Professional Documents
Culture Documents
1993 V 03
1993 V 03
~~I 2000lbs
250 plf I
8O~f
3588lbs 23521bs,
span 20'
The maximum moment for this loading is 20267 Ib, ft The equivalent uniform load to
produce this moment would be 405 Ibs. per ft.
The maximum end reaction is 3588 Ibs. The equivalent uniform load to produce this
reaction would be 359 Ibs. per ft:
The K series joist tables show a 16K3 (with a 20' span) has a total load capacity of 410 Ibs.
per ft. The designer should show a 16K3SP on the drawings.
The SP indicates special requirements for the joist. The joist manufacturer will review
the designated joist for its ability to carry the special loads shown.
Joist Girders with unequal panel point loads must also be defined by showing the load
diagram on the structural drawings.
'For all standard K senes )OIStS the maximum end reaclion IS 8700 Ibs. " more reaction capacity IS needed,
conSider uSing two (or more) )OIStS to share the load. For LH and DLH 10lsts a conservative end reaction
can be found by diViding the tabulated SAFE LOAD by two.
/NCJ/
NICHOLAS J. BOURAS, INC.
PO BOX 662. 475 SP Rf N~F f El.D AVl
SUMMIT NEW JERSEY 07'102-0662 JQ08J277-16J7
•
•
properties
Inc.
30 DESIGNING ARCHITECTURALLY
EXPOSED STEEL TUBES
All in-depth examination of belldillg and cOllllection
requirements for engineers and fabricators
40 JOINTLESS REDECKING OF
SIMPLE-SPAN STRI GERS
E/iminatioll of U/1/lecessanj roadway expansion joints cml
often be accomplished withollt major structural
rehabilitation
•
111 order to create atl exoskelatoll fornt 01/ the
Hotel de las Artes complex, fire braced frame 47 REDUCING PARKING STRUCTURE COSTS
was disassociated and plllli'll away from the Parking structures framed with composite girders
plane of the whtdow wall. To {i"d out more supporting a double tee deck system can reduce costs by
about this irlllavathJe project, tum to page 18, 12% to 15%
•
Chicago, IL 60601-2001.
Beams
Second-class postage paid at Chicago, IL • New Questions
and at adctltonal mailing offices.
Use newly introduced facilities like NON-LINEAR Release 17 marks the debut of AutoST AAD/MAX - the
analysis, TIME HISTORY analysis, user-controlled world's first integrated structural software system that
multiple iteration P-Delta analysis, steel design for works entirely within AutoCAD .
transmission towers (ASCE Pub. 52) etc. in addition to
14 different steel , concrete , and timber codes, to explore All these powerful capabilities coupled with the
the widest possible range of design solutions. industry's most knowledgeable and experienced support
staff, makes STAAD-III/ISDS the ultimate productivity
Release 17's powerful printer plolting capabilities allow tool you've been waiting for.
you to generate the industry's sharpest and most
comprehensive run output. For the first time, you can STAAD-III/ISDS Release 17 - there are those
combine numerical output with graphical output - all in who have seen the future .. . have you?
the same run document. Yes, we support the widest
possible range of printers - from sophisticated lasers to
down-to-earth dot- matrix printers. ~ c.c.
,.... Research
Engineers, Inc_
On the graphics front , Release 17 features an 1570 N. Batavia, Orange, CA. 92667.
enormously enhanced graphics input generator with CALL TOLL FREE (800) 367-7373
paralle,led speed and power. In addition , Tel: (714) 974-2500 FAX:(71 4) 974-4771
Advertising Sales
Pattis-3M
7161 North Cicero
Lincolnwood, IL 60646
(708) 679-1100
FAX (708) 679-5926
structure system design by Mulach Parking Structures. What is
implied-but never actually stated in the article-is that to make the
system work the steel fa bricator must be willing to assume lead
respon ibility . Essentially, the project must be bid and built using a
design/ build proced ure.
Does the system work? Yes. Mulach has documented savings of
•
nea rly 15% compared to any conventionally designed and built parking
structure.
AISC Officers So why aren' t more firms involved in design/build? I'm afra id that
Stephen E. Egger, the answer is a lack of willingness to change and adopt innovative
Chairman
Frank B. Wylie, III, proced ures, and not just by fabrica tors but also by engi neers and
First Vice Chairman building owners. How many fa bricators are truly taking ad vantage in
Robert E. Owen, the lalest CNC and CAD equipment? How many engineers have
Second Vice Chairman
Robert D. Freeland,
completely switched over to LRFD? How many companies are willing
Treasurer to examine their management structure with an eye to making
Neil W Zundel. comprehensive changes?
President Maybe I'm wrong. Maybe there are companies out there that have
David Ratterman,
Secretary & General Counsel taken a serious look at design/build and have determined it to be
Lewis Brunner, ineffective. Maybe there are more than a half-dozen up-ta-da te
Vice President, fabri cators out there willing to take advantage of the latest technologies
Membership Services
Geerhard Haaljer, to reduce cost and increase efficiency. And maybe the number of
Vice President, engi neers keeping up-to-date on the latest design trends is growing. If
Technology & Research so, I'd like to hear from them. Put pen to paper (or fi ngers to keyboard)
Morris Carninef,
•
Vice President,
and tell me about innovations within your firm.
Finance/ Administration I know the entrepreneurs and innovators are out there. I know the
ta lent is out there. And I'd like to hear wha t you're doing. SM
·Jr:;fr7~llr;,.r7;! f~lt7f~Jl~.~
I'll! q Ur.nmr.r.Jr.:7
•
r~r" {1I1'll}?::> I.W.'. r.r-1.
• •
•
• Steel Interchange
Stt'l'llnterchnnge is an open forum for Modem Sled COlIStructioll
readers to exchange useful and practical professional ideas and in-
Answers and / or questions should be typewntten and double
sp..lced. Submittals that have been prep.lred by word·processing
formation on all phases of steel building and bridge construction. are appreciated on computer dl~kctte (either as a wordperfect file or
Opinions and suggestions are welcome on any subject covered in in ASCII fonnat).
this magazine. If you have a question or problem thai your feUow The opinions expressed in Sterlltlt("rcilatlgr do not necess.1riiy
readers might help to solve, please forward it to Modern Steel Con- represent an official position of the American institute of Steel Con·
structIOn. At the same lime feel free to respond to any of the ques- struction, Inc. It is recogni zed that the design of structures is within
tions that you have read here. Please send them to: the scope and expertise of a competent licensed slrod-urill engineer,
Steellnterchange architect or other Licensed professional for the .1ppJication of pnnci-
Modem Steel Construction pies to a particular structure.
1 EOIslWackerDr. Information on ordering A1SC publications mentioned in this ar-
Suite 3100 ticle can be obtained by ca lling AlSC at 312/670-2400 ext. 433.
Ch icago, IL 60601
•
less Steel Structural Members (ANSI/ ASCE 8-90), Amer- ing built-up members:
ican Society of Civil Engineers, New York, NY, 114 1. Gllide to Stability Desigll Criteria for Metal StrllC-
pages. (Stock No. 794) (Phone 800 548-ASCE) tllres, 4th Edition, Edited by Theodore V. Galambos,
This document, which is an update of the 1974 john Wiley & Sons, Inc., 1988.
AISI specification, gives nominal (ultimate) shear and
2. Gllide Specificatiolls for Horizolltally Cllrved High-
tension stresses for several types (alloys) and condi-
way Bridges, Published by the American Association
tions (annealed, cold-worked, etc.) of stainless steel
of State Highway and Transportation Officials, Wash-
fasteners. Recommended resistance factors are also
ington D.C.
given, consistent with the LRFD format. Stresses
apply to bolts less than, and equal to or greater than 3. Allalysis alld Desigll of Cllrved Steel Bridges,
1/2 in. diameter. Hiroshi akai and Chai I long "jay" Yoo, McCraw-
2. Metal Cllrtaill Wall Fastellers (AAMA TIR-A9- Hill Book Co., 1988.
1991), American Architectural Manufacturers Associa- 4. Highway Strllctllres Desigll Halldbook, AISC Mar-
tion, Palatine, IL, 47 pages. (Phone 708/202-1350) keting, Inc., Chapter 12-Horizontally Curved Girders,
This second document, which is based on allow- Pittsburgh, PA.
able stress deSign, is devoted entirely to various types Additionally, please note that the Federailligh-
of fasteners (up to 1 in. diameter). In addition to back- way Administration and the National Research Coun-
ground and design examples, this booklet presents ta- cil of the Transportation Research Board are plan-
bles of allowable shear and tension values for seven ning/undertaking research in the area of horizontally
different "alloy group/condition" combinations of curved steel girders:
stainless steel fasteners in fourteen diameters (#6 up to
NCHRP 12-38, III/proved Desigll Speci[icatiolls for
1 in.)
Horizolltally Cllrved steel Girders, and
This booklet also reprints the abstract of ASTM
F593 which gives the mechanical properties for seven FHWA Contract DTFH61-92-C-00136, EllgiTleerillg
alloy groups and seven conditions. In addition, a table Services forCllrved Steel Bridge Research Project.
cross references "type" (e.g. 304 alloy) to "group" (e.g. john M. Yadlosky, P.E.
•
group one) . HDR Engineering, Inc.
'ames C. LaBelle, Doc'£', P.E. Pittsburgh, PA
Computerized Structural Design, Inc.
Milwaukee, WI
-
~"' ._
Weigltl-Hal/dlil/g Eqllipmel/I alld Service Crafl, has an ex- 1_ _ ....... " ' _ ...........
,
_ _ _ _ ,. ~ "",., 0"".
.... •
into a radius?
..-..
r-
I--
WEST
Seanle
I Date
3130
- I-
MIDWEST
SI. Louis
- Date
4113
,- NORTHEAST
NewYor1< ~4129
O.t.
f-
I--
Kansas City
Dallas
San Antamo
- f-
4115
516
- -
Charlotte
Birmingham _
- - 4121
9/9
- r-
Baillmore
WashIngton 1- 5118
5120
611 Miami _ 9/14 Philadelphia 6123
I- r-' -
Houston 618 Orlando 9116 Cleveland 10119
I-- - f-
Atlanta 9128 Cincinnati 10121
f- -
Richmond 9130
- '--
The Pennsylvania 11.rnpike is considered one of For example, its high strength permits longer
the safest and best maintained roads in the nation. spans, thus reducing the number of piers required. And
But improvements were badly needed near that leads to foundation cost savings.
Pittsburgh to provide better access to the city's OTHERSTRO G REASONS.
airport and [-80. For another, it can be easily inspected, measured
The 1\ lahoning Rivcr Bridge, the largest of and evaluated. [f necessary, it can be readily repaired.
the 21 bridges being built on the new Beaver It's also highly adaptable to redecking, widening and
Valley Expressway, is a dual-lane, continuous- performing other structural modifications.
span, welded plate structure. The five interior Weathering steel also eliminates the need for
spans arc 258 ft with end spans of 182 ft and both initial and maintenance painting. What's more,
228 ft for an overall length of 1,700 ft. it's as attractive as it's environmentally sound.
WHY WEATH ER[NG STEEL? Kempf comments, "The PTC's principal crite-
The bridge is built with 4,600 tons of ria for selecting materials for bridges and other
Bethlehem's ASTM A588 weathering steel. ' Ihrnpike applications aren't based on price alan .
According to Kempf, the PTe finds but also include long-term serviceability and dura-
weathering steel a very cost-effective bridge bility, And with environmental restrictions being
material for a number of reasons. what they arc today, it's only prudent to usc
,D
ID
'...
Will save us more than money." Fmnk J, Kempf. Jr.. P.E. Bridge Engineer, Pennsylvania Turnpike COlllmi~sion .
Bethlehem ~
-H:chnical Bulletin, TB-307 on "Uncoated
Weat hering Steel Struclllres," get in to uch with
yo ur nearest Bethlehem sales office. Or ca ll:
Brian Walker at (215)694-5906. Bethlehem Steel
. Corporation. Constllletion \I arketing Division,
Bethlehem, PA 180 16-7699.
~n('r. Penn"")" anin TUnlpikc Comrnis"iun. Iluni'lhllrg. I~A
FllhrlclltOr. I tilth SIt..'Cl Structure!!. Inc .. LIUlCustt..'f", I'A
\\'euthering Steel Supplio..r. lkthlchclll Slecl Corporul ion. Ikthlel'M.-m . J'A
NSCC93
1993 NATIONAL STEEL
•
CONSTRUCTION CONFERENCE
ORLANDO CONVENTION/CIVIC CENTER
ORLANDO, FL' MARCH 17·19
-
11·800·258.76661
o Office Hours
Monday-Thursday
Send one reservallon form per
room Names of occupants musl
should be made directly Wllh Ihe
Orlando HOUSing Bureau Your
800am -700pm EST be lis led In Ihe SpOI below room confirmation will arnve
Fnday 800 am· 5-00 p m Reservatrons are made on a fllsl- directly from Ihe Bureau
come. Ilrst-served baSIS
CONFERENCE HOTEL:
•
(The Clanon Plala Hotel IS the offiCial Conference Hotel Located 1/2 block from the Conventron Cenler II serves as Ihe
pnmary holel for sleeping accommodations All tours and opllonal evenls depart and relurn 10 Ihe Clanon Plala HOlel
The Peabody Orlando IS across the street Irom Ihe Convention Cenler and The Ou~llty Inn IS 2 blocks away The Peabody
and Ihe Ouallty Inn have limited space SUites are available upon requesl atlhe Clanon and Peabody
•
CARD OWNERS SIGNATURE 407/363-5800
OFFICE PHONE
HOUSING BUREAU
HOME PHONE DEADLINE OATE :
FEBRUARY 15, 1993
FAX
--- --- --
NSCC93
PRELIMINARY SCHEDULE OF EVENTS
• MONDAY, MARCH 15
11:00-5:00
A panel of experts presenllhe majOr Slructural
shape producers VIews 01 steel prodUClion leeh
nrques Inlo Ihe 2t SI century There Will be partlC
ular emphaSIS on new product d V Iopment nd
p.m. Exhlbllor Move-In - conllnues unlll lOOp m the Impact on Ihe fabncalors market for the
fulure
TUESDAY, MARCH 16
3:00·5:30 Exhibits Open
Noon·5:oo Wedne ;day p.m.
p.m. AISC Committee on Research 5:45-6:30 Exhibitor Workshops (A·G)
4:00-8:30 Meeting/luncheon p.m. Th, •• e .pi lal se' lon~ )ffer 3 forum where
p.m. Partners in Education/Committee on companreh share Ih, lale'.! Itchn logical
advances In their hetds. conduct demonSlratlons
WEDNESDAY, MARCH 17 or quesllon-and-answer dIalogues and Inlro-
duce new or updaled equlpmenl and programs
8:3()'Noon Education Meeting
Design Responsibility Panel Discussion 6:30·8:00 AISC Welcome Reception
A ,peelal panel made up of ,nd,v,duals wllh dlf- p.m. All conference attendL and ~pou' es are Invil
ferenllnduslry vlewp0lnls WIll d,scuss slruclural ed 10 th,s party In ExhibIt Hall
sleel deSIgn responslblhty All NSCC attendees
enc'JUr.lged tl attend
•
Iron Work. Corp Whitehouse NJ oped In Europe and th U S
Panel: Companies represented on the
panel include Bethlehem Steel, British 9:00 a.m.· Universal Studios of the Stars
Steel, Chaparral Steel, Northwestern 2:00 p.m.
