You are on page 1of 17

concept design report

MARIE H. REED COMMUNITY


LEARNING CENTER

submitted to district of columbia


department of general services

31 JULY 2015

DRAFT
Concept Design Report
TABLE OF CONTENTS page 3 INTRODUCTION

page 4 EXECUTIVE SUMMARY

page 10 CONCEPT DESIGNS

page 23 PROGRAM ANALYSIS

page 25 HISTORY

page 26 EXISTING CONDITIONS

APPENDICES

appendix A ANC 1C RECOMMENDATIONS

appendix B FEASIBILITY REPORT SUMMARY

appendix C EDUCATION SPECIFICATIONS SUMMARY

appendix D APPLICABLE CODES

appendix E PERMIT REVIEW MATRIX

appendix F CIVIL SURVEY

appendix G CIVIL NARRATIVE

appendix H LANDSCAPE NARRATIVE

appendix I STRUCTURAL NARRATIVE

appendix J MECHANICAL, PLUMBING, ELECTRICAL & FIRE PROTECTION NARRATIVE

appendix K FOOD SERVICE NARRATIVE

appendix L HAZARDOUS MATERIALS

appendix M CONCEPT DESIGNS CONSIDERED

appendix N HISTORICAL DRAWINGS

appendix O PROJECT SCHEDULE

Marie H. Reed Community Learning Center


District of Columbia Public Schools 31 JULY 2015 | DRAFT 2
Concept Design Report
INTRODUCTION
Elementary schools promote personal
Project Description School Improvement Team (SIT) growth and a sense of identity within
these contexts:
Marie H. Reed Community Learning Center is located at 2201 18th Street, NW. The DC Department of General Services (DGS)
existing building was constructed in 1977 and is approximately 140,000 square feet.
The Marie H. Reed Elementary School occupies the great majority of the building. The
current facility houses a swimming pool that is operated by the DC Department of
Parks & Recreation which also shares other spaces with the elementary school. Three Client objectives
Self
community partners provides daycare and healthcare services to the Adams Morgan
community at the center. At present the school is an “open plan” facility and straddles Quinn Evans Architects to bring this project to fruition within budget while meeting all
Champlain Street, NW. programmatic requirements and responding to stakeholder goals.

The DC Department General Services and DC Public Schools has engaged Quinn Evans
Architects for design services to renovate or modernize the Marie H. Reed Community Design Team
Learning Center (the “Project”). It will be designed in such a way so as to achieve, at a
minimum, LEED for Schools - Gold certification. Architect: Quinn Evans Architects

Landscape Architect: Bradley Site Design, Inc.


Scope & Schedule
Civil / Site Engineer: Wiles Mensch Corporation
Family
Construction of the Project is scheduled to begin in spring 2016 and to be complete in
August 2017, in time for the 2017-2018 School Year. To meet this deadline the Design Team Structural Engineer: SK&A Structural Engineers
is targeting the following interim submission dates:
MPE & FP Engineer: JVP Engineers
• Concept Design (This Report) in July 2015
Strategic Engineering & Energy Modeling: In Posse
• Schematic Design in September 2015
• Initial work with the CM Advisor in October 2015 Acoustics, AV & IT: Convergent Technologies

• Design Development in December 2015 Foodservice Design: Nyikos Associates


• Permit Documents in February 2016
Hazardous Material Consultant: Apex Companies
• Construction Documents in April 2016
Cost Estimating: Forella Group Community

Immediately following the work on this Report, the Design Team in collaboration with the
DC Department of General Services, DC Public Schools and the School Improvement
Team is proceeding with Schematic Design and we are planning to make presentations to
the Community and the Commission of Fine Arts in September and October 2015.

Stakeholders

District of Columbia Public Schools (DCPS)

District of Columbia Department of Parks & Recreation (DPR) Nation


Marie Reed Health Center – The Community of Hope

Children’s Hospital - Marie Reed Clinic

Marie Reed Early Head Start

Advisory Neighborhood Commission 1C (ANC 1C)

Adams Morgan Community

World

Marie H. Reed Community Learning Center


District of Columbia Public Schools 31 JULY 2015 | DRAFT 3
Concept Design Report
EXECUTIVE SUMMARY

