

Pitch = 300 mm

16d = 192 mm

Least dimension of column = 400 mm

Pitch = 192 mm (least)

Diameter of stirrups = least of (0.25*dia of smallest bar or 6mm)

Taking stirrups size more than 5mm = 8 mm

Hence, provide 12# of 12-T bars with 8mm ties@ 192 c/c

67
MANUAL DESIGN CHAPTER 8

8.5 ISOLATED FOOTING DESIGN

Design Procedure:

Given data:

Axial load = 690.796 kN

Mx = 96.23kN

My = 17.36 kN

Column height = 3m

Column dimension = 400 x 400 mm

Diameter of the bar = 12 mm

Unit weight of concrete = 25 kN/m2

Soil bearing capacity = 200 kN /m2

M30 grade of concrete and Fe500 steel bar

Cover for reinforcement = 50 mm

Area required for footing:

Area required = 3.8 m2

length of footing (Lf) = 2.05 m

Breadth of footing (Bf) = 1.85 m

Providing Lf = 2.6 m and Bf = 2.4 m considering safe bearing capacity

Net soil pressure on footing:

Along x axis,

Maximum soil pressure = 236.044 kN/m2 < 1.5 SBC

Minimum soil pressure = 129.280 kN/m2 >0

Along y axis,

68
MANUAL DESIGN CHAPTER 8

Maximum soil pressure = 193.095 kN/m2 < 1.5 SBC

Minimum soil pressure = 172.229 kN/m2 >0

Hence footing is safe for bearing pressure.

Check for bending:

The critical section is at the face of the column.

Along the longer face,

Length of the overhang section (L) = 1.1 m

Resisting width (b) = 2.4 m

Bending moment at the longer face of the column = 380.496 kN

For calculation of depth considering moment about longer edge,

For Fe500, from SP -16, Table c

Depth required (dreq)= 200 mm

Along the shorter face,

Length of the overhang section (B) = 1.1m

Resisting width (b) = 2.6m

Bending moment at the shorter face of the column = 313.311 kNm

For calculation of depth considering moment about shorter edge,

For Fe500, from SP -16, Table c

Depth required (dreq)= 175mm

Providing effective depth greater of 2 values considering moment but for safety
against shear failure, the selected depth should be taken 2 to 3 times higher,

Provide overall depth (D) = 450 mm

Depth in longer face (d1) = 394 mm

Depth in shorter face (d2) = 382 mm

69
MANUAL DESIGN CHAPTER 8

Calculation of reinforcement:

Along y – axis (parallel to longer side)

From IS 456:2000, Annex G

Percentage of area of steel (% Ast) = 0.244% >0.12% of bD

Area of steel required = 2635.2 mm2

Spacing required = 103mm <180 mm (To ensure safety against cracking)

Provide spacing as 100mm.

Number of bars required = 25 bars

Area of steel provided = 2827.434 mm2

Hence provide 25 numbers of 12mm diameter bar at spacing 100mm centre to


centre parallel to longer edge.

Along x – axis (parallel to shorter side)

From IS 456:2000, Annex G

Percentage of area of steel (% Ast) = 0.196% >0.12% of bD

Area of steel required = 2293.2 mm2

Spacing required = 128.228mm <180 mm (To ensure safety against cracking)

Provide spacing as 120mm

Number of bars required = 23 bars

Area of steel provided = 2601.23 mm2

Hence provide 23 numbers of 12mm diameter bar at spacing 120mm centre to


centre parallel to shorter edge.

Check for one way shear:

Along longer direction,

Soil pressure at d = 207.053 kN

Resisting width (b) = 2.4 m

70
MANUAL DESIGN CHAPTER 8

Shear force = 375.392 kN

Maximum shear stress = 0.393 N/mm2

For M30 grade of concrete and percentage of steel (P%) = 0.299%

From IS456: 2000, pg 73 Table- 19

Design Shear stress of concrete (τc) = 0.3959 N/mm2

Hence Design Shear stress of concrete > maximum shear stress, it is safe against
one way shear. Also for shorter direction, it will safe as the depth is sufficient.

