Casta Engineers Pvt. Ltd. SS
In Joint Venture with
SOWiL Ltd.
Ref: CASTA/GSHPL/Gohana-Sonipa/TL/2021/0235 Date: 18.02.2021
To,
Authorized Signatory,
MIS GohanaSonipat Highway Pvt. Ltd.
4 floor, Vikash Surya Shopping Mall,
Plot No.-18, Manglam Palace, Sector-3, Rohini, Delhi-1 10085
Sub: 4-Laning of Gohana-Sonipat (Pkg-2) Section from km 40.601 to km 78.837 (Length = 38.236km) of
NH-352A in the state of Haryana under BharatmalaPriyojna under NH (O) to be implemented on Hybrid
Annuity Model (HAM), Reg. Progress of the Project Highway.
Ref:
‘Our office letter No: CASTA/GSHPL/Gohana-Sonipat/TL/202 1/0230, Dated: 11.02.2021.
(Our office letter No: CASTA/GSHPL/Gohana-Sonipat/TL/2021/0192, Dated: 13.01.2021
Your office letter No: GSHPL/2021/467, Dated: 07.01.2021.
Authority letter No: NHAV/PIU/SNP/NH-352A (PKG-02)/G-08/2020/D-3475, Dated: 29.12.2020,
‘Authority letter No: NHAV/PIU/SNP/NH-352A (PKG-02))G-08/2020/D-3446, Dated: 23.12.2020.
‘Our office letter No: CASTA/GSHPL/Gohana-Sonipat/TL/2020/0154, Dated: 23.12.2020.
Our office letter No: CASTA/GSHPL/Gohana-Sonipat/TL/2020/0132, Dated: 07.12.2020.
Our office letter No: CASTA/GSHPL/Gohana-Sonipat/TL/2020/0094, Dated: 01.10.2020.
eI ABER
Dear Sir,
In reference to above captioned subject & referred letters, we refer to progress of the works made so far for
aforementioned Contract Agreement.Despite, several correspondences Concessionaire is considerably
lagging in expediting progress and consistently falling behind in coping up with respect to time.
Further, itis to bring in your kind notice that Concessionaire’sagain submitted Construction Time Schedule
showing the planned progress of the project highway vide letter referred at sr. no: 03, in which mile stone
dates have been revised without taking in account that EOT has not been approved yet. Therefore,
Concessionaire does not get relieved from its obligation of achieving project mile stone-1
AAs, so far 28.63% of the contract period has been elapsed already and as per your submitted MPR for the
Month of January 2021, the overall Physical Progress achieved as on 31.01.2021is 5.44%, whichclearly
shows that no concrete actions have been takenin these passed months to scale up construction activities,in
spite of several notification by IE. Also,Concessionaire has failed to achieve Project Milestone-I.
Again, we would like to remind you that as per Clause 2.1 Schedule-G of CA, the Project Milestone-1 shall
occur on the date falling on the 160®Day (One Hundred and Sixtieth) from the Appointment Date
(24.07.2020), hence the Project Milstone-I shall have occurred on i, 30.12.2020, in which Concessionaire
shall have commenced construction of the project and achieved 20% physical progress
Moreover, Pursuant to CA clause 12.3.2 “The Concessionaire shall construct the Project in accordance with
Project Completion Schedule set forth in Schedule-G. In the event that the Concessionaire fails to achieve
any Project Milestone within a period of 90 (Ninety) days from the date set forth for such Project Milestone
in Schedule-G, unless such failure has occurred due to Force Majeure or for reasons attributable to the
Authority, it shall pay Damages to the Authority in a sum calculated at the rate of 0.1% of the amount of
Performance Security for delay of each day until such Project Milestone is achieved; provided that if any or
all Project Milestones or the Scheduled Completion Date are extended in accordance with the provisions of
this Agreement.”
On
‘ oO
eae
- Page dota
Engineers Pv. Ltd in JV with M/s SOWiL Ltd. House No-4129, Ward No-31, Indian Colony, Sugar Mill
car Railway Bridge, Sonepat, Haryans-131001, E-mail: asta gchanasonepat@.gmailcomCasta Engineers Pvt. Ltd.
In Joint Venture with
SOWiL Ltd.
In view of the above, Concessionaire needs to take immediate action for expediting progress and also
provide justification that why shall damages not be levied onto you, in failure to achieve Project Milestone-1
This is for your information and immediate necessary action please.
‘Thanking you and assuring best co-operation at all times,
With best regards
For, CASTA EPL JV SOWIL LTD.
epoer ut
ERE NL LTO ay
ens Ko
Praveen Rum: a crud goat OP
{Team nie) of Stn 80
Copy To:
1, The Regional Officer, Regional Office-Chandigath, NHAI, Bay No. 35-38, First Floor, Sector4,
Panchkula, Haryana, (For Information Please)
2, The Project Director, Project Implementation Unit, National Highway Authority of India A-3,
Upper Ground Floor, Pushpanjali Enclave, Near Navjeevan Hospital, Pitampura, New Delhi-
110034. (For Information Please)
3. MIS Casta Engineers Pvt. Ltd. A-26 Ist Floor, B-1 Extension, Mohan Co-Operative Industrial
Estate, New Delhi-1 10044, (For Information Please)
Page2of2—
Project Office: M/s Casta Engineers Pvt. Lid in JV with M/s SOWiL. Ltd, House No-4129, Ward No-31, Indian Colony, Sugar Mill
bypass, Near Railway Bridge, Sonepat, Haryana-131001, E-mail: asta yohanasonepat@inailicom