Professional Documents
Culture Documents
BIDDING DOCUMENTS
Sp19.VSUP1.Vt-0422R
~iiiiiill' COMPOSITION
VOLUME I - COMMERCIAL PROVISIONS
VOLUME 11.1 - STANDARD SPECIFICATIONS (PART 1)
VOLUME 11.2 - ~TANDARD SPECIFICATIONS (PART 3, 4 & 5)
VOLUME 11.3 - STANDARD SPECIFICATIONS (PART 9, 10, 11 & ANNEXES)
VOLUME 111.1 - TECHNICAL DATA SHEETS (PART 1)
VOLUME 111.2 - TECHNICAL DATA SHEETS (PART 3, 4, 5 & ANNEXES)
VOLUME IV - BID PRICE SCHEDULE AND BID FORMS
VOLUME V.1 - BID DRAWINGS (PART 1)
VOLUME V.2 - BID DRAWINGS (PART 2)
VOLUME V.3 - BID DRAWINGS (PART 3)
VOLUME V.4 - BID DRAWINGS (PART 4)
VOLUME V.5 - BID DRAWINGS (PART 5)
VOLUME V .6 - BID DRAWINGS (PART 6)
TABLE OF CONTENTS
CLAUSE PAGE
NUMBER TOPIC NUMBER
: ...
02-922905510917 -8459055/whlstleblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2- INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
CLAUSE PAGE
NUMBER TOPIC NUMBER
1. Scope of Bid
1.2. Bids shall be for the entire Works on a single responsibility basis
covering site inspection and assessment of the extent of Works to
be done, including supply, delivery, erection, installation, testing and
commissioning, and other necessary works.
1.3. Bids shall cover all items as indicated in the prescribed Bid Form.
Bids covering only a portion of the Works called for shall not be
considered. The quantity and unit of each item stated in the
prescribed Bid Form shall not be changed by the Bidder when
calculating his Bid Price for such item.
2. The Owner
2.1. The Owner shall determine the eligible prospective Bidders, receive
and open bids, conduct evaluation of bids, and award the Contract.
a. defines, for purposes of this provision, the terms set forth below
as follows:
: ...
02·922905510917-84590551whlstle blower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2 - INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
3.2. Further, the Owner will file the necessary civil and criminal cases
available under the applicable law on individuals and organizations
deemed to be involved with corrupt, fraudulent, or collusive and
coercive practices.
b. Poor performance;
02·9229055/0917-8459055/whlstleb lower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2- INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
5. Eligible Bidders
02·92290SS/0917-84590SS/whlstloblowor@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2 - INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
6. Subcontracts
6.1. The Bidder shall include in the Bid the details of all the major items
of Works that it will subcontract which shall not be more than fifty
percent (50%) of the value of the Contract. The Bidder shall indicate
the specific items or major items of the Works that will be
subcontracted.
6.3. The Contractor shall be responsible for the acts or defaults of any
Subcontractor, his agents or employees, as if they were acts or
defaults of the Contractor.
7. Disclosure of Relationship
7.2. For this purpose, "Affiliate" means any person which, directly or
indirectly, is in control of, is controlled by, or is under common
control with, another person. For the purposes of this definition,
NATIONAL GRID CORPORATION OF THE PHILIPPINES 2-4
02·922905510917 -8459055/whlstlebiower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2- INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
8.3. The Bidder is expected to examine all instructions, forms, terms, and
specifications in the Bidding Documents. Failure to furnish all
information or documentation required in the Bidding Documents
shall result in the rejection of the Bid and the disqualification of the
Bidder.
9. Pre-Bid Conference
9.1. The Bidder by the act of submitting its Bid, shall be deemed to have
inspected the site and determined the general characteristics of the
contract works and the conditions of the contract to bid.
10.1. Bid Bulletins may be issued upon the Owner's initiative for purposes
of clarifying any provision of the Bidding Documents at any time prior
to the deadline for the submission of Bids. Any modification to the
Bidding Documents shall be identified as an amendment which shall
be communicated in writing to all who have obtained the Bidding
Documents . Bidders who have submitted Bids before the issuance
of the Bid Bulletin/Amendment must be informed and allowed to
modify or withdraw their Bids.
10.2. It shall be the responsibility of all Bidders who secure the Bidding
Documents to ensure that they are aware of and secure any Bid
Bulletins/Amendments that may be issued thru the Owner's website
as indicated in the Invitation to Bid.
: ...
02-922905510917 · 8459055/whlstloblowor@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2- INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
11.1. The Bidder is advised to visit and examine the Site of Works and its
surroundings and obtain for itself on its own responsibility all
information that may be necessary for preparing the bid and entering
into a Contract for the completion of the Works. The costs of visiting
the Site shall be at the Bidder's own expense.
11.2. The Bidder and any of its authorized personnel or agents will be
granted permission by the Owner to enter upon its premises and
lands for the purpose of such inspection. The Bidder, its personnel
and agents, will release and indemnify the Owner and its personnel
and agents from and against all liability in respect thereof and will be
responsible for death or personal injury, loss of or damage to
property and any other loss, damage, costs and expenses incurred
as a result of the inspection.
12.1. The Bidder shall bear all costs associated with the preparation and
submission of its Bid, and the Owner shall not be responsible or
liable for those costs, regardless of the conduct or outcome of the
bidding process.
: . . .
02·922905510917 -845905Siwhlst1eblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2- INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
b. Completed Bid Price Schedule stating the unit price, total prices
per item for all items, total amount and the expected countries
of origin of the Plant and Equipment and Works to be
performed under the Contract;
! • • •
02 -9229055/0917-8459055/whlslleb lower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2- INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
16.1. The Bidder shall complete the appropriate Bid Price Schedules
included herein, stating the unit price, total price per item, the total
amount and the expected countries of origin of the Plant and
Equipment and Services to be performed under the Contract.
16.2. Bidders shall indicate in the Bid Price Schedule furnished in the
Bidding Documents the unit price for every pay item.
16.3. The Owner shall not accept any unconditional or unsolicited discount
proposed by the Bidder. Any unsolicited discount shall not be
included in the evaluation of bids.
16.5. The Bidder shall fill in the prices corresponding to all the pay items
specifically described in the Bid Price Schedule. When any of the
pay items in the Bid Price Schedule is/are left blank or no prices are
indicated, it is deemed that the price/s for the particular pay item/s
is/are included in the total submitted bid price proposal.
16.7. The Bidder shall comply with the above instructions on the manner
of entering prices for items under ITB Clause 16.6.a, ITB Clause
16.6.b, ITB Clause 16.6.c and ITB Clause 16.6.d in the
corresponding columns in the Bid Price Schedule. Bids which do not
comply with aforesaid manner of entering prices shall be considered
as non-responsive pursuant to ITB Clause 32 and shall be rejected.
16.8. The term CIF and all lncoterms shall be governed by the rules
prescribed in the current edition of lncoterms, published by the
International Chamber of Commerce, Paris France, on the date of
the Invitation to Bids.
16.9. Prices quoted by the Bidder shall be fixed during the Bidder's
performance of the Contract and not subject to price escalation on
: • 0 •
02 -9229055/09 17-8459055/whlstleblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2- INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
17 .3. The Bidder shall comply with the above instructions in quoting the
corresponding currencies indicated in ITB Clause 17 .1.a, ITB Clause
17.1 .b, ITB Clause 17.1.c, and ITB Clause 17.1.d. Bids which do not
comply with above instructions in quoting the currencies shall be
considered as non-responsive pursuant to ITB Clause 32 and shall
be rejected.
18.1. Bids shall remain valid for a period of One Hundred Eighty (180)
days from the deadline of submission of Bids.
: . . .
02-922905510917 - 8459055/w h l stleblower~ngcp . ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2- INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
Bid Security shall also serve as a guarantee that, after receipt of the
Notice of Award, the winning bidder shall enter into contract with the
Owner within the prescribed time and furnish the securities required
under the Bidding Documents.
19.2. The Bid Security shall be in the form of cash, manager's check or
Surety Bond issued by a bonding company accredited by the Owner,
in an amount indicated in the BDS based on the Exchange Rate
Bulletin from the Treasury Department of Bangko Sentral ng
Pilipinas, ten (1 0) days before the Bid Opening Date.
19.3. The Bid Security shall be forfeited in any of the following cases:
a. The Bidder has withdrawn its Bid after Bid opening or prior to its
expiry-date;
b. The Bidder did not accept the correction of the Bid Price;
19.4. The Bid Security shall be valid for a period of Two Hundred Ten
(21 0) days from the deadline of submission of Bids and any period
of extension, if requested under ITB Clause18.2.
19.6. Bid Securities shall be returned to the bidders after the Contract for
the project has been signed and the Securities required under the
Bidding Documents has been furnished to the Owner, but in no case
later than sixty (60) days after the expiration of the Bid Validity
Period.
20.1. The Bidder shall submit one (1) original of the Bid Security, one (1)
original of the Technical Proposal and one (1) original of the
Financial Proposal as described in ITB Clause 14 and clearly mark
each as "ORIGINAL - BID SECURITY", "ORIGINAL - TECHNICAL
PROPOSAL" and "ORIGINAL - FINANCIAL PROPOSAL". In
addition , the Bidder shall submit one (1) copy of the Bid Security,
Technical Proposal and the Financial Proposal, and clearly mark
them "COPY NO. 1 - BID SECURITY", "COPY NO. 1 -TECHNICAL
PROPOSAL" and "COPY NO. 1 - FINANCIAL PROPOSAL". In the
event of any discrepancy between the original and the copy, the
original shall prevail.