Steel & Wire, Nucor·Yamato Steel, and
TradeARBED
STEEL
STANDS
•
FORTHE
FUTURE
9:15 · General Session: Design and
10:00 a.m. Construction of the Cooper River Bridge FRIDAY, MARCH 19
Presiding: Hollis L. (Pat) Hance, Jr.,
NSCC Co·Chairman 7:30·8:15 Exhibitor Workshops
Speaker: Raymond J. McCabe, Howard a .m.
Needles Tammen & Bergendoff 8:30·9:15 General Session:
June 20, 1992 marked the opening of the a.m. Moderator: Robert F. Lorenz, AISC
Cooper River Bridge, the tong est bndge In South Director of Education
Carolina Serving as a vllallink In the 1-526 Mark Presiding: Robert H. Woolf
Clark Expressway the conSlructlon challenges T.R. Higgins Lecture - winner to be
were met wllh Innovative design elemenls. The announced
main river span of thiS 5. I-mile bridge IS a mod
ern slate-of the-art parallel chord steel truss with 9:00·3:00 Cypress Gardens Luncheon & Tour
span~ of 400 feel, 800 feet and 400 feet p.m.
9:00 a .m. Exhibits Open
9:30·3:30 Park Avenue Shopping/Boat Ride Lunch will be served from 11 :30·1 :00
p.m. p.m. in the Exhibit Hall
10:00·3:00 Exhibits Open
p.m. Lunch will be served from Noon·1 :30 9:30·2:30 Walt Disney World Village
p.m. in the Exhibit Hall. p.m.
10:00· Technical Sessions
10:45· Technical Sessions 11 :30 a.m. 6R Fabrl<:atlon of Archllecturally Exposed
12:15 p.m. (See Techmcat Session section for deSCription) Structural Tubtng
2 Managing Subcontract Delalling 7R Current Issues In Steel BUilding DeSign
3 Manual of Sleel Construction Volume II· S OSHA's ReView of Steel Construction
Connections
4 BUilding and Motivating a Productive
Workforce
5 Fire Restorallon and Protecllon
6. Fabrication of Architecturally Exposed
Structural Tubing
9 Ste.·1 Bridge Rehabihlallon
1:00 p.m.
Accidents
9R Steel Bridge Rehablillatlon
11 R Construction Automation In Steel Framing
14R The Fabrication Shop and Ihe EnVIronment
Exhibits Close
•
1 :00·2:30 Technical Sessions
12:30·2:00 Poster Session (Exhibit Hall) p.m. 1R Industrial BUilding'
p.m. An exhibition of technical papers will be diS- 3R Manual of Steel Construction Volume"
played throughout the conference . Authors of Connections
papers Will be available dunng thiS time penod SR OSHA's ReView of Steel Construcllon
for diSCUSSion of the papers' contents Accldenls
t 2R Prolect Management Organizing the Job
1 :30·3:00 Technical Sessions 15R Seismic DeSign In Steel
p.m. t Industrial BUildings 16R Quality Stand~rds vs Fitness for Purpose
4R Building and Motivating a Productive
Workforce 2:40-4:10 Technical Sessions
10 Welding Symbols and What They Really p.m. 2R Managing Subcontract Detailing
Mean 5R Fire Restoration and Protection
11 Construction Automation In Steel Framing tOR Welding Symbols and What They Really
12 Profect Management. Organizing the Job Mean
13 Composite Structures 13R Composite Structures
r
5:15-6:00 Exhibitor Workshops 9:00·4:00 Kennedy Center Tour
p.m. p.m.
7:00·11 :30 Conference Dinner at Church Street
p.m. Station
!)
·D
~
,~
I - ----------------------------
REGISTRATION FEE : REGISTRATION FEES INCLUDE: General SeSS'OI1S. workstK1PS scm nars extu-
Iplease circle appropriate feesl bltlOO coffee blanks. luncheon, Th J(-,day cmd Friday COCkla Rec~pl on Wedrocsday
evening and a printed, bound lIPY If the NSCC Proceod "gs Exh b tors 81 enttlcd
AISC Member Fee: $290.00
to ()(U1I regls(r ...llO~ for E :/l 10 In 11 f'XMlfl space reserved Added Exh b tor
let. payab INlY,1 exe(' )1 j:~fiorq:~l(t xlOUcx btspace
(Include AISC- Ac 'VI A< 0<; all
& Pr~;( I)(l MI rnb4 If ) REGISTRATION CANCELLATION POLICY: ~'" Intel I!QI1S receNed on or
bdore Marer? If¥::l3 tOO of ~fC'~ d ft J tr;;tlOO' ,W1 be refunded atter
Non·Member Fee: $340.00 MarCh '2 50 WI be refundl'd Thosl In 'f- ng afll r Mar h 2 N rocolvea cclpy 01
Educator Fee: $100.00 the Conferer 'f> Proceedings Reful"rj~ WI bp. ~n' rlller II N, (
(Employed full·lim at accredlled archlleclural
or eng,nee"ng colleqe or u",verSlly.) REGISTRATION FOR OPTIONAL AND SPOUSE EVENTS
Student Fee: S 75.00
L ," f from 'acully advi Ir)r eqUivalent reqUIred ) Event No T'ltal Pr'.e
Exhibitor. in booth: No charge OPTIONAL EVENTS
Added Exhibitor: $100.00 I 1-Conlerence Dinner al Church SI SlallOO I> 551 00 $_ __
Spouses' Fee: $100.00' (Thurs 700 pm)
12 a World Paily ill $62 50 $ _ __
'Includi Wed evening reception eXhibit floor paSS
I pousp lour each day Wed Thurs FII (F" 500 p.m)
• 3-Kennedy Space Cenler il$3 t 00 .... $. _ __
(Sal 900am) _ _ @$2500$. _ _
PARTIAL REGISTRATION FEES SPOUSE EVENTS
(You al;() may pre-reglSler lor one day or half ·day ) (NOle $/00 Spouse Package Choose one lour e.lch day)
z Circle your choice below:
Design Responsibility Panel $50.00
. A-Maglc 01 Mlng
(Wed 1200am)
.. $18 00 $_ __
-
Half Day Sessions: flur r not tn Udf d) 0$5800$ _ __
o Wedn day aflernl 00
Thursday morning
$ 5500
$ 7000
I B-Unlvorsal Siudio Tour
(Thurs 900 am)
I e-W,nler Park/Boal Ride 0$3800$
Thursdayaflernoon $ 7000 (Thurs 930 am)
FIIday morning $ 70 00 ' O-Cypress Gardens $3200$. _ _
(F" 9 00 am)
One Day Sessions: I E- Wall Disney World Village 0$1500$, _ __
Thuroday (Includl • lunch) $16000 (Fn 9 30a m)
F"day (Includes lunch) $16000 I F- AISC Cockla" RecepllOO ~_ @S2000$:-:-_ _
Exhl Ilor FlOOr Pass $ 500 (Wed 630 P m Included wllh spouse or regular retJ'sliahon)
(Includod In full parllal md spouse reglSlrallOOs) I G-Exhlbll Floor Pass _ _ .. $ 5 00 $,-,_ _
(Wed Thurs FII Includ, d Wllh 'POU'
Or regular reglstrallOl1)
Company
•
ment tower, a six
developer of a story office block, and
low-rise retail and
45-story public spaces.
The program for
Olympic hotel the hotel tower called
for 460 rooms ar-
to utilize a steel ranged primarily on
two sides of a 118' (36
exoskelaton meter) square tower
over the lower 32
floors .
By Ha l Iyengar, P,E., The upper 13
John Zils, P.E., and floors contain 32 de-
Roberl Sinn, P.E. luxe apartments ar-
ranged generally on
the basis of two or
three units per floor.
The elevator core is
located in the center of the floor
plate along with interior columns. Exoskeleton DeSign
This tower together with an adja- Architects and engineers have
cent office tower forms a twin- continually searched for structural
tower gateway into Barcelona and systems that would make tall
the Olympic Village area from the buildings economical and efficient.
Mediterranean seafront. The de- The critical factor in the evaluation
sign concept was ba ed on an ex- of tall building structural systems
posed exoskeleton steel frame has historically been the resistance
which envelopes a smooth glass to lateral wind and seismic forces.
and metal rectilinear prism con- This process has led to a genre of •
taining the hotel and apartment structural systems which utilize the
floors . entire three-dimensional exterior
, ,-
I
...... , ............ I
~ Interlor
Fireproofed
Steel
Pla ne of Exterior 'Claddin
+ 4 00",",
BUilT-UP
CRUCIFOR M
IUI ~ I
I Wth28
Coif,.... "
I W 2 1Kl01
W211l57
WlM21
W21
mum resistance to lateral loads. S.,I ••
Contrasted to a fully trussed
tube such as the Hancock building
in Chicago, it is also possible to cre-
ate a trussed tu be in the form of a
megaframe. Essentially, this con-
sists of vertical braced frame "legs"
•
in each corner of the building inter-
connected at several locations by
horizontal braced frame intersec-
tions. This mega frame form, w hile
LABOR PI.".~
]_1- -j
j- EU.' ~
'f ....
~I
Eu" lo.
MONEY
CI ,,,,, I,,;
WITH WFBEAM
CUSTOM SERVICES:
DR!FT
~
~.-- 'f\" 28 .3 (h / 2001
" t , "
'~-~--~'
, I I "
" I I ~,
.. +4.))f'..JV"7I--;;n
T I ~,
..1.
TEE'SPLITTING
; , , ..
"
DRILL & COPE
I
END MILLING WITHOUT WITH
•
•
MID DLE BA Y MIDDLE BAY
DIAGONALS DIAGONALS
-
CUT·Ta-LENGTH
At top are arcliitectural alld structural floor pIa liS for tlie liotel, while pictured above is
the structure's deflected shape finder wind wi,h and without middle bay diagonals.
AA
o 0
not as efficient as a fully trussed
tube, still brings on the essential tu·
bular behavior and is suitable for
One drawback to this type of ex·
posed structure has historically
been fire and corrosion protection
STORAGE. TRANS-SHIP medium height to supertall build· requirements. In most cases, the
ings depending on the number and members needed to be fireproofed
spacing of the interconnections. with concrete or sprayed·on mate·
In order to create an exoskeleton rial and then enclosed in masonry
form, the braced frame must be or metal and glass facades . While
disassociated and pulJed away other fire protection systems, such
from the plane of the window walL as flame shielding and liquid
This approach was taken for the cooled members, have been at·
Hotel de las Artes tower, which al- tempted , they tend to camouflage
lowed the structure to be displayed and confuse the frame expression.
against the backdrop of the win· However, the development of
dow wall system. The exoskeleton an analytical fire engineering ap-
form provides a basis for a purer proach to determine the steel tern·
structural expression; the clear ar· peratures when exposed to differ-
AAI<ANSAS srEEl PROCESSING. INC. ticulation of the character of the ent fire conditions, as well as the
ARMOREL. AR 72310
structure in terms of member pro· determination of the character and
A FUll-SERVICE STRUCTURAL
STEEL PROCESSING CENTER portions, shapes, and joinery is nature of the fire, has been the real
made possible by fully exposing breakthrough in the design of ex· •
these members and their connect· posed structural steel systems. The
ing joints. pioneering work by Margaret Law
•
such designs and the technical fea-
sibjJjty of exposing structural steel
has brought on a new vocabulary
in architecturally expressing the
structural frame. It is now possible
to emulate the natural beauty of
exposed steel with all its crisp
member proportions as exempli-
fied in the Eiffel Tower and the
great Victorian train stations in
London and Europe.
The Hotel tower exterior frame
is placed approximately five feet
away from the window wall sur-
face thus creating the exoskeleton
form. The noor framing projects
through the window wall and con-
nects to the exterior frame. Bar
type horizontal diagonal braces in
the plane of each noor complete
the engagement of the exterior
frame with the noor slabs to estab-
lish the required diaphragm action.
Each elevation consists of X-braced
frames over a 30' (9.2 meter) width
on each comer that are intercon-
nected hOrizontally at the 2nd,
33rd, and 41st noors by another X-
•
braced frame in the center bay. The
frames on each elevation are con-
nected by continuous beams along
chamfered comers. These frame in- SORB'I'EX structural bearinQ pad
terconnections serve to induce Expansion Bearings which meets today's
three-dimensional behavior under hiQh r load requirements
wind forces, thereby establishing • Hi~h Load while remaininQ cost
the efficiency of an equivalent tu- • Seismic and Thermal effective.
bular system. movement control
Two sets of columns were
• Low Friction Voss Slide Bearings
placed on the interior; one set at Steel bacl~..>(\ PTfE
the edge of the hotel rooms and the • Low Deflecti n
other in the core area. Floor beams accomodates stru tural
were placed 15' (4.6 meters) on • Rotation Capabilities movements due to
center corresponding to the divid- • AASHTO Approved thermal expansiOns - am
ing partitions between hotel rooms. also be bonded to olher
The noor beams were designed on
a composite basis with a 3" (75 FlBERLAST Voss BearinQS t allow for
mm) composite metal deck and A new choice in a misaliQnment or rotati n.
