ID Task Name Duration Start Finish Qtr 4, 2015 Qtr 1, 2016

Nov Dec Jan Feb Mar


1 1 Network Monitoring System 108 days? Fri 12/4/20 Thu 4/8/21
2 1.1 Administration 49 days? Fri 12/4/20 Fri 1/29/21
3 1.1.1 PO Release term 1 1 day Fri 12/4/20 Fri 12/4/20
4 1.1.2 PO Release term 2 1 day Thu 12/17/20 Thu 12/17/20
5 1.1.3 PO Release term 3 1 day Wed 1/13/21 Wed 1/13/21
6 1.1.4 Handover credit Bill from MMK to Everin Jan 19 days? Fri 1/8/21 Fri 1/29/21
2021-Dec 2021
7 1.2 Preparing Material 36 days? Tue 12/22/20 Sun 1/31/21
8 1.2.1 Import Netbiter 31 days Mon 12/7/20 Mon 1/18/21
9 1.2.2 Purchase Devices Remote IO 14 days? Sat 1/9/21 Mon 1/25/21
10 1.2.3 Purchase Sensor Temp, DC to DC, and the other 14 days? Sat 1/9/21 Mon 1/25/21
accssories
11 1.2.4 Fabrication Panel 14 days Tue 1/19/21 Wed 2/3/21
12 1.2.5 Wiring Panel and testing before installation 10 days? Thu 2/4/21 Wed 2/17/21
13 1.3 Installation, Activation, Credit (Pulsa) 51 days? Tue 2/9/21 Thu 4/8/21
14 1.3.1 Jabodetabek Area (17 ) 28 days? Wed 2/10/21 Sat 3/20/21
15 1.3.1.1 JK-2276-H-B 2 days? Wed 2/10/21 Thu 2/11/21

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 1
ID Task Name Duration Start Finish Qtr 4, 2015 Qtr 1, 2016
Nov Dec Jan Feb Mar
16 1.3.1.2 JK-0482-M-B 2 days? Fri 2/12/21 Sat 2/13/21
17 1.3.1.3 JK-0485-M-B 2 days? Mon 2/15/21 Tue 2/16/21
18 1.3.1.4 JK-0614-M-B 2 days? Wed 2/17/21 Thu 2/18/21
19 1.3.1.5 JK-0823-M-B 2 days? Fri 2/19/21 Sat 2/20/21
20 1.3.1.6 JB-0704-T-B 2 days? Mon 2/22/21 Tue 2/23/21
21 1.3.1.7 JK-2037-M-B 2 days? Wed 2/24/21 Thu 2/25/21
22 1.3.1.8 JK-0804-M-B 2 days? Fri 2/26/21 Sat 2/27/21
23 1.3.1.9 JK-0942-M-B 2 days? Mon 3/1/21 Tue 3/2/21
24 1.3.1.10 JK-0524-M-B 2 days? Wed 3/3/21 Thu 3/4/21
25 1.3.1.11 JK-0596-M-B 2 days? Fri 3/5/21 Sat 3/6/21
26 1.3.1.12 JK-0981-M-B 2 days? Mon 3/8/21 Tue 3/9/21
27 1.3.1.13 JK-0940-M-B 2 days? Wed 3/10/21 Thu 3/11/21
28 1.3.1.14 JK-0692-M-B 2 days? Fri 3/12/21 Sat 3/13/21
29 1.3.1.15 JK-0368-M-B 2 days? Mon 3/15/21 Tue 3/16/21
30 1.3.1.16 JK-0315-M-B 2 days? Wed 3/17/21 Thu 3/18/21
31 1.3.1.17 JK-0727-M-B 2 days? Fri 3/19/21 Sat 3/20/21

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 2
ID Task Name Duration Start Finish Qtr 4, 2015 Qtr 1, 2016
Nov Dec Jan Feb Mar
32 1.3.2 Makasar Area (5) 10 days? Mon 3/22/21 Thu 4/1/21
33 1.3.2.1 SN-0003-TS 2 days? Mon 3/22/21 Tue 3/23/21
34 1.3.2.2 MKS_01I0001 2 days? Wed 3/24/21 Thu 3/25/21
35 1.3.2.3 SN-0009-T-S 2 days? Fri 3/26/21 Sat 3/27/21
36 1.3.2.4 MSC133 / SN-0042-T-S 2 days? Mon 3/29/21 Tue 3/30/21
37 1.3.2.5 SN-0172-T-B 2 days? Wed 3/31/21 Thu 4/1/21
38 1.3.3 Medan Area (2) 4 days? Fri 4/2/21 Tue 4/6/21
39 1.3.3.1 SU-0052-T-S 2 days? Fri 4/2/21 Sat 4/3/21
40 1.3.3.2 SU-0056-T-S 2 days? Mon 4/5/21 Tue 4/6/21
41 1.3.4 Mojokerto Area (1) 2 days? Tue 2/9/21 Wed 2/10/21
42 1.3.4.1 JI-0442-M-B 2 days? Wed 4/7/21 Thu 4/8/21
43 1.4 ATP NMS Batch 2 49 days? Wed 2/10/21 Wed 4/7/21
44 1.4.1 Jabodetabek Area (17 ) 33 days? Wed 2/10/21 Fri 3/19/21
45 1.4.1.1 JK-2276-H-B 2 days? Wed 2/10/21 Thu 2/11/21
46 1.4.1.2 JK-0482-M-B 2 days? Fri 2/12/21 Sat 2/13/21
47 1.4.1.3 JK-0485-M-B 2 days? Mon 2/15/21 Tue 2/16/21

