Well N.

: Dated On : H) Pre_running in hole Check list - Build up Survey : Completion :


A) Administrative B) Certificate check list 0-check load cell Wieght on Surface 1- Deal with GC if flow push T\S up Or add more stem
1- Program With All Approval 1- vehicules paper 1- F/T Service Tool well head pressure 2- Fully open the valve when you get control of situstion
2- well schematic (checking) 2- PCE certificate 2- O reference (Gauges in Lock) (RTE for completion) 3- Stop 30 min befor change to shut-in pass (100% shut-in)
3- PTW open / Close 3- Fire extenguisher 3- Top T/S Measure the L & OD of S/T 4-clamps & barrier Tap
6- Ask for common tool 4- wire certificate 4- Pump Stuffing Box 5- Open oiler 5- Pull (Remove Clamps, Pooh 150 ft/min, record all times )
7- unit-pre job inspection 5- Crew Field Pass & HSE training 7- Close Manifold No Dynamic weight for backer - Temperature survey: 
8- work Order (rig or less) Q - Swabbing :- 3 1/2 tubing ( V= CP X L'    CP= 0.0087  V[BBL]) 1- Rih to 50 ft  wait 30 min or follow programme
Z) HSE : 1-H2S monitor 1 per person 1- Check (Flow line, Pit, caller, ) swabbing sheet 2- Max speed 30 ft/min 
2- wind socks 2 per unit 2- SIWHP (if 0 swab, if not F\Pit, if vacume wait = 0) 20 min 3- Record time each 150 ft till the end
3-Emergency escape per 2 3- Drift run + F collar stop Rih to 2100 Pooh to 2000 4- Wait 20 min before POOH at max 150 ft/min
C) Well schematic details 4- SCBA 2 per unit 45min 4- Find TOP (OF 800ft ) 200 ft Min up to 1500 ft Max D)- MPLT
1- Min ID + Depth 2.69'' 5- Fire extenguisher 2 per unit Pooh fast, Close B\O when start leak record Depth 1- Flwing drift 14- don’t use brake revers the handel
2- Deviation degree 6- Gaz test Monitor 1 per unit if flow increase install 16/64" choke and flow  2- enough stem wight & Lubricator lenght
3- Rigless or Completion 7- First aide & eyes wash Never leave Swbbing Down while fillupping & set Plug 3- 2 0 referance (encouder & counter depth)
4- Original RTE 8- Keep eyes on Sttufing leaks ground level O referance in workover 4- use R/B check Pin 9- reccord the length of MPLT
5- Tubing ID 1- BOP stradel L - Down Hole change: 4 Runs 5- Inform Control room for any well head changing
2- injec-sub & Glycol Pump Drift run (WHSIP,CISP to compare P after Perf) Fluid Level 6- open a well at 500 m 7- speed limit
7- Trssv Depth 3- Safety harness Set plug & inflow test 11- crane Zonal 12- connect encouder
8- Upper & Lower Completion 4- secured Scuffbuild Open SSD (fluid level Tu & Cis, HP calculation, expectation) 8- the flowing weight is ok (great then Su/W + wire W)
9- Well Head PCE Connection 5- Emergency contact 161 monitor pressure for each jar up in both tubing-caising 13- reduce revs to control speed of drum
10- PCE Adapter 6- 2 assombley piont Production SSD (No need to Eq-P),Curcilating SSD Eq-P 0,108 33 lbs 0,125 43 lbs
6- duel comletion (Don’t Pass Short Weg) 7- bankes man jaket M - Back to normal 3 Runs ` 10- Reduce the speed to 20 in completion
E) PCD check list: 8- Wheel Blockage Close SSD inflow test Retrieve plug S) gaz lift
1- check sizes According to the Schematic contact GC to open a well 1- find the fluid level calculat HP
2- Eq- system use Eq-probe Keep well production with Asphaten N - Tubin Perforator: 4 Runs 2- set plug prong & tool catch

