Professional Documents
Culture Documents
Management
andControl
(AE 452)
Lecture 9
Network Definition:
A network is a logical and sequential graphic representation
of the activities (and events) composing a project.
and
- Arrow networks were
Introduction more popular in the 1960s
Introduction
Arrow Diagramming Method (ADM):
Activity On arrow (AOA) networks , or the I–J method
For example, activity A is also known as 10–20, B as 20 – 30, C as 20 – 40, and so on.
Activity IPA
Arrow B D
A - 30
B A A E
Network C A
10 20 40 50
D B
C
E C, D
IPA : Immediate Preceding activities
- The project has five activities, each represented by an arrow. Each arrow
connects two nodes (CIRCULE). Each node represent event
❑ The end of activity E means the end of the project. Activity A is considered a
predecessor activity to activities B and C
❑ we can also say that activities B and C are successor activities to activity A
❑ - Node 20 represents the end of activity A and the start of activities B and C
❑ - Node 40 represents the end of activities C and D, and the start of activity E.
dummy
activity
Redundant dummy:
It is interesting to note that when you are building an arrow network, you can have not
only a logically inappropriate network but also a proper one with redundant dummy
activities. This fact is especially true for complicated networks. Redundant dummy
activities are not logically improper: they are just redundant (see Figure 9.8). (Note:
Students may lose points on exams for having redundant dummies.)
Redundancies
Arrow Diagramming Method (ADM):
Activity On Node (AON) networks
Nodes (activities) are connected with arrows (or lines) that represent the logical
relationships.
Node B
30
D
Activity IPA
Network A -
10
A
20 40
E
50
B A
C
C A
D B
E C, D B D
A E
- There is no need in the node
diagram for dummy activities.
C
Activity on Node (AON) networks
we like to start any network with one node (whether this node represents an
event or an activity) and end it with one node. Doing so may require one or
two fictitious activities in node diagrams that start or end with more than
one activity. We call these activities PS (project start) and PF (project finish),
displayed as diamond-shaped nodes. For example, let us redo Figures 9.3 ,
9.4 as node diagrams. Note we can solve example 9.4 without using the
Node annoying dummy activities.
Network
Arrow networks cannot accommodate lags. The only solution in such networks is to
treat it as a real activity with a real duration, no resources, and a $0 budget (Figure
9.16b).
Lags and
Leads With arrow networks, an activity was defined as ‘‘a unique unit of the project which
can be described within prescribed limits of time’’ or ‘‘a time-consuming task’’
Note that: these definitions include ‘‘waiting activities’’ that have no real work or
resources but the author of this book suggests changing the definition to ‘‘a resource-
consuming task,’’ since waiting periods are treated as lags rather than real activities.
The term lead simply means a negative lag. It is seldom used in construction. In simple
language: A positive time gap (lag) means ‘‘after’’ and a negative time gap (lead)
means ‘‘before.’’
Lags and leads are covered in chapter 4, when we discuss CPM calculations.
Recommenda
tions for
Proper Node
Diagram
Drawing
AOV VS AOA:
1- Node networks are easier to draw.
Comparison 2- Node networks do not require dummy activities to fix the activity identity problem.
3- Node networks do not require dummy activities to straighten up the logic.
of Arrow and 4- Node networks can accommodate lags between activities without the addition of
more activities.
Node 5- Node network represent not just the traditional finish-to-start relationship but also
three other relationships (start to start, finish to finish, and start to finish).
Networks
Networks:
1- Networks show logic (i.e., the relationships among activities). Bar charts do not.
2- Networks can better represent large and complicated projects.
3- Networks can estimate, or predict, the completion date of the project, or other
Networks dates, on the basis of mathematical calculations of the CPM.
The project manager produces customized reports that include only a small group of the
Effective Use project activities (e.g., bar chart reports for subcontractors for their particular activities,
or for activities that are supposed to start in the next 2 weeks). or only critical activities.
of Bar Charts
Presentation to high-level staff:
with the CPM
CEOs and senior managers are usually not concerned with the progress at the individual
activity level. They like to get an overall picture of the project and the main components.
Roll-up or summary bar charts have become a popular option in computer software. A
group of activities is rolled up or summarized according to a common factor such as area,
responsibility, phase, or the company’s work breakdown structure (WBS).
Time-Scaled Logic
Diagrams
Time-Scaled Some scheduling software vendors tried to take
Logic the advantage of networks (logic, or relationships)
and impose it on bar charts in what some persons
Diagrams called time-scaled logic diagrams but also did not
make the logic as clear as it is in networks.