Purpose foundations saves labor, material and time; and the construction risks associated new building, a period of intense demotion and earth work is needed to prepare the
with basement and foundation work are largely removed from the Project. site. And while placing the new Building on the existing soccer field allows for continued
Consistent with the Owner’s Program and Schedule for the Project, this report occupancy of the existing building during construction; there is a risk the remnants from
presents results from the Concept Design Phase of the Project. The DC Department of Concept Design B – Construction of a New School & Recreation Center & Selective the original Morgan school will interfere with the new foundation work. Briefly stated the
General Services and the Community requested that we develop and evaluate concept Renovation – this design recommends demolition of the existing Marie Reed Concept B - New Building(s) approach presents additional risk and requires significantly
designs intended to address at least 2 approaches to the Project, one focused on new Building west of Champlain Street, construction of a completely new school and more time and resources to complete than Concept A – Major Modernization.
construction and another focused on major modernization. The purpose of this phase recreation center building on the existing soccer play-field, and renewal of the
is to develop and build consensus support for a Concept Design that includes a Site existing Marie Reed Building east of Champlain Street to serve the community
Master Plan, Building Plans, Phasing Recommendations, Preliminary Cost Estimates, and partner programs. Then to complete the works, a major site reconstruction Findings – Survey & Study Results
an updated Project Schedule. and renewal project is needed to re-establish and enhance its place within the
Adams Morgan Community.
Consistent the Feasibility Study dated 10.10.13; this Report recommends Major
Activity to Date Respecting the significance of the site, our Team developed a series of site Modernization of the existing Marie Reed Learning Center Building. The Design Team,
strategies designed to maintain and enhance the central plaza and recreation the School Improvement Team and the Community are now more confident that with
To this end, Quinn Evans Architects and our Consultant Team (the Design Team) have programs. As a central open space, the Marie Reed Site is as important to the comprehensive work, the existing structure can be redeveloped to serve the Project
led a series of 5 School Improvement Team (SIT) Meetings, a larger Neighborhood Work Adams Morgan Community as the DuPont Circle is to the DuPont neighborhood, Program. Following is a brief summary of the Concept Phase survey and Study findings.
Session and initiated the work on the following tasks: and as important as Canal Park is to the Capitol Riverfront neighborhood. Given
the importance of the public space and the advantages in regards a phased • Program Confirmation – both proposed Concept Designs largely meet
Program Confirmation construction process, our team recommends that the best new construction programmatic requirements defined by the Education Specifications.
Life Safety & Building Code Analysis option would be place the new building on the existing soccer/playfield. This • Life Safety & Building Code Analysis – A preliminary life safety and building
approach mirrors the construction process that was undertaken in 1978 when the code analysis has been completed, the design will be develop to meet current
Leadership in Energy & Enviromental Design (LEED) Concept and Strategy current Marie Reed was constructed upon open land adjacent to the Morgan life safety and building codes.
Development School and then the Morgan School was demolished to create playfields.
• LEED Concept and Strategy Development – Preliminary sustainable concept
Value Engineering Workshops and strategies have been explored, the project will be designed to meet LEED
Preparation of an Environmental Impact Screening Form (EISF) Concept A: Major Modernization – Recommended Approach Gold certification
Survey of the Existing Facility • Value Engineering Workshops – Preliminary cost analysis have been developed,
Concept A seeks to maintain the best of the past while looking to the future. Using the value engineering is and will be integral to the design process to assure that the
Geotechnical Investigations existing building as a framework for the facility addresses several key project objectives: Project can be completed with the allocated funds
Hydrant Flow Tests a reduced construction impact, efficient use of existing resources and inspired way to
celebrate the community history. The proposed major modernization will function as a • Preparation of an EISF – Documentation required to complete the Environment
Alternative Mechanical Systems Evaluation new building in regards to the full range of design objectives including: environmental Impact Screening Form is underway.
Audio Visual and Acoustic Consultation responsibility, appropriate acoustic separations, daylight and views. Further, we intend • Survey of the Existing Facility – Preliminary survey of the existing facility has
to draw upon lessons learned from over thirty years of ongoing operation to improve the been perform, more detail surveys will be performed during the design process
Prepare and Submit a Phase 1 Archaeological Survey
design of the renewed building. • Geotechnical Investigations – Geotechnical borings and report will be
Concept Development performed once the design is solidified
One of the defining features of the existing building is its open plan layout and central
skylights at the upper level. Respecting the acoustic and operational value associated • Hydrant Flow Tests – The needed Hydrant Flow Tests will be applied for in
Findings – 2 Primary Approaches
with distinct classrooms, we proposed to ring the central areas with “traditional” August 2015.
Briefly stated, we have developed two approaches to the Project: classrooms, and then with skylights enhance the central areas to create inspired, shared • Alternative Mechanical Systems Evaluation – Multiple system are being
learning environments. Replacing the existing concrete barrel vaults with a new steel evaluated in regards to efficiency, initial and lifecycle costs.
Concept Design A – Major Modernization – this design recommends repair and and glass clerestory structure will transform the central spaces with refreshed, indoor/
outdoor feeling that would be very expensive to replicate in new construction. In • Audio Visual and Acoustic Consultation – AV and acoustical strategies will be
reuse of the existing concrete structure and major utility connections, and near
summary, working with the existing concrete frame enables a running start to the project implemented as design progresses.
complete replacement of the interior partitions, the building MEP systems and
the exterior envelope to better serve the school, recreation and community and facilitates development of an inspired new school environment. • Prepare and Submit a Phase 1 Archaeological Survey – the required survey will
partner programs. Further to complete the works, a comprehensive site renewal be initiated in August 2015.
project is needed enhance the Center’s place within the Adams Morgan
Community. Concept B New Building(s): No further Development
Next Steps
While phased construction within the existing building present challenges, Replacement of the existing Marie Reed Structure with new buildings presents an array
of construction challenges. Demolishing the existing concrete frame building requires
working with the existing structure presents significant advantages. This Given Approval of this Concept Design Submission, the Design Team will continue
powerful and high capacity heavy equipment; tons of concrete must be broken into
approach retains the single, central community center program that was work on a Schematic Design that is largely consistent with and improves upon the
established in 1978. Efficiencies of scale can be found with central utility manageable chunks and trucked off site and the resulting holes must be filled with
compacted soil before we begin new construction. Then prior to development of the Recommended Concept A presented herein.
service, heating and cooling and other building services. Reuse of the existing

Marie H. Reed Community Learning Center


District of Columbia Public Schools 31 JULY 2015 | DRAFT 4
Concept Design Report
SITE DESIGN PRINCIPLES

Place
• Project a unique sense of place and identity to school community and the
community at large
• Create a sense of arrival that defines entry
• Provide design elements of defensible spaces on the site
• Provide a diversity of gathering places that supports small and large groups
• Provide spaces for all student populations, including specials needs
Play
• Provide multi-sensory environments that stimulate well being and promote
exploration and discovery
• Provide both active play and recharging environments in which students can
take respite during outdoor time
Landscape
• Provide indigenous, sustainable plant selections that accommodate seasonal
and temporal change
• Use the vertical changes of the site as opportunities for creative solutions
• Seamlessly integrate sustainable practices and storm-water management into
the design
Learning Lincoln Center, NYC
• Provide landscape environments which support outdoor teaching and
learning
• Landscaping should reinforce narratives about natural systems, stewardship,
and connectivity with nature

Normal, IL
Marie H. Reed Community Learning Center
District of Columbia Public Schools 31 JULY 2015 | DRAFT 5
Concept Design Report
BUILDING DESIGN PRINCIPLES