3- check the selectivity Setting Probe Drift run (WHSIP,CISP to compare P after Perf) Fluid Level 3- NCP to fill up tubing or casing
4- File up the active area F/T tool Set the F coller or tubi stop 3ft below desired depth 4- equalize fluid to fluid, gaz to gaz 5- Open SSD
5- use RO lock with Kx valve C) Stuffing Box Inspect the Tubing should be clear from any flow coupling….. 6- the valve should be change from below to the top
6- use RB for first Run with risky status 1- Bop Plunger + packing Rih TP set J\D, J\Up to start Punshing Pooh by order to avoide traped pressure
G) Rig UP check list 2- Test stuffing box Pack off Circulation test Tubing casing Pull F-collar stop - D2-shifting tool: Otis 3.12'' Backer 2.89''
1- TBT + wind direction 3- Fill up Hoses By oil Get stuck for any reason J\D Shear 5/16 & Pooh 1- the D-2 Is selective tool use to model L SSD 
2- Ensure 2 Barrier 4- Sub Injection O - Collar stop DW 5 Runs 2- Jar up to open 31/2(171/8,SB+0.03)23/8(1511/16,+0.03)

3- Record WHP & Annulus Long term Stand by 1-Drift run 3-J/D to release from SSD with out shear Pin
4- confirm angle drive & splitter box 12 - Check laodcell 2- Set F-collar stop (Tubing Type) 4- run in invert position to close the sleeve
A) PCE rig up check list 12- check BOP 3-Rih slowly to 350 ft Using SB Pooh 50 -- Rih till set Q) Fishing steps
1- Gaz test (Leak, cellar) 13- Adjust Combigauge 4- Hand jar down few time Pooh 1- calculate the Top of wire 200 lbs tension on WC
7-lower the tool string to left Lub 2- Check Lib plugs 5- check set 100 ft up and down to tag 3- blind box to cut a wire from R/S 2- wire finder
9- Connect Manifold Use (thread chaser) 3- Tag line 6- DW hold pressure from below Max 1750 psi & (Bypass) 4- wire grape with correct size
4-Confirm Lib length Crane Zonal 6-wind direction ` 7- set 10 ft above F-collar stop Z - Rig down :
5- connect stuffing box hoses & Check o-ring Tu. Drift SB. NG.R 8- pull up to set, put 750 lbs to check set for 2 min 1- Ensure 2 barrier 5- Call Corrdinator & W/O
8- watch the top using crane (Power Lines) 23/8 1.90 1.820 1.700 9- hand jar up to shear 1/8 and 5/16 for w R\T 2- P/T cap & B/O the pressure & close a valve
10- Lubricator to be leveled with BOP To take O ref 1.995 1.875 1.822 10- to pull Equilize pressure Latch J\D Retrieve 3- Record WHP & Annulus 6- Close well door
H) Tool string check list 31/2 2.86 2.750 11- Retrieve F-collar stop
2.690 4- Declaration ( Moving or Material left on site)
1- check the OD of any new Items Add to T/S 2.991 2.810 2.756 P - Gauge Survey: Enough Libricator , Crane Zonal N test tool :
1-Deviation (F/D with P/R tool + Knuckle Joint + L-Jar Roller stem) 1- drift run 8- Remove all jars 1- check the correct size & TOF 3- make tention for while
2- (Pull or Set) C/W packing ( use Oil jar + Eq-System) 2- connect batteries record On Off times Y Tool : Use RS and SS to set and pull
9- Pass through WEG use F/D with all service tools 3- set 0 referance 10 min on surface
10- Asphaltene use upstrok jar 4- Max speed 150 ft/min 45 m/min
5- eash stop should be 15 or follow a programme
6- always wait 2 min for each change
7- casing static survey need DHCH & produce 24H & SN 24h
Perforator : Swabbing
check the bottom grab screw Max Pull 1400 to 1900
change BOP

