No Description Width Length Height No Unit Qty Rate Amount

Excavation
Clearing before the construction and after the construction and M
2 1 $108
removing all the debris from the 9 12 1 1 108.00
1 site .
2 Excavation of trenches at an 0.4 72.75 0.5 1 M
3 14.55 $175
average depth of 0.50 m 12

Sub Total $283


Masonary Work $0
Rubble stone foundation in cement & sand mortar 1:4 mix at an $1,019
1 average depth 0.4 72.75 0.70 1 M
3 20.37 50
of 0.7 m upto the ground level.

Sub Total $1,019


Back filling
Backfilling with selected sand to an average depth of and $292
1 compacting to a desired compacting 1 81.00 0.30 1 M
3 24.30 12
level
2 Backfilling with selected hardcore to an average 1 81.00 0.1 1 M
3 8.10 $105
depth of 0.1 m 13

1 Sub Total $397


Concrete Works
ground beam $1,091
1 0.4 72.75 0.2 1 M
3 4.37 250

Casting RCC (1:2:4 mix) Tie beam with 4N0. Y12 re-bars & R8 $1,091
1 links 0.4 72.75 0.2 1 M
3 4.37 250
@ 250 mm c/c.
Lean concrete 10 cm thick with (1:3:6) mix for levelling and $750
2 smoothening of the floor over the 1 75.00 0.1 1 M
3 7.50 100
compacted sand
3 Cast RCC (1:2:4 mix) Lintel beams Y12 re-bars & 0.2 72.75 0.2 1 M
3 2.91 $669
R8 links @ 200 mm c/c. 230

Sub Total $2,511


Walls
1 Supply and built hollow cement block walls type with mixture of 1 56.00 3 1 168.00 18 $3,024
1:4 cement & sand mortar and fill the space between the blocks 2
M

Sub Total $3,024


Doors & Windows
Supply and install internal imported wooden doors size . With all 200 $1,000
3 required sealants, locks, specifications and engineer's instructions 1 1 1 5 PCS 5.00

Supply and install internal imported wooden doors size. With all 180 $360
4 required sealants, locks, specifications and engineer's instructions 1 1 1 2 PCS 2.00

Providing & Fixing aluminium glazed sliding window with 4.00 $896
mm and size of inclduing safety grill 1 1.4 1.6 5 M
2 11.20 80

Providing & Fixing aluminium glazed sliding window with 4.00 $125
8 mm and size of 1 0.8 0.6 2 M
2 0.96 130
including safety grill
9 Entrance door (Minar) 1 1 1 1 M
2 1.00 120 $120
10 Entrance door (Main Gate) 1 1 1 1 M
2 1.00 700 $700
Sub Total $3,201
Roof and Celing
1 ceremic tiles inclduing Verandah tiles 1 87.0 1 1 M
2 87.00 14 $1,218
8 Local tiles for the lawn 1 50.0 1 1 M
2 50.00 12 $600
2 wet area ceramic ties (Kitchen and Toilets) 1 37.0 1 1 M
2 37.00 14 $518
3 Corrugated Iron Sheet Roof, nr 28 including 85.00 1.2 1 2 102.00 $2,040
woods
M
20
4 Ceiling ( suspending ceiling) 87.00 1 M
2 87.00 10 $870
Sub Total $5,246
Plastering
1 Plastering on walls surfaces with 12mm plaster 1 81.0 3 2 M
2 486.00 $1,944
thickness 4

Sub Total $1,944


Painting
Apply three coats of white wash and distemper paint up to the $1,458
1 ceiling level of plastered wall 1 81.0 3 2 M
2 486.00 3
surface.
Apply two coats of paints up to the ceiling level of plastered wall $1,458
2 surface and colour to be advised in 1 81.0 3 2 M
2 486.00 3
later stages
Sub Total $2,916
Plumbing $0
1 Water supply . . . . LS $1,200
All toilets should have full accessories, including wash hand $800
2 basin with mirror, wash spray, floor drainage and have ceramic . . . . PCS 3.00
tiles with skirting
Sub Total $2,000
Electrical
1 Electrical instalation . . . . LS 3% $1,000
Sub Total $1,000
Septic tank
Concrete septic tank size 3000Lx2000Wx3400mm Deep. The M
3 75 $1,500
septic tank must be lower the ground by minimum 300mm and
1 build to resist cars load and septic tank to have 200mm thick slab 2 2 4 1 20.00

Sub Total $1,500


TOTAL $25,039
Ground Floor Total $25,039.35
General Notes:
M-metre
No- numbers M3-cubic metre M2-square metre
Lm- linear metre
Mm-milimetre LS- Lump Sum PCS- pieces