Relative Importance Index (RII) Relative importance index (RII)= (5n5+4n4+3n3+2n2+1n1)/(A*N)

Not at all Slightly somewhat Very Extremely 1n1 2n2 3n3 4n4 5n5 Sum A N A*N Mean SD RII Rank
item no Critical Barriers to Implementing RM Total respondent
influential influential influential influential influential

1 Un availability of Resources 5 8 6 45 21 85 5 16 18 180 105 324 5 85 425 3.8117647 1.0964675 76.235294118 10

2 Limited Understanding of Risk Management 0 5 2 45 33 85 0 10 6 180 165 361 5 85 425 4.2470588 0.7700631 84.941176471 1

3 Resistance to Change 2 7 11 38 27 85 2 14 33 152 135 336 5 85 425 3.9529412 0.9988789 79.058823529 4

4 Lack of Regulatory Pressure 1 8 12 40 24 85 1 16 36 160 120 333 5 85 425 3.9176471 0.9538364 78.352941176 7

5 Cultural and organizational barriers 2 15 7 44 17 85 2 30 21 176 85 314 5 85 425 3.6941176 1.0581152 73.882352941 12

6 Limited Awareness 3 7 8 46 21 85 3 14 24 184 105 330 5 85 425 3.8823529 0.9929725 77.647058824 9

7 Limited Expertise 2 6 9 40 28 85 2 12 27 160 140 341 5 85 425 4.0117647 0.9697093 80.235294118 3

8 Lack of cooperation and commitment among construction stakeholders 1 6 7 55 16 85 1 12 21 220 80 334 5 85 425 3.9294118 0.8134031 78.588235294 6

9 Not enough historical data 0 13 8 35 29 85 0 26 24 140 145 335 5 85 425 3.9411765 1.0276295 78.823529412 5

10 Inadequate communication 4 9 5 41 26 85 4 18 15 164 130 331 5 85 425 3.8941176 1.1022005 77.882352941 8

11 Narrow focus 2 12 9 42 20 85 2 24 27 168 100 321 5 85 425 3.7764706 1.0394191 75.529411765 11

12 No guidelines on the standard procedure of managing risk 3 4 11 31 36 85 3 8 33 124 180 348 5 85 425 4.0941176 1.0307594 81.882352941 2

Relative Importance Index (RII) Relative importance index (RII)= (5n5+4n4+3n3+2n2+1n1)/(A*N)

Not at all Slightly somewhat Very Extremely 1n1 2n2 3n3 4n4 5n5 Sum A N A*N SD RII Rank
item no Effect of Risk Management on Project Performance Total respondent
influential influential influential influential influential

1 Deteriorate planning and budgeting 4 5 7 46 23 85 1 10 21 184 115 331 5 85 425 3.9294118 1.0093401 77.882 3

2 Poor resource allocation 4 8 6 35 32 85 4 16 18 140 160 338 5 85 425 3.9764706 1.123096 79.529 1

3 Lack of stakeholder engagement 4 12 4 38 27 85 4 24 12 152 135 327 5 85 425 3.8470588 1.1599044 76.941 6

4 Increasing liability and cost 4 9 6 42 24 85 4 18 18 168 120 328 5 85 425 3.8588235 1.0927569 77.176 5

5 Poor project quality 6 15 10 30 24 85 6 30 30 120 120 306 5 85 425 3.6 1.2649111 72.000 13

6 Poor decision-making 2 13 4 37 29 85 2 26 12 148 145 333 5 85 425 3.9176471 1.1042317 78.353 2

7 Lack of Identification and mitigation of potential risks 5 11 8 38 23 85 5 22 24 152 115 318 5 85 425 3.7411765 1.1665266 74.824 7

