The court considered whether liquidated damages stipulated in a contract between the State of Tasmania and a construction company were a legitimate liquidated damage or an unenforceable penalty.
The contract stipulated liquidated damages of $8,000 per day for delays in completing highway construction by the specified date. When construction was delayed, the company paid over $1.8 million in liquidated damages under protest.
The Chief Justice found the $8,000 per day sum to be a penalty rather than a genuine pre-estimate of damages for two reasons: 1) It was disproportionate to the likely losses of delayed capital expenditure and administrative costs cited by the state, and 2) It did not represent a reasonable pre-
The court considered whether liquidated damages stipulated in a contract between the State of Tasmania and a construction company were a legitimate liquidated damage or an unenforceable penalty.
The contract stipulated liquidated damages of $8,000 per day for delays in completing highway construction by the specified date. When construction was delayed, the company paid over $1.8 million in liquidated damages under protest.
The Chief Justice found the $8,000 per day sum to be a penalty rather than a genuine pre-estimate of damages for two reasons: 1) It was disproportionate to the likely losses of delayed capital expenditure and administrative costs cited by the state, and 2) It did not represent a reasonable pre-
The court considered whether liquidated damages stipulated in a contract between the State of Tasmania and a construction company were a legitimate liquidated damage or an unenforceable penalty.
The contract stipulated liquidated damages of $8,000 per day for delays in completing highway construction by the specified date. When construction was delayed, the company paid over $1.8 million in liquidated damages under protest.
The Chief Justice found the $8,000 per day sum to be a penalty rather than a genuine pre-estimate of damages for two reasons: 1) It was disproportionate to the likely losses of delayed capital expenditure and administrative costs cited by the state, and 2) It did not represent a reasonable pre-
LIQUIDATED DAMAGES BACKGROUND (c) The amount payable under
this clause 11.6 will be a debt OR PENALTY? In June 1999 the State of due from the Contractor to the Tasmania and Leighton Nick Rudge Principal’ Contractors Pty Ltd (Leighton) Sebastian Rudkin entered into a project deed for RELEVANT LAW Leighton to design, construct Allens Arthur Robinson Referring to Clydebank and maintain (for 10 years) 13.65 Engineering and Shipbuilding kilometres of new highway to Co.2 Chief Justice Cox stated be incorporated into the Bass that the essence of a penalty is Highway comprising of two payment of monies stipulated as sections called the Westbury in terrorem of the offending party Bypass and the Hagley Bypass. and that the essence of liquidated When construction was not damages is a genuine covenanted completed by the stipulated date, pre-estimate of damage. Whether and according to the liquidated a stipulated sum is a penalty, or damages provisions of the project liquidated damages, is a question deed, Leighton paid $1,832,000 of construction to be decided to the Tasmanian Government. upon the terms and inherent When this and other matters circumstances of each particular became the subject of litigation, contract judged at the time of the the court had to consider making of the contract, not at the whether the sum stipulated in time of the breach.3 the provision was a legitimate Chief Justice Cox quoted Mason liquidated damage or a penalty. and Wilson in AMEV-UDC The court found the sum to be a Finance4 where they referred penalty.1 to the ‘landmark decisions’ of THE DAMAGES PROVISION Clydebank and Dunlop Pneumatic Tyre Co5 and said: ‘an agreed sum The issue relevant to this decision is a penalty if it is “extravagant, involved the validity of the exorbitant or unconscionable”’. liquidated damages provisions in the project deed. Again, quoting AMEV-UDC Finance 6: Clause 11.6 of the project deed provided: ‘The test to be applied is one of degree and will depend on ‘ (a) If the Date of Construction a number of circumstances, Completion has not occurred including (1) the degree of by the Date for Construction disproportion between the Completion, the Contractor stipulated sum and the loss must pay liquidated damages at likely to be suffered by the the rate of $8,000 for every day plaintiff, a factor relevant to the after the Date for Construction oppressiveness of the term to Completion until the Date of the defendant, and (2) the nature Construction Completion or this of the relationship between the Deed is terminated, whichever is contracting parties, a factor first. relevant to the unconscionability (b) The amount referred to of the plaintiff’s conduct in in clause 11.6(a) is a genuine seeking to enforce the term.’ pre-estimate of the Principal’s Chief Justice Cox thought it a fair damages if the Contractor observation that in this case the does not achieve Construction nature and relationship between Completion by the Date for a state and a large corporation, Construction Completion. such as Leighton, did not suggest any relevant imbalance in bargaining power.