20 .2. The original and one (1) copy of the Bid shall be typed or written in
indelible ink and shall be signed by the Bidder or a person or
persons duly authorized to bind the Bidder to the Contract. All pages
of the Bid where entries or amendments have been made shall be
initialed by the person or persons signing the Bid.
20.4. The Bidder shall submit its Bid through their authorized managing
officer or their authorized representative using the appropriate Bid
Forms on or before the deadline specified in the ITB Clause 22.
These forms must be completed without any alterations to their
21.3. If any of the envelopes are not sealed and marked as required, the
Owner will assume no responsibility for the misplacement or
inadvertent opening of the Bid.
22.1. Bids must be received by the Owner at the address and on or before
the date and time indicated in the Invitation to Bid.
22.2. The Owner may, at its discretion, extend the deadline for the
submission of bids by amending the Bidding Document in
accordance with ITB Clause 10, Amendment of Bidding Documents,
in which case all rights and obligations of the Owner and Bidders
previously subject to the deadline shall thereafter be subject to the
deadline as extended.
23.1. Any Bid submitted after the deadline for submission and receipt of
Bids prescribed by the Owner, pursuant to ITB Clause 22, shall be
declared "Late" and will not be accepted by the Owner.
: . . .
02 -9229055/0917-8459055/whl sUeblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2 - INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
24.1. A Bidder may modify his bid anytime after it has been submitted;
provided that this is done before the deadline for the submission and
receipt of bids. The Bidder shall not be allowed to retrieve its original
bid, but shall be allowed to submit another bid equally sealed,
properly identified, linked to its original bid marked as "TECHNICAL
MODIFICATION" or "FINANCIAL MODIFICATION" and stamped
received by the Owner.
24.2. A Bidder may, through a Letter of Withdrawal, withdraw its Bid after
it has been submitted, for valid and justifiable reasons, provided that
the Letter of Withdrawal is received by the Owner prior to the
deadline prescribed for submission and receipt of Bids. Provided
further, that the corresponding Letter of Withdrawal contains a valid
authorization from the signing authority requesting for such
withdrawal.
24.4. No Bid may be modified after the deadline for submission of bids. No
Bid may be withdrawn in the interval between the deadline for
submission of Bids and the expiration of the period of Bid validity
specified by the Bidder on the Bid Form. Withdrawal of a Bid during
this interval may result in the forfeiture of the Bidder's Bid Security.
25.1. The Owner shall open bid envelopes at the time, date, and place
specified in the Invitation to Bid in the presence of the Owner's
representatives only.
26. Confidentiality
02-9229055/0917-8459055/wh!Slleblower@ngc p.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2- INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
26.3. Notwithstanding ITB Clause 26.2 , from the time of bid opening to the
time of Contract Award, if any Bidder wishes to contact the Owner
on any matter related to the bidding process, it may do so in writing.
27.2. If a Bidder does not provide clarifications of its Bid by the date and
time set in the Owner's request for clarification , its Bid may be
rejected.
a. if accepted, would:
29 .3. The Owner shall examine the Bid submitted to confirm that all
requirements of the Bidding Documents have been met without any
material deviation or reservation.
30.1. Provided that a bid is substantially responsive, the Owner may waive
any nonconformity in the bid that does not constitute a material
deviation, reservation or omission.
31.1. If so allowed in accordance with ITB Clause 17.1, the Owner for
purposes of Bid evaluation and comparing the bid prices will convert
the amounts in various currencies in which the Bid Price is
expressed to Philippine Pesos at the exchange rates officially
prescribed for similar transactions as established by the Bangko
Sentral ng Pilipinas on the date of Bid opening.
02·92290SS/0917-84590SS/whlstleblower@ngcp.p h
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2 - INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
32.1. The Owner shall conduct a detailed evaluation of the Bids and
submit the Bid Evaluation Report to the ABEAC for approval.
32.3. In evaluating the Bid Price Proposal, the Owner shall undertake the
following:
d. If there is discrepancy between the unit price and the total price
that is obtained by multiplying the unit price and quantity, the
unit price shall prevail and the total price shall be corrected,
unless in the opinion of the Owner, there is an obvious
misplacement of the decimal point in the unit price, in which
case, the total price as quoted shall govern and the unit price
shall be corrected.
32.4. The Owner shall have the right to verify/validate the authenticity of
the Joint Venture or Consortium and other pertinent documents
submitted by the Bidder. In case of a misrepresentation or false
statement, the Bidder's Bid Security shall be forfeited in favor of the
Owner.
: ...
02-9229055/0917-8459055 /whiSlleblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2- INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
33. Owner's Right to Accept Any Bid, to Reject Any or All Bids, Conduct
Negotiation or Declare a Failure of Bidding
33.1. The Owner reserves the right to accept or reject any bid, conduct
negotiation , and to annul the bidding process and reject all bids at
any time prior to Contract award, without thereby incurring any
liability to Bidders. In case of annulment, all bids submitted shall be
promptly returned to the Bidders.
33.2. The Owner reserves the right to conduct negotiation with Bidders as
deemed necessary through other forms of negotiation to obtain the
most advantageous bid and to ensure that the contract amount is
within the approved budget. The Owner may invite a shortlist of
complying bidders to participate in the negotiation. The result of
negotiation shall be subject for approval by the approving authority.
33.4. In such instance as described in ITB Clause 33.3.c, the Owner shall
consider other complying Bidders for award or to conduct a re-
bidding if necessary.
33.5. After the second failed bidding, however, single source contracting
(negotiation) may be resorted to.
02 -9229055/0917-8459055/whlstleblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 2- INSTRUCTIONS TO BIDDERS Series of 2018 Version 1
or
35.1. The Owner shall award the Contract to any of the complying Bidders
based on the Submitted Bid Price or Corrected Bid Price, whichever
is lower.
36.1. The Owner shall issue a written Notice of Award to the successful
Bidder. The Notice of Award shall be sent to the successful Bidder
either by registered mail, personal delivery or by facsimile. The
Notice of Award shall state the proposed Contract Price together
with documentary requirements for the Contract.
36.2. Upon the issuance of the Notice of Award to the successful Bidder,
the Owner shall furnish the successful Bidder the Contract Form,
incorporating all the agreements between the contracting parties.
37.1. The Contract shall be signed by the Owner and successful Bidder
within ten (1 0) days from receipt of the Notice of Award. The
successful Bidder shall, within thirty (30) days from receipt of the
Notice of Award and/or PO/Contract whichever comes first, submit
to the Owner:
38.1. The Owner shall issue the Notice to Proceed to the successful
Bidder on the Effective Date of the Contract indicating therein the
Start Date.
38.2. The Contract Effectivity Date shall be the date of the contract signing
unless the Parties agreed on a different date, which date shall be
stated in the Contract, but such date shall not be earlier than the
date of signing of the Contract.
39.3. The Performance Security shall cover the period from the time of the
signing of the contract until the Final Acceptance of the Project,
which includes the Defects Liability Period plus thirty (30) days.
: . . .
02-9229055/0917-8459055/whlslleblower@ngcp.ph
VOLUME I
COMMERCIAL PROVISIONS
SECTION 2a:
BID DATA SHEETS
ITB Clause
1.1 The name of Project is:
No. Description
1. Calbayog Substation
2. Daanbantayan Substation
3. Maasin Substation
4. Tabango Substation
5.3 BIR Revenue Regulations 10-2012 - Joint Venture or Consortium
Formed for the Purpose of Undertaking Construction Projects and
Mandatory Enrollment of Local Contractors in the Electronic Filing
and Payment System (EFPS).
8.1 (II) VOLUME II-STANDARD SPECIFICATIONS
; . . .
02-9229055/091 7 -8459055/whlstleblower@ngcp. ph
BIDDING DOCUMENTS VISAYAS SUBSTATION UPGRADING
PROJECT, STAGE 1 (REBIDDING)
SECTION 2a- BID DATA SHEET Sp19 .VSUP1 .Vt-0422R
ITB Clause
9.4 The Owner's contact information is:
14.2.(g)
A. Substation Equipment:
1. Power Transformer
2. Power Circuit Breaker
3. Disconnect Switch/Earthing Switch
4. Current Transformer
5. Voltage Transformer
6. Surge Arrester
B. Secondary Devices:
1. Substation Protection System
2. Network Disturbance Monitoring Equipment
3. Power Line Carrier
4. Remote Terminal Unit
: . . .
02·9229055/ 0917 ·8459055/w hist leb lower@ngcp .p h
BIDDING DOCUMENTS VISAYAS SUBSTATION UPGRADING
PROJECT, STAGE 1 (REBIDDING)
SECTION 2a- BID DATA SHEET Sp19.VSUP1 .Vt-0422R
ITB Clause
C. Two (2) QA/QC Engineers
1. One (1) Electro - Mechanical Engineer
2. One (1) Civil- Architect
14.3.c
19.2 The Bid Security shall be in the amount of Twenty Million Pesos
(Php20,000,000.00}
Submitted To:
: . . .