Along shorter direction,

Soil pressure at d = 188.591 kN

Resisting width (b) = 2.6 m

Shear force = 356.265 kN

Maximum shear stress = 0.385 N/mm2

For M30 grade of concrete and percentage of steel (P%) = 0.261%

From IS456: 2000, pg 73 Table- 19

Design Shear stress of concrete (Soil pressure at d = 207.053 kN)

Resisting width (b) = 2.4 m

Shear force = 375.392 kN

Maximum shear stress = 0.393 N/mm2

For M30 grade of concrete and percentage of steel (P%) = 0.299%

From IS456: 2000, pg 73 Table- 19

Design Shear stress of concrete (τc) = 0.3959 N/mm2

Design Shear stress of concrete > maximum shear stress = 0.3852 N/mm 2

Hence, design Shear stress of concrete > maximum shear stress, it is safe against
one way shear.

71
MANUAL DESIGN CHAPTER 8

Check for two way shear:

The critical distance is at distance d/2 from the face of the column

d = 388 (average of d1 and d2)

Perimeter of resisting section (Pr) = 3.152 m

Area of resisting section (tributary section) = 5.619 m2

Shear force or punching shear (Vmax) = 1026.38 kN

Max shear stress = 0.839 kN/m2

Permissible shear stress as per IS456:2000, Cl.31.6.3.1

Τc = 1.369 N/mm2

Since, Τv =1.369 N/mm2 > Τmax

Hence, it is safe in two way shear

Check for development length:

Diameter of the bar = 12 mm

Ld = 543.75 mm

Available length B = 1.1m

Hence, the column bars are extended into footing up to Ld rests on the footing
reinforcement.

72
MANUAL DESIGN CHAPTER 8

8.6. DESIGN OF STAIRCASE

Given data:

Stair hall measure = 6.53 x 5.23 m

Available vertical space between floor = 3.6 m

Horizontal span of staircase = 2m

Risers = 0.15m

Treads = 0.3m

Concrete = M30

Unit weight of concrete = 25 KN/m2

σcbc = 10

m = 9.33

fy = 500 N/mm2

σst = 275 N/mm2

Nominal cover = 15mm

Effective cover = 20mm

General Arrangement:

Height of 1st flight = 1.8 m

Number of risers required in 1st flight = 12

Number of threads required in 1st flight = 11

Space occupied by threads = 3.3m

Width of landing = 2m

Space left for passage = 0.07m

Height of 2nd flight = 1.8m

Number of risers required in 2st flight = 12

Number of threads required in 2nd flight = 11

73
MANUAL DESIGN CHAPTER 8

Space occupied by threads = 3.3m

Design Constraints:

For HYSD bars,

Concrete M30

Unit weight of concrete = 25 kN/m2

σcbc = 10

m = 9.33

fy = 500 N/mm2

σst = 275 N/mm2

K = 0.253

J = 0.916

R = 1.16

Loading on each flight:

The landing slab is assumed to span in the same direction as stair and is considered
as acting together to form a single slab.

Let the bearing of landing slab in wall = 160mm

The effective span = 5m

Let the thickness of waist slab = 209mm

Weight of slab on slope = 5225 N/m2

Dead weight of horizontal area = 5842 N/m2

Dead weight of step = 1875 N/m2

Total dead weight per meter run = 7717 N

Weight of finishing = 100 N

Live load = 2500N

Total weight = 10317 N

74
MANUAL DESIGN CHAPTER 8

Design of Waist Slab:

Bending moment = 32241 Nm

Effective depth required = 167mm

But available = 180 mm

Reinforcement:

Ast = 767.98 mm2

Using 10 mm diameter bars, area provided = 79 mm2

Number of bars = 20

Spacing = 100 mm c/c

Hence use 10mm diameter bar at spacing 100 mm centre to centre

Distribution steel area = 200 mm2

Using 8 mm diameter bars, area provided = 50 mm 2

Spacing = 252 mm c/c

Hence use 8mm diameter bar at spacing 250 mm centre to centre

75
SEWAGE TREATMENT PLANT CHAPTER 9

Chapter 9

9.0. Sewage Treatment Plant

9.1 POPULATION ESTIMATION:

Indoor patients = 150

Outdoor patients = 400

Staffs = 260

Total population = 810

Number of boarding residents = 410

Water required for boarding residents as per IS = 135 lpcd

Number of day scholars = 400

Water required for day scholars = 45 lpcd

Total water consumption = (410*135) + (400*45)

= 73350 lpcd

= 0.07335 MLD

Average sewage generated= 85% of water consumed

= 85% of 0.07335

= 0.06235 MLD

= ~0.070 MLD

Average sewage generated= 70 KLD

Average sewage flow = 70 KLD

= (70*1000) /1000

= 70 Cum/day

Peak flow factor = 3

(Assume) ∆ peak flow = 3 x times the average sewage flow

= 3*70

Peak flow = 210 cum/day

76
SEWAGE TREATMENT PLANT CHAPTER 9

9.1.1 TYPE OF SECONDARY TREATMENT:

Extended Aeration Type Of Activated Sludge Treatment.