2 \-2" (60 mm) of stone concrete top"
ping. A second 2" (SO mm)-thick NEW CRI11CAL BEARING PAD DATA!
concrete slab was added to the
composite slab system to provide a Wril~ lor your free ~\lI1 MdnUdl "nd
s(~dre 1~"lJ1 disc. AlsldV.siIdt
two-hour fire separation between I it ~ 1,.1. 'm1\.'nUt'nlll'l'lolnUdl dD
noors. Bar type diagonals were
provided where required to brace
the columns and vertical diagonals
of the exterior frame as well as to
resist diaphragm shears. The noor
framing at the apartment levels
was similar to that of the hotel
•
noors. N 11.101hn AV\:.
UIl<:(~n",,)(XI.IL6(h45
ph 706 b73 t\l1(X)
t..~ 708613 1408
Modl..'rn 51l'<.'l Construction I Mdrch 1993 / 21
LOADS OF
INFORMATION.
III
r
•
P2 P, INTIERIOA
l
1 1 11 BRACING
Itt]'
Whelher you're an architect, eng,neer
,
The diagram above shows tile stability
or contractor, thIS aI~new, 3tll-page. system four·story cOllcept of desigll . The
6Q.year Manual has everything you need photo at right shows tlte bars a,.d clro'ses at
10 determine load capacities in existing tI" gallery IL'Vf!/,
JOISt·supported structures txJit from 1928
through 1988 Inside you'll find' The structural steel for the frame
• the onglnal '1(" senes specdicabons was obtained from various Euro-
and load tables pean sources. Locally available Eu·
ropean standard (lPE, HEA, HEB)
• joist girder specifICations and steel shapes were used for Ihe ligh-
welQhltabies ter floor framing and some interior
, the complele expanded ' H' series columns, while the exterior frame
load tables rolled shapes were obtained
, suggested Invesloga"ve procedures through AISC-member Trade-
and hme-saving data for use when ARBED. All structural steel in the
anal)'Zlng e",shng structures tower, both interior and exterior,
, a complele IIshng of commonly used
was ASTM A572-Grade 50.
live and dead loads throughout this
Sherardized coated (a British pro-
•
penod of time
cess Similar to galvanizing) high-
strength bolts for exterior connec-
Don't wa~ a momenllonger, Fill out tions were obtained from Great
this coupon and send for your manual Britain while conventional bolts for
today! Just $59 00, Including postage interior application were obtained ing as a vertical cantilever, while
and handling ($69 00 outSIde US.). locally. minimizing the dimension of the
The project' owner is The bracing required on each facade.
Travelstead Group, architects/en- The four story high, 30 foot wide
Also available - braCing module wa appropriate
The New gineers was Skidmore, Owings,
and Merrill, and general contractor for the scale of the 460 foot tall
SJI Catalog! tower. The framed beam connec-
Siandard was Bovis International.
tions at the chamfered corners em-
SpecifICations, Frame Behavior And Analysis phasized discreetness of the brac-
Load Tables ing on each facade while providing
and WelQhl Tables for Apart from gravity loads, the
braced megaframe was required to structural continuity around the
Steel JOISts and Jots! G,rdOfS corner. The net result of this sys-
resist wind and seismic lateral
forces. Barcelona is in an area of tem was 10 provide L-shaped
_ Send me _ new 6Q.year Steel frames at each corner of the build-
Joist Manual(S) at $5900/per
relatively low seismic activity and
as such the seismic lateral forces ing. Preliminary frame analysis
_ Send me _ new SJI Catalogue(s) under wind load with only these
at SlO.00/per
did not control the design of the
tower, Based on applicable Spanish corner frames revealed large lateral
Total enclosed sway deformations on the order of
Payment includes'~firs-I:-cl-:a-ss-pos-'ta-g-e-a-nd loading codes and wind tunnel
testing, two levels of design wind 25", (64 cm) and also produced sig-
handling and must accompany order nificant uplift forces in the columns
loads were established: one at a SO-
NMOO ________________ and foundations . The addition of
year recurrence period which was
r~ _________ used for stiffness/sway control; braced bays in the middle module
Company Name ___________ and the other at a 100-year recur- of each facade only at three vertical
Address _ _ _ _ __ rence period used for strength and locations, namely the 2nd, 33rd,
•
tability design. and 41st levels, significantly im-
The braced frame system was proved the stiffness resulting in a
:.-_-_-_-_-_--_-_- Z-'P-_-_-_-_-_-_-_- sway deformation of 8.6" (22 cm).
conceived on the basis of maximiz-
ing efficiency under wind load act- The threefold increase in stiff-
~
ad to' Managing Director
Steel JOIsllnstnule
1205 48th Avenue North
Myrtle Beach, SC 29577
ness produced with only 0.25 psf
•
0.2 kg/square meter) of steel ex-
pended for the middle bay bracing
diagonals testifies to the efficiency
of the system. The tension forces
that existed at the middle facade
columns in the unlinked condition
ANCHOR BOLTS, PLATE & SLEEVE
ASSEMBLIES, TIE RODS, STUDS, SWEDGE o
were eliminated when the links BOLTS, U-BOLTS, HEX BOLTS & EVE BOLTS
were introduced. In behavioral Custom fabricated to exact specifications from certified domestic
terms, the isolated L-shaped corner steel up to 4-inch diameter and 4().loot lengths in steel & alloy.
braced pieces were linked together
by the middle bay braCing to STRUCTURAL BOLTS, NUTS & WASHERS in A325, A490 &TENSION
achieve an equivalent cantilever CONTROL BOLTS, WELD STUDS, CONCRETE ANCHORS, B·7 STUDS,
utilizing the entire three-dimen- CLEVISES, TURNBUCKLES and ali types of fasteners in various grades
sional form of the tower as a mega- and materials; plain, plated and galvanized.
portal frame. The cantilever effi- Stocked for immediate shipment
ciency, as a proportion of the
efficiency developed on the as- * SAME DA V SHIPPING
OVERNIGHT TO MOST U.S. CITIES
*
sumption of a fully effective col-
umn stack with neutral axis MID·SOUTH BOLT &SCREW
~
through the center of the building
Central States East Coast
cross-section, was 78 percent, 499 Cave Road 59 Uberty Road
which compares well with the effi- Nash~lIe . TN 37210 Empona. VA 23847 J
ciencies of systems such as the 615-889-8341 804-634'()240
John Hancock Center and Sears FAX: 615-885-6542 FAX: 804-634'()541
------ 11
Tower. The resulting steel quantity 1-800-251·3520 1-800-366-BOLT
for the tower was 17.8 psf (86.9
kg/square meter) applied over the
5SO,OOO sq. ft. (51,100 square me-
•
ters) gross framed floor area.
The dynamiC properties of the r.~~~~~;,,;;,,;;,,;;,,;;,,;;,,;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;::::.::::::::::::
tower corresponded to a 5.2 second
period for the fundamental sway FA C T:
mode and 2.15 seconds for the tor- I
sional mode which resulted in ac-
celerations at the top of the build- RAMSTEEL was the highest rated of all Structural
ing of 19 mg for a 10 year wind as Engineering Software on the market today according
determined by the wind tunnel
study.
to the 1992 Modern Steel Construction Magazine user
The general attachment laterally software survey.
of the diaphragm and the frame
was by means of diagonal bars at I
"RAMSTEEL allowed us to meet
I
I :J
the exterior columns at each floor
and at the vertices of the vertical X- a very tight schedule with a
braces. The 2" (SO mm) diameter smaller, more efficient design
horizontal diagonal bar braces team. The savings in man hours
were chosen to represent the least quickly paid lor the cost 01 the
visual encumbrance with respect to program."
the clarity of the frame expression. NIIbih YOU5Stf, S.£., Prtsidtnt,
The design procedure with respect I
NIIbih YOU5Stf" AssodtItts, IIIC.1.os Angtlts, CA
RAMSTEEL provides user interaction lib
to column and frame instability you've never seen before!
can be summarized as follows:
• All columns taken as isolated in- I _...........
_-,, , __..
dividual elements were designed
with an effective length of one _....- ..-
",'-
---
...
"
....
-
•
AND DRAFTING OF STEEL BWWINGS
• Eigenvalue studies were under-
taken to evaluate the possibility
of four story buckling of all col-
For more information or an in-house
demonstration, call 800-726-7189
'at
- --
---
umns taken together (one vertical FAX 911>895-3544
Ram Analys is II!
5315 Avenida Encinas, Suite M 1-_ _ _ _ _ _ _ _ __ _...1
Carlsbad, CA 92008 Break into the LRfl) rompetitive edge with full
Fax: 6191431-5214 ASO VI. LRFD comparisons.t the dick of • button.
aoof726-7789
bracing module). posed exterior structure . combustible material available or
• Since the slender horizontal bar on a code prescribed fire load mag-
•
brace at the diagonal vertex was Fire Engineering nitude. A fire load of 5 psf (25
insufficient to prevent the four The approach taken for the fire- kg/square meter) in the hotel
story buckling mode, it was de- engineering of the exposed, exte- rooms and 10 psf (SO kg /square
cided to add secondary vertical rior structural steel frame was meter) in the apartments was used
braced frames in the core area to based on the latest state-of-the-art based on European codes. Second,
supply the required stiffness and methods developed in the United based on the fire load, the compart-
strength to induce a two story States and Europe. The problem of ment and window opening sizes,
group buckling mode. fire rating of an internal element and the amount of ventilation pres-
Exposed steel frames exltibit exposed to fire loading is well doc- ent, the character of the fire and the
thermal movements due to sea- umented and is based on standard- flame profile as well as the dura-
sonal temperature changes which ized tests conducted in a fire cham- tion of the fire are determined
must be addressed both in terms of ber according to ASTM E119 or based on empirical fire engineering
induced stresses and in terms of ISO standards. equations. Third , the temperatures
relative vertical displacement of The case of an external element of the exposed steel elements op-
the exterior structure with respect exposed to fire is much different. posite the window opening are de-
to the interior frame. The moderate External elements will be exposed termined by classical heat-transfer
climate in Barcelona produced a to the effects of: radiant heat from theory and compared against ac-
seasonal variation of only 25 de- the fire through the window open- cepted maximum values. Finally,
grees C. This allowed the use of ing, radiation and convection from high-temperature structural analy-
simple, conventional partition de- flames projecting outward toward sis of the exterior frame is per-
tails which accommodated the rel- the steel, and radiant heat loss to formed to demonstrate structural
ative vertical movement between the surrounding atmosphere. The stability under fire loading condi-
the interior and exterior structures. design procedure involves four tions.
Any additional ambient thermal distinct steps. First, the fire load Since the hotel floors are com-
stresses caused by restraints in the must be determined based on ei- partmentalized by fire rated parti-
system were absorbed in the ex- ther a survey of the amount of tions between the rooms, the extent
G.W.Y., INC.
P.O . Box 293 Forest Road • Greenfield, NH 03047
TEL: 603/547-3800 • FAX: 603/547-3801
of the fire was confined to a single
room at a time. The compartmen-
. l::!~
I
~
.. _(
.~
. I
Jobber III
AC/IiQ/ Silt 3 114 ·x 5 112 ·x 318 •
I
.~El~~=-
III ElElElEl
..prg •• • •• • ••
•••••
I'rol,".o".. , D •.",Mlo".1 Ctlcltl.lor
• • • 111 111
Dimensional Calculator
The Calculator that does it All ! • 00 • •••••••
The Indispensable Tool for Everyone Who Works with DIMENSIONS
Detailers, Fabricators, Foreman, Crewleaders, Layout Men, Engineers
& Architects. The Worlds BEST Feet/Inches/Sixteenths Engineering
Calculator that also works in Decimals & Metric (millimeters) with
Instant Conversion at the touch of a button!
New Features Include:
*Built-in Trig.Functions That Automatically Solve Bevel.Rise.Run & Slope in all Modes.
Makes Calculating Beams, Columns, Frames, Stairs, Rails, Braces, Roof Slopes & Circles Easy.
* The only Calculator with the Jobber ill patented 0/15 Keyboard that cuts keystrokes by 66 % ,
Saving You time & entry errors over "old fashion calculators" & that Means Money to YOU !
* 4 Memories that automatically retain your data even when the Jobber ill is off.
• Everyone who works with Dimensions needs the Power of the Jobber III.
Jobber Instruments
Special Price Order Toll-Free
•
P.O. Box 4112-C
$ 99.95 + $4.50 S&'H Sevierville, TN, 37864 1-800·635-1339
•
suIt. In lieu of fire protecting the through the intact curtain wall. to the various members based on
frame in this region, a two-hour Fire engineering analysis indicated the maximum steel temperature
fire rated glazed window wall sys- that the maximum steel tempera- opposite the top of the window
tem was used which prevented the tures were 169 degrees C. 386 de- opening reduced somewhat to ac-
flame from extending through the grees C, and 383 degrees C for the count for the temperature gradient
window wall until all the fire load columns, beams, and diagonals re- along the lcngth of the member
was exhausted. spectively which was well below away from the heat source. Stabil-
A number of hypothetical de- the accepted maximum tempera- ity of the exterior frame under fire
sign fire events representing differ- ture of 550 degrees C (1000 degrees loading was checked using the
ent locations of hotcl compart- Fl. At this temperature, stccl re- standard AISC ASD beam-column
ments were considered. The tains 75% of its yield strength and interaction equations modified to
characteristics of the fire and com- modulus of elasticity and beyond account for reduced modulus of
partment are indicated as well. which these properties begin to elasticity and yield strength at ele-
Two types of design fire event rapidly deteriorate. vated temperatures. A minimum
were considered in designing that The final step in the fire engi- 25% additional reserve capacity
portion of the exterior frame oppo- neering procedure for the exterior was included in the member de-
site the apartment floors where the frame was a high temperature signs for the fire load cases.
window wall assembly is fire- structural analysis for the various It should be noted that most
rated. First, the posSibility of a lo- design fire events. Each design fire model building codes in the United
calized breakage of the rated glass required a unique set of material States and Europe, including the
•
wall was considered to account for properties based on a reduced Uniform Building Code, BOCA,
the possibility of accidental dam- modulus of elasticity correspond- and the Southern Building Code,
age during the fire and second, the ing to the calculated steel tempera- allow fire engineering calculations
effect of radiation of the firc tures. Thermal loads were applied to determine the fire resistance as
•
fire rating .