02-922 9055/0917 -8459055/whistleblower@ngc p.ph
BIDDING DOCUMENTS VISAYAS SUBSTATION UPGRADING
PROJECT, STAGE 1 (REBIDDING)
SECTION 2a- BID DATA SHEET Sp19 .VSUP1 .Vt-0422R
ITB Clause
Submitted By:
[Name and Address of Bidder]
; . . .
02·922 9055/0917 -8459 055/wh ist\eb\ower@ngcp. ph
VOLUME I
COMMERCIAL PROVISIONS
SECTION3:
GENERAL CONDITIONS OF
THE CONTRACT
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
TABLE OF CONTENTS
CLAUSE PAGE
NUMBER TOPIC NUMBER
CLAUSE PAGE
NUMBER TOPIC NUMBER
: . . .
02·9229055/0917-8459055/whi•UeblowerCPngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3 -GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
CLAUSE PAGE
NUMBER TOPIC NUMBER
! • • •
GENERAL PROVISIONS
1. Definitions
a. The Owner is the party who employs the Contractor to carry out
the Works as named in the SCC.
: ...
02 -9229055/09 17-8459055/whl stle blower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
e. The Arbiter is the person appointed jointly by the Owner and the
Contractor to resolve disputes in the first instance, as provided
for in GCC Clause 87, Settlement of Disputes.
: ...
02·9229055/0917-8459055/whlstleblower@ngcp .ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
: ...
02-9229055/0917-8459055/whlstleb lower@ngcp .ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
b. The Site is the place provided by the Owner where the Works
shall be executed and any other place or places designated in
the SCC, or notified to the Contractor by the Owner's
Representative as forming part of the Site.
d. The terms Erect, Install, Place, Apply, Lay, Test include all works
done and all expenses, including labor, materials, tests, plant,
overhead (including all applicable fees) and profit margin of the
Contractor in receiving a specified item or article at a
geographical location designated in these Specifications, in
transporting it to and storing it at the site of Work, and thereby
erecting, installing, placing, applying, laying, or testing it as
shown on the drawings or as directed, and unless otherwise
specified, to be by and at the expense of the Contractor.
e. The phrases Furnish and Erect, Furnish and Install, Furnish and
Place, Furnish and Apply, Furnish and Lay, Furnish, Install and
Test include all works done and all expenses, including labor,
materials, tests, plant, overhead (including all applicable fees),
and profit margin in providing, delivering, transporting, storing
and erecting, installing, placing, applying, laying or testing a
specified item or article, as shown on the drawings or as
directed, and unless otherwise specified, to be by and at the
expense of the Contractor.
: . . .
02-922905510917 -8459055 /wh lstleblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
2. Interpretation
2.3 lncoterms
The term CIF and all lncoterms shall be governed by the rules
prescribed in the current edition of lncoterms, published by the
International Chamber of Commerce, Paris France, on the date of
the Invitation to Bids.
The Contract constitutes the agreement between the Owner and the
Contractor and supersedes all communications, negotiations and
agreements (whether written or oral) of parties with respect thereto
made prior to the date of Contract.
2.5 Non-waiver
2.6 Severability
3. Communications
4.1 This Contract has been executed in the English language, which
shall be the binding and controlling language for all matters relating
to the meaning or interpretation of this Contract. All correspondence
NATIONAL GRID CORPORATION OF THE PHILIPPINES 3·7
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
4.2 This Contract shall be interpreted in accordance with the laws of the
Republic of the Philippines.
4.5 The Contractor shall bear all costs of translation to the governing
language and all risks of the accuracy of such translation.
c. Scope of Work;
e. Drawings;
f. Technical Specifications;
i. Notice of Award;
j. Notice to Proceed;
I. Performance Security;
6.1 The Owner shall have the right without further authorization from the
Contractor to use, copy, reproduce and forward to any third party
the drawings, instructions and any other information related to the
Project to the extent that it is necessary to the work of third parties
performing any work related to the Project or part thereof. No
statement, stamp or any other reference shall exist in the
documents which might bind or seem to limit the Owner's rights in
respect to these Clauses. The Contractor shall delete, or add a
note, waiving the restrictions imposed by all such markings
appearing on drawings and other documents and witness such
deletions or waivers with its signature.
7. Confidential Details
7.1 The Contractor's and the Owner's Personnel shall disclose all such
confidential and other information as may be reasonably required in
order to verify the Contractor's compliance with the Contract and
allow its proper implementation.
7.2 Each of them shall treat the details of the Contract as private and
confidential, except to the extent necessary to carry out their
respective obligations under the Contract or to comply with
applicable laws. Each of them shall not publish or disclose any
particulars of the Works prepared by one Party without the previous
agreement of the other Party. However, the Contractor shall be
permitted to disclose any publicly available information, or
information otherwise required to establish his qualifications to
compete for other projects.
8.1 The Contractor shall keep himself fully informed of all the laws,
ordinances, regulations, orders and decrees of government
agencies having any jurisdiction or authority, which, in any manner,
02 -9229055109 17 -8459055/whlstleblower@ngcp. ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
8.2 The Contractor shall, at all times, observe and comply with all such
laws, ordinances, regulations, orders and decrees, and shall protect
and indemnify the Owner and its representatives against any claim
or liability arising from or based on the violation of any such laws,
ordinance, regulation, order or decree, whether by himself, its
employees, or its subcontractor.
Applicable taxes and fees, but not limited to, withholding taxes,
VAT, municipal licenses, permits, fees, clearances and other similar
expenses, shall be for the account of the Contractor, and shall be
deemed included in the Contract Price.
8.3 For the purpose of the Contract, it is agreed that the Contract Price
of the Contract Agreement shall consider applicable taxes, levies
and charges (herein after called "Tax") prevailing after the date of
the Invitation to Bid in the Philippines. If any rates of Tax are
increased or decreased, a new Tax is introduced, an existing Tax is
abolished, or any change in interpretation or application of any Tax
occurs in the course of the performance of the Contract, which was
or will be assessed on the Contractor, Subcontractor or their
employees in connection with the performance of the Contract, an
equitable adjustment of the Contract Price shall be made to fully
take into account any such change by addition to the Contract Price
or deduction therefrom, as the case maybe, in accordance with
GCC Clause 67.1, hereof.
THE OWNER
9. Possession of Site
9.1 On the date specified in the Notice to Proceed, the Owner shall
grant the Contractor possession over the Site, as indicated in the
sec, as may be required to enable the latter to proceed with the
execution of the Works. If the Contractor suffers delay due to
Owner's failure to grant possession, the Contractor can request for a
Contract Time Extension but it shall not exceed the number of days
of delay in taking possession over the site .
: ...
02·9229055/0917 -8459055/whlstleblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
9.4 The Contractor shall allow the Owner's Representative and any
person authorized by the Owner's Representative access to the Site
and to any place where work in connection with this Contract is
being carried out or is intended to be carried out.
10.2 The notice shall be given as soon as practicable and no longer than
28 days after the Owner became aware, or should have become
aware, of the event or circumstances giving rise to the claim. A
notice relating to any extension of the Defects Notification Period
shall be given before the expiry of such period.
10.3 The particulars shall specify the Clause or other basis of the claim,
and shall include substantiation of the amount and/or extension to
which the Owner considers itself to be entitled in connection with the
Contract. The Owner's Representative shall then proceed to agree
or determine (i) the amount (if any) which the Owner is entitled to be
paid by the Contractor, and/or (ii) the extension (if any) of the
Defects Notification Period.
12.3 The presence of the Owner's Representative shall not relieve the
Contractor or the Contractor's representative of any responsibility for
the proper execution of the Works. The decision of the Owner as to
the quality of the material and workmanship shall be final.
12.4 No work shall be covered up or put out of view without the approval
of the Owner. The Contractor shall afford full opportunity for the
Owner to examine and measure any work which is about to be
covered up or put out of view. Accordingly, the Contractor shall give
written notice to the Owner whenever such work is ready for
examination and the Owner will attend as required for the
examination and measurement of the work unless the Contractor is
advised to the contrary by the Owner.
with any of the terms and conditions of this Contract shall not be
considered as a waiver on the part of the Owner for the enforcement
of the Contract, nor shall it relieve the Contractor of any of its
obligations provided therein.
13.1 All Drawings prepared by the Contractor for the execution of the
Temporary Works, are subject to prior approval by the Owner's
Representative before its use.
13.4 The Contractor shall obtain approval of third parties on the design of
the Temporary Works, when required by the Owner.
14. Determinations
14.2 The Owner shall give notice to both Parties of each agreement or
determination , with supporting particulars within 28 days from the
receipt of the corresponding claim or request except when otherwise
specified. Each Party shall give effect to each agreement or
determination unless and until revised under GCC Clause 87,
Settlement of Disputes.
THE CONTRACTOR
i. Said overall responsibility shall lie with the Contractor until the
date of Final Acceptance. After such date the responsibility will
lie with the Owner. Should the Contractor, after the Final
Acceptance have to perform modifications to some works, these
shall again be placed under its responsibility throughout the
duration of the repair work, according to a certificate of
commencement and termination of repair work, which will be
issued by the Owner.
15.2 Security
17.1 Prior to the start of Works, the Contractor shall secure all necessary
licenses, permits and clearances to import, to construct/install
required by government entities, agencies, and local government
units (LGU's). These may include, but are not limited to, building
permit, sanitary permit, electrical permit, water permit, ground
excavation permit, permit to operate generator sets, National
Telecommunication Commission (NTC) permits. All costs and
expenses for licenses, permits, clearances and certificates shall be
for the account of the Contractor.
