CPM PERT
Deterministic Probabilistic
No statistics applicable Statistics Applicable
Activity Oriented Event Oriented
Single time (tij) Three time Estimate
(to , tm , tp)
Known Project New Project
Accuracy - 100 % Accuracy - Probability
PERT Activity :
i j
to - tm - tp
to = a = Optimistic time
tp = b = Pessimistic time
B distribution
to tm tp
to = a = Optimistic time of activity
Vij = Variance
= ij
2
project = Standard deviation of project
completion duration
V project = V ( i j ) critical on C . P.
project =
2
( i j ) critical on C . P.
TE = Expected completion duration of
project based on teij