GSP Bigfoot 1

Engineering, Procurement, Construction, Installation & Commissioning of the Midia Gas Development Project
Daily Progress Report
MGD-E-GSPO-IL-FOR14-001
To: Client (Black Sea Oil & Gas) CC Contractor (GSP Offshore)

Position Name E-mail Address Position Name E-mail Address


CEO Mark Beacom Mark.Beacom@blackseaog.com Project Manager Frank Wong frank.wong@gspoffshore.com
COO Ludovic Metayer ludovic.metayer@bleackseaog.com DCC - mgd.dcc@gspoffshore.com
Offshore Installation archie.mathie@blackseaog.com Project Installation Team - mgd.off@gspoffshore.com
Archie Mathie
Manager
Contract and geroge.theodor@bleackseaog.com Project Controls Team - mgd.pco@gspoffshore.com
George Theodor
Procurement Manager
EPC Contract Manager Keith Niven keith.niven@bleackseaog.com Barge Superintendent Ted Wolford ted.wolford@gspoffshore.com

Project Control Manager Andrea Sassi andrea.sassi@bleackseaog.com Diving Manager Nicolae Visan nicolae.visan@gspoffshore.com

Comunication and CSR Ana-Maria.Pericleanu@bleackseaog.com Barge Master - bf1.captain@gspoffshore.com


Ana -Maria Pericleanu
Manager
Logistic Manager Sorin Aftinici sorin.aftinici@bleackseaog.com Chief Engineer - bf1.chmec@gspoffshore.com
HSE Manager Cristian Olteanu cristian.olteanu@bleackseaog.com Chief Electrician - bf1.chel@gspoffshore.com
HR Manager Daniela Stroe daniela.stroe@bleackseaog.com GSP Bigfoot 1 Radio - bf1.radio@gspoffshore.com
QA/QC Manager Mihai Badea mihai.badea@bleackseaog.com Vessels Division Manager Vasile Raceanu vasile.raceanu@gspoffshore.com
Attn: marian.nedelcu@bleackseaog.com Attn: Technical Superintendent Radu Georgescu radu.georgescu@gspoffshore.com
IT and Data Manager Marian Nedelcu
Project Lead Document gavin.busbridge@bleackseaog.com Corporate HSEQ Gary Peebles gary.peebles@gspoffshore.com
Gavin Busbridge
Controller
Project Assistant Ana Daniela Pancu dana.pancu@bleackseaog.com Project QA/QC team - mgd.qac@gspoffshore.com
Offshore Installation george.grigorescu@bleackseaog.com ROV Manager Tiberiu Neagu tiberiu.neagu@gspoffshore.com
George Grigorescu
Engineer
Field Installation lavir.mitrovic@bleackseaog.com COO Andrea Fragiacomo andrea.fragiacomo@gspholding.com
Lavir Mitrovich
Engineer
Transferred Items
Jean-Cristophe Bannier jean-christophe.bannier@bleackseaog.com Deputy CEO Mihai Bratu mihai.bratu@gspoffshore.com
Package Manager
Offshore Installation hsesupervisor.wp3@bleackseaog.com OFC Managing Director Vincent McCarthy vincent.mccarthy@gspoffshore.com
Dan Cosma
HSE Supervisor
Offshore Installation hsesupervisor.wp3@bleackseaog.com HSE Coordinator Teodor Petrica teodor.petrica@gspoffshore.com
Mircea Caprar
HSE Supervisor
Commercial Manager Mario Perrone mario.perrone@gspoffshore.com
OFC Managing Director Mihai Carlan mihai.carlan@gspoffshore.com
Engineering Manager Ashutosh Singhal ashutosh.singhal@gspoffshore.com
Vice President Operations Kimon Ardavanis kimon.ardavanis@me.gspoffshore.com
MGD-GSP-BF1-DPR 039 Date 23-Oct-20 Time (0000-2359 Hrs)
PROJECT DETAILS

PROJECT
DETAILS
Project Contract Number Contractor Client

EPCIC MGD C1759 GSP Offshore SRL Black Sea Oil & Gas SA

WORK LOCATION

WORK LOCATION Location Project Coordinates Country Tax Sector


Latitude North Longitude East Easting [m] Northing [m]

Ana & Doina Fields Ana Platform 44° 4' 18.28'' 29° 58' 11.79'' 737829.00 4884131.00 Romania Romania

