FutureForm – UK – Southwark, London Modular construction is widely used for hotels, where speed of construction leads to financial benefits to the hotel operator. A new hotel for Citizen M on busy Southwark Street on London’s south bank has taken modular construction to a new level of design sophistication. FutureForm’s modular solution uses a new form of 95 double room and corridor modules of 2.5m width and 15m length together with a small number of single room modules.
Hotel on Lavington Street, Southwark, London
The 6-storey hotel comprises 192 bedrooms, with the hotel reception, restaurant and other facilities located at ground floor. The modules are built to a high specification including full height windows, local heating and cooling of the air supply, mood lighting, and a high level of acoustic separation between the rooms. The modules are supported by a storey steel frame with the hotel reception and restaurant at first floor.
MODCONS Case Study – FutureForm – UK – CitizenM Page 1 of 3
It was designed to 90 minutes fire resistance with in-built high mist sprinklers, which is in excess of Building Regulation requirements. The overall wall zone was only 200 mm and the combined floor and ceiling zone was only 400 mm, which is remarkably narrow for a double layer construction. A fully glazed façade wall was created by a welded frame using 80 x 40 RHS sections. This rigid frame provides the resistance to horizontal loads acting on the 5- storey assembly of modules, and also provides the attachment points between the modules.
View inside the atrium of the hotel
The steel structure at ground floor level is based on a 6m x 5m grid and each beam supports two modules. Steel columns aligned with the width of pairs of modules. Modules weighed up to 10 Tonne were lifted into place at an average rate of 6 per day by the 50m boom of a 500 Tonne mobile crane positioned roadside. The loads on the foundations were minimised by the use of lightweight modular construction. The stair and lift modular cores on the upper levels were installed at the same time as the bedroom modules. The modular bedrooms are fully finished before delivery to site and the corridors were finished by second fix services on site. FutureForm’s sub-contract as modular designer and
MODCONS Case Study – FutureForm – UK – CitizenM Page 2 of 3
supplier was only 35% of the total build cost of £14 million. The installation of the modules took only 5 weeks out of a 9-month construction programme, saving an estimated 6 months relative to more traditional building, which was very important to the client in the run-up to the 2012 Olympic Games. The project achieved BREEAM ‘Very Good’. Measured air-tightness of the modules was 5m3/m2/hour, which is significantly better than traditional building. The measured sound reduction between rooms was over 60 dB.
Hotel during construction
MODCONS Case Study – FutureForm – UK – CitizenM Page 3 of 3