Since fire engineering is a ratio-
nal method that uses first princi-
ples, it cannot be compared with
prescriptive methods generally
stated as the number of hours of
rating for an assumed standard
time-temperature curve. However,
as an approximate verification, a
fire test was performed at the re-
quest of the Barcelona fire depart-
ment officials to verify that the fire-
engineered design of the structure
would produce temperatures
equivalent to the code requirement
of a two-hour fire rating.
The test chamber approximated
the conditions of a typical hotel
room. Steel sections were placed in
front of the test chamber represent-
ing the lightest and therefore the
most critical exposed steel sections
used for the actual frame. More
than 100 thermocouples were
placed in various positions on the
steel pieces. Gas jets located within
the compartment were calibrated
so as to produce an equivalent of
•
the standard ISO time-temperature
curve and were allowed to remain
active for three hours. The maxi-
mum steel temperatures recorded
during the test were well below the
550 degrees C critical temperature
and indeed were far below the
temperatures calculated using fire
engineering principles. The test
showed that the nature of a fire
with flames emerging through an
opening in the exterior wall as in a
real fire is generally more critical
than any application of the stan-
dard ISO fire within the hotel room
for this situation. frame without disruption by the connections were chosen based on
gusset plate. erectability, accessibility for paint-
Exterior Framing This basic member orientation ing and future maintenance, limit-
The general nature of structural was used throughout the structure. ing the potential for corrosion, and
steel is one of wide flange shapes The exterior frame erection was fa- aesthetic visual considerations. The
expressed by their thin outstanding cilitated by designing a shop pre- sections chosen for the various
flanges. The frame character is best fabricated unit involving two col- frame members represent a h,erar-
exhibited by continuity of the umns and interconnecting beam, chical progression based on their
flanges at the beam-column joint. with all welding of the intercon- relative importance with respect to
The general placement of the wide necting jOints performed in the lateral and gravity load resistance.
flange column web parallel to the shop and later field bolted. The dominant role of the col-
building plane provided a head on Similarly, corner moment con- umn element in directly resisting
view of the flanges and the beam- nections were end plate type, field gravity loads and overturning mo-
• column intersections. The diagonal bolted . Column splices were also ments due to wind is expressed by
connection with a single gusset field bolted butt-plate type connec- choosing deep W21-serics rolled
plate in the plane of the member tions. shapes rather than conventional
webs allowed for continuity of the The exterior frame members and W12 or W14-scries columns. By
•
ries members from TradeARBED four types depending on the loca-
for the lower story columns, all ex- tion and access requirements. The
terior columns were rolled shapes basic sequence of painting systems
of constant depth between the application involved shop clean-
flanges. The second level of frame ing, priming, and painting of the
expression included the 16" (400 steel for shipment to the site and
mm) deep built-up cruciform diag- application of a second finish coat
onal member and W21-series pri- in the field after erection and final
mary horizontals on the four-story cleaning.
vertical module. A cruciform sec- Two types of exterior exposed
tion was chosen for the vertical di- steel fire protection were utilized
agonal as the open shape best for the structural steel members
suited for painting accessibility, that extended between the exterior
simplicity in connection detailing, window wall and the exoskeleton
and consistency with the flange ex- frame. An epoxy resin, preformed
pression of the other components. intumescent material was used to
The connection detailing philos- provide a two hour protection for
ophy was formulated based on all horizontal diagonal struts,
eliminating site welding of the ex- clevises, and associated gusset
posed painted steelwork and di- plates. The mesh reinforced intu-
rectly expressing the bolted charac- mescent fireproofing thickness re-
ter of the connecting joints. All quired to provide the two hour rat-
exterior frame details were com- ing was 9116 inch (14 mm) which
If you need lead and chrome pletely specified on the working was used throughout. The material
drawings including weld sizes, was preformed to the appropriate
free, VO( compliant coatings, gusset plate dimensions, bolt spac- shapes and then applied directly to
ings, and plate thicknesses. All de- the steel members with adhesive. A
ask us about Enviro-Guard®, tails were computer generated flat fireboard material was used for
•
with typical details developed and all exposed wide-flange floor fram-
our environmentally-friendly reviewed with the architectural ing beam ends. Both exterior fire-
team via three-dimensional com- proofing materials were suitable
puter renderings. for exterior exposure.
family of coatings. From joist Rules for the symmetric and or- The Hotel de las Artes tower
ganized placement of connection represents a significant step for-
dip tanks to shop coat primers plates, bolt heads, and splices were ward in establishing the validity of
specified as well. Gusset plates fire engineering methods in expos-
for structural steel to high were shaped to more clearly define ing steel frames in tall buildings.
the underlying flow of forces The use of a mega-portal frame
performance protective through the structure. All shop system illustrates the adoption of a
welding of exposed steelwork was powerful modular system for
coatings- Enviro-Guard can continuous and completely
wrapped around connection cor-
buildings in the mid-height range.
By mark.i.ng a major international
ners and intersections to avoid cor- event in the summer of 1992 and
handle them all. rosion. by serving as a catalyst for the
reawakening of Barcelona as a
~o
Painting Systems major European capital; the Hotel
The exposed, unfireproofed ex- de las Artes tower represents a sig-
terior steel structure received a nificant step in the development of
coating system designed to pro- tall building structural systems and
Southern vide "long life" as defined by Brit-
ish Standard BS 5493 for an "exte-
architectural design.
Coatings
South,tn Cooling, The (ompony thot istens •
rior exposed polluted coastal
atmosphere" with finish coats. Due
to the various conditions of expo-
Hal Iyengar, P.E., is a partller and
director of structllml ellgineerillg,
101m Zils, P.E., R.A., is all associate
sure and accessibility, a number of partller alld senior structllml engilleer,
different coating systems were re- alld Bob Sillll, P.E., is all associate and
•
quired to achieve the desired level project structllral eflgifleer with
PO Box 160, Sumtet, S( 29151 of corrosion protection while at the Skidmore, Owings, afld Merrill. This
same time maintaining the aes- article was adapted from a paper deliv-
...- ."'" I .. 1 " "' . 111 ((l \l""~
I thetic visual appearance. ered at the 1993 NSCC.
•
been extremely difficult," said Project construction professionals. ask for
Engineer Jack Petersen of Martini Hilti's "Deck Tech" at 1-800-879-8000 .
Martin Consulting Engineers of Wheat
Ridge. Colorado. "The versatility of
H,lti's DX7S0 made it an ideal choice
for the decking application ."
P.O. Bo' 21148
Tulsa, Oklahoma 74121 · '148
Unlike welding , the DX7S0 system
worked well despite cold and wet
weather. Using a self·contained ~ e ~·®
FARGODOME Engineers Specify the DX750
•
Designing
Architecturally
•
Exposed Steel
Tubes
OIl"Ho E COUHlV COHV[N'T ION CIVIC CEN TER I
ORLANDO, FLORIDA
•
However, structural engineers in tubes 3x3 and smaller. Table 1
and fabricators must pay special shows some typical tubing sizes
and fabricators attention to two aspects of design and the approximate minimum ra-
when working with tubes: radius dius curve that can be mechani-
By Lawrence A, Kloiber, P.E. bending and connections. cally formed .
Note that it is possible to bend
Tube Bending smaller radius curves on some
Tubing can be readily formed to sizes of rectangular tubing bent in
small radius curves because with the weak axis direction by using
the closed shape there is excellent some type of internal stiffener to
torsional resistance and no unsup~ help prevent buckling.
ported edges, which have a ten- Magnetic induction bending can
dency to buckle. If proper wall produce even smaller radius
width thickness ratios are main- curves by combining heating with
tained, there will be no local buck- mechanical bending. The tube is
ling the walls when forming. first passed through magnetic in-
There are basically three meth- duction coils that heat the tube
ods of bending tubes-heat cam- enough to substantially lower its
bering, mechanical bending, and yield strength. While hot, the tube
magnetic induction bending. is mechanically bent similar to the
Heat cambering is limited to rel- cold bending process. The heated
atively large radius curves such as tube not only requires less force to
those used for beams and trusses. bend, but the material in this con-
It can be done in the fabrication dition also will accept greater
shop using standard heating strains without buckling. As a rule
torches. of thumb, tubing can be bent with
Mechanical bending is capable this process to a radius of approxi-
of forming smaller radius curves, mately five times its section depth.
•
such as would be required for Because of the equipment re-
arches and domes. The bending is quired and the cost of the process,
done by applying enough force to magnetic induction bending is the
permanently deform the tube. Be- most expensive way of forming.
•
two separate faces. Most bolted 8" Standard 6'-6" CLA
tube-to-tube connections require
connection material to be welded 10" Standa rd 12'-0" CLA
to each tube and then the connec- 12" Standard 24'-0" CLR
I
--+ f - -i--
~
I I
I
I
-
Ii
I I
I
I ,I
I
I I
I
I
I I
I
I
I
I
r r
•
tions are used in exterior expo- quate to simply size welds for the
MAX WEISS CO.. INC. sures, it is important to provide load in the member. Due to the dif-
8625 W BrOdley Rood M92
Mllwoukee. WI 53224 some method of sealing the tubes. ference in stiffness across the wall
Telephone 414-355 8220 Direct welded tube-to-tube con- of the member normal to the load,
MAX FAX 414 355-4698
• TUBE CORP.
FIG . 30
Manufacturer of
Structural Steel
Tubing
2" - 6" Square
2W' x 11;2"
4" x 8" Rectangular
Wall Thickness
FIG. 3b .120" - .375"
(708) 496-0380
Fax (708) 563-1950
6226 W. 74th St.
Chicago, IL 60638
DETAIL S I EEL
• ERECTION B LT
OPTIONAL
•
where the entire tube is exposed .
Production Control
Get unrivaled control over 1'''-''''''' •• ,. ...... : .. ·-1
every piece in your shop, .lJIlllIlmmmJI ::.:... IUJIIl1ff1llllmU
every step of the way .,,'
1 ",,0.:'" '7 - ,,;;
Lt.!IOIIt I
0-:..
,It_, 11
S
Z
31
3J
..
J l:6w< -
1>: -
SII -
"",t
~
,• tZ
'lZ
IrDc
•
II ~~ \I ~1I11111~ I - ~ 1111
How would you like to be ab'e to punch a few keys on your
computer and get instant. detailed tracking reports on the status
01 individual pieces or entire jobs in your shop? That's exactty
what Structural Sottware's new Production Control Tracking
System can do for you. Shipping tickets. loading reports and
other status reports show what shop stations a piece passed
through on what date, who did the Work, how many manhours
the work took and what still needs to be done to that piece. Bar
graphs, like the one shown, give the number and percentage of completion on any piece mark, sequence or ;Ob, The new tracking system
gives youthe power to see exactiywhat shop work remains to finish a given piece marl<. sequence orjob. Sor1ed fists show individual piece
weights, assembly weights, even weig ht 01 all steel on a drawing. Production Control interfaces with our Purchase Orders program to
generate cutting lists that give you the added capability of tracking material from the time it's ordered to the time it's cut. The cutting lists
show shop employees exactiywhich pieces to puff. which pieces to cut from them andwhidl pieces to scrap orreturn to inventory. Production
Control also works with our new Combining program to optimize your material cutting for even more savings.
,r-""""T""-r-=7
• I
I
I
I
FOR BEAMS,
CHANNELS,
PIPE & OTHER
SYMMETRICAL
I
I SECTIONS
~------
the "easy way", 20" pipe, 15" round bar, 13" square bar, 16" x 12"
fl at bar the "easy way" and 16" x 10" fl at bart he "hard way" .
Section modulus capacities to 725 in'.
-
SHOP DETA I LS
TRUE
FALSE
FALSE
.p- T NAl
•
problems must be complex and difficult
to use.
Structural engineering software can never TRUE FALSE
be fun to use.
If you answered TRUE to any of the above, or you would like to know more
about a truly innovative software progrom, call usl
~ J r·yRlCflON Cl
Rt\J'
RISA-2D ~. THP'O ~
v~ L
Your comptete sotutlon for
frames, trusses, beams,
shear walls and much more!
~
RISAS, t
Lake Forest. CA 92630
1-800-332-7472
~;;;;;;;;;;;;;;;;;;;;;;~~~~~~~;;;~~~~~~~
..
Unfortunately, many architects
think they can get an improved ap-
•
pearance by writing specifications
Structural Material Sorter Ver. 4.2 calling for grinding all welds. This
is not only costly, but it may also
A series of programs
I
result in poor appearance and im-
proper weld size or profile. Certain
welds, such as butt welds, can be
easily ground if appearance is es-
deSigned to help pecially critical. However, even
when grinding butt welds it is im-
steel fabricators possible to get a perfectly flat,
smooth surface. There is usually al-
manage material. ways some misalignment between
pieces, and weld metal is always
higher in strength than the base
• Reduces labor - Increase. accuracy. metal. When grinding, there is a
• Automatically computes weights, sur' ace
area., bolt count. and lineal totals. tendency to either over or under
• Quickly sorts Ii,ts Into proper order. grind parts of the joint. The best
• Produce. optimum length·cutting listl from you can expect is a smooth transi-
in·house stock, vendor's stock or the best tion.
combination of each.
• Provides shipping lilts based on piece- Fillet welds are very difficutt to
_~ mark sequence. grind (as shown in Figure 8). The
_':.:J;S • Tallies material costs, shop hours lind field convex weld bead is positioned at
_. ~ hours 'or easy •• timating. 45 degrees to the intersecting joint
~ • Uses simplified terms so non-tech perl on -
__ :.:.:J.: nol can operate with ease. faces, making it impossible to place
---- • External Data Interlace can Import existing the face of the grinder on the weld.
.: r:: ill.ill1 ~=]~= • ~~~~:~;b,~~e: Fn;.~:rf:!!~t~it, including
th e full .y.tem'. operator'. manuall
The grinding has to be done with
the edge of the grinding wheel or •
disk. Any attempt to continuously
E.J .E. INDUSTRIES . INC. grind a fillet weld in this manner
COMPUTER SOFTWARE FOR STEEL PROFESSIONALS
287 Dewey Avenue Washington, PA 15301 (800) 321-3955
Fig. 7
• &--
o
..--+-...,j-
I SLOT
ON Q
~
~
.LLN
•. t1 -(@ LOT
•
Toul lot P"lSr.ltnI (JNIHWlit, ,h/PPIn3 and hInd!!"&> S~_ _ __
ance, then epoxy resin fillers 10I•• 1IId", tN USA. tI>II CMAd_ 0flIy• .pr.ApriI 1M)
should be used to dress the welds. C
D'"''''
These fillers can be sanded to pro-
vide a smooth transition. Also, it
_ _ _ _ _ _ _ _ __ r.xr
a MAmac.uo 0 ~ II
o.UL-- D CHIC'KINCl.O!iID
•
mcludes the minimum reinforce-
FIG. 8 ment requirements shown.
f;~f'~t
Visual Acceptance Criteria
The decision on what is an ac-
ceptable final product is highly
subjective. Jt IS complicated by the
difference between inspecting a
piece close at hand in the fabricat-
ing shop and viewing it in place.