Doina Wellhead 44° 10' 49.19'' 30° 8' 5.99'' 750587.00 4896682.00
BARGE'S STATUS & POSITIONING
BARGE STATUS & POSITIONING

Barge Details Time GPS POSITIONING AND TRUE HEADING


12:00 Latitude 44° 26' 6727" N Longitude 28° 52' 2856" E Heading 69
GSP Bigfoot 1
23:59 Latitude 44° 26' 8308" N Longitude 28° 52' 9042" E Heading 69.9
5:50 - 24:00 GSP Altair a/s P/S - Loading Pipes
Vessels Alongside 7:05 - 7:36 GSP Alcor a/s STBD
23:36 - 24:00 GSP Alcor a/s STBD
WORK SUMMARY
WORK SUMMARY & AREA OF CONCERN

Completed Today Tomorrow's Plan

Work Summary Recovered 16" pipeline


Continue laying 16" pipeline in DP Continue laying 16" pipeline in DP
Performed electrical connection of the anode mattresses to the pipeline

AREA OF CONCERN

Item Description

1
WEATHER CONDITION

Item Description 6:00 12:00:00 18:00:00 23:59:00


1 Wind (Direction, Speed [Knots]) SW 8 kts SW 8 kts SW 7 kts SW 5 kts
WEATHER CONDITION

2 Sea State [Direction, Ht., Period] SW 0.4 m SW 0.4 m SW 0.4 m SW 0.4 m

3 Swell [Direction, Ht., Period] W 0.4 m W 0.4 m W 0.3 m W 0.3 m


4 Current (Direction, Speed)

5 Visibility [Mls] 10 10 10 10

6 Pressure [mbar] 1028 1027 1027 1026


7 Temperature [°C] 15 23 20 14

8 Weather Dry Dry Dry Dry


WEATHER FORECAST

Max. mean Wind speed (Knots) 7 kts 9 kts 8 kts


WEATHER FORECAST

1 9 kts
2 Max. Wave Height [m] 0.5 m 0.5 m 0.5 m 0.5 m
3 Temperature [°C] 15 23 21 15

4 Weather Dry Dry Dry Dry


5 Risk of Lightning 23

6 Risk of Fog Nil

SUPPORT SPREAD ROB


SUPPORT SPREAD ROB

Previous Report ROB ROB Today


Item Vessel Name Type Location
Fuel (t) Lube Oil (l) Fresh Water (t) Fuel (t) Lube Oil (l) Fresh Water (t)

1 GSP Queen AHTS In port 33.93 4969 60 24.76 4769 50


2 GSP Altair PSV In field 80.339 4824 231 75 4824 0

4
SAFETY ACTIVITIES

S.No Description Previous Today Total

1 Safety inductions 81 0 81
2 Project planning / briefing meetings 0 0 0
3 Safety Observation Cards Rec'd 194 3 197
4 Safety Observation Cards Closed 183 2 185
5 Permit to Work (PTW) 385 13 398
6 Task Risk Assessment (TRA) performed
SAFETY ACTIVITIES

385 13 398
7 Near Miss Incident 3 0 3
8 Damage to property 2 0 2
9 Number of days since last LTI BSOG Project: 39
10 LTI 0 0 0
11 Fatality 0 0 0
12 First Aid case 0 0 0
13 Medical Treatment Case 0 0 0
14 Safety Walks / Inspections 23 1 24
15 Incidents 0 0 0
16 Accidents 0 0 0
17 HSE Trainings 10 0 10
SAFETY MEETINGS AND DRILLS SINCE START OF PROJECT

S.No Activity Today Total

1 Fire Drill 0 1
2 Muster Drill 0 0
3 ER Drill 0 0
4 Other Drills 0 5
5 Safety Meeting 0 12
6 Barge Management Meeting 0 0
TOTAL 0 18
SAFETY MEETINGS AND DRILLS

Page 1 of 4
SAFETY MEETINGS AND DRILLS
TOOLBOX MEETINGS
Previous Today Total
S.No Department
Meetings Attendees Meetings Attendees Meetings Attendees

