Consultancy Services for Demolition and re-construction of Distressed Vivekananda Road Flyover- A.

Vetting of Methodology and Checking Technical Specification of the demolition works submitted by the
selected agency of KMDA; B. Supervision of the demolition works; C. Preparation of New DPR of the Vivekananda Road Flyover
PHASE I WORKS (ALONG STRAND ROAD FROM RABINDRA SETU TO POSTA JUNCTION, 256M)
PROGRESS REPORT - BAR CHART SHOWING DETAIL ACTIVITIES OF INDIVIDUAL SPAN TO BE DISMANTLED
RABINDRA SETU POSTA JUNCTION
P13-P12 (GIRDERS ONLY), P11-910, P10-P9, P9-P8, P9-P7, P7-P6)
P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12 P13 P14
15.06.21

15.06.21

15.06.21

30.06.21

15.07.21

24.07.21

13.07.21

13.07.21

15.06.21
STATUS OF DISMANTLING OF PIER COLUMNS

P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12 P13 P14

15.07.21

24.07.21

15.07.21

15.07.21
NAWAB
LANE

STATUS OF DISMANTLING OF PIER CAPS

P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12 P13 P14

16.07.2021 27.07.2021 Girder Only Girder Only


01.07.2021

19.07.2021 31.07.2021 Girder Only


06.07.2021

STATUS OF LOWERING DOWN OF SUPERSTRUCTURES

Summary of Progress so far…


TOTAL COMPLETED PENDING Completed
SUPERSTRUCTURES 12 nos. 5 nos. 7 nos. Next Target
PIER CAPS 9 nos. 4 nos. 5 nos. Subsequent target after completion of next target
PIERS 14 nos. 9 nos. 5 nos.
7/16/2021 7/11/2021
7/15/2021 7/10/2021
7/16/2021 7/16/2021
7/19/2021 7/17/2021
7/16/2021 7/11/2021
7/19/2021 7/16/2021
7/20/2021 7/20/2021
7/24/2021 7/20/2021
7/24/2021 7/21/2021
7/24/2021 7/23/2021
7/26/2021 7/23/2021
7/26/2021 7/26/2021

6/22/2021 6/15/2021
6/30/2021 6/22/2021

7/15/2021 7/10/2021
7/1/2021 7/1/2021
7/5/2021 7/1/2021
7/3/2021 7/1/2021
7/5/2021 7/3/2021
7/6/2021 7/6/2021
7/10/2021 7/6/2021
Start date

End date

PHASE I WORKS (ALONG STRAND ROAD FROM RABINDRA SETU TO POSTA JUNCTION, 256M)
PROGRESS REPORT - BAR CHART SHOWING DETAIL ACTIVITIES OF INDIVIDUAL SPAN TO BE DISMANTLED

Cutting of 3.0m concrete portion


Stage #1 Removal of end cross girders
Welding of stiffeners and closing of access holes
Erection of 8 nos. of testle supports
Erection of top jack supporting beam (4 nos.)
Stage #2
Erection of strand jacks on top of jack supporting beams (4 nos.)
Assembling, jacking up the lifting beam and fitting with girder bottoms (2 nos.)
Stage #3 Testing of jacks by lifting up the superstructure, cutting of long girders, lowering down of span
Stage #4 Dismantling and removal of debris of slab & girder
Stage #5 Dismantling and removal of debris of pier

SPAN P6-P7 SPAN P7-P8 SPAN P8-P9 SPAN P9-P10 SPAN P10-P11 SPAN P11-P12 SPAN P12-P13
Eastern c/w Western c/w P6 Eastern c/w Western c/w P7 Eastern c/w Western c/w P8 Eastern c/w Western c/w P8 Eastern c/w Western c/w P8 Eastern c/w Western c/w P8 Eastern c/w Western c/w P8
Date #1 #2 #3 #4 #1 #2 #3 #4 #5 #1 #2 #3 #4 #1 #2 #3 #4 #5 #1 #2 #3 #4 #1 #2 #3 #4 #5 #1 #2 #3 #4 #1 #2 #3 #4 #5 #1 #2 #3 #4 #1 #2 #3 #4 #5 #1 #2 #3 #4 #1 #2 #3 #4 #5 #1 #2 #3 #4 #1 #2 #3 #4 #5
15 June 2021 X
16 June 2021 I
17 June 2021 I
18 June 2021 I
19 June 2021 I
20 June 2021 I
21 June 2021 I
22 June 2021 X X
23 June 2021 I
24 June 2021 I
25 June 2021 I
26 June 2021 I
27 June 2021 I
28 June 2021 I
29 June 2021 I
30 June 2021 X
01 July 2021 X X X
02 July 2021 I I
03 July 2021 I X X
04 July 2021 I I
05 July 2021 X X
06 July 2021 X X
07 July 2021 I
08 July 2021 I
09 July 2021 I
10 July 2021 X X X
11 July 2021 X I X I
12 July 2021 I I I I
13 July 2021 I I I I
14 July 2021 I I I I
15 July 2021 I X I X
16 July 2021 X X X X
17 July 2021 X I
18 July 2021 I I
21 July 2021 I X
22 July 2021 I I
23 July 2021 I I X X
24 July 2021 X X X I
25 July 2021 I
26 July 2021 X X
27 July 2021
28 July 2021
29 July 2021
30 July 2021
31 July 2021
01 August 2021
02 August 2021
03 August 2021
04 August 2021
05 August 2021
06 August 2021
07 August 2021
08 August 2021
09 August 2021
10 August 2021
11 August 2021
12 August 2021
13 August 2021