18.1 The Contractor shall post a Performance Security, which covers the
Advance Payment Security, within thirty (30) days from receipt of
the Notice of Award, in the form of Surety Bond callable on demand
issued by a bonding company accredited by the Owner, in the
amount of Thirty Percent (30%) of the Total Contract Price.
18.2 The Performance Security shall cover the period from the time of the
signing of the Contract until the Final Acceptance of the Project, or
in case of Projects with various independent components, segments
or stages, until the final acceptance of each component, segment or
stage, by the Owner wherein the Warranty Period as prescribed in
GCC Clause 60 shall have commenced. The coverage of the
Performance Security shall include a period of thirty (30) days after
the Defects Liability Period and shall be due for release only after
the Certificate of Final Acceptance is issued by the Owner.
18.3 The Performance Security shall be posted in favor of the Owner and
shall be forfeited in favor of the Owner in the event that the
Contractor violates or is in default of any of its obligations under the
Contract, including failure to satisfactorily perform the Works within
the period/s specified in the Contract.
18.7 In case of reduction in the contract value, the Owner shall allow a
proportional reduction in the original Performance Security, provided
that any such reduction is more than ten percent (1 0%) and that the
aggregate of such reduction is not more than fifty percent (50%) of
the original Performance Security.
NATIONAL GRID CORPORATION OF THE PHILIPPINES 3 - 17
; . . .
02 -9229055109 17 -8459055/whi stleblower@ngcp. ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
19.1 The Contractor shall submit to the Owner for its consent the name
and particulars of the person authorized to receive instructions on
behalf of the Contractor.
20. Sub-Contracting
20.1 The Contractor shall furnish the Owner with the duly executed
Subcontractor Agreement within thirty (30) days after contract
signing.
20.3 Subcontracting of any portion of the Works shall not relieve the
Contractor of any liability or obligation under the Contract. The
Contractor shall be held responsible for the acts, omissions,
defaults, or negligence of its Subcontractor, agents, servants or
workmen. Such acts, omissions, defaults, or negligence of its
Subcontractor, agents, servants, and workmen shall be considered
as the Contractor's own acts, omission, defaults or negligence.
21 .2 The Owner will not be responsible for any claims which may arise
from the use or non-use of any access route. The Owner does not
guarantee the suitability or availability of any particular access route,
and will not entertain any claim for any non-suitability or non-
availability for continuous use during construction of any such route.
: ...
02·9229055/0917 -8459055/whlstleblower@ngcp .ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
22.1 The Contractor shall bear all costs and charges for special or
temporary rights-of-way required for access to the Site. The
Contractor shall also provide, at its own cost, any additional facilities
outside the Site required by the Contractor for the purposes of the
Works.
23.1 The Contractor shall be responsible for the air, sea and land
transportation of all Plant and Equipment, Materials and Supplies as
well as equipment and machineries to be used for construction,
operation and maintenance and testing of the Works from their
place of origin to the Site and more precisely to their point of
utilization at the Site. All incidental works shall be performed by the
Contractor and corresponding costs related therewith including, but
not limited to, transportation, insurances, cost of loading and
unloading, customs clearance, cost of carrying out customs
formalities, all applicable taxes, permits, licenses and other fees
shall be for the account of the Contractor.
23.2 The Contractor in its own interest shall check the capacity of the
loading and unloading facilities available, as well as the limitations in
respect of roads, bridges, and railways, piers, etc. Any damages to
roads, bridges and railways, piers, etc. arising out of the neglect by
the Contractor, its representative or its subcontractors, or its
employees shall be the responsibility of the Contractor.
23.3 All Plant and Equipment and Materials and Supplies as well as
equipment and machineries to be used for construction requiring
covers and/or shelters shall be provided by the Contractor at its own
expense.
23.4 In the event that the Owner, as consignee, is made liable for the
costs or charges in relation to the transportation and delivery of all
Plant and Equipment, the Owner may advance the payment of the
costs or charges, subject to reimbursement by the Contractor of
actual costs and charges paid by the Owner, and/or deduction from
the Contractor's progress billing, retention money, or any amount
due to the Contractor, whichever is convenient to NGCP.
: . . .
02-922905510917-8459055/Whlstleblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
and Materials and other things required for the completion of the
Works.
24.2 The shipment shall be consigned to the Owner and the details of
shipping and/or other documents to be furnished by the Contractor
are as follows:
Upon shipment, the Contractor shall notify the Owner, c/o Head
of Technical Strategic Sourcing Department, by fax or email the
full details of the shipment including Contract Number,
description of Plant and Equipment, quantity, the vessel, the Bill
of Lading (sea freight)/Airway Bill (air freight) number and date,
port of loading, date of shipment, port of discharge, etc., and
shall provide the Owner the original copies of the following
shipping documents, which should contain the Contract Number,
project description and invoice number, not later than two (2)
days after loading of shipment in the port of origin for purposes
of filing with the Department of Finance (DOF) :
5. Certificate of origin;
2. Delivery receipt;
25.1 The Contractor shall strictly comply with the requirements of, and
shall be liable for any damage/destruction to the environment
including penalties that will be imposed by the Department of
Environment and Natural Resources (DENR).
26.1 The Contractor shall cooperate and share the Site with other
contractors, public authorities, utilities, and the Owner between the
dates given in the schedule of other contractors particularly when
they need to access the Site. The Contractor shall also provide
facilities and services for them during this period. The Owner may
modify the schedule of other contractors, and shall notify the
Contractor of any such modification.
27.2 Upon completion of the Works, the Contractor shall remove from the
Site all said Construction Plant and Equipment and Temporary
Works remaining thereon and any unused materials provided by the
Contractor. However, the unused/excess imported materials shall be
accounted by the Contractor and turned-over to the Owner in
accordance with GCC Clause 36.4.
c. The Owner shall have the right to use the equipment owned by
the Contractor and pay such reasonable rental therefor in such
amount as the Owner's Representative shall fix taking into
account current market rates for the rental of similar equipment
and the age and efficiency of the equipment.
27.4 The Contractor shall, when entering into any subcontract for the
execution of any part of the Works, incorporate in such subcontract
(by reference or otherwise) the provisions of this Clause in relation
to Contractor's Plant and Equipment, Temporary Works or Materials
brought on to the Site by the Subcontractor.
28.1 The Contractor shall be entitled to use, for purposes of the Works,
supplies of electricity, water and other services as may be available
on the Site the details of which are given in the Technical
Specifications. The quantities consumed shall be determined by the
Owner's Representative, the amount of which may be deducted by
the Owner from the Monthly Progress Payment and Final Payment
Certificates . The Contractor may, at his own risk and cost, provide
any apparatus necessary for such determination and for his use of
these services.
30.1 Either the Owner's Representative or the Contractor may require the
other to attend a coordination meeting. The coordination meeting
shall review the plans for remaining work and deal with matters
raised in accordance with the early warning procedure stated in
GCC Clause 47. The responsibility of the parties for actions to be
taken shall be decided by the Owner's Representative either at the
coordination meeting or after the coordination meeting and stated in
writing to all who attended the meeting.
NATIONAL GRID CORPORATION OF THE PHILIPPINES 3-23
: . . .
02·9229055/0917-8459055/whlstie blowor@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
31.2 This GCC Clause 31 shall not exclude or limit liability in all the cases
where the applicable Law prohibits such exclusion/limitation.
33.1 The Contractor shall conduct the Works with due regard to health
and safety in accordance with its Construction Safety and Health
Program (CSHP) duly approved by the Owner in compliance with
the DOLE Department Order No. 13 - The Guidelines Governing
Occupational Safety and Health in the Construction Industry which
includes but not limited to the following:
33.2 The cost associated with the implementation of the approved CSHP
of the Contractor shall be made part of indirect/overhead cost of the
Contractor's Bid Price.
33.3 If the Owner notifies the Contractor of any non-compliance with the
provisions of the CSHP, the Contractor shall make all reasonable
efforts to correct the unsafe conditions or acts. Satisfactory
corrective action shall be taken within the specified time.
34.1 The Contractor shall employ competent personnel to carry out the
Works.
35.1 All materials incorporated in the Works shall be new and unused ,
free from all defects and imperfections, and of first class commercial
quality.
35.4 Materials and supplies required in the Works but which may not be
covered by the Specifications shall be standard products of
reputable manufacturers suitable for the intended use. Such items
will be subject to the approval of the Owner.
Except for the items indicated in GCC Clause 36.2, the Contractor
shall furnish all materials and equipment necessary to complete the
Works under the Contract. No separate payment will be made for
the cost of furnishing, transporting, storing and caring of these
equipment and materials. All costs incurred thereof shall be included
in the unit and lump sum prices of pay items to which they pertain.
: ...
02-9229055/09 17 -8459055/wh1stl eb1ower@ngcp. ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3 - GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
The Owner shall furnish and issue to the Contractor the materials
and/or equipment at the stockyard/warehouse specified in the
detailed description of work on the technical data sheets (as
applicable). The Contractor shall be held responsible and
accountable for all equipment and materials furnished to him. In this
regards , the Contractor shall check all items issued to him regarding
their condition prior to receiving them. Any equipment or materials
damaged, lost or unaccounted for after his receipt thereof, shall
either be replaced in kind by the Contractor or charged to his
account in the amount it cost to the Owner including applicable
taxes, plus fifteen percent (15%) surcharge. Deduction for such loss
or damage shall be made from payment due or which may become
due to the Contractor under the Contract and/or collect such loss or
damage from the Retention Money of the Contractor or Contractor's
Performance Security whichever is convenient and expeditious to
the Owner.
