I. OBJECTIVE
i. Learn how to use computer programming for Construction Estimates.
ii. Acquire proficiency in algorithm development using a high-level programming lan
iii. Use high level language and programming applications in solving civil engineering
II. PROBLEMS
A series of 8 rectangular concrete columns with typical cross-sectional dimensions of 20 x 20 cm. i
The column has a clear height of 5.00 meters from the floor line to the bottom line of the beam. S
concrete, determine the quantity of cement, sand, and gravel required and the cost intended for the
V. TABULATION OF DATA
Table 1-4 QUANTITY OF CEMENT, SAND AND GRAVEL FOR PO
AND GIRDER PER METER LENGTH
CLASS MIXTURE
DIMENSIONS (cm)
40kg CEMENT 50kg CEMENT
side side A B A
15 20 0.270 0.225 0.210
15 25 0.338 0.281 0.263
15 30 0.405 0.338 0.315
15 35 0.473 0.394 0.369
15 40 0.540 0.450 0.420
Length 8m
Length of 1 column 5 pcs
Length 8 x 5
mensions of 20 x 20 cm. is supporting a beam. (STEP 2) Determine the quantity of eac
ottom line of the beam. Specifying class “A”
the cost intended for these concreting works. CLASS:
Cross-sectional Dimensions: 20
LET'S SOLVE IT
ON OF DATA
ND AND GRAVEL FOR POST, BEAM
METER LENGTH (STEP 3) Accomplish the Bill of Qu
MIXTURE AGGREGATES
50kg CEMENT (cu. m.) Option 1:
B SAND GRAVEL CEMENT (40kg): 15 x
0.180 0.015 0.030 SAND: 1 x
0.225 0.019 0.038 GRAVEL: 2 x
0.270 0.023 0.045
0.315 0.026 0.053 TOTAL PRICE:
0.360 0.030 0.060
Option 2:
0.240 0.020 0.040 CEMENT (50kg): 12 x
0.300 0.025 0.050 SAND: 1 x
0.360 0.030 0.060 GRAVEL: 2 x
0.420 0.035 0.070
0.480 0.040 0.080 TOTAL PRICE:
X No. of columns
= 40 m
mine the quantity of each material
A
cm x 20 cm
0.36 = 15 bags
0.28 = 12 bags
0.02 = 1 cu. m.
0.04 = 2 cu. m.
Option 1:
261.00 = PHP 3,915.00
1,365.00 = PHP 1,365.00
1,425.00 = PHP 2,850.00
PHP 8,130.00
z
Option 2:
330.00 = PHP 3,960.00
1,365.00 = PHP 1,365.00
1,425.00 = PHP 2,850.00
PHP 8,175.00
ng Excel formulas can greatly assist us, civil engineers, in determining the
ction project, as well as completing the bill of quantities, which will
and faster. Although working in this laboratory isn't always rainbows and
ut different formulas, functions, and so on. The formula we utilized was
manageable and enjoyable over time. This laboratory, on the other hand,
validation, and restriction. These observations experiences will truly help