Professional Documents
Culture Documents
GATE Questions & Answers Of: Project Planning and Network Analysis - PERT and CPM
GATE Questions & Answers Of: Project Planning and Network Analysis - PERT and CPM
Total 5 Questions have been asked from Project planning and Network analysis - PERT and CPM.
topic of Construction Materials and Management subject in previous GATE papers. Average marks
1.60.
GATE - 2017 02
Question No. 45
Activity Depends on
Q
P --
P
Duration (in days)
6
15
R Q,T 12
S R 16
T P 10
U Q,T 14
V U 16
The estimated minimum time (in days) for the completion of the project will be ___________
Show Answer
Answer : 51 to 51
Subject : Construction Materials and Management Topic : Project planning and Network
analysis - PERT and CPM.
For a construction project, the mean and standard deviation of the completion time are 200 days and
6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate z =
1.64 for the 95% con dence level. The maximum time required (in days) for the completetion of the
project would be _______________
Show Answer
The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the
critical path are given below in the format O-M-P.
Show Answer
Answer : 37 : 38
Subject : Construction Materials and Management Topic : Project planning and Network
analysis - PERT and CPM.
GATE - 2016 01
Question No. 120
A construction project consists of twelve activities. The estimated duration (in days) required to
complete each of the activities along with the corresponding network diagram is shown below.
Duration Duration
Activity Activity
(days) (days)
A Inauguration 1 G Flooring 25
B Foundation work 7 H Electri cation 7
Structural
C 30 I Plumbing 7
construction-1
Structural
D 30 J Wood work 7
construction-2
E Brick masonry work 25 K Coloring 3
Handing over
F Plastering 7 L 7
function
Total oats (in days) for the activities 5-7 and 11-12 for the project are, respectively,
Show Answer
GATE - 2016 02
Question No. 149
The activity-on-arrow network of activities for a construction project is shown in the gure. The
durations (expressed in days) of the activities are mentioned below the arrows.
Show Answer
Timber
Bitumen
Cost Estimation
About
This is not the o cial website of GATE.
It is our sincere e ort to help you.
Follow Us On
Contact Us
Email: gateexam.in@gmail.com
Search In Website