: ...
02·9229055/0917.8459055/whlstleblower@ngcp . ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
37.1 The Contractor shall submit to the Owner signed certificates from
manufacturers or sole distributors of materials to be furnished and
installed by the Contractor, certifying as to the kind, quality, quantity
and other descriptions of the materials delivered under a receipt
number and date.
39.3 The Contractor shall submit a written request for substitution at least
one (1) month before such materials are actually needed. Such
request shall be accompanied by samples to be substituted and
corresponding certification as required in GCC Clause 37,
Certification of Materials.
39.4 The Contractor shall bear the cost for the approved substitution of
materials of a better kind.
a. such spare parts as the Owner may elect to purchase from the
Contractor, provided that this election shall not relieve the
Contractor of any warranty obligations under this Contract; and
40.2 The spare parts required are listed in the Technical Data Sheet of
the equipment and the costs thereof are included in the Contract
Price.
41. Packaging
41.2 The packaging , marking, and documentation within and outside the
packages shall comply strictly with such special requirements as
shall be expressly provided for in the Contract, including additional
requirements, if any, specified below, and in any subsequent
instructions ordered by the Owner. The packaging case of the Plant
and Equipment shall be marked "Tax and Duty Free".
41 .3 The Contractor shall prepare and load all equipment, materials and
accessories supplied, under the Contract for overseas export
shipment in such a manner as to protect them from damage in
transit and shall be responsible for and make good any and all
damages due to improper preparation or loading for shipment until
Final Acceptance. Any article or material that might otherwise be
lost shall be boxed or bundled with steel bands and plainly marked
for identification. Boxed parts, whenever it is unsafe to attach slings
to the box, shall be packed with slings attached to the parts, the
slings to project through the box or crate so that attachment to the
hoisting equipment can be made. Boxes, which must remain upright,
shall be marked with large arrows pointing to the side which is to be
up. The equipment will be subject to open storage for several
months at the project site and shall be suitably protected from
NATIONAL GRID CORPORATION OF THE PHILIPPINES 3-30
: ...
02· 922905510917 · 8459055/whlstleb\ower@ngcp . ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
42.1 The design, the Plant and Equipment, the construction documents,
the execution, and the completed Works shall comply to the
Philippines' national specifications, technical standards, building,
construction and environmental regulations, regulations applicable
to the product being produced from the Works and the standards
specified in the Contract Document or defined by law. References in
the Contract to such specifications and other matters shall be
understood to be references to the edition applicable at the date
thirty (30) days prior to deadline for submission of Bids, unless
stated otherwise. If substantially changed or new applicable national
specifications, technical standards or regulations shall become
effective after the above said date, the Contractor shall submit
proposals to comply with the new or revised standards,
specifications, regulations, etc., to the Owner's Representative. In
the event that the Owner's Representative determines that such
proposals constitute a variation, he shall then initiate a variation in
accordance with GCC Clause 63.
43.1 The Owner or its representative shall have the right to inspect
and/or to test the Plant and Equipment or Works in accordance with
the provision stated in the Technical Specifications. If factory test is
required in the Technical Data Sheets, the Owner shall notify the
Contractor in writing, in a timely manner, of the identity of any
representatives retained for these purposes.
43.3 Whenever the Contractor is ready to carry out any such test and
inspection, it shall give a reasonable advance notice, including the
place and time, to the Owner. The Contractor shall obtain from any
relevant third party or manufacturer any necessary permission or
consent to enable the Owner or its designated representative to
attend the test and/or inspection.
43.4 The Owner may require the Contractor to carry out any test and/or
inspection not required by the Contract but deemed necessary to
verify that the characteristics and performance of the Plant and
Equipment comply with the technical specifications, codes and
standards under the Contract, provided that the Contractor's
reasonable costs and expenses incurred in the carrying out of such
test and/or inspection shall be added to the Contract Price. Further,
if such test and/or inspection impede the progress of manufacturing
and/or the Contractor's performance of its other obligations under
the Contract, due allowance will be made in respect of the Delivery
Dates and Completion Dates and the other obligations so affected.
43.5 The Contractor shall provide the Owner with a report of the results
of any such test and/or inspection.
43.6 The Owner may reject any Plant and Equipment or Works or any
part thereof that fail to pass any test and/or inspection or do not
conform to the specifications. The Contractor shall either rectify or
replace such rejected Plant and Equipment or parts thereof or make
alterations necessary to meet the specifications at no cost to the
Owner, and shall repeat the test and/or inspection, at no cost to the
Owner, upon giving a notice pursuant to GCC Clause 3.
43.7 The Contractor agrees that neither the execution of a test and/or
inspection of the Plant and Equipment or Works or any part thereof,
nor the attendance by the Owner or its representative, shall release
the Contractor from any warranties or other obligations under this
Contract.
43.8 Nothing in this clause shall in any way release the Contractor from
any warranty or other obligations under this Contract.
: ...
02-9229055/0917 -8459055/whlstle blower@ngcp . ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
44.1 The whole of the Works and its various components, segments or
stages, if applicable, under this Contract shall be completed within
the time stated in the SCC reckoned from the Start Date, plus any
contract time extension, as may be allowed under GCC Clause 46.
For this purpose, the period to complete each component, segment
or stage shall be treated as a separate Contract Time.
When the whole of the Works have been completed and have
satisfactorily passed all final tests that are required by the Contract,
the Contractor may give notice to this effect to the Owner. Such
notice shall be deemed to be a request by the Contractor for the
Owner to issue a Certificate of Final Completion in respect of the
Works.
The Owner shall, within fifteen (15) days from receipt of such notice,
issue a Certificate of Final Completion stating the date on which, in
its opinion, the Works were completed in accordance with the
NATIONAL GRID CORPORATION OF THE PHILIPPINES 3-33
; . . .
02·9229055/09 17-8459055/whlslleblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3 - GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
Every month thereafter during the life of the Contract, the Contractor
shall furnish the Owner with a certificate to the effect that "Agreed
Critical Path Network" and "Agreed Time Bar Diagram", or as the
case may be, their latest approved revisions are still in effect. Any
approved revisions and subsequent approved revisions thereof,
shall be prepared based only on the previous Agreed Critical Path
Network and Agreed Time Bar Diagram. If, in the opinion of the
Owner, the Works are not being adequately or properly prosecuted
in any respect, the Owner shall require the Contractor to submit a
new Critical Path Network and Time Bar Diagram providing for the
proper and timely completion of the Works.
The Contractor shall see to it that the "Agreed Critical Path Network"
is followed as much as possible. No activity in the Network shall be
started ahead of time at the expense of another unless it can be
NATIONAL GRID CORPORATION OF THE PHILIPPINES 3-34
: . . .
02·9 229055/09 17·8459055/whlstlo blowor@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
45.5 If, in the opinion of the Owner, the Contractor falls behind his work
schedule, the Contractor shall take such steps as may be necessary
to improve its work progress and submit a supplemental schedule or
schedules as may be directed to demonstrate the manner in which
the agreed rate of progress will be regained. In the event the
Contractor fails to demonstrate to the satisfaction of the Owner that
he can regain the agreed progress or falls behind on the revised
work schedule, the Owner may require him to increase the number
of shifts and/or overtime operations, days of work, and/or the
NATIONAL GRID CORPORATION OF THE PHILIPPINES 3 - 35
: ...
02-922905510917-8459055/whlslleblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
45.7 After the receipt of the Notice of Award and before the signing of the
Contract, the Contractor shall submit the Program of Work showing
the general methods, arrangements, and schedule of all the
activities involved in the execution of the Works to the Owner's
Representative for the latter's approval.
45.8 An update of the Program of Work shall show the actual progress
achieved on each activity and the effect of the progress achieved on
the timing of the remaining work, including any changes to the
sequence of the activities.
45.11 When the Program of Work is updated, the Contractor shall provide
the Owner's Representative with an updated cash flow forecast. The
cash flow forecast shall include different currencies, as defined in
the Contract, converted as necessary using the Contract exchange
rates.
: . . .
02·9229055/ 0917-8459055/whiS!Ieblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
: . . .
02·92290SS/0917-84S90SS/wh lstleblower@ngcp .ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
In the latter case, the Owner is not bound to take into account any
claim for an extension of time unless the Contractor has delivered
Notice to the Owner, prior to the expiration of the contract time for
the whole of the Works, or for each component, segment or stage,
and within thirty (30) days after such work has been commenced, or
not later than thirty (30) days after the circumstances leading to
such claim have arisen.
46.3 Requests for Contract Time Extensions not acted upon by the
Owner within a period thirty (30) days from receipt thereof, shall be
deemed disapproved by the Owner.
: ...
02·9229055/0917· 8459055/wh lslle blower@ngc p.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3 - GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
stages, unless it can be proven that the contract time extension will
affect the other components, segments or the succeeding stages. In
such case, the Owner shall specify the approved Contract Time
Extension for each component, segment or stage, so affected.
46.8 Extension of contract time may be granted for other causes such as:
46.9 The Contractor shall be required to extend the validity period of the
Performance Security in case of Contract Time Extensions until the
date of Final Acceptance of the Project.
: ...