8 Poor project communication 4 11 4 42 24 85 4 22 12 168 120 326 5 85 425 3.8352941 1.1217234 76.706 8

9 Lack of stakeholder confidence 5 16 11 29 24 85 5 32 33 116 120 306 5 85 425 3.6 1.2459458 72.000 9

10 Late project delivery 4 13 11 39 18 85 4 26 33 156 90 309 5 85 425 3.6352941 1.1217234 72.706 10

11 Lack of organizational reputation 1 15 14 41 14 85 1 30 42 164 70 307 5 85 425 3.6117647 1.0011198 72.235 11

12 Lack of project safety 1 14 4 40 26 85 1 28 12 160 130 331 5 85 425 3.8941176 1.0581152 77.882 12

13 Lack of project sustainability 2 12 11 41 19 85 2 24 33 164 95 318 5 85 425 3.7411765 1.0368558 74.824 13

14 Enhancing project delays and disruptions 5 11 11 36 22 85 5 22 33 144 110 314 5 85 425 3.6941176 1.1652052 73.882 14

Relative Importance Index (RII) Relative importance index (RII)= (5n5+4n4+3n3+2n2+1n1)/(A*N)

Not at all Slightly somewhat Very Extremely 1n1 2n2 3n3 4n4 5n5 Sum A N A*N SD RII Rank
item no Strategies to Enhance Risk Management Total respondent
influential influential influential influential influential

1 Provide risk management training 1 1 3 32 48 85 1 2 9 128 240 380 5 85 425 4.4705882 0.733 89.412 1

2 Early identification of potential risks 3 1 4 47 30 85 3 2 12 188 150 355 5 85 425 4.1764706 0.862 83.529 4

3 Clearly include the risk handling in general condition of contract 2 6 8 44 25 85 2 12 24 176 125 339 5 85 425 3.9882353 0.945 79.765 11

4 Increased regulation 2 4 6 49 24 85 2 8 18 196 120 344 5 85 425 4.0470588 0.872 80.941 6

5 Culture and risk awareness within organization 2 9 4 39 31 85 2 18 12 156 155 343 5 85 425 4.0352941 1.029 80.706 7

6 Legal and regulatory compliance requirements 2 6 10 43 24 85 2 12 30 172 120 336 5 85 425 3.9529412 0.950 79.059 13

7 Increase cooperation and commitment among construction stakeholder 3 6 5 45 26 85 3 12 15 180 130 340 5 85 425 4 0.988 80.000 10

8 Participation through the whole project life cycle 2 3 11 45 24 85 2 6 33 180 120 341 5 85 425 4.0117647 0.880 80.235 9

9 Effective information exchange between the actors 1 5 7 49 23 85 1 10 21 196 115 343 5 85 425 4.0352941 0.837 80.706 7

10 Continuously monitor and evaluate 1 4 3 47 30 85 1 8 9 188 150 356 5 85 425 4.1882353 0.809 83.765 3

11 Implement risk mitigation strategies 1 3 7 41 33 85 1 6 21 164 165 357 5 85 425 4.2 0.828 84.000 2

12 Conduct a comprehensive risk assessment 1 7 9 45 23 85 1 14 27 180 115 337 5 85 425 3.9647059 0.906 79.294 12

13 Prioritize risks 2 8 11 40 24 85 2 16 33 160 120 331 5 85 425 3.8941176 1.000 77.882 14


14 Have a guidelines on the standard procedure of managing risk 2 5 6 35 37 85 2 10 18 140 185 355 5 85 425 4.1764706 0.966 83.529 4
Relative Importance Index (RII)

item no Factors affecting the implementations of modern scaffolding materials RII Rank / Frequency

1 Financial capacity of the main contractor 76.235 10


2 Initial Cost of the material 84.941 1
3 Foreign currency problem to import the material easily 79.059 4
4 Availability of the material 78.353 7
5 Financial capacity of the sub- contractor 73.882 12
6 It’s not considered as a direct cost 77.647 9
7 Suppliers problem 80.235 3
8 Construction skill / skilled man power needed 78.588 6
Due to improper utilization of the material, the use value/ life time of the
9 5
modern metal scaffolding material might be decreased 78.824
10 Construction time 77.882 8
11 The quantity/amount of the external work 75.529 11
12 Awareness problem regarding the material with benefit 81.882 2
13 Poor site organization on the site 0.000 13
14 Project stability 0.000 13
15 Pace of the construction 0.000 13