9.1.2 LOADING PARAMETERS:

The loading parameter for extended aeration type is given below:


Table 9.1. Loading Parameters

9.1.3 PROCESS FLOWCHART:

Sewage Characteristic

Influent BOD = 350 mg/l

Effluent BOD = <20 mg/l

Influent TSS = 250mg/l

Effluent TSS = <10 mg/l

Influent pH = 6.5 to 7.5

Effluent pH = 6.5 to 7.5

Temperature maximum @ 32°

77
SEWAGE TREATMENT PLANT CHAPTER 9

Treatment Type = Extended Aeration Type Of Activated Sludge process.

9.1.4 TREATMENT UNITS :

 Inlet chamber
 Screen chamber
 Grit chamber
 Aeration tank for ASP
 Secondary clarified
 Sludge drying beds.

9.2 DESIGN OF INLET CHAMBER:

Peak flow = 210 m3/d

= {(210) /(24*60*60)}

= 2.431x 103 m3/s

Assuming:

Horizontal velocity Vh = 0.45 m/s

Length = 2m

B/D = 1.5:1

Free board = 0.3 m

Area of cross section Ax = (Q/Vh)

= 0.0054 sq.m

A = BxD

= 1.5D x D

D = 0.06m, say 0.3 m

B = 1.5xD

= 0.45m

Net C/S area = 0.135 sqm

Total depth = 0.6 m

Provide inlet chamber size of 2m x 0.45m x 0.6m

n (Manning's co-efficient) = 0.013 for cement concrete

Wetted perimeter (p) = 2D+B

78
SEWAGE TREATMENT PLANT CHAPTER 9

= 1.05 m

Hydraulic mean radius(R) = A/P

= 0.129

Vh = 0.694 (Adopting slope of 1 in 800)

Vh > 0.6 m/s as per design requirement.

CHECK:

D/3 = 0.1

A = DxB

= 0.1x0.45

= 0.045 sqm

P = 2D+B

= 0.65 m

R = A/P

= 0.0692

Vh @ D/3 = 0.46 > 0.45 m/s

Hence slope 1 in 800 is acceptable.

The out flow from the inlet chamber shall be taken to the screen chamber.

Bye-pass chamber pipe = 400 mm (assumed)

9.3 DESIGN OF SCREEN CHAMBER:

Assume number of screen chamber = 2 numbers

Qmax = 2.431 x 103 m3/s.

ASSUMPTIONS:

Type of bar = MS flat

Size = 10mm x 50 mm (Facing flow= 10mm)

Clear spacing between bars = 20 mm

79
SEWAGE TREATMENT PLANT CHAPTER 9

• Manual cleaning (assumed)


• inclination of bars with horizontal = 80°
• velocity normal to screen = 0.8 m/s (assumed)
• net inclined area required = 0.00243/0.8 = 0.00304 sq.m
• Gross inclined area = 0.00304 x 1.5= 0.0046 sq.m
• Gross vertical area required = 0.0046 x sin 80°= 0.00453
sq.m
• Providing Submergence depth = 0.3 m
• Width of channel = (0.00453/0.3)= 0.0151 m
• Adopted width of channel = 0.2 m
• Velocity check in duct = {(0.00243/(0.3 * 0.2) } =0.0405
m/s
• Not greater than 0.42 m/s

Provide 20 bars of 10mm x 50 mm @ 20 mm clear spacing.