The desired quality level also can
be affected by how readily the con-
nections can be viewed.
We recently went to consider-
able effort for the connection de-
tails for architecturally exposed
tubmg only to find catwalks and
d~ctwork everywhere, effectively
hldmg many of the connections.
An experienced engineer once
told me that architecturally ex-
posed steel should be inspected
from the same distance as it can be
viewed after erection .
. It's also important that expecta-
tIOns be realistic. We had a recent
FIG. 9 project where we had to cut and
taper tubes for columns and beams
•
in a large entrance canopy and
monumental stairway. The archi-
tect expected the weld seem along
the taper to be completely invisi-
ble: And even after we used epoxy
resm fillers and special sanding,
the architect was not satisfied. We
later found out that the architect
KENILWORTH STEEL
t6/373·t995
Wlrren, OH : 2
•
Jointless
Redecking Of
•
Simple-Span
Stringers
t the age of
Elimination of
unnecessary
A
ing
40, the Tioga
Ri ver cross-
in Steuben
County, Y, was
roadway showing signs of de-
terioration, though it
expansion still was capable of
the same H20 truck
loading capacity as
joints can when it was first
•
opened to traffic. To
often be ensure the bridge's
future functionality,
accomplished the State of New
York committed to
without major an extensive rehabili-
tation program. A retrofit project eUminated expallsioll joints i" part by
structural Existing
splicing 1/" bridge'S slringers.
Conditions
rehabilitation The structure was built in 1949
joint leakage and accompanying
corrosion of the steel support com-
and is composed of four 100' spans ponents.
By Philip C. Pierce, P.E. of simply supported steel wide- The existing stringer bearing de-
flange stringers. The cross section tails also were unusual. Both bear-
consists of five stringers spaced at ings at the center pier were fixed
6' -9" supporting a 24' -wide road- steel pedestal style. The bearing at
way with 2'-6" brush curb and the side piers and abutments were
metal railing on both sides. steel rocker style. A steel strap was
Although the stringers are sim- welded on the top of the bottom
ply supported, the deck was cast as flanges at the piers that apparently
a semi-jointless system. The deck was intended to provIde stabIlity
slab is supported directly on top of during erection and during the ser-
the abutment backwalls and was vice life of the structure (the end
cast with a cold joint and non-con- spans are supported by rockers at
tinuous reinforcement at the piers. each end).
A detail of copper flashing and as- By the late 19805, some of the
phaltic material over the pier joint steel straps had fractured in the
in combination with a 3" asphalt gap between the adjacent stringers.
•
overlay sealed the joint; however, The resistive forces at the abut-
normal deterioration over 40 ments from the approach pave-
years---<ombined with the lack of ment pressure and wingwalls and
continuous reinforcement-led to the frictional resistance at the inter-
... -:'l'~. ,
Although the existing structure
was composed of multi-span sim-
ply supported steel stringers, " "
"'- -
NYSDOT desired the elimination
of roadway expansion joints. This
led to the consideration of splicing
.
!YPI( A, erA W "!'llef OE ' All . 1 PIEft
•
project participant. ''It was done
because it made sense."
However, it was clear that elimi-
nating deck joints did make good
economic sense. Eliminating three
expansion joints resulted in: re-
duced fabrication and erection
costs; reducing bridge railing costs; , .
reduced stringer connection costs
from multiple rocker bearings; and
savings from not having to inter-
rupt the slab reinforcing and con-
crete placement. Note, though, that
there was the additional cost of the
...
stringer flange continuity connec-
tions.
In addition to first costs, elimi-
nating the deck joints also provides
~8'I'J.) ... .
')plro !So
E>. '~1.
\'
o
, " .
T • , ;" . " ':I,
substantial life cycle cost advan-
tages. The elimination of deck
joints will eliminate deterioration
E..
0"
1&1
'.
..'
,
'
of the stringer ends, diaphragms
and bearings due to the potential •1>,
leakage of seal jOints. Further, the
tops of the piers are protected from
the corrosive nature of roadway
salts in the event of seal leakage.
( fOOl"l 5'de Of • .
' ;J.
~1 1o;
e,~ . • P ft'
Bro;:. e P Itr
.
'
~' J
,
.,
Engineering services were pro-
•
vided by Mcfarland-Johnson. The TYPI CAL BcAM ~PLI C E DLTAIL AT PIER
structure rehabilitation contract Seo 8 ' 'I, I O~
MDX software
by
-MERLIN DASH V~Rrr,ON4.5
DeSign & Analysis 01 SlrBlghl Sleel Girder Bridges
"AASHTO - 11191lnl.rim
" FHWA - ~ Ind UHd by
•
" DOrs - Ustd by M2!! SIal..
" Design -/WI capability
Excellent for both analysis and design " Manu-Driv.n InpuI- YIlX E.y
• Generates and loads influence Jines, then desIgns girders with 8
"Graphks DI",I.y 01 OUtput __- - - - ,
powerful optimization method (one that workslJ " OUtput R.port 5.1"'1100
• Non-prismatic I girders and box girders, 8S well as rolled shapes
• Composite or non-composi te; all types of web haunches
• Up (0 12 continuous spans; variable horizontal curvature capability
• User may specifv ranges l or (or fix) any of the variables
• Generated designs salisly 1992 AASHTO specificlltion, including
latigue stress ranges and dellection limItations
-MICROBARS
Mlcro-Co"lJUler Bridge Anatysls & Rating System
• Allowable Stress and Load Factor versions " Deriv.d lrom Original BARS Program
• SeQuential slab placement studies lor construc tibiJity " Co!rpallble wllh DOr. SIru<lurlIl D.I.b ....
• Free· lorm or menu driven input, includes a 'smart editor' that ./ Rates All Conventional Member Types
organizes and checks user input lor inconsistencies " Consld ... All ConllnJellon Mal.rials
• Comprehensive output, including performance ratios
• Grllphlcill output of stresses and dellections on screen or printer
And many more!
MDX software
1412 Ridgemont Court
Columbia . MO 65203 EJPTI-MATE.
Phone (3141 446 -322 1 P. o. Bo, 9097. Dept. A, Bethl.hem, PA 18018
Fax (3141446-3278
---------------------------
•
loads and future dead loads.
The details of the connection in-
clude a flange splice plate on top of
the stringer ends and twin plates
on the top of the bottom flanges.
The splice plates are bolted to the
existing stringer; however, due to
interference with the top shoe of
the bearings, a length of field fillet
weld is utilized over the bearings
to seal the edges against moisture
penetration and to restrain the
plate against buckling. The use of
the fillet weld causes recognition of
the fatigue characteristics of the
connection, thereby leading to the
size of the plate being governed by
fatigue allowables. The continued
use of the steel bearings permitted
the elimination of the web splice
plates.
With HS20 as the minimum de- considered, and, as mentioned
sired live load capacity, the splice above, governed the size of the Future Rating Considerations
plates were designed for the nega- plates. It should be noted that truck The splice was designed to pro-
tive moment associated with four loading was used for design in lieu vide in excess of HS20 capacity
span continuous behavior of HS20 of lane loading d ue to the rural 10- based on fatigue considerations.
live load with impact. The associ- cation of the bridge. Hence, ratings based on non-fa-
ated fatigue moments also were tigue allowable will be in excess of
©'" ~
~
A-325
Type 1
'" "325
A·325
Type 3
COUNTERSUNK
D
SQUARE BUTTON
MACHINE HEAD
C"/JUbi li tie."
•
system re presents a n Integrated dcsign·analys is . Stati c ,
\ _ _ _ _ _ 1 environment. It includes complete reinforced
. D)namlc .. ~ Timl' Iti .. toq
concrete and sleel design ca pahditics. The D) namic,, · Rc.,pon\l' SpcLtrum
design procedure') are close ly co upled to th e
SC ADA analys is methods. SCADA includes + P· l)clta
an efficient 3-D fin ite element structural + Bucking
analysis module with a large clement library + Nonlincar Static .. dnd OllHlmil.:"
and a wid e ran ge o f analY'I is cH pabilitie:-,. GCllRlClric anJ Matl'rial Nunlinl'ilril)
It offers th e choice of three preproccs"iing
. CumplCle Etl'nlCnl Lihraq
,~_ _---~::: model definit ion proccdurc~ - spreadsheet Tru .... , BeOtm, Kirchhoff PIJh.", Shear
style. drafting styl e and adva nced geometric and
Plate, Plane Stre ..... Plane Slr.lin.
solid mode lin g st yle. A~i .. )",mclril.: , Shell, Solid
The S ADA di splay capabiliti es arc powerful and
effi cie nt . including :-,haded image. co ntinuous . Stec! and Connell' Dl'.,ilo:n
color co ntour . CAO Tr.. n .. lator'!'
and line . Ccumctric and Solid Modclin~
conto ur
. Mc,h Generation
plotting.
• QL Rel:uiunal Dataha .. e Reporting
•
6. Place new deck concrete in The existing slab was cast on top decision to replace them with
positive moment areas to within 5' of the abutment back wall stem. It NYSDOT standard neoprene bear-
of pier. was considered appropriate to con- ings. The use of neoprene bearings
7. Drill/ream holes in the re- tinue that type of slab support. A required the installation of web
maining side of the top splice, in- detail of the area is depicted in Fig- splice plates in addition to the
stall bolts, and tighten all bolts in ure 3, including an embedded flange splice plates. This project is
top and bottom flange splices. armor angle and closed cell expan- scheduled for construction in 1992.
8. Place closure pour of deck sion joint material with membrane The design of the rehabilitated
concrete in the 10' void above the waterproofing intended to mini- Tioga River crossing did not re-
piers. mize moisture penetration through quire sophisticated analysis or de-
9. Install bridge railing. the slab/abutment stem sliding sign techniques. Also, this general
The contractor chose to repaint joint. concept has been utilized by others
the structural steel after the deck and is readi ly applicable to many
removal and prior to installation of Adaptability older bridges.
the new deck forms. The bolting McFarland-Johnson was se-
sequence at the pier required lected to provide engineering ser- Philip C. Pierce, P.E., has beell ill-
touch-up painting of bolt heads vices for a similar bridge following volved with bridge and structllral en-
and nuts. Elimination of touch-up the completion of the Tioga River gilleering for more thml 20 years. He is
of the bottom bolts may have been crossing. The second structure sup- cllrrently the manager of the struc-
possible if all of the bottom bolts ports the bridge crossing of Depot tllres department at McFarlalld-Jolm-
were installed at full tension prior Street over the Canisteo River in SOli, a transportation engineering firm
to painting and deck concrete the village of Canisteo. The bridge headqllartered in Binghamton, NY.
placement. Though such installa- is composed of three simply sup- This article is adapted from a paper
tion would cause minor bending of ported spans of 63' each. Unlike presented at the 1993 National Steel
the bottom splice plates during ini- the Tioga River Bridge, the Depot Constrllction Conference.
tial concrete, it still might be Street Bridge was built with con-
judged acceptable . ventional fixed and expansion
•------.
PORTLAND BOLT
AND
MANUFACTURING
Domestic Manufactu rers of
ASTM FASTENERS/HOT
DI PPED GALVANIZED
A193, A307, A325, A449 , A490
CARBON-ALLOY-STAINLESS
1/.> - 41/.>" Diameter Bolts
& Anchor Rods
Short Lead Times,
In House Testing
3441NWGuam
Portland, Oregon 97210
(503) 227-5488;
Fax (503) 227-4634
. L.-____. . .
1-800-547-6758
Find out why some 01 the top fabricators In the United States
and Canada have choosen Steel 2000. Call 601-932-2760
Reducing
CONSTRUCTION
CONFERENCE
f)![ 0 .... , 'It.·STfh· CONr[II[NCf:
ANO TII AO( SttOW' IH Tkf. U t
Parking
Structure Costs
OIl.NeE c","lfn CONwOIllON CIVIC CO~T(II
ORLANDO , FLORIDA
D
uring the past
Parking three decades,
parking struc-
structures ture design has been
dominated by precast
framed with concrete frames with
double-tee deck
composite beams and by steel
frames with a cast-in-
girders place post-tensioned
concrete deck. Both
systems had advan-
supporting a
•
tages-and serious
flaws.
double tee deck Steel-framed park-
ing structures have
system can smaller dead loads,
lower shipping Shuwn above is fhe instoJ/n/ioll of ..;Ieel side form . . for flit
reduce costs by weight for structural
components, and
custom form of a composite system . Note Q steel bt.'tWI is
already ill positioll to receive ti,e eOflcrete flallge.
12% to 15% more rapid erection.
Also, the flexibility of
steel frames allow them to more features of both materials. The de-
By Robert M, Barnoff, P.E., Ph.D. easily adapt to temperature sign features single symmetric hy-
and Edwin L. Mead, P.E. changes and lateral forces without brid composite girders framed into
causing excessive cracking in struc- steel columns. These girders have
tural or non-structural compo- spans varying from 54' to 62', de-
nents. However, steel parking pending on the building's foot-
structures may have higher labor print. Spacing of the girders vary
costs for the cast-in-place concrete from 20' to 40'. The girders are fab-
deck compared wi th the precast ricated from three plates using con-
deck used on concrete parking tinuous welds to connect the
decks. fl anges to the web. End plate con-
But while precast systems have nections arc used to connect the
lower deck labor costs, they also girders to the columns.
are heavy and require large foun- A unique feature of the compos-
dations. Also, shipping costs may ite girders is the encasement of the
be high, especially in areas far from top flange in high strength con-
an existing precast plant. crete. This concrete a Iso forms a
portion of the parking deck and
•
Marrying Steel And Concrete provides support for the precast
Recently, Mulach Parking Struc- concrete double-tee beams that
tures Corp. has developed and span in the longitudinal direction
tested a system to combine the best between the girders.