1 Deck / Construction crew 530 10218 18 364 548 10582

2 Welding, NDT, FJC (Serimax) 152 3796 4 86 156 3882

3 Electrical 9 22 0 0 9 22

4 Engine Crew 35 101 2 5 37 106

5 Catering 38 636 1 17 39 653

6 Marine 54 283 2 10 56 293

7 ROV 1 6 1 6 2 12

8 Survey (GeoTeam) 0 0 0 0 0 0

9 Diving 131 659 6 30 137 689

10 Other 9 88 0 0 9 88

11 TOTAL 959 11991 34 518 993 16327


LOG OF EVENTS

Start Time End Time Duration Activity Description

Time: GMT+3

BARGE AT LOCATION - CONSTANTA

ENGINE DAILY WORKS


0:00 0:00 24:00:00 DG and auxiliary FW system SW pump suction strainer cleaned
Galley grease trap cleaned
STP maintenance carried out
Accommodation vacuum failure fixed
FW bunkering from GSP Altair
Cleaned and greased all anchor winches
Cleaned around machinery small crane 60T
Top up fuel oil to deck service air compressors

ELECTRICAL DAILY WORK


0:00 0:00 24:00:00 Replace navigational light bulb
Repaired windsock light connection and soldering holder
Checked and repair 220V connection at Station 0 & installed 100 Watts LED
Blasting station breaker trip and due to Serimax connection
Thruster 0 station pipe stop sensor realignment

MARINE DECK DAILY WORK


0:00 0:00 24:00:00 Maintenance of the vessel and safety equipment
Cleaning outside accommodation
Vessel in DP operation

OPERATIONS PROGRESS
0:00 0:02 0:02:00 Weather Downtime
0:02 4:43 4:41:00 Changing from Anchors Mode to DP
0:02 4:43 4:41:00 Recovery of the pipeline
2:36 2:45 0:09:00 Transfer load from A&R to Tensioners
2:45 4:43 1:58:00 Continue recovery sequence (including cutting, A&R head, beveling, NDT of pipe end etc.)
Laying the 16" pipeline in DP mode
4:43 4:57 0:14:00 Pull Joint #701
4:57 5:14 0:17:00 Pull Joint #702
5:14 5:25 0:11:00 Pull Joint #703
5:25 5:35 0:10:00 Pull Joint #704
5:35 5:50 0:15:00 Pull Joint #705
5:50 6:18 0:28:00 Pull Joint #706
6:18 6:36 0:18:00 Pull Joint #707
6:36 6:47 0:11:00 Pull Joint #708
6:47 7:05 0:18:00 Pull Joint #709
7:05 7:19 0:14:00 Pull Joint #710
7:19 7:26 0:07:00 Pull Joint #711
7:26 7:36 0:10:00 Pull Joint #712
7:36 7:44 0:08:00 Pull Joint #713
7:44 7:53 0:09:00 Pull Joint #714
7:53 8:02 0:09:00 Pull Joint #715
8:02 8:11 0:09:00 Pull Joint #716
8:11 8:19 0:08:00 Pull Joint #717
8:19 8:27 0:08:00 Pull Joint #718
8:27 8:35 0:08:00 Pull Joint #719
8:35 8:44 0:09:00 Pull Joint #720
8:44 8:53 0:09:00 Pull Joint #721
8:53 9:00 0:07:00 Pull Joint #722
9:00 9:07 0:07:00 Pull Joint #723
9:07 9:15 0:08:00 Pull Joint #724
9:15 9:25 0:10:00 Pull Joint #725
9:25 9:35 0:10:00 Pull Joint #726
9:35 9:43 0:08:00 Pull Joint #727
9:43 9:52 0:09:00 Pull Joint #728
9:52 10:04 0:12:00 Pull Joint #729
10:04 10:15 0:11:00 Pull Joint #730
10:15 11:10 0:55:00 Weld repair Joint #726
11:10 11:16 0:06:00 Pull Joint #731
11:16 11:28 0:12:00 Pull Joint #732
11:28 11:36 0:08:00 Pull Joint #733
11:36 11:44 0:08:00 Pull Joint #734
11:44 11:53 0:09:00 Pull Joint #735
11:53 12:03 0:10:00 Pull Joint #736
12:03 12:26 0:23:00 Waiting for pipe in the bead stall
12:26 12:34 0:08:00 Pull Joint #737
12:34 12:43 0:09:00 Pull Joint #738
12:43 12:56 0:13:00 Pull Joint #739
12:56 13:04 0:08:00 Pull Joint #740
13:04 13:12 0:08:00 Pull Joint #741
LOG OF EVENTS

