Professional Documents
Culture Documents
Engineering, Procurement, Construction, Installation & Commissioning of the Midia Gas Development Project
Daily Progress Report
MGD-E-GSPO-IL-FOR14-001
To: Client (Black Sea Oil & Gas) CC Contractor (GSP Offshore)
Project Control Manager Andrea Sassi andrea.sassi@bleackseaog.com Diving Manager Nicolae Visan nicolae.visan@gspoffshore.com
PROJECT
DETAILS
Project Contract Number Contractor Client
EPCIC MGD C1759 GSP Offshore SRL Black Sea Oil & Gas SA
WORK LOCATION
Ana & Doina Fields Ana Platform 44° 4' 18.28'' 29° 58' 11.79'' 737829.00 4884131.00 Romania Romania
Doina Wellhead 44° 10' 49.19'' 30° 8' 5.99'' 750587.00 4896682.00
BARGE'S STATUS & POSITIONING
BARGE STATUS & POSITIONING
AREA OF CONCERN
Item Description
1
WEATHER CONDITION
5 Visibility [Mls] 10 10 10 10
1 9 kts
2 Max. Wave Height [m] 0.5 m 0.5 m 0.5 m 0.5 m
3 Temperature [°C] 15 23 21 15
4
SAFETY ACTIVITIES
1 Safety inductions 81 0 81
2 Project planning / briefing meetings 0 0 0
3 Safety Observation Cards Rec'd 194 3 197
4 Safety Observation Cards Closed 183 2 185
5 Permit to Work (PTW) 385 13 398
6 Task Risk Assessment (TRA) performed
SAFETY ACTIVITIES
385 13 398
7 Near Miss Incident 3 0 3
8 Damage to property 2 0 2
9 Number of days since last LTI BSOG Project: 39
10 LTI 0 0 0
11 Fatality 0 0 0
12 First Aid case 0 0 0
13 Medical Treatment Case 0 0 0
14 Safety Walks / Inspections 23 1 24
15 Incidents 0 0 0
16 Accidents 0 0 0
17 HSE Trainings 10 0 10
SAFETY MEETINGS AND DRILLS SINCE START OF PROJECT
1 Fire Drill 0 1
2 Muster Drill 0 0
3 ER Drill 0 0
4 Other Drills 0 5
5 Safety Meeting 0 12
6 Barge Management Meeting 0 0
TOTAL 0 18
SAFETY MEETINGS AND DRILLS
Page 1 of 4
SAFETY MEETINGS AND DRILLS
TOOLBOX MEETINGS
Previous Today Total
S.No Department
Meetings Attendees Meetings Attendees Meetings Attendees
3 Electrical 9 22 0 0 9 22
7 ROV 1 6 1 6 2 12
8 Survey (GeoTeam) 0 0 0 0 0 0
10 Other 9 88 0 0 9 88
Time: GMT+3
OPERATIONS PROGRESS
0:00 0:02 0:02:00 Weather Downtime
0:02 4:43 4:41:00 Changing from Anchors Mode to DP
0:02 4:43 4:41:00 Recovery of the pipeline
2:36 2:45 0:09:00 Transfer load from A&R to Tensioners
2:45 4:43 1:58:00 Continue recovery sequence (including cutting, A&R head, beveling, NDT of pipe end etc.)
Laying the 16" pipeline in DP mode
4:43 4:57 0:14:00 Pull Joint #701
4:57 5:14 0:17:00 Pull Joint #702
5:14 5:25 0:11:00 Pull Joint #703
5:25 5:35 0:10:00 Pull Joint #704
5:35 5:50 0:15:00 Pull Joint #705
5:50 6:18 0:28:00 Pull Joint #706
6:18 6:36 0:18:00 Pull Joint #707
6:36 6:47 0:11:00 Pull Joint #708
6:47 7:05 0:18:00 Pull Joint #709
7:05 7:19 0:14:00 Pull Joint #710
7:19 7:26 0:07:00 Pull Joint #711
7:26 7:36 0:10:00 Pull Joint #712
7:36 7:44 0:08:00 Pull Joint #713
7:44 7:53 0:09:00 Pull Joint #714
7:53 8:02 0:09:00 Pull Joint #715
8:02 8:11 0:09:00 Pull Joint #716
8:11 8:19 0:08:00 Pull Joint #717
8:19 8:27 0:08:00 Pull Joint #718
8:27 8:35 0:08:00 Pull Joint #719
8:35 8:44 0:09:00 Pull Joint #720
8:44 8:53 0:09:00 Pull Joint #721
8:53 9:00 0:07:00 Pull Joint #722
9:00 9:07 0:07:00 Pull Joint #723
9:07 9:15 0:08:00 Pull Joint #724
9:15 9:25 0:10:00 Pull Joint #725
9:25 9:35 0:10:00 Pull Joint #726
9:35 9:43 0:08:00 Pull Joint #727
9:43 9:52 0:09:00 Pull Joint #728
9:52 10:04 0:12:00 Pull Joint #729
10:04 10:15 0:11:00 Pull Joint #730
10:15 11:10 0:55:00 Weld repair Joint #726
11:10 11:16 0:06:00 Pull Joint #731
11:16 11:28 0:12:00 Pull Joint #732
11:28 11:36 0:08:00 Pull Joint #733
11:36 11:44 0:08:00 Pull Joint #734
11:44 11:53 0:09:00 Pull Joint #735
11:53 12:03 0:10:00 Pull Joint #736
12:03 12:26 0:23:00 Waiting for pipe in the bead stall
12:26 12:34 0:08:00 Pull Joint #737