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 3
ID Task Name Duration Start Finish Qtr 4, 2015 Qtr 1, 2016
Nov Dec Jan Feb Mar
48 1.4.1.4 JK-0614-M-B 2 days? Wed 2/17/21 Thu 2/18/21
49 1.4.1.5 JK-0823-M-B 2 days? Fri 2/19/21 Sat 2/20/21
50 1.4.1.6 JB-0704-T-B 2 days? Mon 2/22/21 Tue 2/23/21
51 1.4.1.7 JK-2037-M-B 2 days? Wed 2/24/21 Thu 2/25/21
52 1.4.1.8 JK-0804-M-B 2 days? Fri 2/26/21 Sat 2/27/21
53 1.4.1.9 JK-0942-M-B 2 days? Mon 3/1/21 Tue 3/2/21
54 1.4.1.10 JK-0524-M-B 2 days? Wed 3/3/21 Thu 3/4/21
55 1.4.1.11 JK-0596-M-B 2 days? Fri 3/5/21 Sat 3/6/21
56 1.4.1.12 JK-0981-M-B 2 days? Mon 3/8/21 Tue 3/9/21
57 1.4.1.13 JK-0940-M-B 2 days? Wed 3/10/21 Thu 3/11/21
58 1.4.1.14 JK-0692-M-B 2 days? Fri 3/12/21 Sat 3/13/21
59 1.4.1.15 JK-0368-M-B 2 days? Mon 3/15/21 Tue 3/16/21
60 1.4.1.16 JK-0315-M-B 2 days? Wed 3/17/21 Thu 3/18/21
61 1.4.1.17 JK-0727-M-B 2 days? Fri 3/19/21 Sat 3/20/21
62 1.4.2 Makasar Area (5) 9 days? Mon 3/22/21 Wed 3/31/21
63 1.4.2.1 SN-0003-TS 1 day? Mon 3/22/21 Mon 3/22/21

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 4
ID Task Name Duration Start Finish Qtr 4, 2015 Qtr 1, 2016
Nov Dec Jan Feb Mar
64 1.4.2.2 MKS_01I0001 1 day? Wed 3/24/21 Wed 3/24/21
65 1.4.2.3 SN-0009-T-S 1 day? Fri 3/26/21 Fri 3/26/21
66 1.4.2.4 MSC133 / SN-0042-T-S 1 day? Mon 3/29/21 Mon 3/29/21
67 1.4.2.5 SN-0172-T-B 1 day? Wed 3/31/21 Wed 3/31/21
68 1.4.3 Medan Area (2) 3 days? Fri 4/2/21 Mon 4/5/21
69 1.4.3.1 SU-0052-T-S 1 day? Fri 4/2/21 Fri 4/2/21
70 1.4.3.2 SU-0056-T-S 1 day? Mon 4/5/21 Mon 4/5/21
71 1.4.4 Mojokerto Area (1) 1 day? Wed 4/7/21 Wed 4/7/21
72 1.4.4.1 JI-0442-M-B 1 day? Wed 4/7/21 Wed 4/7/21

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 5
Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Ju

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 6
Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Ju

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 7
Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Ju

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 8
Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Ju

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 9
Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Ju

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 10
Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct No

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 11
Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct No

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 12
Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct No

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 13
Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct No

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 14
Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct No

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 15
Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 16
Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 17
Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 18
Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 19
Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 20
Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 21
Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 22
Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 23
Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 24
Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 25
2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Se

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 26
2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Se

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 27
2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Se

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 28
2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Se

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only

Page 29
2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Se

Task External Tasks

Split External Milestone

Milestone Deadline

Summary Path Predecessor Milestone Task

Project Summary Path Predecessor Summary Task

Inactive Task Path Predecessor Normal Task

Project: Time Schedule EMS 251 Inactive Milestone Path Driven Successor Milestone Task
Date: Mon 1/25/21 Inactive Summary Path Driven Successor Summary Task

Manual Task Path Driven Successor Normal Task

Duration-only Critical

Manual Summary Rollup Critical Split

Manual Summary Progress

Start-only Manual Progress

Finish-only