Screen chamber width = {(10x20) +(20x22)}/2

= 0.62

Provide Screen chamber width as 0.6 m (width of one screen chamber)

Let, 2 numbers of CI penstock gates shall be provided ( one for each channel)

Liquid depth @ peak flow = 0.013 m

Free board = 0.3 m

Total Channel Depth = 0.3+0.013

= 0.313

Total Channel Depth =~ 0.45 m

Assume number of penstock gates = 2 nos

Size of penstock gates = 350mmx450mm

9.4 DESIGN OF GRIT CHAMBER:

Design flow = 70x1.25

= 87.5

=~ 100 cum/day

Assume surface loading = 1100 m3/sqm/day

To account for turbulence and short circuiting reduce the surface loading rate to 800
m3/sqm/day
80
SEWAGE TREATMENT PLANT CHAPTER 9

• Area required = 100/800

= 125 sq.m

• Provide 1 m dia chamber Area = 0.79 m2


• Detention time = 60 sec (assumed)
• Volume = (100x60) /(24x3600)
= 0.0694 cum
• Liquid depth = 0.0694/0.125
= 0.555 m
• Free board = 0.6 m (assumed)
• Total depth = 1.160 m
• Size of grit chamber = 1m diameter
• Check for horizontal velocity.
• C/s of grit chamber = 0.555x1
= 0.555 sqm

Velocity = (100/1x0.555x24x350)

= 0.00209 m/s < 0.8 m/s

Assuming grit generation = 0.005 cum/1000 cum of sewage.

Grit storage period = 8 hrs (assumed in spite of continuous raking of


grit)

Storage volume required = {(70x8)/24}x(0.05/1000)

= 0.0017cum

=~ 0.002cum

Grit storage area = (π/4) x 12

= 0.785 sq.m

Grit storage depth = 0.002 / 0.785

= 0.00255 m

Total liquid depth = 0.555+0.002548

= 0.580

=~ 0.6 m

Provide grit chamber of size 1.2m depth & 1m dia.

Outflow from the grit chamber shall be carried to the aeration tank through a 600mm
wide R.C.C. Channel provided with fine bar screen (manually operated). The clear
spacing b/w bars shall be 10 mm.
81
SEWAGE TREATMENT PLANT CHAPTER 9

9.5 DESIGN OF AERATION TANK :

Number of tanks = 2

Average flow to each tank = 70/2 = 35 cum/day

Influent BOD = 350 mg/l (BOD entering to aeration tank )

Assuming that negligible BOD is removed in screening and grit chamber.

• BOD left in outlet = 20 mg/l


• BOD to be removed in activated plant = 350-20
= 330 mg/l
• Minimum required efficiency = ( 330/350) x 100
= 94.29 %
• Adopt Extended Aeration Process which can remove BOD up to 95% to
98%.

ASSUMPTIONS:

MLSS (Xt) = 3000 mg/l (assumed)

Yo = 350 mg/l (initial BOD)

F/M = 0.12 (ratio between 0.18 and 0.10)

F/M = ((Q*Yo)/(V*Xt))

Volume (V) = 35 x(350/3000) x (1/1.2)

Volume of aeration tank = 33.25 cum

Let us assume aeration tank of depth 2m and width 5m.

Length of the tank = V/(B*D)

= 33.25/(2 x 5)

= 3.325 m

=~ 4m

Volume provided = 2 x 5 x 4 = 40 cum

9.5.1 Check For Aeration Period (or) H. R. T (t)

t = (V/Q) x 24 (hrs)

= (33.25x24)/35

82
SEWAGE TREATMENT PLANT CHAPTER 9

t = 22.8 which lies between 10hrs and 25 hrs

9.5.2 Check For Volumetric Loading

Vol. loading = (Q*Yo)/V gm of BOD5/cum

= (35x350) /40

= 306.25 gm/cum

= 0.31 kg/cum (It should lie between 0.2 to 0.4)

9.5.3 Check For Return Sludge Ratio (for SVI ranging between 50 - 150 ml/gm)

Assuming SVI = 100 mg/l

Xt = 3000 mg/l

Qr/Q = Xt/((106/SVI)-Xt)

= 3000/((10^6/100) -3000)

Qr/Q = 0.031 it should be within 0.5 to 0.1

Hence we will provide 50% sludge recirculation giving, SVI = 111

(iv) check for SRT (θc) Solid Retention Time

V.Xt = {αy . Q. (Yo -Ye) θc }/{ 1+Ke θc}

αy = 1

Ke = 0.06 d-1

Yo = 350 mg/l

Ye = 20 mg/l

V = 40 cum

Xt = 3000 mg/l

Q = 35 cum/day

(40x3000) = {1x35x (350-20)xθc}/ { 1+(0.06xθc) }

θc = 25 days

From calculations it is between 10 to 25 days.