Community
• Organization of program spaces to support the school’s existing culture of
collaboration and promote interdisciplinary learning
• School to support engagement by the parents, community, and industry
leaders and role models
• Spaces should be flexible to support both school time and after-school
activities, enabling community partners to be culturally integrated into the
school
Learning
• Learning environments to cultivate and inspire a passion for lifelong learning
in preparation for the 21st century workplace
• Furnishings and technology are carefully considered for various modes of
learning
• Student galleries to provide opportunities to personalize their respective
learning communities, fostering a positive school culture
• Manifest the dual language program in the design
Pride
• Promote a sense of identities - Community, Neighborhood, School, Grades,
Classes and Student places
• Display of student work provides an understanding of the standards of
exemplary work, and fosters a sense of pride and ownership
• Promote sustainability, a sense of stewardship and global awareness as a
shared value for the community and the school in a manner that reinforces
the educational curriculum
Fitness
• Feedback loops promote educational achievement, physical fitness, and
sustainable literacy
• Through athletics and kinesthetic activities, the school to support learning
and physical fitness
Creativity
• The cafeteria and student commons to promote positive social interactions
and support formal and informal student expression through dance, art,
spoken word, and music
• The school should support visual and performing arts - both traditional and
emerging media - with adequate facilities to create and share art
Environment
• Provide a safe and secure environment that supports the policies and
procedures developed by DCPS and the School
• Provide circulation and adjacencies that foster daily routines and sequence
of activities
• Provide universal design throughout
• Provide daylighting and visual access to exterior
• Provide thermal comfort
• Provide access to outdoor space

Marie H. Reed Community Learning Center


District of Columbia Public Schools 31 JULY 2015 | DRAFT 6
Concept Design Report
GREEN DESIGN STRATEGIES

The following list of sustainable design strategies shall be considered during


Schematic Design

Sustainable Sites
• Use native plants
• Green roof
• Innovative and integrated storm water management best practices
• Underground cistern or storage system
• Garden
• Living vertical wall

Water Efficiency
• Low flow fixtures

Energy & Atmosphere


• Employ photo-voltaic panels
• Purchase power generated from renewable resources (sun, wind)
• Provide immediate feedback on energy use to facilitate student monitoring
and learning
• Employ a waste water source heat pump system
• Employ solar thermal panels for hot water

Material & Resources


• Use of local materials wherever possible
• Use of material containing recycled content wherever possible

Indoor Environmental Quality


• Use of shading devices on west facade to minimize glare and solar gain.
• Use of light shelves to bounce light further into spaces
• Use of skylights to increase daylight in spaces
Sustainable Strategies Diagram
Innovation in Design
• Alternative pool water treatment system (bromine)

Marie H. Reed Community Learning Center


District of Columbia Public Schools 31 JULY 2015 | DRAFT 7
Concept Design Report
PRECEDENT STUDY

Case Study - Claire T. Carney Library

Claire T. Carney Library, located at the University of Massachusetts Dartmouth, was


originally designed by Paul Rudolph between 1962 and 1974. It is of the same era in
history as Marie Reed (1971-1977), and of a similar building style. In 2013, the building
underwent a transformative renovation that enhanced the interior environment,
increased daylight and visual connection to the exterior, all while respecting the
quintessential character of the original building.

Before Renovation

After Renovation
Marie H. Reed Community Learning Center
District of Columbia Public Schools 31 JULY 2015 | DRAFT 8
Concept Design Report
ANC 1C RECOMMENDATIONS
ANC RECOMMENDATIONS
Celebrate the Community
• REFRESH AND EXPAND THE RECREATIONAL FACILITIES
Embrace the ideas expressed in the Advisory Refresh and expand the recreational facilities
• Provide
Neighborhood Commission for soccer,
1C Marie swimming and
Reed Vision gymnasium facilities
• Provide for soccer, swimming and gymnasium facilities
Statement of 20 •
AprilProvide
2015. playgrounds, tennis and• related game courts
Provide playgrounds, tennis and related game courts
• Provide needed support facilities• – restrooms and
Provide needed lockers
support facilities – restrooms and
Provide a better sense of center, a town square

DEVELOP AN EXCELLENT ELEMENTARY
lockers
SCHOOL FACILITY
Improve the facility presence and provide improved
access for DCPS,•DPR Fulfill the community
and other DCPS Educational
partners. Specifications
Develop an excellent elementary school facility
PROVIDE PLACE FOR COMMUNITY USE
• Fulfill the DCPS Educational Specifications
Consider Alternatives • Support community meetings
• Renovate • Support adult learning
Provide place for community use
• Build new
• Support performance events • Support community meetings
• A (hybrid) combination: some renovation and some new
PROVIDE EXPANDED SPACE FOR
construction THE WOMEN
• Support adult learning INFANTS AND
• ConfirmCHILDREN PROGRAM
adequate funding and assure quality renewal • Support performance events

• Support s provided to over 200 clients each month


• Support the synergistic relationship
Develop a “green” building betweenspace
Provide expanded the for
WIC the and theInfants
Women, Community
and Children
program (WIC)
• Provide comfort of Hope
• Support provided to over 200 clients each month
• •
Assure energy efficiency
• Support the synergistic relationship between the WIC
• Apply best practices in regards to environmental
SUPPORT EXPANDED DEVELOPMENT
responsibility
and theOF THEofEARLY
Community Hope CHILD-
HOOD LEARNING CENTER
Support expanded development of the early childhood
• Support
Provide clear physical delineations growth beyond the current 16 child limit.
learning center

MAINTAIN AND EXPAND THE COMMUNITY
Define appropriate entrance locations and boundaries
between facilities OFtheHOPE
• Support growth beyond current 16 HEALTH
child limit

