Actividad Act. Proced.

Tiempo % Total %
A - 3 33% 100/18 6%
B A 6 17%
C A 4 25%
D C 9 11%
E C 11 9%
F B 3 33%

0 1 2 3 4 5 6 7 8 9
Tiempo Avance del proyecto Avance de las actividades
Hora 1 6% 6% A 33%
Hora 2 6% 11% A 67%
Hora 3 6% 17% A 100% Se completo A
Hora 4 6% 22% B 17%
C 25%
Hora 5 6% 28% B 33%
C 50%
Hora 6 6% 33% B 50%
C 75%
Hora 7 6% 39% B 67%
C 100% Se completo C
Hora 8 6% 45% B 83%
D 11%
E 9%
Hora 9 6% 50% B 100% Se completo B
D 22%
E 18%
Hora 10 6% 56% D 33%
E 27%
F 33%
Hora 11 6% 61% D 44%
E 36%
F 67%
Hora 12 6% 67% D 56%
E 45%
F 100% Se completo F
Hora 13 6% 72% D 67%
E 55%
Hora 14 6% 78% D 78%
E 64%
Hora 15 6% 83% D 89%
E 73%
Hora 16 6% 89% D 100% Se completo D
E 82%
Hora 17 6% 95% E 91%
Hora 18 6% 100% E 100% Se completo E
F

Tiempo (Horas,
Dias, Semanas,
10 11 12 13 14 15 16 17 18 Meses)