83
SEWAGE TREATMENT PLANT CHAPTER 9

Aeration tank size is 4mx5mx2.6m ( 2m liquid depth+0.6m free board) , overall


depth.

Outlet weir type = adjustable

The effluent from the aeration tank will be taken to the final (secondary
clarified. The inflow to the secondary clarified shall be by means of 250 mm dia
C. l pipes, which will give a velocity of 0.78 m/s at peak flow.

9.5.4 Aerator Sizing:

BOD5 applied to each tank = 350 mg/l

Average flow to each tank (Q) = 35 cum/day

BOD5 to be removed in each tank = 35x0.35

= 12.25 kg/day

= 0.510 kg/h

Oxygen requirement = 1.2kg/kg BOD applied.

Peak oxygen demand = 125%

Oxygen transfer capacity of aerator in} = 1.9 kg/kwh

Standard conditions } = 1.41 kg/hp/hr

Oxygen transfer capacity of aerator in}= 0.7x1.41

Standard conditions = 0.98 kg/hp/hr

Oxygen to be applied to each tank = 1.2x0.510x1.25

= 0.765 kg/hr

HP of aerators required = 0.765/0.98

= 0.780hp

=~ 1 hp

Provide 2 generators each of 1 hp.

Check For Mixing Consideration:

Power required for mixing as per practice = 0.02 kw/hr

Volume of each aerator tank = 35 cum

84
SEWAGE TREATMENT PLANT CHAPTER 9

SHP required = 0.02x35

= 0.7 kw

HP of motor required = 0.7 /(2x0.97)

= 0.36 HP

Considering a power margin of 25% on motor rating,

Motor HP required = 0.36 x1.25

= 0.45 < 0.5hp

Provide 1 no of 1 HP motor / aerator in each tank

9.6 DESIGN OF SECONDARY CLARIFIER:

Number of secondary clarifier = 1

Average flow = 70 m3/day

Recirculate flow(say 50%) = 35 cum/day

Total inflow = 70+35

= 105 m3/day

Hydraulic detention time = 2hrs (assumed)

Volume of bank (excluding hopper portion) = (105x2)/24

= 8.75 m3

Assume liquid depth = 2m

Area (superficial) = 8.75/2

= 4.375 m2

Surface loading rate of average flow = 8.75 m3/m2/d

Surface area to be provided = 70/8.75

= 8 sq.m (provide area greater of two i.e,.8 sqm)

Diameter of circulation tank (d) = √{(8x4) /π}

= 3.19

=~ 3.5 m.

85
SEWAGE TREATMENT PLANT CHAPTER 9

Actual area provided = 3.52 * (π/4)

= 9.62 m2

Diameter = 3.5m & Depth = 2m

9.6.1 Check For Weir Loading:

Average flow = 70 cum/day

Weir loading = 70/(π×3.5)

= 6.37 cum/d/m < 185 m3/d/m

9.6.2 Check For Solids Loading:

Recirculating flow (say 50%) = 35 cum/day

Average flow = 70 cum/day

MLSS in the tank = 3000mg/l

Total solids inflow = (70+35) x3

= 315 kg/day

Solids loading = 315/8

= 39.4 kg/day/sqm

Provide a clarifier of 3 m diameter having a liquid depth of 2 m.

Hopper slope = 1:12 (assumed)

Free board = 0.3m (assumed)

Sludge will be withdrawn from the clarifier through a C.I pipe. The sludge will be
taken to the return sludge pump house. The treated effluent from the secondary
clarifier can be disposed off in a safe location.

86
SEWAGE TREATMENT PLANT CHAPTER 9

9.7 RETURN SLUDGE PUMP HOUSE:

Total return flow = 35 cum/day

= (35/24x60)

= 0.024 cum/min

Detention time = 15 mins

Volume of wet well = 0.024x15

= 0.35 cum

Provide wet well of 2mx1mx1.5m (assume)

Provide a dry well = 2mx1.5m (assume)

Size of annex control room = 2mx2m.

Provide 2 numbers of pump of each 0.35 MLD capacity in dry well for returning the
sludge to aeration tank.

Return sludge pipe diameter = 150 mm (assume)

Excess sludge shall be taken to sludge drying beds by providing necessary fittings in
the main return sludge header. The sludge feed line to the sludge drying beds shall
be 150mm diameter C.I pipe.