• Define aCENTER
place for the Elementary School, the
Maintain and expand the Community of Hope health center
• Provide
Recreational Facilities a facility
and the Health well
Facilities anddesigned to accommodate over 13,600 patient visits
other Partners • Provide a facility well designed to accommodate over
per year 13,600 patient visits per year
• Anticipate growth
Honor history for facility to serve as a “civic heart” • Anticipate growth
• CONSIDER AND ALLOW FOR DEVELOPMENT OF A NEW
Celebrate the re-conceptualization of Adams Morgan as
BRANCH LIBRARY
a place that has embraced a diverse racial, cultural, and
socio-economic community
Consider and allow for development of a new branch library
• Anticipate of
• Anticipate future funding and development future funding
a new and development
branch library of a new
branch library
• In the meantime, assure that quiet reading spaces are provided for within
Minimize disruption during construction • In the meantime, assure that quiet reading spaces are
the existing Elementary School and provided
Community Center
for within the existing Elementary School and
• Maintain continuity of programs to the greatest extent
feasible Community Center
• Build quickly

District of Columbia Public Schools


Marie H. Reed Community Learning Center
Marie Public
District of Columbia ReedSchools
ElementarySchool DRAFT
| DRAFT
31 JULY 2015 9
Concept Design Report
NARRATIVE - CONCEPT DESIGN A

Concept A - eXTERIOR
Enhancing the Image of Marie Reed
The Marie H. Reed Learning Center is a unique building within Adams Morgan that
contributes to the history and character of the neighborhood. It represents the vision
of a community that is dedicated to the health, welfare, and achievement of all of its
residents regardless of age or background. The same goals that inspired the existing
facilities are valid today. For this reason it is important to consider the reuse and
renovation of the existing building as an alternative to the complete demolition and
rebuild of the facility.
Concept A maintains the best of the past while looking to the future. Using
the existing building as a framework for new spaces is not only an efficient use of
resources but also represents the goals of the community - to build upon the values
of the past. A renovation of the building will integrate new design goals such as
environmental responsibility, acoustic needs, daylight and views that either were not
fully met in the original design or have fallen into disrepair. The renovation approach
will use the lessons learned from the existing facility to improve the design of the
renewed building.
Rendering, 1978 Dedication of Marie Reed Community Learning Center Building Entries Diagram
Responding to External Conditions
A large building that spans multiple blocks, Marie Reed Learning Center has a to
address multiple circulation paths and neighborhood scales. On its east side, the
building faces a primarily residential neighborhood with town-homes from the early
1900’s. Ontario Rd which bounds the east of the site is relatively less trafficked by
both pedestrians and automobiles. Concept A proposes that the school entry at this
edge of the site be a secondary entry for younger children. Architecturally this entry
and facade should be less pronounced and articulated at a smaller more residential
scale.
Along the south-east, the site fronts a combination of industrial and commercial
uses. In particular, the building edge along Old Morgan School Place is isolated from
the majority of neighborhood due to the large, industrial type uses which bound the
site. The concept design proposes the use of this building edge for back of house
uses including entry to the underground parking, loading, and garbage collection. The
southern facade along Old Morgan School Place will be designed to shield unwanted
views of back of house functions. At the upper levels, the facade will be articulated in
way appropriate for the school function.
Subdividing the site into east and west sections is Champlain Street. This axis
through the site links a residential area to the north with a commercial area to the
south. Currently serving the lower levels of the building and separated from the upper
level school entries, it is the natural access for partners spaces that are located on the
ground floor of the building.
The south-west facade overlooking the playing fields has sweeping views over the
city. The facade here would take advantage of these existing views particularly at the
upper levels that are dedicated for school use. Below at the ground level the facade
would allow for strong visual connections between the recreation uses at the south
end of the site and the recreation center uses at the lower level. The main entry to
the recreation center will be located between the existing and new buildings. It will be
adjacent to the transverse access across this portion of the site.
On the west side of the site, the character is primarily commercial along the 18th
Street corridor. This is the existing front door to the building as the majority of school
Existing Structure New Learning Communities New Skylights

Marie H. Reed Community Learning Center


District of Columbia Public Schools 31 JULY 2015 | DRAFT 10
Concept Design Report
NARRATIVE - CONCEPT DESIGN A

CONCEPT a - exterior (Continued)

and recreation occupants enter from this direction. Concept A proposes using the
natural grading of the site to create two distinct main entries for the school and
recreation center. The entry to the school will be located in its current location.
However, the new architectural expression at the entry will break the horizontal
stacking of the overall building massing to clearly identify this as the primary entry to
the school. A north-south internal circulation spine between these two entries will be
expressed in the massing along the west facade.
The north facade of the building faces a primarily residential section of the
neighborhood. This edge is the least prominent of all the edges as the grade rises at
this end of the site. The architectural modifications of this edge would address the
smaller scale of the adjacent neighborhood. Entries along this edge will be secondary YOUNG
and less prominent. CHILDREN
The predominant axis of the existing building is north-south. The building’s largest
surface areas face the eastern and western sun. This condition often creates a
high level of solar heat can along the western face of the building. The design of
the mechanical system can overcome this effect. However, to improve the energy OLDER
efficiency of the building, the cladding can be designed to reduce heat gain on CHILDREN
the west and southern faces. Shading that limits solar gain on the western face of
the building will respond to the low angle of the sun late in the day. This could be
expressed as vertical fins or screens. The smaller southern faces of the building will
also be designed to reduce solar heat gain in the middle of the day. A potential design Horizontal Building Circulation
option would be horizontal light shelves. The design of all facades of the building will
be considered with regard to solar orientation.

