You are on page 1of 33

PERT and CPM

 Network techniques
 Developed in 1950s
 CPM by DuPont for chemical plants (1957)
 PERT by Booz, Allen & Hamilton with the U.S. Navy,
for Polaris missile (1958)
 Consider precedence relationships and interdependencies
 Each uses a different estimate of activity times
Six Steps PERT & CPM
 Define the project and prepare the work breakdown structure
 Develop relationships among the activities - decide which
activities must precede and which must follow others
 Draw the network connecting all of the activities
 Assign time and/or cost estimates to each activity
 Compute the longest time path through the network – this is
called the critical path
 Use the network to help plan, schedule, monitor, and control
the project
Questions PERT & CPM Can Answer
 When will the entire project be completed?
 What are the critical activities or tasks in the project?
 Which are the noncritical activities?
 What is the probability the project will be completed by a specific date?
 Is the project on schedule, behind schedule, or ahead of schedule?
 Is the money spent equal to, less than, or greater than the budget?
 Are there enough resources available to finish the project on time?
 If the project must be finished in a shorter time, what is the way to
accomplish this at least cost?
Network, Activity, Event

i-j - an activity, i & j are events


i - starting event of activity i-j
j - end event of activity i-j
tij - duration of activity i-j
Example of a Network

2
A
C
1 3
B

Activities : A, B, C

Events : 1, 2, 3
Definition
1. Network - Pictorial representation
of the interrelationship of all
events & activities.
2. Event - instant of time when
certain activities have been
started or completed.
3. Activity - The work content
required to be achieved to
accomplish an event.
Errors in Network
1. Looping
2. Parallel activity

Looping

2
A
C
1 3
B
Parallel activity
A

1 2

2
A
dummy
1
B 3
An example of dummy activity
A Comparison of AON and AOA
Network Conventions
Activity on Activity Activity on
Node (AON) Meaning Arrow (AOA)
A comes before
(a) A B C B, which comes
before C A B C
A A
A and B must both
(b) C be completed
before C can start C
B B
B
B and C cannot
(c) A begin until A is B
completed A
C C
A Comparison of AON and AOA
Network Conventions
Activity on Activity Activity on
Node (AON) Meaning Arrow (AOA)

C and D cannot
A C begin until both A C
(d) A and B are
completed
B D B D

C cannot begin until


both A and B are
A C completed A C
(e) D cannot begin until Dummy activity
B is completed
B D A dummy activity is
introduced in AOA B D
A Comparison of AON and AOA
Network Conventions
Activity on Activity Activity on
Node (AON) Meaning Arrow (AOA)

B and C cannot
begin until A is
completed
A B D D cannot begin A B D
until both B and C
(f) are completed Dummy
A dummy activity activity
C
C
is again
introduced in AOA
Critical Path Method (CPM)
Earliest start (ES) = earliest time at which an activity can start, assuming
all predecessors have been completed

Earliest finish (EF) = earliest time at which an activity can be finished

Latest start (LS) = latest time at which an activity can start so as to not
delay the completion time of the entire project

Latest finish (LF) = latest time by which an activity has to be finished so


as to not delay the completion time of the entire
project
ANALYSIS OF NETWORK

• How to locate Critical Path ?

• For Event : E, L,

• For Activity : EST, EFT, LST, LFT


Network for Analysis
2
D 5
B 5 H
9A 1
1
F
3 7
4 9 J
C 1 G 8 0 8
2 8
4 3 6 I
E

A - J : Activities

1 - 8 Events
E=9 E=14
D 5
2
B 5 H
9 E=4 1 E=(15,13, 12) = 15
1 A 3
F 7
E=0
4 9 J
1 8 0 2
C G 8 8
4 3
E 6 I E=(17,20) = 20
E=1 E=(4, 12) = 12

E = Earliest Occurrence
time of Event
L=12 L=17
D
2 5
B 5 H
9 L=( 4,9 ) = 4 1 L=18
1 A 3
F 7
4 9 J
1
L= ( 3,0,8 ) G 8 0 2 8
C 3 8
=0 4 6 L=20
E I
L=9 L=( 12,18 ) = 12

L = Latest Occurrence
time of Event
E=9 E=14
L=12 L=17
2
D 5 E=(15,13, 12)=12
5
B E=4, L=(9,4)=4 H
9 1 L=18
1 A 3 F 7
4 9 J
E=0 C 1 E=(14,20)=20
G 8 0 8
2 8
L=0 4 3 L=20
E 6 I
E=1
E=(4, 12)=12
L=9
L=(18,12)=12
E=9 E=14
L=12 L=17
D
2 5
B 5 E=(15,13, 12)=12
H
9 E=4, L=(9,4)=4 1 L=18
A F
1 3 7
4 9 J E=(14,20)=20
E=0 C 1 2
G 8 0 8 L=20
3 8
L=0 4 6
E I
E=1 E=(4, 12)=12
L=9 L=(18,12)=12
For Events 1,3,6 and 8 E = L
Hence 1, 3, 6 and 8 are Critical Events
E=9 E=14
L=12 L=17
D
2 5 E=(15,13, 12)=12
B 5 H
9E=4, L=(9,4)=4 1 L=18
A F
1 3 7
4 9 J
E=0 C 1 E=(14,20)=20
G 8 0 2
8
L=0 4 3 8 L=20
E 6 I
E=1 E=(4, 12)=12
L=9 L=(18,12)=12

Hence 1 - 3 - 6 - 8 is a Critical Path


Critical Events : E=L : 1, 3, 6, 8
Critical path is 1 - 3 - 6 - 8
Critical path should be a path from first to last
event.
Critical path is a Longest path.
Critical Path is a path on which all events
are Critical.
A path joining all critical events need not be
a path or a longest path.
A network can have more than one critical
Path.
Identify the critical activities and critical path for the network
shown below.
Identify the critical activities and critical path for the network
shown below.
Identify the critical activities and critical path for the network
shown below.

You might also like