F.F. CRUZ & CO., INC.

Civil & Geodetic Engineers • Constructors


800 EDSA, Quezon City
DAILY REPORT

PROJECT TITLE: ATI MANILA SOUTH HARBOUR EXPANSION PROJECT : EIB RECLAMATION DATE: Monday, March 18, 2019
LOCATION: ATI MANILA SOUTH HARBOUR, MANILA DR. NO. DR-026

DETAILS OF WORK / ACTIVITY

START FINISH LOCATION DESCRIPTION OF WORK ISSUES/CONCERN

7:00am 11:45am Offshore •Unloading of sandfill materials at Barge Benjamin.


• Final draft of Barge Benjamin.

7:00am 11:00am Tipsi Continuoua retouch of painting of I-beam, H-piles and C-channels.

On -going operational works of drag flow at SMC Area. Temporary


whole day near SMC Area unloaded sand were suctioned inside the basin.

1:47pm 7:00pm Offshore • Unloading of sandfill materials at Barge Urbiz Tondo.

Prepared by: Reviewed by: Noted by:

Engr. Marck Angelo Fernandez


Engr. Victor Bartolome
Engr. Raymond Fruto / Don Villanueva Engr. Joey Albert Cipriano
Field Engineer Project Engineer Project Manager

FFC-F-EIB-001 Revision: 0 Effective: 03-01-2019