Communicating Sustainability
A complete sustainable building strategy includes a multitude of tactics including,
but not limited to, energy efficiency, air quality, and water use reduction. The
strategies employed are often hidden to the occupants of the building. However, in
a learning environment, it is particularly important to implement techniques that are
expressive and are reinforced throughout the built environment. The concept design
proposes identifying a cohesive sustainability story that illustrates multiple sustainable
methods for addressing an important environmental theme. This story or grouping of ADULT AND
strategies should be graphically illustrated in a cohesive way both inside and outside OLDER
the building. CHILDREN
In particular, the exterior cladding will address the following issues:
• Heat Island Effect
• Site and Stormwater Management
• Energy Efficiency
• Daylight and Views
• Acoustics

Site Circulation Vertical Building Circulation


Marie H. Reed Community Learning Center
District of Columbia Public Schools 31 JULY 2015 | DRAFT 11
Concept Design Report
NARRATIVE - CONCEPT DESIGN A

Envelope Design Criteria

ONT
LEGEND
The exterior cladding system will be determined based on a set of criteria that has
DAYCARE

ARIO
been generated from the client program requirements and school/community input.
The intent is to explore a series of cladding options that will be vetted based on their
ability to meet these needs. Due to theSITEscaleBOUNDARY
of the building and the multitude of

ROA
functions, a variety of systems will likely be employed. The criteria assessment will
assist in determining where to best locatedDESIRE
theLINES
cladding options. x

D NW
• Contextually appropriate for Adams Morgan neighborhood and Washington, x EARLY
DC
x x x SCHOOL ONLY ZONE DURING x
DESIGNATED HOURS x CHILDHOOD
• Architecturally represents the (DEFENSIBLE
building functions
SPACE)both at the whole building PUMP
and space planning level. STATION
COMMUNITY BUFFER
• Ability to be hung or attached to either the existing or proposed structural EDUCATION
system STRUCTURED
x CIRC.

FACILITY NODE
Contributes to sustainability of the whole building in the following categories: x PLAY
o Energy Efficiency - including solar loading and insulation EXISTING
o Local and Regional Materials DCPS BUILDING
o Renewable Resources ENTRY
o Daylight to interior spaces x
o Acoustics PLAZA/
• Ease of maintenance and durability including impact resistance and graffiti PARK
removal

CHAM
• Availability of manufacturers and installers x x
x

PLAIN
• Ease of phasing construction
DPR
• Budgetary constraints x x
• Bidding Requirements - US manufacturer, lead times, CBE requirements

STRE
18TH STREET NW

ET NW
Exterior cladding systems and materials currently under consideration include, but
are not limited to:
• Terracotta Rain Screen
• Ceramic Tile Rain Screen, such as Porcelanosa ORGANIZED
• Curtain Wall - Stick Built SPORTS
• Curtain Wall - Unitized
• Sloped glazing system
• Fritted glass for curtain wall systems and skylights

W
• Metal screen panels with custom cut openings

EN
• Metal panel system, such as Alucobond, Sobotec

AV
• Fiber Cement Panel rain screen system, such as Eternit

IDA
• Brick cavity wall CALIFORNIA STREET NW

R
0 100 200 FT

FLO
• Pre-cast concrete panels
SCALE 1”=100’

Marie H. Reed Community Learning Center


District of Columbia Public Schools 31 JULY 2015 | DRAFT 12
Concept Design Report
NARRATIVE - CONCEPT DESIGN A

CONCEPT A - INTERIOR

Design Opportunities
The existing Marie Reed facility has a variety of unique characteristics that provide
opportunities for a renovation of the building. The building has a large floor plate with
wide column grid spacing. Floor to floor elevations are typically 12’-0” which is adequate
to provide system routing through the ceilings and allow for typical ceiling heights in the
8’-0” to 9’-0” range. At the lower level, large spaces containing recreation spaces span
multiple floors. These spaces provide the opportunity for reuse as recreation spaces or as
infill for other, smaller scale functions. One of the defining features of the existing building
is its open plan layout and central skylights at the upper level. Though a complete open
plan learning space is currently not asked for in the education specifications, these areas
provide opportunities for common spaces to be shared learning environments.
Concept A proposes replacing the barrel vault and clerestory with larger skylights
that define central common spaces between more traditional classroom spaces. These
central spaces will each have unique learning environments that will define the classroom
neighborhoods which surround them.
In addition to the skylights that are the defining architectural elements of the upper
level, the existing building has exterior patio areas adjacent to the entry at the west
and the auditorium at the east. These spaces provide opportunities for clearly defined
exterior learning spaces adjacent to interior classrooms.

Design Challenges
The existing Marie Reed facility is a large building that spans multiple blocks. Though Birdseye View of Site Looking Northeast
the size of the building provides the ability to house multiple functions, it also provides
a challenge for wayfinding and separation of uses within the space. Defining entries and
functions through exterior massing and cladding design will be integral to articulating
the multiple uses of the building. Additionally, creating a clear internal organization and
connection points between functions will create a legible building that is easily accessed
by its occupants.
The large floor plates which are an opportunity at the upper level also pose challenges
at the lower levels where access to skylights are not available. The interior spaces may
not have the desired access to daylight and views. Classrooms and core learning spaces
will be placed at the perimeter to take advantage of natural light. Additionally, providing
vertical openings between the upper and lower levels may provide shared daylight
from the upper level skylights. These openings can also provide a visual connection and
wayfinding opportunity within the space.

Interior Organization
Concept A proposes organizing the building vertically. Typically, partner and recreation
functions will be located at the lower levels with dedicated, separate entrances. The
upper levels will be slated for school functions. The entrance for the school will be
maintained at the west, 18th Street facade.
The ground floor west of Champlain Street will house the recreation functions of the
building. A separate, identifiable entrance to the recreation function will be located at
this level. The concept also proposes a possible pool addition to the west of the building.
The shared gym space will bridge the school and recreation functions to the north.