•
3"-0:_ _ _ _-.1'
pressive stresses in the composite
.j.: r-
SJUO$ • I • c/C
girder can be accommodated by
the concrete, the top flange of the
single symmetric steel girder is
smaller than the bottom flange.
~~~,;=--f! -
Further economies and reduction
in steel weight are obtained by
, ! using A36 for the top flange and
,
...J
"
._'-:~ L _ _ _
. _ _
web and ASTM A572 Grade 60 or
65 for the bottom flange. Note,
however, that in seismic zones,
• • 4 - YI1.5 .. YI1,o WIfI( IIIESH A572 Grade 50 steel is used for the
bottom flange in accordance with
CG:JO • 74.1 the LRFD Seismic Provisions.
TOPPL-,.,,-"J6
lIIIlIPL-:JO."-A36
BOTA - , • ~
_ "'1£-60 Lateral Loads
Lateral forces due to winds or
seismic activity are resisted by
frame action provided by the end
plate moment connections in the
transverse direction. Precast con-
SECTION AA (@ CENTER OF 60' SPAN) crete panels that act as shear walls
provide restraint in the longitudi-
nal direction. If required, addi-
tional restraint can be provided by
CONCRETE fLANGE . - STEEL COLUMN braCing in the interior longitudinal
column lines. An alternate method
+ for providing restraint in the longi-
•
tudinal direction is to frame two
structural steel tubes between the
columns in the longitudinal direc-
tion to act as longitudinal bracing
and to serve a dual function as a
barrier.
The composite girder is usually
cast at the job site in reusable steel
1 STEEL TUBING DOU8lE TEE
forms. However, when the con-
struction site has limited space, the
SINGLE SYMMETRIC
STEEL BEAM girders may be cast off site and
transported to the site by truck.
Most parking structures have a
CONCRETE fACADE PANEl clear span of approximately 60'
and composite girders with this
span have an average weight of 20
tons.
An important detail for parking
COMPOSITE GIRDER garages is adequate drainage for
the deck ramps and level turn
Pictured above is a schematic diagram and a retrdering of a composite girder. around areas. Two drainage swales
are provided for the ramps by
sloping the top of the concrete
flanges. In the turnaround areas,
the depth of the swales varied from
maximum at the first interior com-
posite girder to zero at the span-
drel girder.
•
and in many instances, the most PA~ (l SPACING VARI(S 24' TO " 0'
successful-remedy is the use of
high quality concrete.
..I
The concrete used in the precast
composite girder, which was cast
on site, has a design compressive
strength of 7,000 psi and is ob-
tained from commercial batch Pictured, from top
plants. Silica fume additive is used to bottom, are: n
in the mix to increase strength and partial frammg plan
reduce permeability of the con- for a typical parkillg
crete. stmcture; a partial
High water reducing admixture structural frammg
is usually introduced at the job site plall; alld typical
to improve workability of the mix. details of a slllgi.
A water-<:ement ratio of 0.4 is used symmetric beam .
with this mix design, and en- Pictured on the
trained air admixture is used to fo/lowillg page is a
provide resistance to freeze-thaw composite girder
6 Bl( TE[
deterioration. Best results for this elevation .
mix are obtained when crushed
limestone is available for use as the
coarse aggregate and 660 lbs of
high early strength cement is used
in each cubic yard of concrete. De-
sign of the concrete mix, and place-
ment and curing of the concrete, is
done in accordance with American
•
Concrete Institute, "Building Code
Requirements for Reinforced Con-
crete" (ACI 318-89).
Longitudinal reinforcement in DOUBLE T",EE'-_-+it-_.J
the concrete flange of the compos- BEAMS
ite girder consists of deformed
round steel bars. Steel in these bars
conforms to ASTM standard A615-
90, Grade 60. Transverse steel may
be either deformed bars or welded
wire steel fabric (ASTM A185-90a).
All reinforcement is detailed, fabri- 't SPAN
cated and placed in accordance I
with ACl318-89. I
Concrete in the double-tee deck
beams has an ultimate compressive 3/16' ~ ~3/15' ~3'-O'
strength of 5,000 psi.
The steel girders are fabricated
I
in accordance with the AISC LRFD
Specifica tion, with A572-60 or VARIES 54' TO 52'
ASTM A572-65 used for the bottom
flanges and A36 for the top flanges
and webs. Steel columns, filler
beams, braCing and miscellaneous
steel are fabricated from A36 or
A572-SO. High strength A325 bolts
are used.
Since the girders are precast in
•
supported steel forms on site, they
are designed in accordance with
shored construction requirements.
This procedure, along with the use
•
partial restraint at the girder ends used in the elastic analysis that Parking Structllres Corp., Bridgeville,
provided by the connections re- flexural tension stresses do not PA . This article is based 01/ a paper
quired to resist lateral loads. This exist in any part of the concrete presellted at the 1993 Natiollal Steel
restraint results in a significant re- flange. COllstructioll COl/ferel/ce.
1fST DRIVE SOFTWARE THAT WlU CHANGE THE WAY YOU WORK!
VISIT OUR BOOTH AT THE NAnONAL STfEl. CONmUmON CONFERENCE
•
(DXF, HPGl file impart/export .. )
metrosoft 0, 0 AVA LABLE (LIMITED VERSION OF PROGRA WITII Sf F-RUN ING E PLES)
331 PmenolJ An' OVER 1200 USERS WORLDWIDE fOR MORE INFORMAnON (AU 201-438-4915 OR FAX TO 20 1-438·7058
Emf RUI"eifonl, NJ 07073
•
NATIONAL STEEL
CONSTRUCTION
CONFERENCE
THE OHl Y ALl..sTEEL· CONffJIENCf
Steel •
AHO TI'IAO£ SttOW IH TMIE U S
Construction
OR"HOE CooNlY COHYlNlION CIYIC CUffER
ORLANDO , FLORIDA
Accidents
E
ach year, newspapers report The steel deck floor was placed up
Incorrect fatal construction accidents, to the third level. And in the re-
But for design and construe- mainder of the area, preparations
design or tion professionals, these accounts were underway to erect additional
are of only minor interest because steel.
construction they only report what happened,
not why,
The beam-to-beam connections
and beam-to-column connections
procedures can However, an examination of
several steel construction accidents
at different levels were completed
to varying degrees. Up to the third
have fatal reveals a common thread: incorrect
design or construction proced ure.
level, the shear connections were
completed for beam-to-beam and
While this article will only discuss beam-to-column framing. The
consequences two accidents, infonnation on sev- fourth level beams and the roof
eral more accidents is contained in level beams were held in place
By Mohammad Ayub, P.E. "Case Studies Of Steel Construc- only by the erection bolts, with the
tion Accidents" in the 1993 Proceed- number of erection bolts varying
illgs of the National Steel COllstrllc- from one to five depending on lo-
tioll COllferellce. cation. Welding of the flanges of •
the girders to the column was not
Case Study: yet completed, so there were no
moment connections. Therefore, ill
Four-Story Computer the case of allY belldillg momellt, the
Facility erectioll bolts woliid be reqllired to re-
sist the additiollal force arisillg from
Description of accident: Several the momellt.
beams collapsed during the erec- Discussion: Shop drawings in-
tion of structural steel for a com- dicated that all bolts to be used in
puter facility and three ironwork- beam-to-beam connections be 7-i!"
ers on the fourth level of the diameter A325 bolts. For the canti-
structure were killed. levered beam-to-column connec-
The framing for the 320' x 320' tions, 1" diameter A490 bolts were
structure consisted of steel col- specified. When the cantilever
umns and composite steel girders beams were erected on the roof
with infill beams. The floor con- and fourth level, they were held in
sisted of 2112" concrete over 2" deep place by W' diameter erection bolts
composite deck. Typical bay size in 11116" diameter holes.
was 40' x 40' and the floor-to-floor Immediately prior to the acci-
height was 16'. dent, a crew of four ironworkers
At the time of the accident, con- was engaged in levelling the canti-
struction activity was limited to a levered beam framing to column
small area in the northwest corner line B-3 on the fourth level. The
of the building. Steel erection was levelling procedure was necessary
proceeding in the area bounded by because permanent shear connec-
column lines 1 and 4 and column tions were being made at the joint
line A and C up to the roof level. where the cantilevered beam
The third floor structural beams, framed to the column. The proce- •
the fourth level beams and the roof dure was to use a wire rope come-
level beams already were erected. along of two-ton rated capacity
•
roof cantilever beam directly above
the fourth level cantilever beam
and the bottom attached to the can-
tilever beam being levelled.
The intent of the design was to
support the cantilever beams on
column lines 3 and 4 by providing •~
moment connections at the column
j, ....
p~_l-." .u__ ~:~~~- ".~
"ttl "l! ..
~
joints. The moment due to the can-
tilever action would be transferred I
to the columns through full pene-
•I
I '1' I -
tration welds of the flanges and the
beam shear due to gravity load r.
would be resisted by 1" diameter
~ ........ I
-L- ....... ...... I
A490 bolts. "- ~
•
diameter hole had an ultimate ca- a factor of safety of 2.35. load factor of 1.4 and a resistance
pacity of 43.9K and an overstress of • Five erection bolts in the first, factor of 0.65 were taken as re-
1%. However, with a load factor of second, third, fifth and seventh quired by AISC, the bolt was over-
1.4 and resistance factor of 0.65, as holes in the shear plate were used stressed by a factor of 1.71.
•
joists. There were two iron workers
N
on the roof at the time; one
I.i) ~ <"-:if ~ plunged to the ground along with
the collapsing frame and was
killed, while the other fell along
J
J1 tals and foundation walls with an-
chor bolts. All concrete pedestals
were supported by individual foot-
ings.
Construction activity was boun-
• Five erection bolts in the first, ceeded by a ratio of 5.1 with the ded by column grid lines A
second, fourth , sixth and seventh most stressed fasteners being lo- through E in the -S direction and
holes in the shear plate were used cated in the roof and fourth level column grid lines 5 through in E-
for the fourth level cantilever beam cantilever beams. W direction. In addition, columns
on column line B-4. There was a re- Conclusion: The cause of the at grid location 4A also were
action of 5.0K and a moment of collapse was the overstressing of
•
erected. The roof framing members
27.54K-ft. due to the self weight of the erection bolts of the roof canti- were all placed in position except
the beams. The top and bottom lever beam on column line B-3 and for the roof joists in the bay
bolts were subjected to a shear was precipitated when tension was bounded by column lines 5 and 6
force of 12.78K, which was well gradually applied to the come- and column lines C and E. The joist
within the ultimate shear strength along. girders along column lines A, C
of 43.3K. Taking the load factor of The top end of the come-along and E were in place in the E-W di-
1.4 and resistance factor of 0.65, the was fastened to the roof cantilever rection. The long span joists
factor of safety was only 1.6. beam, which resulted in additional 36LH09 spanning in the -S direc-
When the come-along was ten- load on the connection at column tion between column lines A and C
sioned (for computations, it was line B-3 at the roof level. This pro- were placed from column lines 5
assumed to be fastened 12" from cedure was adopted without any through 8. Between column lines E
the center line of the perimeter engineering calculations to verify and C, bar joists 24K? also were
beams along the cantilever beam) it the adequacy of the existing con- placed from column lines 6
would impose an additional load nection. The method of erection for the through 8. The longspan joists and
of 8.8K from the fourth level to the calltilet",r bealllS shollld hat'" been bar joists also were positioned on
roof cantilever beam. Due to the etJ/llllated for the '1III11ber, size alld 10- the column lines, as required by
this additional load, the roof canti- catioll of erectioll bolts at each callti/e- contract documents.
lever beam on column B-3 would ver cmmectioll to the colllmll before Typically, the structural tube
be subjected to an additional reac- erectioll was IIlIdertakell. colu mns had shop welded base
tion of 8.8K and an additional mo- plates and were supported on con-
ment of SS.7K-ft. The cantilever Case Study: One-Story crete pedestals/foundation walls.
beam-column joint at the roof level At the center of the underside of
at column B-3 would therefore be Warehouse
the base plates were shims to fill
subjected to a total reaction of 16.25 Description of Accident: Struc- the space between the top of the
and a moment of l04K-ft. This tural steel framing for a one-story concrete and bottom of the plate.
would produce a shear force of warehouse was being erected The base plates were connected to
l04K and the actual force would when a portion collapsed. Struc- the embedded 1Vi' diameter an-
•
exceed the ultimate strength by a tural framing bounded by column chor bolts with nuts. No levelling
ratio of 2.4. If the load factor and lines 4 through 8 and A through E nuts were provided.
resistance factors were used, then collapsed minutes after a fourth Roof decking materials, consist-
the force in the bolt would be ex- stack of roof decking material was ing of wide steel decks 28'-2" long
•
with each pile weighing 4,931 Ibs., fore, the longspa n joists and bar
were placed on the roof along col- joists on the grid lines in the -5
direction did not provide any ri-
High Strength
umn line A. After placement of the
fourth pile between column lines 5 gidity. The stability of the frame Weathering Steel
and 6, one iron worker proceeded could then only depend upon the
to walk toward column 7C, while rigidity of the column base connec- Structural & Plate
the other was positioned at the tions to the footings or base walls.
mid-position on column line A be- AISC publication 0 -801 "Col- Grade Specifications
tween column lines 5 and 6. umn Base Plates', has given guide-
Oiscussion: The lateral stability lines for the tensile capacity of an- A588! A572
of the steel frame for the completed chor bolts and the minimum edge • Anglel • Beaml • Squarel
structure in the -5 direction was distance for hooked bolts. For A307 • Flatl • Platel • Roundl • Channell
based on the permanent structural bolts, the minimum embedment
crossbracings provided in grid length is 12 times the diameter and A606· Type 4
lines 1 and 8 and the roof steel the minimum edge distance is five • Sheets • Coill
deck diaphragm. The lateral stabil- times the diameter but not less
ity of the frame in the E-W direc- than 4". A242· Type 1
tion was based on the rigid connec- The jOist girder spanning in the AR360 • A514 Gr. A&E
tions of the joist girders at each E-W direction between column Plates
column line created by providing lines 6 & 7 on column line A was
~
welded connections at the top and analyzed to determine its load car-
bottom chords of the joist girder.
