You are on page 1of 3

LIQUIDATED DAMAGES

LIQUIDATED DAMAGES BACKGROUND (c) The amount payable under


this clause 11.6 will be a debt
OR PENALTY? In June 1999 the State of
due from the Contractor to the
Tasmania and Leighton
Nick Rudge Principal’
Contractors Pty Ltd (Leighton)
Sebastian Rudkin entered into a project deed for RELEVANT LAW
Leighton to design, construct
Allens Arthur Robinson Referring to Clydebank
and maintain (for 10 years) 13.65
Engineering and Shipbuilding
kilometres of new highway to
Co.2 Chief Justice Cox stated
be incorporated into the Bass
that the essence of a penalty is
Highway comprising of two
payment of monies stipulated as
sections called the Westbury
in terrorem of the offending party
Bypass and the Hagley Bypass.
and that the essence of liquidated
When construction was not damages is a genuine covenanted
completed by the stipulated date, pre-estimate of damage. Whether
and according to the liquidated a stipulated sum is a penalty, or
damages provisions of the project liquidated damages, is a question
deed, Leighton paid $1,832,000 of construction to be decided
to the Tasmanian Government. upon the terms and inherent
When this and other matters circumstances of each particular
became the subject of litigation, contract judged at the time of the
the court had to consider making of the contract, not at the
whether the sum stipulated in time of the breach.3
the provision was a legitimate
Chief Justice Cox quoted Mason
liquidated damage or a penalty.
and Wilson in AMEV-UDC
The court found the sum to be a
Finance4 where they referred
penalty.1
to the ‘landmark decisions’ of
THE DAMAGES PROVISION Clydebank and Dunlop Pneumatic
Tyre Co5 and said: ‘an agreed sum
The issue relevant to this decision
is a penalty if it is “extravagant,
involved the validity of the
exorbitant or unconscionable”’.
liquidated damages provisions in
the project deed. Again, quoting AMEV-UDC
Finance 6:
Clause 11.6 of the project deed
provided: ‘The test to be applied is one
of degree and will depend on
‘ (a) If the Date of Construction
a number of circumstances,
Completion has not occurred
including (1) the degree of
by the Date for Construction
disproportion between the
Completion, the Contractor
stipulated sum and the loss
must pay liquidated damages at
likely to be suffered by the
the rate of $8,000 for every day
plaintiff, a factor relevant to the
after the Date for Construction
oppressiveness of the term to
Completion until the Date of
the defendant, and (2) the nature
Construction Completion or this
of the relationship between the
Deed is terminated, whichever is
contracting parties, a factor
first.
relevant to the unconscionability
(b) The amount referred to of the plaintiff’s conduct in
in clause 11.6(a) is a genuine seeking to enforce the term.’
pre-estimate of the Principal’s
Chief Justice Cox thought it a fair
damages if the Contractor
observation that in this case the
does not achieve Construction
nature and relationship between
Completion by the Date for
a state and a large corporation,
Construction Completion.
such as Leighton, did not suggest
any relevant imbalance in
bargaining power.

32 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #100 JANUARY/ FEBRUARY 2005


CALCULATING LIQUID ‘Conceptually I do not think that it Chief Justice Cox took the
DAMAGES? is correct to say that public works view that the estimate ...
because they may not yield a cash
The sum of $8,000 per day was not a genuine pre-
flow, cannot result in damages
for liquidated damages was, to the state or public authority estimate of the likely
according to the project director, if delay in construction occurs. damage to the State
calculated by having regard to the At least in some instances, an
following aspects of the project: appropriate measure of liquidated
• daily rates of the principal, damages is the cost of capital tied
principal’s representative, project up for the period of delay. I regard
director and the principal’s site it as an inadequate answer, in
representative (calculated on a the case of public work, to say
six-day week); that if the work were delayed
say six months, no damage
• administrative aspects such is suffered, and no liquidated
as OH&S, secretarial and legal
damages could be validly agreed
services; and
because there was no delay in
• site vehicles, site running receipt of cash flow, and there
expenses, travel and was mere deferment of a planned
accommodation. recoupment of capital and
Chief Justice Cox referred to interest costs over time.’
the annual calculations for the DECISION
principal, project director and
principal’s representative and In this case, Chief Justice Cox
considered that the respective thought that the only estimate
annual rates of $360,000, that was made for the principal’s
$430,000 and $330,000, OH&S of loss was the direct costs
$2400 per week and an allowance of supervising an over-run
of two hours of legal advice contract and it was the court’s
per day was total conjecture. view that those costs were
When it was considered that the extravagant, exorbitant and totally
principal’s representative had a disproportionate to the likely
number of other projects under actual costs anticipated to be
his scope of responsibilities, and incurred.
that the other roles had been Chief Justice Cox also stated that,
calculated on an annual basis, as the cost of the project was fully
the charge-out rates for all other funded by the Commonwealth
personnel whose services might Government, the State was not
be required if the contract overran exposed to either its capital cost
were extremely high, extravagant or the costs incurred after the
and speculative. date for construction completion.
The fact that the project was a Chief Justice Cox took the view
public utility with no anticipation that the estimate of $8,000 for
of a loss of revenue by reason of each day of delay was not a
the delay is not in itself a proper genuine pre-estimate of the likely
reason for claiming that the State damage to the State resulting
could suffer no damage other from the late opening of the
than the direct costs itemised. bypass and, as a result, was
Chief Justice Cox quoted Cole unconscionable.
in Multiplex Constructions Pty v The court ordered the State to
Abgarus Pty Ltd 7 and stated: repay the sum of $1,832,000
deducted as liquidated damages.

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #100 JANUARY/ FEBRUARY 2005 33


... any entity needs to be FUTURE CONSIDERATIONS REFERENCES
very careful to ensure its Chief Justice Cox’s decision 1. State of Tasmania v Leighton
estimate is a genuine pre- highlights the difficulty a Contractors Pty Ltd (No.3) [2004]
estimate government entity, as a principal, TASSC 132 (16 November 2004)
may have in ascertaining a (Cox CJ).
liquidated damages sum that is a 2. Clydebank Engineering and
genuine pre-estimate of its loss. Shipbuilding Co v Don Jose
Where the project is in fact being Ramos Yzquierdo y Castaneda
entirely funded by another tier of [1905] AC 6.
government, that problem will
be magnified. If the project is not 3. Public Works Commissioner v
being funded from elsewhere, the Hills [1906] AC 368 and Webster v
cost of the capital tied up by the Bosanquet [1912] AC 394.
delay, on the current authorities 4. AMEV-UDC Finance Ltd v
would be a good place to start Austin & Anor (1986) 162 CLR 170
in ascertaining the liquidated at 198.
damages sum. In relation to other
expenses or costs that would be 5. Dunlop Pneumatic Tyre Co Ltd
incurred as a result of the delay, v New Garage and Motor Co Ltd
such as project management [1915] AC 79.
services, any entity needs to be 6. AMEV-UDC Finance Ltd v
very careful to ensure its estimate Austin & Anor (1986) 162 CLR 170
is a genuine pre-estimate of the at 193.
cost that would be incurred with
7. (1992) 33 NSWLR 504 at 518-
reference to the specific project.
519.
The decision, including the
liquidated damages issue, is
being appealed.
This article first appeared in
Allen Arthur Robinson’s Focus:
Construction January 2005.
Reprinted with permission.

34 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #100 JANUARY/ FEBRUARY 2005

You might also like