02·92290SSI0917-84S90SSiwhlstle blower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
48.1 If the Works is not completed within the period indicated in GCC
Clause 44 (Contract Time), or in case of projects with various
components, segments or stages, within the period indicated in
each component, segment or stage under GCC Clause 44, inclusive
of any duly approved contract time extensions, the Contractor shall ,
without need of any demand, pay the Owner, liquidated damages an
amount equal to one-tenth (1 /1 0) of one percent (1 %) of the Total
Contract Price, for every day of delay, but in no case shall the
liquidated damages exceed ten percent (1 0%) of the Total Contract
Price, unless otherwise stated in the SCC.
48.4 To be entitled to such liquidated damages, the Owner does not have
to prove that it has incurred actual damages. Any sum payable to
the Owner for such liquidated damages shall be deducted from:
48.6 The obligation of the Contractor to pay liquidated damages shall not
relieve the Contractor from its obligation to complete and finish the
performance of the Works.
48.7 Neither the taking over by the Owner of the Work for completion by
administration nor the award of the same to another Contractor shall
be construed as a waiver of the Owner's rights to recover liquidated
damages against the Contractor.
48.8 The provisions for liquidated damages shall not prevent the Owner
from terminating the rights of the Contractor and to proceed in taking
over the Works in case of default, as provided for in GCC Clause
52, Right of the Owner to Take Over.
49.1 The Owner shall have the authority to suspend the work wholly or
partly by written order for such period as may be deemed
necessary: (1) due to force majeure or any fortuitous events, (2) for
failure on the part of the Contractor to correct bad conditions which
are unsafe for workers, or for the general public, (3) to carry out
valid orders given by the Owner (4) to perform any provisions of the
Contract, and (5) due to adjustment of plans to suit field conditions
as found necessary during construction. The Contractor shall
immediately comply with such order to suspend the work wholly or
partly.
49.2 The Contractor or its duly authorized representative shall have the
right to suspend work operation on any or all projects/activities along
the critical path of activities after fifteen (15) calendar days from date
of receipt by the Owner of the written notice from the Contractor
without the Owner acting on the written notice, under any of the
following cases:
: • 0 •
02-922905510917 -8459055/whistleblowor@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
49.4 Before the suspension order expires, the Owner shall either lift such
order or terminate the work covered by the same. If the suspension
order is lifted, or if the period of the order expires, the Contractor
shall have the right to resume work. Appropriate adjustments shall
be made in the contract schedule, accordingly.
50.1 When the Owner wants the Contractor to finish before the Contract
Time of the whole of the Works, or for each component, segment or
stage, as the case may be, the Owner's Representative will obtain
price proposal for achieving the necessary acceleration from the
Contractor. If the Owner accepts this proposal, the Contract Time of
the whole of the Works, or for each component, segment or stage,
will be adjusted accordingly and confirmed by both the Owner and
the Contractor.
02-9229055/0917 -8459055/whlstleblower@ngcp.p h
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3 - GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
51 .1 The Owner shall take over the Site and the Works, or any
component, segment or portion thereof, within seven (7) days from
the date the Owner's Representative issues a Certificate of Final
Completion.
52.1 If the Contractor fails to complete the Works herein specified and
agreed upon, or if the Works are abandoned, or the Contract is
assigned otherwise than specified herein, or if at any time the
Owner is of the opinion , after verifying the facts, that the Works or
portion thereof are unnecessarily or unreasonably delayed, or that
the Contractor is violating any of the conditions, covenants and
agreements of this Contract, or he is not executing the same in
good faith or is not making such progress in the Works or portion
thereof as to insure its completion within the required time, then in
any of these cases, the Owner shall have the right to take over the
Works or portions thereof, by giving notice in writing to that effect to
the Contractor and its sureties of the intention of the Owner to take
over the Works, or portion thereof. Such notice shall contain the
reasons for such intention to take over.
52.2 If within ten (1 0) calendar days after serving such notice, the
Contractor fails to remove the cause or causes of the delay or the
violation or if the Contractor fails to make satisfactory arrangement
for its correction, upon expiration of said ten (1 0) calendar days, the
right of the Contractor to execute the Works, or portion thereof,
himself ceases.
52.3 Upon expiration of the said ten (1 0) calendar days, the Owner shall
proceed to take over and perform the Works or portions thereof,
either by administration or otherwise for the account of, and
chargeable to the Contractor.
52.4 The Owner may use such equipment, tools, appliances and
materials of every description owned by the Contractor as may be
found on the Site of the Works or at points where materials are built
or framed for the Works, and also may procure such or other
equipment, tools and materials for the completion of the Works or
portions thereof, as may be required.
52.5 Before such equipment, tools, appliances and materials are used by
the Owner, they shall be inventoried in the presence of
NATIONAL GRID CORPORATION OF THE PHILIPPINES 3-43
: ...
02·922905510917·8459055/whlstleblower@ngcp. ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
52.7 Should the Owner take over the Works or portions thereof, and
complete it by administration or otherwise, it shall ascertain and fix
the value of the Works already completed by the Contractor but not
paid for and all usable materials on the Site of the Works taken over
by the Owner. The price of completing the Works or portions thereof
shall be charged against the Contract Price of the remaining work
including retention money and in case of insufficiency thereof, the
excess shall be charged to the Contractor and/or its Performance
Securities.
52.9 It is expressly agreed that in the event the Owner takes over the
Works or portions thereof, from the Contractor, the latter and its
sureties shall continue to be liable under this Contract for any
expense in the completion of the Works in excess of the Contract
Price and the Performance Securities filed by the Contractor shall
be answerable for such expenses and for any and all damages that
the Owner may suffer as a result of and in connection with the
takeover.
53. Waiver
53.1 Neither an extension of time nor the acceptance of any part of the
Works shall be deemed a waiver by the Owner of the right to take
over the Works for any of the causes expressly provided for in GCC
Clause 52, Right of the Owner to Take Over.
54.1 Upon expiry of the Defects Liability Period, provided that there are
no reservations pending in the Works, the Owner shall issue the
Certificate of Final Acceptance for the completed Works.
DEFECTS LIABILITY
55.1 The Contractor shall assume full responsibility for the Works from
the time the project commenced up to Final Acceptance by the
Owner and shall be held responsible for any damage or destruction
of the Works except those occasioned by force majeure. The
Contractor shall be fully responsible for the safety, protection,
55.2 The Defects Liability Period shall be one (1) year, or as extended for
the period stated in the SCC, from project completion up to Final
Acceptance by the Owner. For project with various independent
components, segments, or stages with individual Contract Time and
completion date, Defects Liability Period shall commence from the
completion date of each component, segment, or stage.
55.3 During this period, the Contractor shall undertake the repair works,
at his own expense, of any damage to the Works on account of any
breach of contract by the Contractor, including the use of materials
of inferior quality, within ninety (90) days from the time the Owner
has issued an order to undertake repair. In case of failure or refusal
of the Contractor to comply with this order, the Owner shall
undertake such repair works and shall be entitled to full
reimbursement of expenses incurred therein upon demand from the
Contractor.
55.4 In case the Contractor fails to comply with the preceding paragraph,
it shall be disqualified from participating in any bidding conducted by
the Owner and its property or properties shall be subject to
attachment or garnishment proceedings to recover the costs. All
payables of the Owner in the Contractor's favor shall be offset to
recover the costs.
56.1 The Owner's Representative shall check the Contractor's work and
notify the Contractor of any defects that are found. Such checking
shall not affect the Contractor's responsibilities. The Owner's
Representative may instruct the Contractor to search , uncover
defects and test any work that the Owner's Representative
considers below standard or defective.
58.3 The Contractor shall correct the defects which it discovers before
the end of the Defects Liability Period.
58.4 The Owner shall certify that all defects have been corrected. If the
Owner considers that correction of a defect is not essential, it can
request the Contractor to submit a quotation for the corresponding
reduction in the Contract Price. If the Owner accepts the quotation,
the corresponding change is a Variation.
59.1 The Owner shall give the Contractor at least fourteen (14) days'
notice if it has the intention to use a third party to correct a Defect. If
the Contractor does not correct the Defect within the period, the
Owner may have the Defect corrected by the third party. The Owner
shall be entitled to full reimbursement of expenses incurred therein
upon demand from the Contractor.
59.2 The use of a third party to correct defects that are uncorrected by
the Contractor will in no way relieve the Contractor of its liabilities
and warranties under the Contract.
60.1 The Contractor warrants that the Works or any part thereof shall be
free from defects in the design, engineering, materials and
workmanship of the Plant and Equipment supplied and of the Works
executed.
60.2 The Warranty Period shall be one (1) year from the date of Final
Acceptance of the Project, or as extended for the period stated in
the SCC. For projects with various independent components,
segments, or stages with individual date of Final Acceptance, the
02-9229055/0917-8459055/whl stleblowor@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
60.4 The Contractor's obligations under this GCC Clause 60 shall not
apply to:
60.5 The Owner shall give the Contractor a notice stating the nature of
any defect together with evidence thereof, promptly upon discovery.
The Owner shall afford all reasonable opportunities for the
Contractor to inspect such defect.
60.6 The Owner shall afford the Contractor all necessary access to the
Plant and Equipment and the Site to enable the Contractor to
perform its obligations under this GCC Clause 60.
60.7 The Contractor may, with the consent of the Owner, remove from
the Site any Plant or any part of the Plant and Equipment that are
defective if the nature of the defect, and/or any damage to the Plant
and Equipment caused by the defect, is such that repairs cannot be
expeditiously carried out at the Site.