At the time of the accident, the
progress of the construction was
rying capacity clue to the applica-
tion of the construction load on the
day of the accident. It was deter-
W Cetlb'al Steel
Service, Inc.
limited to four bays in the E-W di- mined that the compressive stress
rection and two bays in the N-S di- in the top chord was 4.65 ksi. Since 1·800·868·6798
rection. Therefore, the lateral sta- the critical buckling stress, based
P,O, Box 126 • Pelham, AL 35124
bility of the erected frame would on the unsupported length of 56' 2051664·2950 • Fax: 205I66H391
•
depend upon the rigidity of the was determined to be 2.69 ksi, fail-
connections of the erected structure ure of the joist girder ullder the appli-
or upon temporary bracings. catIOn of the cOllstructioll load would r.==============~
The AlSC Code of Stalldard Prac- be expected. In fact, the joist girder
tice ill Section 7.9.1 states that tempo- manufacturer in its general notes DESCON
rary supports, such as temporary guys for the erection had stated that "no DESIGNS AND DETAILS
and braces, will be determined, fur- loads shall be placed on the joist
nished alld illstalled by the erector. girder until the joists bearing on STEEL CONNECTIONS
In the -5 direction, which was the girder are in place and welded
the direction of the collapse, the to the girder" to provide the lateral
longspan joist between column restraint to the girder top nange.
lines A & C and the bar joist be- Concl usion: The cause of the
tween lines C & E were supported,
respectively, by l¥16"x2" and
9,j6"x2" slotted holes at their bear-
collapse was the instability of the
frame caused by the inadequate
temporary connection of the mem-
I
ing seats on the grid lines. The con- bers and placement of construction
nections at the column lines were materials over the roof members.
made with one ¥.!" diameter A325 Temporary bracing of the struc- 'I
bolt and one Vi' diameter bolt for tural steel framing as required by
the longspan and bar joists, respec- the project specification and recog-
tively. The bottom chords of the nized by the industry as the gener-
joists were not connected to the ally accepted means to brace the
column. steel structure during construction
Eyewitness accounts reported were not provided by the steel
that the bolts were handwrench erection company.
tightened . The filler longspan joists
and bar joists were simply placed Mohammad Ayub, P.E., is chief of FOR A FREE DEMO DISK
over the top of the joist girders the Division of Engilleering ill the Of- CALL OR WRITE TO
•
with neither bolted nor welded fice of COIlstructiOlI and Engilleering
connections. The bottom chords of for the Occupational Safety alld Health OMNITECH ASSOCIATES
the filler joist also were not con- Administratioll, Departmellt of Labor. P.O. BOX 7581
nected to the joist girders. There- BERKELEY. CA 94707
(510) 658-8328
Modern Steel ConstructIon I M inch 1993/ 55
STRUCTURAL S TEE L DESIGN
I--
SOFTWARE
FROM AISC
;;;;
721;:,0.-,7_900
r--...
6110
•
lit I 112
Factored Moment Envdopc
CONXPRT ELRFD
A knowledge·based, menu-dri· ==
- 5 A new sophisticated program
ven PC software system for
the design of comections in
steel framed buildings. All
r
I,;
for interactively checking
structural steel building
components for compiiariCe
with AISC specification.
strength limit states are
e
checked and expert advice Checks whether member
from long·time fabricator engi· sati sfies all limit states and
neers is used to augment the limitation requirements set by
.....-
design rules. the LRFD Specification and
• Generates cope sizes, allows reports which sections are
bolt stagger and permits satisfied or violated.
different bolt diameters for - II • Review in detail the formulas
---
shop and field use and rules used in the
• Designs can be stored on evaluation and interactively
disk, allowing electronic WEBOPEN assess any mathematical
communication between Designed to enable engineers expression on the screen.
design parties.
• Generates complete reports
to quickly and economically
design beam web openings. lIIOCIJ • Fully interactive MS Windows·
based user interface.
Uses state of the art criteria • Disk includes ELAFD
showing details and strength
II 10m
•
for each limit state checked. and features a clear and logi· ChecklBrowser, AISC
3· 112" or 5· 114" disk cal data entry system with Structural Shapes Database
MODULE I:
SHEAR CONNECTIONS
easy-Io-use color coded input
windows. Wrinen by practicing
engineers for engineers, incor-
B10rn and sample problems
, User Guide and Aeference
1st edition LRFD
Version 1.02
9th edition ASD
$300 porating expert design checks
and waming messages which
enhance the application of the
HPIOCD Manuai .
3-112" disk only $495
Version 2.0
MODULE II :
MOMENT CONNECll0NS
$400
AISC Design Guide-$teel
and Composite Beams with
C[00 AISC
ASD formal only $400 Web apeningr-to specifiC
design problems.
3- 112" or 5· 114" disk. Includes
IIC[OO DATABASE
Contains the properties and
STEMFIRE AISC Design Guide $495.00 dimensions of structural steel
Determines safe and economi· shapes, corresponding to data
cal fire protection for steel
beams, columns and trusses. AISC FOR published in the most recent
LRFD and ASD Manuals of
Based on rational procedures
developed by AISI which ex·
I'< ;:rv) I-L ","v
~
AUTOCAD Steel Construction. Presented
in the ASCII format for W, S,
tend the published UL fire Saves time doing detail draw·
M, HP and other common
resistive designs to other
possible rolled structural
- r-j- I - _,n
ings of structural steel shapes
in AutoCAD. Lists properties shapes and channels.
Available in U.S. customary
shapes and common protec· corresponding to data in the
most recent LRFD and ASD units or metric units. May be
tion material requirements.
Two 5·114" disks
1<1
,r
![ 1<1" ""~ manuals. Parametrically draws converted to Lotus 1·2·3 PRN
format.
& users manual $96 to scale the end, elevation and
plan views of common shapes. 3·112" or 5·114" disk $60
(sorry. no 3· tl2"
3· 112"or5· 114" disk $120
• Volume" Connections
is a companion and
extension to the AISC
Manual of Steel
Construction (both LRFD.
1st Edition. and ASD. 9th • Covers bolted
Edition). and welded
shear. moment .
• Contains examples and bracing
and information on steel connections in
connections not published applications not
anywhere else. treated in either
the ASD or LRFD
Manual of Steel
• Has practical and
economical examples of Construction.
complex connection
designs in both LRFD • FREE BONUSI
and ASD . An updated copy
of the AISC Code
of Standard
• Based on the latest
AISC LRFD and ASD Practice will be
specifications. sent with each
book.
•
Phone ___________________________________________ 312/670-5403
Check enc losed o Charge my 0 Visa 0 MasterCard
P1ease enclose remIttance
Acctl _____________________Explres _ _ No COD orders. Add S5 for UPS
25% DISCOUNT
fOR AISC MEMBERS Signature charge. Foreign orders S10
mlnlnum for shipping
1993 National Steel Construction
Conference Exhibitors
Amencan Galvolni.7crs Association........ .......... 221
(As of January 31 , 1993)
"JAPTcch. Inc. . ........ ....................... .. .._ ._.....__ ........... 31J7
•
Am. Inst. for Hollow Struct Sect,ons .............. 815/817/819/821 atlonallnstituteofSteel Detailing. ...... TBA
American Insbtute of Steel Construction, Inc. . ...... TBA NSS Industn('C! . ............ ........ 106
The Amcrican Punch Co ......... "" .......................................... ,...... 610 NucorCorpmahon ........................ ... 1:W4/R06/808/810/812
Ark..lns.lsSteell'roc(.'Ssing, Inc. ............................................... , ... 404 Peddingh''''C''rp ................ 311 /3 13/1 15/317/410/412/414/4 18
I Behri ngeT 5.,ws. Inc ... ' .,,,., ............................................... 828/ 830/ 832
icholJS j. Bouras . ............................................................ 207 / :lO6
Portland Bolt .............. . . ................ .... .............................. 121
Ram Anaiy"j'i ............................. .... .............. 220
CNA Insurance Co.. ................... ....................................... ,', TBA Rese,lrch Engin{'{'rs................................... .... ...... .._........ 511
CANA M Steel Corp............................................................. 605/704 St. Louis Screw & Bolt Co.............................................................. 52J
Dailo Selki Co., Ltd ............................................. 421 / 423/520/522 ServlCO Supply Co ......................................................................... 420
lA'Sign D.t. ... ................_.............. 210/212 / 214/216 SouthI:!m Co.lhngs, Inc ............_........................._.._ .......... 406
DogwoodTechnologlcs .............................................. 314/316 stet'l Solullons, Inc......... ....................................... ...515 /517
EL o Industries. Inc. .__..•.._ •... _ ................... ......... 204 Stt."CICad International .................. _ 505/507/604/606
Elite EquIpment, Inc. .. ...................................... 405/ 407/ 5001 /506 Structural SOfh...areCo............... . .............................. .. ......... I~
ITW Buildcx ....... ..... ......................................................... .. III Structural tecl Systems. Ltd. ...... ..... ........... •..................... 513
Kaltenbach ....... .. .............................................828/ &10/832 Towe Iron WorJ..s ...................... _............... . _........... 312
Lejeune Bolt Co. ... .... ..................................... ... TBA TradeARBED. ... .... ...... ................ ............................ .. ........ 305
The Lincoln ElcctficCo ............................................................... 217 J&M Turner. Inc.............................. .. .. ................ 305
Lohr Structural Fa~teners ,...................................................... 205/304 Voss Enginccring .......................................................................... 121
MetroSoft ........ ... ............. .............................................. 207 Weldod Tub< Co of America ............................... 815/817/819/821
Mid·South Bolt & Screw........ ...................................... 104 Westbrook EnglOeeringCo............._..... .. .......... 105
Modem Steel Con"tru tion.. . . ................... . . TBA Zentech ............... ,..... .. .............. .. ........ TBA
A complete new line of punches, dies, and shear ing and bending capabilities of United Steel Deck,
•
blades for Anglcline, Beamline and Portable Inc., can prOVide solutions to most decking needs.
punches is available from the American Pun h Co. Contact: United Steel Deck, Inc. (Nicholas j. Bouras,
Standa rd punches with matching dies are offered in Inc.), 475 Springfield Ave., Summit, Nj 07902-0662
round sizes from 118" 10 1 \02" diameter in \032" incre· (908) 277-1617; fax (908) 277·1619.
•C
ITW Buildex
Booth #6051704 Booth #111
anam Steel provides quality open web joists,
girders and trusses to fabricators from coast-to-
coast from its five North American plants. Develop-
A t this years SCC Show, the company will be
demonstrating the new Autotraxx Fastening Sys-
tem for metal decking. This system is de igned for at-
ment of its own state-of-the-art design and estimation taching deck to structural or deck to deck (stitch). Fas-
software programs enables Canam to assist engineers teners for this system are 10-14 x 74\" or 12-14 X 74\"
and customers in providing the most efficient and ICH Traxx 1 for deck to deck attachments and 12-24 x
economical roof and floor system. 7A\" ICH Traxx / 4 or 12-24 x lW' ICH Traxx /5 for deck
For a free 76-page catalog, contact: Sales Manager, to stmctu ral steel (up to In").
Canam Steel Corp., 2000 West Main St., Washington, Contact ITW Buildex, 1349 West Bryn Mawr Ave.,
M063090 (314) 239-6716. Itasca, IL 60143 (708) 595-3500; FAX (708) 595-3549.
•P
For information or to schedule a demonstration call galvanized to ASTM 6695. Diameters are $11", ¥.!", 7A\",
Design Data at (800) 443-0782 or (402) 476-8278. I", and 1 W' .
For more information contact: Lejeune Bolt 0.,
Dogwood Technologies 8330 West 220th St., Lakeville, M 55044-9106 (612)
462-5521; FAX (612) 469-5893.
Booth #314/316
rocedural Detailing System (POS) is an automated
structural steel detailing system operating under The Lincoln Electric Co.
U IX. Structural members are entered on a text input Booth #217
screen and are automa tica lly generated. I'DS details
beams, columns, horizontal and vertical bracing, girts,
purlins, lintels, door frames, and pan and grated stairs
T he Lincoln Electric Co. will feature the Inverter
V300 PRO, Pro-Cut 40 and inverter Racks at the
NSCC show. The portable Invertec V300 PRO is a 300
with breakovers and landings. A bill of material also amp arc we/ding power source utili7ing si ngle phase
is automatically created. An interactive CAD graphics or three phase input power to produce either constant
model and CNC download are available. current or constant voltage outputs. The Pro- ut 40 is
For more information, contact: Dogwood Technolo- a constant current, single range continu us plasma
gies, 420 Bearden Dr., Suite 100, Knoxville, TN 37919 cutting power source designed to be lightweight and
(800) 467-0096. easily portable.
For more information contact: The Lincoln Electric
Elite Equipment Co., 22801 5t. Clair Ave., Cleveland, OH 44117-1199
(216)481-8100.
Booth #405/407/504/506
• Positioners and Sub Arc Welding Systems, as well as a fasteners to be lubri ated and tested as matched as-
list of used steel fabricating equipment for sale. semblies to assure they will work together properly
Contact: Elite Equipment Inc., P.O. Box 3417, when shipped. Lohr's fasteners are domestically man-
Tustin, CA 92681 (714) 569-1050; FAX (714) 569-1009. ufactured/ lubricated and tested as pre-assembled sets l
•S
(BOO) 237-7059; FAX (314) 389-7510. of re-inputting the piece mark information for C C
tool programming. In addition, the program allows
the shop noor to communicate directly with the piece
mark status database for instantaneous production
Service Fastener Center status recording. And the productivity of every work-
Booth #420 station can be monitored on a real time basis.
ervice Supply Co., Inc., is a leading distributor of Contact: Richard Inserra, Steel Solutions Inc., 2260
a II types of fasteners for the steel construction in- Flowood Dr., P.O. Box 1128, Jackson, MS 39215-1128
dustry. The company has 44 service centers across the (601) 932-2760; FAX (601) 939-9359.
country. On exhibit at the NSCC will be the
company's complete line of structural products, in- Structural Software Co.
cluding tension control bolts manufactured by In-
fasco. Booth #108
For more information contact: Service Supply Co.,
Inc., 603 E. Washington St., Indianapolis, I 46206
(317) 638-2424; FAX (317) 634-9087.
