F.F. CRUZ & CO., INC.

Civil & Geodetic Engineers • Constructors


800 EDSA, Quezon City
DAILY REPORT

PROJECT TITLE: ATI MANILA SOUTH HARBOUR EXPANSION PROJECT : EIB RECLAMATION DATE: Saturday, April 20, 2019
LOCATION: ATI MANILA SOUTH HARBOUR, MANILA DR. NO. DR-058

DETAILS OF WORK / ACTIVITY

START FINISH LOCATION DESCRIPTION OF WORK ISSUES/CONCERN

Spreading of sandfill materials at Engineering Island Basin (EIB)


7:00 PM ONGOING ONSHORE
jobsite.

Measuring of initial draft of Barge LCT308 loaded of sandfill


9:50 PM 10:20 PM RORO
materials with 3,167 cu. m.

10:40 PM 7:00 AM RORO Continuous unloading of sandfill materials from barge LCT308.

Prepared by: Reviewed by: Noted by:

Engr. Mark Angelo Fernandez


Engr. Victor Bartolome Engr. Raymond Fruto
Engr. Don Villanueva Engr. Joey Albert Cipriano
Field Engineer Project Engineer Project Manager

FFC-F-EIB-001 Revision: 0 Effective: 03-01-2019