60.9 If such part fails the tests, the Contractor shall carry out further
repair, replacement or making good, as the case may be, until that
part of the Plant and Equipment passes such tests. The tests shall
be agreed upon by the Owner and the Contractor.
60.11 If the Plant and Equipment or any part of the completed Works
cannot be used by reason of a defect or failure to correct such
defects, the Warranty Period of the Plant and Equipment or such
part of the completed Works, as the case may be, shall be extended
by a period equal to the period during which the Plant and
Equipment or such part of the completed Works cannot be used by
the Owner because of the defects or failure to correct such defects.
60.12 Except as provided in GCC Clauses 60, the Contractor shall not be
liable in respect of defects in the Plant and Equipment or any part
NATIONAL GRID CORPORATION OF THE PHILIPPINES 3- 49
60.13 In addition, any such component of the Plant and Equipment shall
be subject to an extended Warranty Period. Such obligation of the
Contractor shall be in addition to the Warranty Period specified
under GCC Clause 60.2.
61. Clean Up
61.1 When the Works are completed and before the issuance of the
Certificate of Final Completion, the Contractor shall remove from the
Site, without expense to the Owner, all temporary structures, all
surplus materials (except the imported unused/excess materials
which shall be turned-over to the Owner in accordance with GCC
Clause 36.4) and rubbish of every sort, shall fill and dress all holes
and cavities made for Contractor's convenience, and shall leave the
whole area in good order and condition , all as required and directed
by the Owner.
62.1 The Owner's Representative with the prior approval of the Owner
may instruct Variations, up to a maximum cumulative amount of ten
percent (1 0%) of the original contract cost.
63.1 Variation Orders may be issued by the Owner to cover any increase/
decrease in quantities, including the introduction of new work items
NATIONAL GRID CORPORATION OF THE PHILIPPINES 3. 50
: . . .
02-922905510917-8459055/whlstle b lower@ngc p.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
63.4 Any cumulative Variation Order beyond ten percent (1 0%) shall be
subject of another contract to be bid out if the works are separable
from the original contract. In exceptional cases where it is urgently
necessary to complete the original scope of work, the Owner may
authorize the Variation Order beyond ten percent (1 0%) but not
more than twenty percent (20%).
63.5 In claiming for any Variation Order, the Contractor shall, within
seven (7) calendar days after such work has been commenced or
after the circumstances leading to such condition(s) leading to the
extra cost, and within twenty-eight (28) calendar days deliver a
written communication giving full and detailed particulars of any
extra cost in order that it may be investigated at that time. Failure to
provide either of such notices in the time stipulated shall constitute a
waiver by the Contractor for any claim.
64.1 In case any Extra Work shall be required in the proper performance
of the Works contemplated under this Contract, it is understood that
65. Prices
65.1 Prices charged by the Contractor for Works performed under this
Contract shall not vary from the prices quoted by the Contractor in
its Bid, with the exception of any change in price resulting from a
Change Order issued in accordance with GCC Clause 63.
66.1 For the given scope of work in this Contract as awarded, all bid
prices are considered fixed prices, and therefore not subject to price
escalation during contract duration, except under extraordinary
circumstances and upon approval of the Owner.
66.2 The Contractor shall pay all applicable fees and other similar
expenses in consequence of his obligations under the Contract, and
the Contract Price shall not be adjusted for such costs, except as
stated herewith.
67.1 Unless otherwise specified in the Contract, if after the date of the
Invitation to Bid, in the Philippines, any law, regulation, ordinance ,
order or by-law having the force of law is enacted, promulgated ,
abrogated or changed (which shall be deemed to include any
change in interpretation or application by the competent authorities)
that subsequently affects the costs and expenses of the Contractor
and/or the time schedule prescribed by the Owner in GCC Clause
44.2, Completion of Works, the Contract Price shall be
correspondingly increased or decreased, and/or the time schedule
prescribed by the Owner, shall be reasonably adjusted to the extent
that the Contractor has thereby been affected in the performance of
any of its obligations under the Contract. Notwithstanding the
foregoing, such additional or reduced costs shall not be separately
paid or credited if the same has already been accounted for in the
price adjustment provisions where applicable , in accordance with
GCC Clause 66.1 .
: ...
02 -92290SS/0917-84590SS/whlstleblower@ngc p.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
68.1 The Owner shall, upon a written request of the Contractor, which
shall be submitted as a Contract Document, make an advance
payment to the Contractor for an amount not to exceed fifteen
percent (15%) of the Total Contract Price, provided that the
Contractor has posted an acceptable Performance Security required
under the Contract.
69.1 The Contractor may submit a request for payment for Work
accomplished. Such request for payment shall be verified and
certified by the Owner's Representative.
The Contractor may request for Partial Payment for the delivered/
accepted materials per shipment at site and/or Partial Payment for
completed works subject to approval by the Owner.
69.2 The Owner shall have the right to deduct from the Contractor's
progress billing such amount as may be necessary to cover third
party liabilities, as well as uncorrected discovered defects in the
project.
70.1 This is an entire Contract for whole and completed Works and any
partial payment effected or made in pursuance of the Contract
Documents shall not relieve the Contractor of any of its obligations
under the Contract. No progress payment shall be construed as an
acceptance of the Works or any portion of the Works, nor shall the
making of such payment preclude the Owner from demanding and
recovering from the Contractor such damages as the Owner may
70.4 All payments under the Contract shall be subjected to existing laws,
rules and regulations of the Republic of the Philippines concerning
generally accepted accounting and auditing principles.
70.6 All charges including other incidental expenses incurred for payment
through Letter of Credit shall be for the account of the Contractor.
NGCP will advance the payment of related charges for the opening
of UC to be deducted from the Contractor's payments or to be
reimbursed by the Contractor.
71.1 In addition to the ten percent (1 0%) retention and other withhold
payments mentioned in GCC Clause 73, Payment Certificates, the
Owner may withhold in whole or in part any monthly payment to
such extent as may be necessary to protect its interest on account
of:
: . . .
02·9229055/0917- 8459055/w hlstleblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3 -GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
Within the first five (5) days of the month, the Contractor shall
submit in writing to the Owner's Representative for approval, and in
accordance with a prescribed form , the work done during the
preceding month. All measurements and surveys for purposes of
monthly progress estimates shall be made by the Contractor in the
presence of the Owner's Representative. The estimates shall be
supported by the computation of quantities subject to the approval
of the Owner's Representative . The first of such estimates shall be
of the amount or quantity and value of work done since the
Contractor commenced the performance of this Contract, and every
subsequent monthly estimate (except the final one) shall be of the
amount or quantity and value of the work done since the preceding
estimate was done. The quantities used for the monthly progress
estimate shall be subject to correction in the final estimate.
The Final Estimate shall be prepared after all the Works has been
completed. It shall be based on the measurement performed on the
completed Works and shall be submitted to the Owner after a joint
inspection and prior to the issuance of a Certificate of Final
Completion.
The Owner shall then, except for cause herein specified, pay the
Contractor promptly, after the execution of said certificates the
remainder which shall be found due excepting therefrom such sum
or sums as may be lawfully retained under any of the provisions of
this Contract.
Provided that the Final Payments on the Contract shall not be made
until the Contractor has submitted a statement sworn to before an
officer duly authorized to administer oath that all the taxes due from
him, and all obligations for materials used and labor employed in
connection with this Contract have been duly paid , and provided
further, that nothing herein contained shall be construed to waive
the right of the Owner which is hereby reserved to reject the whole
or any portion of the aforesaid Works should the same be found to
have been constructed in violation of the plans and specifications or
of any of the conditions or covenants of this Contract, the Owner
shall make payment to the Contractor on the Final Payment
Certificate.
74. Retention
74.2 The total "retention money" shall be due for release upon Final
Acceptance of the Works.
75.1 Any and all payments due to the Contractor under this Contract
may, at the discretion of the Owner, be offset or charged against
any or all outstanding obligations of the Contractor to the Owner
under any or all other contracts with the Owner or other business
transactions between the Contractor and the Owner, subject to the
usual pre-audit requirement.
NATIONAL GRID CORPORATION OF THE PHILIPPINES 3-57
: . . .
02·9229055109 17-8459055/whlstleblower@ngcp .ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
TERMINATION
76.1 The Owner shall terminate a Contract for default when any of the
following conditions attend its implementation:
c. The Contractor:
76.2 All materials on the Site, Plant, Equipment, and Works shall be
deemed to be the property of the Owner if this Contract is rescinded
because of the Contractor's default.
77.1 The Contractor may terminate this Contract with the Owner if the
works are completely stopped for a continuous period of at least
sixty (60) calendar days through no fault of its own, due to any of
the following reasons:
78.1 The Owner may terminate this Contract, in whole or in part, at any
time for its convenience. The Owner may terminate this Contract for
the convenience of the Owner if he has determined the existence of
conditions that make Project Implementation economically,
financially or technically impractical and/or unnecessary, such as,
but not limited to, fortuitous event(s) or changes in law and National
Government policies.
78.2 The Owner or the Contractor may terminate this Contract if the other
party causes a fundamental breach of this Contract.
a. The Contractor stops work for twenty eight (28) days when no
stoppage of work is shown on the current Program of Work and
the stoppage has not been authorized by the Owner's
Representative;
: . . .