Sectional Perspective of Building Arts & Sciences Commons Perspective

Marie H. Reed Community Learning Center


District of Columbia Public Schools 31 JULY 2015 | DRAFT 13
Concept Design Report
CONCEPT DESIGN A

CONCEPT a - INTERIOR (Continued)

A multipurpose room will be located in the existing pool location. The visual barrier
between the site and this space will be removed to create a connection between interior
and exterior recreation functions. These visual connections between the lower site
and interior recreation functions will create a welcoming space that supports the new
recreation entry at this end of the building.
Across Champlain Street, partner functions including the daycare, clinic and WIC will
be housed in the ground floor level of the east wing. An entry to the community clinic off
of Champlain will be enhanced to create a welcoming entry that addresses the pedestrian
scale. The partner functions that are accessible to the community at large will be clearly
separated from the school functions above.
The top two floors of the building - first and second - bridge Champlain street with an
internal connector. Due to the size and scale of the school function, the program best fits
at these upper levels. The internal organization of the school will address adjacencies to
entries and also clearly define school neighborhoods based on the grade level of core
academic spaces.
Adjacent to the primary entry at the west, the administrative and cafeteria functions
are proposed. Crossing the bridge to the first floor east wing, the early childhood
neighborhood will be located. This location provides on grade access to exterior play
spaces and also provides a strong connection to the administration. The east and
west wings of the second floor will contain the lower and upper level neighborhood,
respectively. Each wing will not only house the core academic functions but also
supporting resource and special classrooms.

Internal Circulation
Three nodes, one at the east and two at the west, define the internal circulation of the
proposed building. Each of these nodes connects vertical and horizontal circulation paths
that knit the building and its multiple functions together.
At the west, the existing entry to the school continues to be an important node that
welcomes students and connects the school and recreation functions. This becomes the
main gate to the school where the administrative functions can oversee the entry from
both the exterior and public recreation spaces. This node will be highly visible on the
exterior through massing and cladding design.
To the south of the school entry, the entry to the recreation space becomes the second
node in the west wing. It is connected to the school node with an internal circulation
spine. This cascading spine connects the large scale recreation spaces along the west
facade of the building.
At the east the vertical circulation that connects the two level of the school becomes
an important third node. This space will be defined by the vertical circulation element. It
should be visually connected and identifiable from the entry node at the west. In addition
to providing vertical circulation functions, it will also bring daylight from the upper level
skylights to the space below. The natural light is an important feature that will enliven the
space and reinforce the architectural design - one which is characterized by its use and
manipulation of daylighting elements.

Perspective of Media Center

Marie H. Reed Community Learning Center


District of Columbia Public Schools 31 JULY 2015 | DRAFT 14
SF
SF 165.57 SF
2586.44 SF 901.52 SF 901.52 SF
ET
ARE STAIR
22 33 44 55 66 77 88 99 10
10 11
11 12
12 13
13
T

SF
ConceptUTILITY
Design Report
58.06 SF
195 1
TOILET
2 3 4 5 6 7 8 9 10 11 12

194 100
SF CONCEPT DESIGN A
UTILITY
M

176.22 SF
130.64 SF
STORAGE 191 STORAGE 2121
2121WARD
WARDPLACE,
PLACE,NW
NW

AFTER CARE STAIR


FOURTH
FOURTHFLOOR
FLOOR

LEGEND 168
WASHINGTON,
WASHINGTON,DC
DC 20036
20036

Middle School Program Legend


31.43 SF UTILITYCLOSET 167 vv202
202298
298

155
6700
6700

STAIR STORAGE
STAIR TOILET TOILET STAIR
STAIR
STAIR ff 202
202298
298

56.34 SF
L 6666 160 SF 170 SF 170 SF 160 SF
6666
WWW.QUINNEVANS.COM
WWW.QUINNEVANS.COM
120
120 SF
SF
193 74 56.34 SF
LITY 141 115 STORAGE170.93 SF STAIR
174.78 SF 114
MARIE REED
DCPS-Core Academic
89 45.68 SF 142
UTILITY
UTILITY EARLY HEAD

158.79 SF 176.22 SF
220
220 SF
SF
Classrooms START

TOILET 1510 SF

4 SF 174.78 SF 164.21 SFUTILITY


UTILITY
270
270 SF
SF STORAGE
STORAGE
DCPS-Food Service 198 K 510
510 SF
SF

Middle School Program Legend 35.67 SF UTILITY


UTILITY
360
360 SF
SF
DCPS-Building Support TOILET

CHAMPLAIN ST NW

CHAMPLAIN ST NW
DCPS-Core
Middle School Program UTILITY
Academic
Legend
192 UTILITY
UTILITY
890
890 SF
SF
DCPS-Elective
Classrooms Classroom
J
PARKING
PARKING
190 23.75 SF 9730
9730 SF
SF

STAIR
Marie H.
STAIR

43.00
SupportSF
160 SF 170 SF MARIE REED
DCPS-Food Service
DCPS-Building
DCPS-Administration Reed
STAIR
STAIR HEALTH CLINIC

UTILITY UTILITY
UTILITY
60
60 SF
SF 10980 SF

2540
2540 SF
SF LOCKER RM - Community
DCPS-BuildingCenter
Support
197 H WARMING
WOMEN
470 SF Learning
DCPS-Media UTILITY
UTILITY KITCHEN LOCKER RM - MEN BUILDING

122.81 SF UTILITY
UTILITY
40
40 SF
SF 220 SF
MULTI PURPOSE
ROOM
460 SF
Center OUTLINE ABOVE

130
130 SF
SF 990 SF FIRST AID
100 SF
Middle School ProgramClassroom
DPR-Recreation
DCPS-Elective Legend UTILITY
UTILITY
50
50 SF
SF CORRIDOR
CUSTODIAL
CUSTODIAL 280 SF
160
160 SF
SF UTILITY
UTILITY
G 30
30 SF
SF
Community Partners
DCPS-Building Support MAINTENANCE
MAINTENANCE&&
DCPS-Administration CUSTODIAL
CUSTODIAL GREEN ROOM UNEXCAVATED
UNDER EXISTING
1050
1050 SF
SF 370 SF
AUDITORIUM WIT