9.8 DESIGN OF SLUDGE DRYING BEDS:

Sludge applied to drying beds = 25 kg/day

Specific gravity = 1.015

Solid contents = 15%

Volume of sludge = (25/15%) x (1/(1000x1.015))

= 1.64 cum/day.

Total number of cycles in one year = 33

Period of each cycle = (365/33)

= 11 days

87
SEWAGE TREATMENT PLANT CHAPTER 9

Volume of sludge/cycle = 1.64x11

= 18.06 cum

Area of bed required = 18.06/0.3

= 60.21 m2

(Sludge depth = 0.3 m (assuming))

Provide 2 beds of 6mx6m

Area of bed provided = 72 sq.m

9.9 FILTRATION PUMP HOUSE & SUMP:

Actual BOD5 removed/day = 70x(350-20) /1000

= 23.1kg

Excess wasted sludge, θc = ( V. Xt )/(Qw .Xr)

25 = (40 x 3000 )/(Qw .Xr)

Qw .Xr = 4800 g/d

= 4.8 kg/day

Volume of excess sludge = 4.8/(1% x (1000x1.015))

(Contains 1% of solid & S.G of 1.015)

= 0.47 cum/day

= 0.02 cum/hr

Detention time = 8hrs

Volume of wet well = 8x0.02 = 0.16 cum

(For 1% concentration)

Provide liquid depth = 1m

Area required for 1% concentration of solid = 0.16/1

=0.16 m2

Diameter of wet well = √(0.16x4) /π

= 0.45 m

88
SEWAGE TREATMENT PLANT CHAPTER 9

Providing 1m diameter wet well for filtrate sump & 1 m liquid depth Below the
incoming pipe line.

This will be covered on top and a 4m high pump room shall be constructed over it. 2
nos of vertical non-clog pumps, each of 0.5 hp capacity , shall be provided in this
pump house. The filtrate from the pump house shall be pumped to distribution
chamber upstream of the aeration tank through 100 mm dia C.I pipe line.

9.10 DESIGN OF RAPID SAND FILTER:

Max length of lateral = not less than 60d

Spacing of holes = 6mm holes @7.5cmc/c Or 13 mm holes @15cmc/c

C.S of lateral = not less than 2 x area of perforations

C.S area of manifold = 2 x total area of laterals

Maximum loss of head = 2 to 5 m

Spacing of laterals = 15 to 30 cm c/c

Pressure of wash water @ perforations = not greater than 1.05 kg/sqcm

Velocity of flow in lateral = 2 m/s

Velocity of flow in manifold = 2.25 m/s

Velocity of flow for wash water= 1.8to2.5 m/s

Velocity of rinsing water = 0.5 to 1.0 m/min

Amount of wash water = 0.2 to 0.4 % of total filtered water

Time of back washing = 10 to 15 mins

Head of water over the filter = 1.5 to 2.5 m

Free board = 60 cm

Bottom slope = 1to 60 towards manifold.

Q = 1.71xbxh3/2

L:B = 1.25:1 to 1.33:1

89
SEWAGE TREATMENT PLANT CHAPTER 9

Allow 0.5%of filtered water for back washing and 30 mins per day for back washing
(10 cum/day)

Total filtered water = 0.41875 Kl/hr

Let rate of filtration be 5000 l/h/sqm

Area of filter required = 0.086

Adopting area of filter as 10 sqm

Assume L/B = 1.3

Hence B=3m & L=4m

Assume depth of sand as 50 to 75 cm

9.10.1 Under Drainage System:

Assuming total area of holes = 0.2 %of bed area

Area of holes = 0.02 sqm

Area of manifold = 0.08sqm

= 800 sqcm

Diameter of manifold = 31.92 cm say 32 cm

Assume c/c of laterals as 30 cm

Total no of laterals = 13.33

=~ 13 on either side

Length of lateral = 1.34 m

C.S of lateral = 2x area of perforations as per lateral

Take diameter of holes as 13 mm

Number of holes = 650

Number of holes as per lateral = 13

Area of perforations per lateral = 17.24 sqcm

Spacing of holes = 10.31 cm

90
SEWAGE TREATMENT PLANT CHAPTER 9

C.S of lateral = 34.48 sqcm

Diameter of lateral = 6.63 cm

Check :