Drift
Duel completion don’t pass the short

Gauges
Shut-in survey if there is leak not work
If swab leak don’t touch UMV in flowing survey (Well will die)
Well Number Date :
Annuler A WHP
Annuler B TRSSV P
SWR Flow Line P
Objective:

At well site long with Document


Well tech isolation / Sign PTW
TBT
Rig UP PCE
Open close well
Tool string configuration
M/U service tool
Open TRSSV from the surface
Stub on Lubricator
Open M/V + S/V P/T PCE 10 Min
RIH the service tool @
RIH Gauges S/N

Pass thruoght TRSSV


P/W H/W @
P/W H/W @
Tag to set Or Atdepth OR Tag to latch
Perform the operation @
PooH P/W H/W
OOH
Close S/V + M/V and B/O
Rig Down
Call Well tech to Hand over the well
Drift
Spring jar Well circulation Water inject Diesel inject

Asphaleten x x x
Salt x x
Restriction x
enountered Object x
P/W every
500 m

x
1
Date 11/11/2021
2 Well number 3 position
3 well type
4 Trssv
5 Connected Tool
6 File name
7 RIHed tool
8 depth
9 timing
10 Tagged depth
11 Report number
12 guagse seriel number
13 Gauge cutter size
14 tool string
15 WHP & annulurs
16 scanning rate
17 Arrivel/ departure
18 summery of operation
19 flowing / shutin / injecting
20 reporter name
21 RKB or THF
Daily tasks

Job email receiving Sall de control canal 1


Ejourney Ops canal 9
Lunch email
Report

On well site
Static shut in 24 hour (check if flowing no job)
uncontrolable Leak
Call HBNS operator revien
sign permit on arreval
sign permit on leaving
If well site supervisor don’t call operator
Call schlumberger Corrdinator

Weekly Tasks
right
SDP
Maintenance
[No Subject]

1 recipients
CC: recipientsYou More
BCC: recipientsYou
Show Details

FROM:

bh_hamou@yahoo.com

TO:

hamouda babahamou

Message starred

Sunday, December 9, 2012 6:31 PM

GDMC jobs procedure 

Preparation:
A)- equipments:
1- P/T Bop F/T
2- wire test log and certifications 
3- self make up tool string 
4- self 
H2S equipments:
    1- H2S monitors for each person 
    2- Emergency escape BA (15min)  for each person
    3- SCBA 2 in unit (45min) 
    4- wind socks  2 in the unit
     5-Fire extinguisher 2 in unit + check for update
 B)- safety meeting :
1- Persons Names 
2- Emergency contacts 160 or 112 ( fire, security, ambulance, H2S  hazards)
3- assembly point 
4- Wind directions
5- Pressure hazards
6- mechanical lifting hazard. ( not walk under loads,  Tag line to be use, nominated bankers man &
7- House keeping
8- Operation explanation

C)- Rigup:
1- leak gaz test H2S ( wind direction & 2 assembly point, SCBA )
2- record WHP annulars leak    
3- Assembly lubricators check o-rings ( should correctly tight rope socket)
4- lift BOP (F/T +Wire inside)
5-  rig up lubricator
6- connect tool muser & take 0 reference
7-open the well open M/V+ S/V,  close S/V + M/V 
8- P/T 10 min 
9- 250 H/m 

Shut in.         LIB or Bailer or Fluid level


Flowing        Gauges cutter 
Tag.          Don't pass short tubing 

A)-     Swabbing procedure: (conducted to remove the produced column water)