MECHANICAL HIGH FOUNDATIO

Parking
182 STAGE LOBBY -
CHILDREN'S
HOSPITAL - MARIE
CIRCULATION REED CLINIC
F GYMNASIUM 370 SF

556.04 SF Basement Plan MECHANICAL


MECHANICAL
6360 SF
1190 SF 2000 SF

SHOWER
SHOWER--MEN
MEN 560
560 SF
SF
820
820 SF
SF
STORAGE
STORAGE STORAGE
570
570 SF
SF 360 SF

OUTSIDE
SHOWER
SHOWER-- CORRIDOR

POOL FLOOR
STAIR STORAGE
WOMEN
WOMEN 1600 SF
E 160 SF 180 SF STORAGE STAIR
980
980 SF
SF 170 SF 160 SF
PLAN
CORRIDOR
CORRIDOR--
Program
Program Legend
Legend OPTION A
STAIR
STAIR
MECHANICAL
MECHANICAL Program Legend
970
970 SF
SF
1100
1100 SF
SF Circulation
Circulation POOL OVERLOOK MECH
POOL
POOL
6360
6360 SF
SF DPR-Recreation
DPR-Recreation
1090 SF 1030 SF Circulation
D
DPR
DPR OFFICE
OFFICE
190
190 SF
SF Parking
Parking DPR-Recreation
LOBBY
LOBBY
610
610 SF
SF DPR
DPR -- SUPPORT
SUPPORT Community Partners
RECEPTION
RECEPTION
130
130 SF
SF CORRIDOR
CORRIDOR
100
100 SF
SF DCPS-Maintenance
DCPS-Maintenance &
& DPR - SUPPORT
STAIR
STAIR
170
170 SF
SF
STAIR
STAIR
Custodial
Custodial DCPS-Maintenance &
OUTDOOR160
OUTDOOR 160 SF
SF
OUTDOOR
OUTDOOR
STORAGE
STORAGE STORAGE
STORAGE
C DCPS-Mech,
DCPS-Mech, Elec,
Elec, Toilets,
Toilets,
STAIR
170 SF STAIR Custodial
170
170 SF
SF 170
170 SF
SF 160 SF
Custodial
Custodial Closets
Closets DCPS-Mech, Elec, Toilets,
Custodial Closets
07/08/15
07/08/15

REVISIONS
REVISIONS
C:\Users\jbecker\Documents\Marie Reed Programming V2015_jbecker.rvt

NO.
NO. DESCRIPTION
DESCRIPTION DATE
DATE
B

Pool Plan Ground Floor Plan

LEVEL
LEVEL OPTION
OPTION A
A
GROUND FLOOR PLAN OPTION A
SK-11A
FERRED
FERREDFROM:
FROM: 1
A SK-11B 1/16" = 1'-0" REFERRED FROM:

Marie H. Reed Community Learning Center


7/16/2015 1:49:35 PM

22 District of Columbia
33 Public Schools
44 55 66 77 88 99 10
10 11
11 12
12 13
13 31 JULY 2015 | DRAFT 15
1 2 3 4 5 6 7 8 9 10 11 12
SF
SF 165.57 SF
2586.44 SF 901.52 SF 901.52 SF
ET
ARE STAIR
2 3 4 5 6 7 8 1 9 2 10 3 11 4 12 5 13 6 7 8 9 10 11 12
T

SF
ConceptUTILITY
Design Report
58.06 SF
195
TOILET
194 M
100
SF CONCEPT DESIGN UTILITY
A 176.22 SF
130.64 SF
STORAGE 191 STORAGE 2121 WARD PLACE, NW

AFTER CARE STAIR


FOURTH FLOOR

LEGEND 168
WASHINGTON, DC 20036

Middle School Program Legend


31.43 SF UTILITYCLOSET 167 L v 202 298
STORAGE
50 SF
STORAGE

155
50 SF
STAIR STORAGE
6700
f 202 298

56.34 SF
TOILET 6666
WWW.QUINNEVANS.COM

193 74 56.34 SF 170 SF


STORAGE170.93 SF STAIR
TOILET TOILET TOILET
LITY 141 115
170 SF 170 SF 170 SF

SECOND GRADE - SECOND GRADE -

89
DCPS-Core Academic 174.78 SF 114
45.68 SF STAIR
160 SF 142
PRE K - 1
1540 SF STAIR
2 1
STAIR
158.79 SF
Classrooms 176.22 SF STAIR 910 SF 910 SF
160 SF 160 SF
TOILET 160 SF

174.78 SF 164.21 SF
COMMONS - COMMONS -
4 SF K PRE-K PRE-S
COMMONS
198
300 SF 300 SF
DCPS-Food Service COMMONS -
FIRST/SECOND 360 SF RESOURCE -
530 SF FIRST
150 SF

Middle School Program Legend 35.67 SF PRE SCHOOL - 3


DCPS-Building Support TOILET
PRE K - 2
1150 SF 1170 SF

CHAMPLAIN ST NW

CHAMPLAIN ST NW
SECOND GRADE -
3 PROJECT LAB FIRST GRADE - 3

DCPS-Core
Middle School UTILITY
Academic
Program Legend
192 J 900 SF 910 SF 870 SF

DCPS-Elective
Classrooms Classroom
190 STAIR 23.75 SF PRE K - 3
1170 SF
PRE SCHOOL - 2
1170 SF STORAGE STORAGE
160 SF 50 SF 50 SF
Marie H. READING ROOM
DCPS-Building 43.00
SupportSF
DCPS-Food Service
DCPS-Administration
TOILET

Reed
1820 SF

UTILITY
180 SF
STAIR
170 SF
OUTDOOR WELCOME ADMINISTRATION
H
KINDERGARTEN -
1 PRE SCHOOL - 1 Community THIRD GRADE - 1 FIRST GRADE - 2