Length of lateral = 1.34 <60d I.e., (60*0.0663) =3.98m

Rinsing wash water velocity in bed = 50 cm/min

Wash water discharge per bed = 0.1 cum/sec

Velocity of flow through lateral = 2.09 m/s

9.10.2 Wash water Gutter:

Discharge of wash water per bed = 0.1 cum/sec

Size of bed = 4mx3m

Assume two through running length at 1.5m c/c

Discharge of each trough = 0.05 cum/sec

Assume b = 0.2m

Q = 1.71xbxh3/2

h3/2 = 0.2775m

H = 27.75cm =~ 30cm

Free board = 5 cm

Total height = 35 cm (slope of 1 in 40)

9.10.3 Clear Water Reservoir For Back Washing:

Capacity of tank = 240 cum (for 4hrs filter capacity)

Assume depth d = 3m

Surface area = 80 sqm

L/B = 2

hence B = 6.5m & L = 13 m

Diameter of inlet pipe coming from the filter = 50cm

Diameter of wash water pipe to overload tank = 67.5 cm

91
SEWAGE TREATMENT PLANT CHAPTER 9

9.11 DESIGN OF ACTIVATED CARBON FILTER:

Criteria: Service velocity = 0.15 to 0.3 m/min

Bed Depth = 1 to 3 m

Contact time = 5 to 30 mins

Backwash velocity = 0.35 to 0.45 m/min

Operating flow rate = 5 cum/hr

Diameter Calculations:

Aaf = Qaf / Vaf

Amin = 0.28 sqm

Amax = 0.56 sqm

Selected area = 0.5 sqm

Daf (filter dia) = 0.80 m say 1m

Let bed height Haf = 2m

Expansion = 0.7m

Free board = 0.3m

Total height = 3m

Contact time (t) = (60*Vaf) / Qaf

Back flow rate:

Criteria :

Vabw = 0.35 to 0.45 m/min

Let's adopt Vabw = 0.4 m/min

Qabe = 12 cum/hr

Qabw,min = 10.5 cum/hr

Qabw,max = 13.5 cum/hr

92
WATER SUPPLY CHAPTER 10

Chapter 10

10.0. Water supply

10.1 TANK-1 (EXCLUSIVELY FOR PEOPLE):

For 100 Bedded Hospital

Population Expected Per Day = 810

According to IS 1172 : 1993 Table 1

Amount of water required for per person = 350 Liters

Factor of safety = 1.5 (Assumption)

810 X 350 = 283500

283500 X1.5 = 425250

1000 liters = 1 meter cube

425250 / 1000 liters = 425.25 meter cube

Splitting into 2 tanks = 425.25 / 2

= 212.625 meter cube

Assuming,

Length = 9m ,Breath = 8m,

LXB = 72 meter square;

Depth of the tank = 212.625 / (9 X 8)

= 2.953 meter

=~ 3m

Size of tank = 9m x 8m x 3m

93
WATER SUPPLY CHAPTER 10

10.2 TANK 2 ( FIRE SAFTEY ) :

According to Tamil Nadu Fire & Rescue Services Department

for Group C (Institutional – Less than 15m height)

Ground plus two or more stories, with bed

Minimum requirement for underground tank = 50000 liters

1000 liters = 1 meter cube

50000 / 1000 liters = 50 meter cube

Length = 5m ,Breath = 5m ,

LXB = 25 meter square; (Assumption)

Depth of the tank = 50/ (5 X 5)

= 2 meter

Size of tank = 5m x 5m x 2m

10.3 TANK 3 ( GARDENING ):

Amount of water required for gardening

Based on site visit, requirement is assumed as 5000 liters

5000 / 1000 liters = 5 meter cube

Length = 2.5m ,Breath = 1m ,

LXB = 2.5 meter square

Depth of the tank = 5/ (2.5 X 1)

= 2 meter

Size of tank = 2.5 m x 1 m x 2 m

94
CONCLUSION CHAPTER 11

Chapter 11

11.0. CONCLUSION:

The structural aspects of planning, analysis and design of hospital building and
sewage treatment plant has been done and get an ideas for execution of structure by
real example of existing ESIC hospital and regulation under IS codes. By using
software the project of Hospital building (G+3) were analyzed. Here the project was
analyzed by both manual and software for an clear idea of structural basis. Also
some disciplinary planning has been followed for the hospital building for user
friendly reachability of departments based on the requirements of public users,
patients, doctors, and workers etc. The waste water generated from the hospital is
treated and disposed as per the requirements.

95

You might also like