A new Production Control program fr m Struc-
tural Software features a comprehenSive piece
and labor tracking system that follows every item in a
job through every phase of fabrication. The system
also generates detailed tracking reports and percent-
Southern Coatings, Inc. age completion bar graphs on the status of individual
Booth #406 pieces or of entire jobs and allows the user to see what
•
Zinc Rich Primer, Chemtec 608 Inorganic Zinc Rich Steel package, PC/PO Link and Inventory ontrol,
Primer and Dura-Pox 646 Epoxy Mastic High Build also offer money-saving potential.
system will be available at the NSCC show. For more information c ntact: Structural Software
For more information contact: Southern Coatings, Co., 5012 Plantation Road .E., P.O. Box 19220,
Inc., P.O. Box 160, Sumter, SC 29151 (BOO) 766-7070. Roanoke, VA 24019-1022 (703) 362-9118.
•
2598 (708) 673-8900; FAX (708) 673-1408.
Booth #513
D
J&M Turner
Booth #107
irect Tension Indicators (Ons) from J&M Turner
are used to assure proper bolt tensions according
ing Co., 23501 Mound Road, Warren, MI 48091 (313)
759-3100; FAX (313) 759-3106.
Yamazen Inc.
Booth #421 /423/520/522
•
to the RCSC Specifications for Structural Joints using
ASTM A325 or A490 bolts. OTIs are now made under
an improved production quality assurance program
D aito 5eiki Co. will introduce their line of CNC
drilling machines to the U.s. market at this
year's SCC show. On exhibit will be their 0 F 1000
that requires lot testing at every stage of production. CNC Structural Drilling Machine, which has the ca-
In addition, design improvements assure proper per- pacity of handling 40" wide by 16" high material. As
formance under field conditions. Also, each OTI is with all of the company's drilling machines, it features
marked with a lot number to allow traceability back to a fixed workpiece, traveling drill design. Each drill
the steel heat lot number. head is independently programmed to move on three
For more information contact: J&M Turner, 101 axes along the flanges
Crofton Dr., Pittsburgh, PA 15238 (412) 967-9302. or the web. This allows
the flange drills to NATIONAL STEEL
CONSTRUCTION
Voss Engineering move down the beam CONFERENCE
and drill all the flange
Booth 121
v
THE OHL' AU-SlfIV eOtl'flllHCl
holes in the pattern AHO TIIAOf SHOW IN THE U 5
oss Engineering will feature PTFE expansion without waiting for the
bearings at this year's NSCC show. The bearings web drilling to be com-
utilize Fiberlast and Sorbtex elastomeric pads as sup- pleted, increaSing both
port for the PTFE clement. These elastomeric materi- speed and accuracy.
als are designed to handle non-uniform loading con- For more informa-
ditions and vibration control. The company also will tion contact: Yamazen
display Neosorb AAsHTO-grade Neoprene pads and Inc., 735 East Reming-
slide bearings made with glass-filled PTFE. The com- ton Road, Schaumburg,
•
pany also will sponsor a seminar on the basic princi- IL 60173-5610 (708) 882-
ples of elastomeric bearing pads and PTFE expansion 8800; FAX (708) 882-
bearings. 4270.
For more information contact: Voss Engineering,
• What's in
a name?
I
• A comprehensive business insurance program
designed especially for AISC.
When you look closely at what a name Plus optional coverages such as inland marine,
like C A offers the American Institute of Steel business interruption and comm r ialumbrclla.
Construction, you'll find everything you need in Even eligibility f r a safety group dividend~
a comprehensive business insurance program And regardless of how mu h or how littl
for your business. covemge y u need, C A deli rs the kind of per-
This coverage is offered by the CNA In urance s nalized loss control services and responsive
Companies. C A offers you experience, stability, claims handling that no structuml te I fabricator
financial strength, and benefits that associations should be without.
just like AISC have been taking advantage of for C A, a mult~line insumnce group, has nearly
over 20 years. 100 years' experience, over $11 billion in revenue,
In fact, C A is the one name that offers you over $35 billion in assets, $5 billi n in stockholders'
a business insurance program endorsed with the eq uity and consis tently high ratings~'
AISC "Seal of Approval:' It's a comprehensive pro- Find out more about this custom business
gram that includes commercial property, commercial insurance program designed especia lly for AISC.
liability, commercial auto and workers' compensation. Call 1-800-CNA-6241.
CNA
For A1t the Commitment. You Mal<
n. CNA Insurance Compan... undefwntlng !hll program WIll vary according 10 tht CO\IeJaQI AlleHabie It'IIhIi eon',nen,aI U S only TheM comPMIINlnCluoe
TranlC)Ol1allOn Insurance Company. valley ForQe Inll./fance Company. Contlnenta, Casualty Company, NatIOnal flre InsuranceComrny
TranlCOtlilneolallnsufance COmpeny or ArneflCfln Casualty 01 Readlno. Pennavtll8nla. CNA PlazAlChIcaOO.IL 6068
01 Hartford
~...AISC 1993 Prize Bridge Competition
Rules •
Eligibility Entry Requirements
To be el igible. a bridge musl be buill of fabricaled All entries mUSI contain an enlry form. pholographs and a
slruclUml sleci. musl be localed wilhin Ihe Uniled Siaies written description of the project. A separate binder muse be
(defined as Ihe 50 Sillies. the District of Columbia. and all submined for each entry. No enlry free is required;
U.S. lerritories). and must have been completed and opened submission materials will not be returned. The u,e of any
to trarlic belween May I. 1988 and April 30, 1993. entry's submined data. detail and/or photograph, by AISC
shall be unrestricted. Note: Projects not receiving an award
slill may be used in Modern Steel COIIStll/ctlO1I magaline or
olher AISC marketing materials.
Judging Criteria
Judging will be based upon aesthetics. economics. design I. EntryJorm ' The complete and accurate entry form and
and englneenng solutions. Quality of presentations. though one copy must be enclosed.
not a criterion. is Imponant.
2. PIIO(()wophs ' A minimum of four profeSSional quality
8x 10 color prints of various views shOWing the enllre
Award Categories bridge. mcluding abutments as well as selecled delails. are
Entnes may be judged in one or more categorie" but can reqUired. 35 mOl slides are strongly recommended.
receive only onc award. Pholographs will not be returned.
Lo ng S pan One or more spans more than 400 n. in length. 3. DeScription : Explanation of design concept. problem,
and solutions. aesthetic studies. project economics and lilly
Medium Spa n, High Cleara nce Vertical clearance of 35 unique or innovalive aspect of the project. Include no
n . or more with longesl span bel ween 125 and 400 n. Ihan II x 17 drawings showing elevation. framing system
and typical details.
Medium Span, Low Clea rance Venical clearance less
than 35 ft. with longest span between 125 and 400 n .
Method of Presentation
S hort Span 0 single span greater than 125 ft. in length. Each entry should be submilled in an 811.!" x II" binder.
contaming transparent window sleeves for d"playing
Grade Separation Basic purpose is grade separation. In<cn; bac~ to bac~ . The entry form included In Ihe
brochure must be easily removable. so that Ihe
Elevated H ighway or Viadu ct Five or more spans. identification of Ihe entry can be concealed dunng Judging.
crossing onc or more traffic lanes.
• Entry Form
Enlry O.,C_ _ _ _ _ _ _ _ __
InnovativeConcepls______________________________________________
D~ i g n Firm : _______________________~~-------------------_
Addres" _ _ _ =::-_______________
5trtcl
--;:===::-_______= _______
Phone
•
Title
Consulting Firm (if any):. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _---,;:--_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __
Phone
Address: _ _--;:-_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _===::_-------__:;::_------
SI~1 Cilyand Stale :Up
Person to COOI3CI :_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _-,:,-;-_ _ _ _ _ _ __
Tille
Genera l Contracling Firm: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _-;;;:=_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __
Phone
Address: _ _~~----------------===::_-------__:;::_------
5trttl City and Siale ZIP
Person (0 contaCI: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _-,:C;C_ _ _ _ _ _ __
Tille
Steel Fabricating Firm:_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _;;;::::::-_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __
Pho""
Address: _ _--;:--,_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _===::_-------__:;::_------
SIJttI Cit)' and Siale ZIP
Persontocontact:. ___________________________________ ~,_;_-- ______
Tille
Steel Erecting Firm :_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _--;;~:_------------------
Phone
Address: _ _----;;,----,----_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _--;:===:_--------:;c::--------
Sttttl Cit)' and Stat~ ZIP
Pe~o nt ocon t ac t:: __________________________________________________________________ ~~-------- _____
Title
Owner::________________________________________________~~------------------------------------
Phone
Add ress: _ _--;:-=_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _=::-:::;-;;:::::-_______--:;:::-______
Stret:t City and Slale ZIP
Pe~ontocontacl:: ______________________________________________________________________ ~~ _______________
Title
Title
Finn:____________________________________________~~-------------------------------------
Ph",~
Addre":_ _--;:--,_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _====----------:;:::-------
SlfC~t City and Slat~ 7jp
STEEL MARKETPLACE
Help Wanted--Draftspeople ~ Free Software Catalog •
Multj·location structural stee l fabricator located in the beautifu l For Structural Steer Oetaifers & Fabricators
Ozarks of Missouri is seeking experienced struct.ural steel Quality. Affordable - PC Softwa re
drafts pcople. Must be self motivated and want a chal lenging job. Steel Detailing with or wloul8 CAD inwrface, 10 integrated calculator
PDS CAD experience a plus. We offer a competitive salary with
benefits
I programs designed for dctailers & checkers, job estimatee. bills of
maleriaJs, ienst h cutting lists, shipping lists & nesling, residentml and
. light commerCial structural design. analysis ofcontinuOU 8 beams (steel,
Please s ubmit resume with references to: wood or concrete ), finite elemenl8nalysis. project management, accounting.
D ' St I I NES, Inc., P.O. Box 2014, EI Segundo, CA 90245
oong ee , nco 800-637-16n (phone). 31()'546-7158 (fax )
2125 N. Golden
Springfield, MO 65803
Save S - Buy Used - All Guaranteed
Elite beam roping rnachuw' E~f 204()'3
Peddmgh u. AnKle ma.ter C19831
GE Cont rol. 6 x t3. 1.02 50' ro n ... Advertiser's Index
F. bnh ne FS IOIO Shenf 10· Angle, 10· Channel, 14 n ata
Kah.enba ch Sa w HOM 1300, 17<l'" x 40 CAP ( 1975)
Trt nnJ aeger LKH 450 Saw 18 II 40 CAP wlConv
AISC Pri ze Bridge Competition ..................... 64-65
Whitney Beam Line 3 Stalom, 100 ton ea Mod. 790 AISC Software ....................................................... 56
RoJa r M-30 Bea m f ace Mill
Vem et 6x6x 1.2 Angle Lmel Not. NC, Arkansas Steel Process ing ................................... 20
DoAII Vertical Band Saw TF24SA 1'I1l24 x 24
Lam maMII/j:Onlll '-'J CAP Bethlehem Steel Corp ...................................... 12-13
Call or fa..: (or complete lilt of " WI. IrGn wo rkef'll .• he8r11 and bnke.: Nicho las J. Bouras ............................................... CII
We.tbrook Engineerin,Co.• 2.6301 Mo und Road, w.rre~. MI <&8092 CNA Insurance .....,..... ,.....,... ", ..." ...", ........ " ... ", .. ,63
Tel: 313·159-3I00or 1-IKIO-899-8182; ,.'AX: 3 13·159-3106
CANAM5teel .......................................................... 8
Central Steel Service ............................................. 55
Engineering Journal C happaral Steel ..................................................... 46
The only technical magazine in the United SLates devoted exclu- Comeq ..................................................................... 35
sively to the design of steel structures, the AISC Engineering
Journal provides structural engineers. a rchitects, fabricators and Computers & Structures, Ine ............................ ClV
educators with the latest infonnation on steel design. resea rch , Computer Detailing Co rp .................................... 35
and construction . Design Da ta .............................................................. 7
For a one·year. U.S . subscription, send $15 to: EJE ........................................................................... 36
American Institute of Steel Construction, lnc. (312) 670·2400
C .W.Y., Inc ............................................................. 24
P.O. Box 806276
Chicago, IL 60680-4124 Hilti ......................................................................... 29
Ind epend en ce Tube ............................................. 33
Steel Industry Software For IBM Compatibles Jobber Instruments ................................................ 25
Kenil wort h Steel .................................................... 39
Structural Steel Estimating Inventory Control
MDX ........................................................................ 42
Production Control Purchase Order
Plate Nesting Length Nesting Manual of Steel Construction- Volume 11.. ...... 57
Detail Drawing Log Rebar Processing Metrosoft ................................................................ 51
Slruct.uraJ Steel Advance Bill of Material Mid South Bolt ....................................................... 23
Romac Computer Services , Inc. National Steel Construction Conference ......14-1 7
P.O. Box 660, Lake City, TN 3n69 Omnilech ................................................................ 55
615-426-9634 FAX 615-426-6454 Optimale ................................................................. 42
Portland Bolt and Manufacturing ..................... .45
Ram Analysis Steel Design Software Rl5A ........................................................................ 36
Now, get S8EAM by Ram Analysis ror only $100, ~~ull reatured Ram Analysis ,...... ,... ", ..... ,....................... ,..... ,..... ,. 23
compoeltelnon-compoaite sinH'le beam de8i ~ a nd analysis sof\ware (LRFD Research Engineers ...... ,......... " ...... ,............... " ....... 5
or ASDJ. Easy·t.o-use with Wmdows graphIca l inte rface. Full 90 day money
back guarantee. SCADA Software .................................................. 44
Also available. the RAMSTEEL Integrated Structural Software Syste m. 55DCP ..................................................................... 33
Fully mtegrated a nalysis, design and dra ftm g or steel beams, joists,
columns. and baseplates. 51. Louis Screw & Bolt ........................................ ..43
Ram Analysis Southern Coatings ................................................ 28
5315 Avenida Encinas, Suite M, Carlsbad, CA 92008 Steel Deck Ins litute ............................................ III
Phone: 8001726-7789
Fax orders: 619/431 -5214 Steel Joist Ins titute ................................................. 22
•
Whitefab ................................................................. 37
For rate and placement information, call:
Greg Poland at (708) 679-1100.
Yamazen Inc ....................... " ... " ................. ...." .. ". 11 J
Or (ax him a note at (708) 679·5926.
ORDER NAME
ADDRESS
COMPANY
CITY
YOUR STATE ZIP PHONE
SOFTWARE METHOD OF PAYMENT:
Institute ----_... .
~t...~1