32 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #100 JANUARY/ FEBRUARY 2005
CALCULATING LIQUID ‘Conceptually I do not think that it Chief Justice Cox took the DAMAGES? is correct to say that public works view that the estimate ... because they may not yield a cash The sum of $8,000 per day was not a genuine pre- flow, cannot result in damages for liquidated damages was, to the state or public authority estimate of the likely according to the project director, if delay in construction occurs. damage to the State calculated by having regard to the At least in some instances, an following aspects of the project: appropriate measure of liquidated • daily rates of the principal, damages is the cost of capital tied principal’s representative, project up for the period of delay. I regard director and the principal’s site it as an inadequate answer, in representative (calculated on a the case of public work, to say six-day week); that if the work were delayed say six months, no damage • administrative aspects such is suffered, and no liquidated as OH&S, secretarial and legal damages could be validly agreed services; and because there was no delay in • site vehicles, site running receipt of cash flow, and there expenses, travel and was mere deferment of a planned accommodation. recoupment of capital and Chief Justice Cox referred to interest costs over time.’ the annual calculations for the DECISION principal, project director and principal’s representative and In this case, Chief Justice Cox considered that the respective thought that the only estimate annual rates of $360,000, that was made for the principal’s $430,000 and $330,000, OH&S of loss was the direct costs $2400 per week and an allowance of supervising an over-run of two hours of legal advice contract and it was the court’s per day was total conjecture. view that those costs were When it was considered that the extravagant, exorbitant and totally principal’s representative had a disproportionate to the likely number of other projects under actual costs anticipated to be his scope of responsibilities, and incurred. that the other roles had been Chief Justice Cox also stated that, calculated on an annual basis, as the cost of the project was fully the charge-out rates for all other funded by the Commonwealth personnel whose services might Government, the State was not be required if the contract overran exposed to either its capital cost were extremely high, extravagant or the costs incurred after the and speculative. date for construction completion. The fact that the project was a Chief Justice Cox took the view public utility with no anticipation that the estimate of $8,000 for of a loss of revenue by reason of each day of delay was not a the delay is not in itself a proper genuine pre-estimate of the likely reason for claiming that the State damage to the State resulting could suffer no damage other from the late opening of the than the direct costs itemised. bypass and, as a result, was Chief Justice Cox quoted Cole unconscionable. in Multiplex Constructions Pty v The court ordered the State to Abgarus Pty Ltd 7 and stated: repay the sum of $1,832,000 deducted as liquidated damages.
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #100 JANUARY/ FEBRUARY 2005 33
... any entity needs to be FUTURE CONSIDERATIONS REFERENCES very careful to ensure its Chief Justice Cox’s decision 1. State of Tasmania v Leighton estimate is a genuine pre- highlights the difficulty a Contractors Pty Ltd (No.3) [2004] estimate government entity, as a principal, TASSC 132 (16 November 2004) may have in ascertaining a (Cox CJ). liquidated damages sum that is a 2. Clydebank Engineering and genuine pre-estimate of its loss. Shipbuilding Co v Don Jose Where the project is in fact being Ramos Yzquierdo y Castaneda entirely funded by another tier of [1905] AC 6. government, that problem will be magnified. If the project is not 3. Public Works Commissioner v being funded from elsewhere, the Hills [1906] AC 368 and Webster v cost of the capital tied up by the Bosanquet [1912] AC 394. delay, on the current authorities 4. AMEV-UDC Finance Ltd v would be a good place to start Austin & Anor (1986) 162 CLR 170 in ascertaining the liquidated at 198. damages sum. In relation to other expenses or costs that would be 5. Dunlop Pneumatic Tyre Co Ltd incurred as a result of the delay, v New Garage and Motor Co Ltd such as project management [1915] AC 79. services, any entity needs to be 6. AMEV-UDC Finance Ltd v very careful to ensure its estimate Austin & Anor (1986) 162 CLR 170 is a genuine pre-estimate of the at 193. cost that would be incurred with 7. (1992) 33 NSWLR 504 at 518- reference to the specific project. 519. The decision, including the liquidated damages issue, is being appealed. This article first appeared in Allen Arthur Robinson’s Focus: Construction January 2005. Reprinted with permission.
34 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #100 JANUARY/ FEBRUARY 2005