Turbine Rolling
Turbine Rolling
3 Turbine Rolling
3a CONTROL MODE: Select Operator Auto- IN Service
3b VALVE MODE: Single Valve- IN
3c LIMITER SET POINT: Valve Position- 100% (Enter)
3d GV will open 100%
4 600 RPM
4a Give RPM Set Point 600 rpm at ramp Rate 100 rpm/min.
4b TV and IV will open accordingly to reach desired rpm.
4c Ensure at 600 rpm CRH NRV open in auto
4d Hold the turbine for 30 min for soaking- Moniter all Critical Parameters
4e Ensure at 16 rpm Turning Gear is disengaging
4f Watch for Turbine lube oil Temperature.It will Start Increasing
5 2450 RPM
5a Give RPM Set Point 2450 rpm at ramp Rate 100 rpm/min.
5b In Critical Speed 1150-2000 rpm ramp rate change automatically to 500rpm/min
5c Hold the turbine for 60 min for soaking- Moniter all Critical Parameters
5d Check JOP will stop at 1200 rpm
6 2950 RPM
6a Give RPM Set Point 2950 rpm at ramp Rate 100 rpm/min.
6b Hold the turbine for 10 min- Moniter all Critical Parameters
6c Transfer TV to GV at 2950 rpm
6d Ensure MOP discharge Pressure 21-22 bar
6e Stop AOP and HP Startup Pump
7 3000 RPM
7a Give RPM Set Point 3000 rpm at ramp Rate 100 rpm/min.
7b Moniter all Critical Parameters
8 SYNCHRONISATION
8a Take Electrical Clearance for Synchronisation
8b CONTROL MODE: Auto SYNCH- IN Service
9 After Synchronisation
9a FEEDBACK STATU: Megawatt Loop - IN
9b CONTROL SP: Target- 18MW at Rate 30MW/min
Note: If 4.9 MW load will not come in 25 seconds then TG will trip on Low Forward Power Relay
Close HP and LP bypass system as soon as Turbine got Synchronised