02·92290SS/0917-84590SS/whlstle blower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
78.4 The Owner can file civil, administrative and/or criminal actions
available under the applicable law on individuals and organizations
deemed to be involved with corrupt, fraudulent, or coercive
practices.
78.5 When persons from either party to this Contract gives notice of a
fundamental breach to the Owner's Representative in order to
terminate the existing Contract for a cause other than those listed
under GCC Clause 78.3, the Owner's Representative shall decide
whether the breach is fundamental or not.
79.1 The following provisions shall govern the procedures for the
termination of this Contract:
: . . .
02-9229055/0917-8459055/whistleblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
80.3 The net balance due shall be paid or repaid within twenty eight (28)
days from the notice of termination.
80.4 If the Contractor has terminated the Contract under GCC Clauses
77 or 78, the Owner shall promptly return the Performance Security
to the Contractor.
81.1 From the Start Date until the Certificate of Final Acceptance has
been issued, the following are risks of the Owner:
: ...
02·92.2 905510917-8459055/whlstle blower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
82.1 The Contractor shall hold and save harmless the Owner, its officers,
agents and employees, from liabilities, damages or obligations of
any nature or kind, including costs and expenses on account of any
copyrighted or uncopyrighted composition, secret process, patented
or unpatented invention, article, method or equipment manufactured
or used in the performance of this Contract.
82.2 The Contract Price is to include all royalties and costs arising from
patents, trademarks and copyrights in any way involved in the
Works. Whenever the Contractor is required or desires to use any
design, device, material, or process covered by a letter patent,
trademark or copyright, the Contractor shall indemnify and save
harmless the Owner from any and all claims for infringement by
reasons of the use of any such patented design, device or material
or process to be performed under the Contract, and shall indemnify
the Owner for all costs, expenses and damages which it may be
obliged to pay by reason of such infringement at any time during the
execution of or after the completion of the Works.
INSURANCE
: ...
02·922905510917-8459055/whlstle blower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
Excepted Risks, the Contractor shall, at its own cost, repair the
damage and injury, or replace the loss so that at completion, the
Works shall be in good order and condition and in conformity in
every respect with the requirements of the Contract. The Contractor
shall also be liable for any damage, loss, or injury to the Works
occasioned by the Contractor for the purpose of complying with its
obligations under GCC Clause 56 Identifying Defects and GCC
Clause 15 The Contractor's Obligations of this Contract and for any
damage, loss or injury due to a cause occurring prior to the issuance
of Certificate of Final Completion.
The Owner shall not, at any time, be liable for, and shall be
indemnified and held harmless by the Contractor in respect of any
damage, injury or loss to any construction plant or support used or
intended for use in the execution of the Contract by the Contractor
or its subcontractors.
: ...
02-92290SS/0917-84590SStwh lst1eblowec@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
84. Insurance
84.1 The Contractor shall, at his own expense, maintain in force the
following insurances from reputable companies acceptable to the
Owner for the duration of the Contract:
The Marine Cargo Insurance shall not cover the permanent and
temporary installation cost. The insurance coverage shall be one
hundred and ten percent (11 0%) of the delivered cost and the
Owner shall be the beneficiary.
: . . .
02 -922905510917-8459055/whlstleblower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
84.4 The Contractor (and, if appropriate, the Owner) shall comply with
the conditions stipulated in each of the insurance policies. The
Contractor shall make no material alteration to the terms of any
insurance without the prior approval of the Owner. If an insurer
makes (or purports to make) any alteration , the Contractor shall
notify the Owner immediately. The certificates shall provide that not
less than thirty (30) days' notice shall be given to the Owner by
insurers prior to cancellation or material modification of a policy .
84.5 If the Contractor fails to obtain and keep in force the insurances
referred to herein or any other insurance which the Contractor may
be required to obtain under the terms of this Contract, the Owner
may obtain and keep in force any such insurances and pay such
premiums as may be necessary for the purpose, and any and all
expenses incurred thereby shall be deducted from any and all sums
due or may become due to the Contractor without prejudice to the
Owner exercising its right to impose other sanctions against the
Contractor pursuant to the provisions of this Contract. The
Performance Security submitted by the Contractor shall also be held
responsible for this contingency.
: • 0 •
1. become bankrupt;
84.8 The Contractor shall be responsible for notifying the Owner within
forty-eight (48) hours for any losses or damages arising out of the
Contract. Failure to notify the Owner within this period of time shall
constitute sufficient grounds for the Owner to exercise its rights
under the Contract.
FORCE MAJEURE
85.1 For purposes of this Contract the terms "force majeure" and
"fortuitous event" may be used interchangeably. In this regard, a
fortuitous event or force majeure shall be interpreted to mean an
event which the Contractor could not have foreseen, or which
NATIONAL GRID CORPORATION OF THE PHILIPPINES 3-67
: ...
02-92290SS/0917-B4590SS/whlstle blower@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
85.6 An additional notice including full data and full particulars of the said
event shall be given to the Owner within a period of ten (1 0)
calendar days from the cessation of the event of Force Majeure
involved.
85.7 Contractor's notice shall be jointly examined by him and the Owner
and the conclusions the Owner will reach from such examination
shall be set forth in Protocol(s) which the Contractor shall be
requested to sign.
85.11 If the event continues for a period of eighty four (84) days, either
party may then give notice of termination, which shall take effect
twenty eight (28) days after the giving of the notice.
85.13 The net balance due shall be paid or repaid within a reasonable
time period from the time of the notice of termination.
86.1 If the Contractor incurs cost as a result of any of the events under
GCC Clause 81, the Contractor shall be entitled to the amount of
such cost. If as a result of any of the said events, it is necessary to
change the Works, this shall be dealt with as a Variation.
: ...
02·92290SS/0917-84590SS/whls11oblowor@ngcp.ph
BIDDING DOCUMENTS Standard Bidding Documents
SECTION 3- GENERAL CONDITIONS OF CONTRACT Series of 2018 Version 1
87.2 If after thirty (30) days, the parties have failed to resolve their
dispute or difference by such mutual consultation, then either the
Owner or the Contractor may give notice to the other party of its
intention to commence arbitration, as hereinafter provided, as to the
matter in dispute, and no arbitration in respect of this matter may be
commenced unless such notice is given.
87.4 In the case of a dispute between the Owner and the Contractor, the
dispute shall be resolved in accordance with Republic Act 9285
("R.A. 9285"), otherwise known as the "Alternative Dispute
Resolution Act of 2004." The place for arbitration shall be
exclusively in Quezon City, Philippines, only.
ASSIGNABILITY OF CONTRACT
88.1 NGCP and the Contractor agree to the Assignment of this Contract,
at the option of the National Transmission Corporation (TransCo), to
TransCo or its nominee, upon the expiration of the Concession
Period or the earlier termination of the Concession Agreement
between NGCP, Power Sector Assets and Liabilities Management
Corporation (PSALM) and Transco.
GCC
Clause
1.3a National Grid Corporation of the Philippines (NGCP)
Power Center, Quezon Avenue corner BIR Road
Diliman, Quezon City, Philippines 1104
Vice President
Planning and Engineering
Vice President
Planning and Engineering
: ...
02·922905 5/0917·8459055/whistleblower@ngcp.ph
BIDDING DOCUMENTS VISAYAS SUBSTATION UPGRADING
PROJECT, STAGE 1 (REBIDDING)
SECTION 3a- SPECIAL CONDITIONS OF CONTRACT Sp19 .VSUP1. Vt-0422R
GCC
Clause
24.2a(7) The following are NGCP's approved Cargo Surveyors:
24.2a(8)
44.1 The whole of the Works is divided into four (4) substations which are
independent from each other. The completion period shall be as follows:
Completion Period
Substation
(reckoned from Start Date)
44.3(f)
46.8b
48.1 If the Works is not completed within the period indicated in GCC Clause 44
(Contract Time), or in case of projects with various components or
segments, within the period indicated in each component or segment under
GCC Clause 44, inclusive of any duly approved contract time extensions,
the Contractor shall, without need of any demand, pay the Owner, liquidated
damages (LD) in the amount equal to the following:
Completion Period
Substation (reckoned from Amount of LD
Start Date)
Calbayog Three Hundred 1/10 of 1% of the Total
Substation Ninety (390) Contract Price of
calendar days Calbayog SS for every
day of delay, but not to
exceed 10% of the Total
Contract Price of
Calbayog SS.
: ...
02· 922905 5/ 09 17 -8459055/whi stle blow er@ngcp .ph
BIDDING DOCUMENTS VISAYAS SUBSTATION UPGRADING
PROJECT, STAGE 1 (REBIDDING)
SECTION 3a - SPECIAL CONDITIONS OF CONTRACT Sp19.VSUP1 .Vt-0422R
GCC
Clause
Maasin Substation Three Hundred 1/10 of 1% of the Total
Ninety (390) Contract Price of Maasin
calendar days SS for every day of delay,
but not to exceed 10% of
the Total Contract Price of
Maasin SS.
55_2
60.2 Warranty Period and Warranty Security
A. Substation Equipment
1. Power Transformer
2. Power Circuit Breaker
3. Disconnect Switch/Earthing Switch
4. Current Transformer
5. Voltage Transformer
6. Surge Arrester
B. Secondary Device
1. Substation Protection System
2. Network Disturbance Monitoring Equipment
3. Power Line Carrier
4. Remote Terminal Unit