DCPS-BuildingCenter
Support
STORAGE
320 SF
CENTER
350 SF 197
1530 SF STAIR
170 SF
1170 SF 1170 SF
Learning
880 SF 870 SF

DCPS-Media STAIR FOURTH GRADE - FOURTH GRADE - TOILET

Center
170 SF 2 1 180 SF
122.81 SF 910 SF 910 SF

Middle School ProgramClassroom


DPR-Recreation
DCPS-Elective Legend VESTIBULE
550 SF COMMONS DECENTRALIZED LAPTOP STORAGE CIRCULATION
STORAGE CONFERENCE
CIRCULATION ADMIN 110 SF ROOM
390 SF 190 SF 4850 SF FIRST GRADE - 1
8000 SF 330 SF 210 SF
G OFFICE 880 SF
OFFICE
150 SF 150 SF
PARENT TEACHER RESOURCE
STORAGE - PERFORMANCE
Community Partners
DCPS-Building Support RESOURCE RESOURCE LAPTOP STORAGE 330 SF RESOURCE - ESL
INTERMEDIATE SPACE
DCPS-Administration CORRIDOR
3350 SF
310 SF 910 SF 190 SF 260 SF
270 SF 4950 SF
COMMONS -
READING

DN
MECHANICAL MUSIC
3020 SF STORAGE KILN
RESOURCE - ESL
RESOURCE -
READING
660 SF

Parking FOURTH GRADE -


140 SF 60 SF
310 SF 300 SF RESOURCE -

182
KINDERGARTEN - KINDERGARTEN - 3 SECOND/THIRD
2 3 COMMONS - WORKROOM
F 860 SF 170 SF
STAIR THIRD 1050 SF
1310 SF 1310 SF VISUAL ARTS LAB
170 SF 410 SF

556.04 SF
1020 SF

AFTER CARE RESOURCE - ESL STAIR STAIR


RESOURCE -
CLOSET 310 SF THIRD GRADE - 2 THIRD GRADE - 3
SPEECH 170 SF 170 SF
180 SF 900 SF 900 SF
550 SF
LIVING LAB
TOILET
1770 SF
180 SF
E INSTRUMENT TOILET
AFTER CARE
CLOSET
170 SF
STAIR
170 SF
STORAGE
150 SF
RESOURCE -
MATH FIRST
WET LAB
890 SF
180 SF

FLOOR PLAN
290 SF
STORAGE STORAGE
STORAGE - 60 SF
OPTION A PRIMARY 60 SF
280 SF
Program Legend FIFTH GRADE - 1
CAFETERIA KITCHEN SUITE &
SUPPORT 860 SF
3320 SF
1810 SF D Circulation FOOD LAB
890 SF
AFTER CARE
CLOSET
Program Legend
110 SF
DCPS-Food Service
Circulation
DCPS-Elective Classroom CIRCULATION
RESOURCE -
FOURTH/FIFTH
COMMONS -
FOURTH
3540 SF
COMMONS - FIFTH 170 SF DCPS-Media Center
DCPS-Administration 530 SF 530 SF
DCPS-Elective Classroom
DCPS-Core Academic STAIR
C 160 SF DCPS-Administration
DCPS-Mech, Elec, Toilets, FIFTH GRADE - 2 FIFTH GRADE - 3 STAIR

Custodial Closets
900 SF 900 SF 160 SF
DCPS-Core Academic
TOILET
170 SF
TOILET DCPS-Mech, Elec, Toilets,
Custodial Closets
STAIR TOILET TOILET STAIR 170 SF
160 SF 160 SF 160 SF 160 SF

STORAGE STORAGE 07/08/15


50 SF 50 SF
C:\Users\jbecker\Documents\Marie Reed Programming V2015_jbecker.rvt

B REVISIONS
NO. DESCRIPTION DATE

First Floor Plan Second Floor Plan

A
OOR PLAN OPTION A SECOND FLOOR PLAN OPTION A
SK-11C
1
7/16/2015 1:50:06 PM

D FROM:

Marie H. Reed Community Learning Center


SK-11D 1/16" = 1'-0" REFERRED FROM:

2
District of Columbia
3
Public Schools
4 5 6 7 8 1 9 2 10 3 11 4 12 5 13 6 7 8 9 31 JULY 2015
10 | DRAFT 16
11 12
SF
SF 165.57 SF
2586.44 SF 901.52 SF 901.52 SF
ET
ARE STAIR
T

SF
ConceptUTILITY
Design Report
195
58.06 SF
TOILET
194 100
SF CONCEPT DESIGN A
UTILITY 176.22 SF
130.64 SF
STORAGE 191 STORAGE
AFTER CARE STAIR
LEGEND 168 31.43 SF UTILITYCLOSET 167
Middle School Program Legend 155
STAIR
56.34 SF STORAGE
193 74 56.34 SF
LITY 141 115 STORAGE170.93 SF STAIR
89
DCPS-Core Academic 174.78 SF 114
45.68 SF 142
158.79 SF
Classrooms 176.22 SF TOILET
4 SF 174.78 SF 164.21 SF
DCPS-Food Service 198
Middle School Program Legend 35.67 SF
DCPS-Building Support TOILET
DCPS-Core
Middle School UTILITY
Academic
Program Legend
192
DCPS-Elective
Classrooms Classroom
190 23.75 SF
43.00
SupportSF
DCPS-Food Service
DCPS-Building
DCPS-Administration
UTILITY Basement Plan

DCPS-BuildingCenter
Support
197
DCPS-Media
122.81 SF
Middle School ProgramClassroom
DPR-Recreation
DCPS-Elective Legend

Community Partners
DCPS-Building Support
DCPS-Administration
Pool Plan Ground Floor Plan
MECHANICAL
Parking
182
556.04 SF

First Floor Plan Second Floor Plan

Marie H. Reed Community Learning Center


District of Columbia Public Schools 31 JULY 2015 | DRAFT 17

You might also like