1-Check flow line to pit 
Check the cellar should be free for any sand or water or h2s or  what ever
2-Check the pit status 
    -Shut in wellhead pressure P record 
)
3-Close well from manifold to GC and open the well to pit and flow the well 
3- full well open check pressure 15 to 20 min should drop to 0 psi
4-rig up T/S ( r/s, kn-j, 10ft stem, M-J, running tool)
   - Tubing check  (drift)
5- Set the tubing stop or F collar stop rih to 2100 static W pooh to 2000 and set (Rih loss weight to
5-find the top Of the fluid 
6- 200 ft as max amount in first 76 m  up to 1500 as maximum depth 
- start pooh fast 
   - swabbing record sheet ( top of fluid )
Open the bleed off valve when start close record and flow to the pit
7- add all the depth and calculate the volume
3 1/2 V= CP X L'    CP= 0.0087  V[BBL]
- If WHFP>10 flow to pit to observe increase or decrease if increase install 16/64" choke and flow 
- If the pressure decrease wait till FWHP=0 and continue swabbing 
Note : not leave the swabbing tool while fill upping the tubing 
            Use plug before to start fill up to avoid any problems 
Light fluid 200 to 400
Heavy fluid 100 to 200

B)-      Gauge survey:  Conducted to identify ( SBHP, FBHT, SBHT,.....)


- static survey
- build up survey
- temperature survey

Gauges , batteries clamps, barrier tap.


1- drift run 

- static survey: 
 .  connect the gauges record power on off, in lib time
 . set o ref, 
 . Open swab Wait 10 min in Lib
 . Max speed 150 ft/min ~ 45 m/min
 . Each station stop should kept for 15 min or flow programme
 . Last stop should be 30 min 
 . Always wait 2 min for each change ( lib, B/O, at surface)
 . Rig down 
           Note 1: casing static survey is required to down hole change ( isolate tubing and  open sleeve

 - build up survey: 
 .  connect the gauges record power on off, in lib time
 . set o ref, 
 . Open swab and Wait 10 min in Lib
 . Watch the weight due flow rate
 . If flow push the T/S up confirm with GC to reduce the flowing rate Or add more stem weight 
 . fully open the wing valve once you get control of situation 
 . Max speed 150 ft/min ~ 45 m/min
 . follow the stops station as per programme
 . 30 min before change to shut-in the well
 . Clamps & barrier tap
 . Make sure that the well is 100 % is shut-in 
 . Pull : ( remove clamps, pooh 150 ft/min, record all times)
 . Rig down

- temperature survey: 
 .  connect the gauges record power on off, in lib time
 . set o ref, 
 . Open swab Wait 10 min in Lib
 . Rih to 50 ft  wait 30 min or follow programme
 . Max speed 30 ft/min 
 . Record time each 150 ft hh.mm.ss until requested depth 
 . Wait 20 min before POOH at max 150 ft/min
 . Always wait 2 min for each change ( lib, B/O, at surface)
 . Rig down 

C):- Collar stop & DW plug : collar stop use to prevent tool from drooping down hole ( swabbing, tu
   -    F collar stop EU & NU tubing (DW)
Check the size and tubing type from well schematic 
Check f collar stop condition
Rih slowly to 350 ft using SB or C1 aluminium pin (don't use c1)
Pooh slowly 50ft
Rih slowly until stop in the groove 
Hand Jar down few time and pooh
Pooh 100 ft and rih to check set
Run slowly desired depth pickup to trip the spring go to the position jar down to lock and shear
to pull use RB land on F collar stop jar up and pooh
     -  Tubing stop.   New vam family 
Run and pull SB 
Run slowly desired depth overrun go to the position or overpull to reposition jar down to lock and
Latch with SB to pull jar down and pooh

DW plug    ??? Hold pressure from below max 1750 psi & allows pass pressure from above??
Check the size as per well schematic 
Function test on surface
Check elements seal is in good condition 
Check th slips from de damage 
Check equalising sub & equaling port is. Working
Pin DW with w running tool
Should be set 10 ft above F collar stop
When rehashed the required depth pull up to set
Put 750 lbs tension and wait 2 minutes
Jar up to shear 1/8 brass pin 
Jar up to shear 5/16 brass pin to the w running tool

