GATE Questions & Answers of Project planning and Network analysis


- PERT and CPM.

 What is the Weightage of Project planning and Network analysis - PERT


and CPM. in GATE Exam?

Total 5 Questions have been asked from Project planning and Network analysis - PERT and CPM.
topic of Construction Materials and Management subject in previous GATE papers. Average marks
1.60.

GATE - 2017 02
Question No. 45

The activity details of a project are given below:

Activity Depends on

Q
P --
P
Duration (in days)
6
15

R Q,T 12
S R 16
T P 10
U Q,T 14
V U 16
The estimated minimum time (in days) for the completion of the project will be ___________

Enter Your Answer Here

Show Answer

Answer : 51 to 51
Subject : Construction Materials and Management         Topic : Project planning and Network
analysis - PERT and CPM.

Question No. 118 GATE - 2017 01

For a construction project, the mean and standard deviation of the completion time are 200 days and
6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate z =
1.64 for the 95% con dence level. The maximum time required (in days) for the completetion of the
project would be _______________

Enter Your Answer Here

Show Answer

Answer : 209 to 211


Subject : Construction Materials and Management         Topic : Project planning and Network
analysis - PERT and CPM.

Question No. 49 GATE - 2016 02

The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the
critical path are given below in the format O-M-P.

The expected completion time (in days) of the project is _________

Enter Your Answer Here

Show Answer

Answer : 37 : 38
Subject : Construction Materials and Management         Topic : Project planning and Network
analysis - PERT and CPM.

GATE - 2016 01
Question No. 120

A construction project consists of twelve activities. The estimated duration (in days) required to
complete each of the activities along with the corresponding network diagram is shown below.

Duration Duration
Activity Activity
(days) (days)
A Inauguration 1 G Flooring 25
B Foundation work 7 H Electri cation 7
Structural
C 30 I Plumbing 7
construction-1
Structural
D 30 J Wood work 7
construction-2
E Brick masonry work 25 K Coloring 3
Handing over
F Plastering 7 L 7
function

Total oats (in days) for the activities 5-7 and 11-12 for the project are, respectively,

 (A)  25 and 1  (B)  1 and 1  (C)  0 and 0  (D)  81 and 0

Show Answer

Answer : (C) 0 and 0


Subject : Construction Materials and Management         Topic : Project planning and Network
analysis - PERT and CPM.

GATE - 2016 02
Question No. 149

The activity-on-arrow network of activities for a construction project is shown in the gure. The
durations (expressed in days) of the activities are mentioned below the arrows.

The critical duration for this construction project is

 (A)  13 days  (B)  14 days  (C)  15 days  (D)  16 days

Show Answer

Answer : (C) 15 days


Subject : Construction Materials and Management         Topic : Project planning and Network
analysis - PERT and CPM.

Topics of Construction Materials and Management

Construction Materials: Structural Steel-Composition, Material Properties and Behaviour

Concrete - Constituents, Mix design, Short-term and Long-term Properties

Bricks and Mortar

Timber

Bitumen

Construction Management: Types of construction projects

Tendering and Construction Contracts

Rate Analysis and Standard Speci cations

Cost Estimation

Project planning and Network analysis - PERT and CPM.

About
This is not the o cial website of GATE.
It is our sincere e ort to help you.

Follow Us On

Contact Us
Email: gateexam.in@gmail.com

Search In Website

2021 © GATE-Exam.in | Complete Solution for GATE

You might also like