You are on page 1of 1

HACCP

CCP decision tree

Q1 Not a CCP
Yes
Is the hazard managed by the (Record the Prerequisite
prerequisite programmes? Programme)

Yes

Q2a
Q2
Are control measures in place for No
Is control necessary?
the hazard?

Yes

Q3
Is the process step specifically designed Yes
to eliminate or reduce the hazard to an
acceptable level?

No

Q4
Could contamination with the
hazard occur at unacceptable levels No Stop
Not a CCP
or increase to unacceptable levels
(if the controls failed)?

Yes

Q5
ocess step eliminate the identified hazard(s) or reduce the hazard to an acceptable level?
No
Critical Control Point

Yes

Stop
Not a CCP