Excavation
Clearing before the construction and after the construction and M
2 1 $108
removing all the debris from the 9 12 1 1 108.00
1 site .
2 Excavation of trenches at an 0.4 72.75 0.5 1 M
3 14.55 $175
average depth of 0.50 m 12
Casting RCC (1:2:4 mix) Tie beam with 4N0. Y12 re-bars & R8 $1,091
1 links 0.4 72.75 0.2 1 M
3 4.37 250
@ 250 mm c/c.
Lean concrete 10 cm thick with (1:3:6) mix for levelling and $750
2 smoothening of the floor over the 1 75.00 0.1 1 M
3 7.50 100
compacted sand
3 Cast RCC (1:2:4 mix) Lintel beams Y12 re-bars & 0.2 72.75 0.2 1 M
3 2.91 $669
R8 links @ 200 mm c/c. 230
Supply and install internal imported wooden doors size. With all 180 $360
4 required sealants, locks, specifications and engineer's instructions 1 1 1 2 PCS 2.00
Providing & Fixing aluminium glazed sliding window with 4.00 $896
mm and size of inclduing safety grill 1 1.4 1.6 5 M
2 11.20 80
Providing & Fixing aluminium glazed sliding window with 4.00 $125
8 mm and size of 1 0.8 0.6 2 M
2 0.96 130
including safety grill
9 Entrance door (Minar) 1 1 1 1 M
2 1.00 120 $120
10 Entrance door (Main Gate) 1 1 1 1 M
2 1.00 700 $700
Sub Total $3,201
Roof and Celing
1 ceremic tiles inclduing Verandah tiles 1 87.0 1 1 M
2 87.00 14 $1,218
8 Local tiles for the lawn 1 50.0 1 1 M
2 50.00 12 $600
2 wet area ceramic ties (Kitchen and Toilets) 1 37.0 1 1 M
2 37.00 14 $518
3 Corrugated Iron Sheet Roof, nr 28 including 85.00 1.2 1 2 102.00 $2,040
woods
M
20
4 Ceiling ( suspending ceiling) 87.00 1 M
2 87.00 10 $870
Sub Total $5,246
Plastering
1 Plastering on walls surfaces with 12mm plaster 1 81.0 3 2 M
2 486.00 $1,944
thickness 4