12:34 12:43 0:09:00 Pull Joint #738
12:43 12:56 0:13:00 Pull Joint #739
12:56 13:04 0:08:00 Pull Joint #740
13:04 13:12 0:08:00 Pull Joint #741
LOG OF EVENTS
Note: Pipe Pull Joint # reference is related to the Bead Stall, while references in the welding section below, are related to WS3, hence it will always be a difference of 2-3
Page 2 of 4
WORK PROGRESS TO DATE
Item Category Main Items Percentage Item Category Main Items Percentage
1 Pipe load-out 100% 21 Demob Welding equipment 0%
ASSET ACTIVITY
Interim mob / demob 0:00:00 0:00:00 0:00:00 Survey 1:28:00 0:00:00 1:28:00
Demobilisation 0:00:00 0:00:00 0:00:00 FJC Repair 11:51:30 0:00:00 11:51:30
Rearranging the anchor wires on the drums, as per MWS request 35:10:00 0:00:00 35:10:00 FJC Repair (in parallel with "Other") 1:59:00 0:00:00 1:59:00
Transfer from anchors to DP (including related works) 95:15:00 4:41:00 99:56:00 Mechanical (in parallel with "Other") 0:25:00 0:00:00 0:25:00
FJC Other (Breakdown equipment etc.) 7:24:00 0:05:00 7:29:00
Cracked Concrete (after tensioners) @ factory repair location 0:22:00 0:00:00 0:22:00
Weather 24:41:00 0:02:00 24:43:00
Total 689:07:00 22:00:00 711:07:00 Total 222:53:00 2:00:00 224:53:00
WELDING ACTIVITY
Pipeline Size 16" OD, 11,9mm WT, 70mm CWC
KP (Bead Stall) @ 23:59 111.530
Water Depth
Laid Today (joints)
NDT - 16"
NDT Repairs 9 1 10
NDT Cut Outs 0 0 0
Repairs Prior to NDT 0 0 0
Cut Outs Prior to NDT 0 0 0
Page 3 of 4
WELDING ACTIVITY
NDT - 8"
Activity Previous Today Total Comments
Total Welds Accepted (NDT Station) 0 0 0
NDT Repairs 0 0 0
NDT Cut Outs 0 0 0
Repairs Prior To NDT 0 0 0
Cut Outs Prior to NDT 0 0 0
NDT Remarks
ROV ACTIVITY
ROV Mob/Demob Dive Time Standby Maintenance WOW Breakdown Other Total Number of Dives
3:48:00 4:10:00 Mojave ROV in water for TDPM - cannot achieve due to environmental conditions 0 visibility, strong currents
ROV Event Log 11:40:00 11:42:00 Mojave ROV in water for TDPM - cannot achieve due to environmental conditions 0 visibility, strong currents
12:00:00 20:00:00 Maintenance of XLX ROV
DIVING ACTIVITY
22:30:00 22:55:00 Mojave ROV in water for TDPM - cannot achieve due to environmental conditions 0 visibility, strong currents
DIVING ACTIVITY
Diving Mob/Demob Dive Time Standby Maintenance WOW Breakdown Other Total Number of Dives
9:27:00 10:40:00 Diver in the water to perform electrical connections of the anode mattresses to the pipeline
Diving Event Log 11:20:00 12:15:00 Diver in the water to perform electrical connections of the anode mattresses to the pipeline
11:25:00 13:00:00 Diver in the water to perform electrical connections of the anode mattresses to the pipeline
14:00:00 16:03:00 Diver in the water to perform electrical connections of the anode mattresses to the pipeline
15:07:00 16:10:00 Diver in the water to perform electrical connections of the anode mattresses to the pipeline
ROB
Item Material Previous ROB Made/Rec`d Today Consumed Today ROB Today Quantity Required Remark
1 Fuel Oil (t) 167.4 0 15.6 151.8
2 Lube (l) 6750 0 50 6700
3 Fresh Water (t) 198 0 36 352
CONSUMABLES STATUS
4 Bilge (m3) 19 0 0 19
5 Sludge (m3) 2 0 0 2
6 Waste Oil (l) 3 0 0 3
7 Grease (kg) 885 0 5 880
8 ArCO2 (Racks) 17 0 0 17
9 Ar (Bottles) 19 0 0 19
10 Propane (Bottles) 40 0 0 40
11 Acetylene (Bottles) 28 0 0 29
12 Oxygen (Bottles) 23 0 0 23
MOVEMENT OF PERSONNEL
MOVEMENT OF PERSONNEL
Marine Crew 31 0 1 30
Catering Crew 17 0 0 17
Client / Visitors 16 0 0 16
Description Personnel per Department Working Time (Per Shift) Today Manhours PREVIOUS TOTAL MANHOURS TOTAL MANHOURS TO DATE
Construction Crew
Marine Crew 30 12 360 11700 12060
REMARKS
REMARKS
Page 4 of 4