To pull run RB with running prong


Run slowly until you loss weight 
Wait to Equalise pressure  
Soft hand jar down to latch 
hard hand jar down 
Pooh

SSD.       Circulating ssd


                  Production ssd    ( down hole change)  set plug open ssd to change production zone (Fwg

1- Drift run ( fluid level ) 


2- Record WHSIP & CSIP 
 -  (R/S knuckle joint, 8 ft stem, mech-j, service tool) include oil jar in pulling  
 - redress plug and measure, 
run plug only static weight, 
over pull 400 lbs for 1 minutes jar up to release running tool 
soft jar to set packing hard jar to set lock
jar up to release running tool POOH, 
3-  test a plug inflow test b/o 50 psi for 10 min (big differential P will drive to blow out when openin
 - to pull use RB static weight latch 
Check latching put 200 lbs tension for 1 minutes
Use oil jar to pull prong make 750 lbs wait to oil jar to work
Always release the winch from brake ready to fast pull to avoid blow out 
 - When you get prong pull fast to 200 ft 
 - Check pressure 
  To pull 
 - Rih with RB with B prob 
 - Check static 100 before 
 - latch and pull 750 lbs to oil jarring
 - if is not coming use mech and oil jar 
 - if is sheared use SB in stead 
4- redress shifting tool & measure it
5- fluid level Hp calculation 
6- if 2 or 3 ssd pass through (D2 may stake in 1ssd little speed to pass ) 
7- each one jar monitor pressure P 

Back to normal  ( close ssd and retrieve plug)


Before retrieve plug close ssd inflow test retrieve prong after that retrieve plug.  Open the well

D2-shifting tool:
1- the D-2 Is selective tool use to model L SSD 
2- Jar up to open To allow use of power jars
3- jar down to release
4- you can release when you locate the first SSD with out shear the pins by going down fast
5- run in invert position to close the sleeve

Tubing perforator :-
The tool string is standard 
We need to equalize pressure before tubing punch ?

Model A perforator 

2 x 3/16 shear pin brass shear by jarring down( lock the finger to come out)
1 x 5/16 shear pin brass shear pin by jarring down ( release the if stuck )

Operations:
- Tubing clearance 
- rih tubing stop w/SB at least 3 ft below the desired  depth and above any flow coupling (be clear o
- you can also tight the Tbg stop bellow perforator 
-  rih the perforator jar down to shear 3/16 breasts shear pin 
- the finger now is come out jar up to start punching
- when the perforation is done the finger will retract POOH
-test circulation tubing casing 
-for any reason you stuck and you can not perforate jar down to shear 5/16 
brass pin retract the pin POOH

Note:- You can use 2ft stem + spang jar 20" + blind box or gauge cutter make move up down sudde
  

duel completion recognize :


Upper flow line short tubing , upper UMV for short or drift to tag first nipple us per well schismatic
lowest flow line long tubing , lowest UMV for long or drift to tag first nipple us per well schismatic 

Babahamou Hamouda 
Contact : 00213 0660504422
                00965 66122356
Skype ID     Bhamou1 
This message sent by IPAd
Reply to:
Reply to bh_hamou@yahoo.com
Reply to bh_hamou@yahoo.com
Send
Reply to bh_hamou@yahoo.com
ated bankers man & crane operator)

et (Rih loss weight to check set)


64" choke and flow 

bing and  open sleeve to produce 24 H from upper zone through SSD (record the casing pressure) 
ore stem weight 

n hole ( swabbing, tubing perf, DW plug)

to lock and shear


ar down to lock and shear off pooh

from above??

production zone (Fwg, Fmh)


low out when opening SSD so well site sup will decide P to be B/O)

g.  Open the well

ing down fast


w coupling (be clear of any flow coupling while performing near to LN or SSD)

move up down suddenly To shear the 3/16 by inertia if any problem you want to pooh just go down above SS

s per well schismatic 


per well schismatic 
ust go down above SSD or LN and jar down to retract.fluid lost  