13:12 13:20 0:08:00 Pull Joint #742


13:20 13:29 0:09:00 Pull Joint #743
13:29 13:36 0:07:00 Pull Joint #744
13:36 13:46 0:10:00 Pull Joint #745
13:48 13:53 0:05:00 Issues with sand blasting machine (electrical connection)
13:46 14:00 0:14:00 Pull Joint #746
14:00 14:09 0:09:00 Pull Joint #747
14:09 14:17 0:08:00 Pull Joint #748
14:17 14:26 0:09:00 Pull Joint #749
14:26 14:39 0:13:00 Pull Joint #750
14:39 14:46 0:07:00 Pull Joint #751
14:46 14:53 0:07:00 Pull Joint #752
14:53 15:02 0:09:00 Pull Joint #753
15:02 15:08 0:06:00 Pull Joint #754
15:08 15:15 0:07:00 Pull Joint #755
15:15 15:23 0:08:00 Pull Joint #756
15:23 15:32 0:09:00 Pull Joint #757
15:32 15:39 0:07:00 Pull Joint #758
15:39 15:47 0:08:00 Pull Joint #759
15:47 15:54 0:07:00 Pull Joint #760
15:54 16:02 0:08:00 Pull Joint #761
16:02 16:09 0:07:00 Pull Joint #762
16:09 16:22 0:13:00 Pull Joint #763
16:22 16:29 0:07:00 Pull Joint #764
16:29 16:37 0:08:00 Pull Joint #765
16:37 16:45 0:08:00 Pull Joint #766
16:45 16:54 0:09:00 Pull Joint #767
16:54 17:00 0:06:00 Pull Joint #768
17:00 17:09 0:09:00 Pull Joint #769
17:14 17:30 0:16:00 Issues with AUT machine
17:30 17:33 0:03:00 Pull Joint #770
17:33 17:42 0:09:00 Pull Joint #771
17:42 17:55 0:13:00 Pull Joint #772
17:55 18:02 0:07:00 Pull Joint #773
18:02 18:10 0:08:00 Pull Joint #774
18:10 18:20 0:10:00 Pull Joint #775
18:20 18:28 0:08:00 Pull Joint #776
18:28 18:37 0:09:00 Pull Joint #777
18:37 18:45 0:08:00 Pull Joint #778
18:45 18:56 0:11:00 Pull Joint #779
18:56 19:03 0:07:00 Pull Joint #780
19:03 19:11 0:08:00 Pull Joint #781
19:11 19:25 0:14:00 Pull Joint #782
19:25 19:33 0:08:00 Pull Joint #783
19:33 19:40 0:07:00 Pull Joint #784
19:40 19:59 0:19:00 Pull Joint #785
19:59 20:06 0:07:00 Pull Joint #786
20:06 20:13 0:07:00 Pull Joint #787
20:13 20:21 0:08:00 Pull Joint #788
20:21 20:28 0:07:00 Pull Joint #789
20:28 20:36 0:08:00 Pull Joint #790
20:36 20:43 0:07:00 Pull Joint #791
20:43 20:50 0:07:00 Pull Joint #792
20:51 21:10 0:19:00 Parent Coating Repair
21:10 21:14 0:04:00 Pull Joint #793
21:14 21:20 0:06:00 Pull Joint #794
21:20 21:27 0:07:00 Pull Joint #795
21:27 21:34 0:07:00 Pull Joint #796
21:34 21:40 0:06:00 Pull Joint #797
21:40 21:47 0:07:00 Pull Joint #798
21:47 21:53 0:06:00 Pull Joint #799
21:53 22:00 0:07:00 Pull Joint #800
22:00 22:14 0:14:00 Pull Joint #801
22:14 22:21 0:07:00 Pull Joint #802
22:21 22:28 0:07:00 Pull Joint #803
22:28 22:35 0:07:00 Pull Joint #804
22:35 22:42 0:07:00 Pull Joint #805
22:42 22:50 0:08:00 Pull Joint #806
22:50 22:57 0:07:00 Pull Joint #807
22:57 23:05 0:08:00 Pull Joint #808
23:05 23:11 0:06:00 Pull Joint #809
23:11 23:17 0:06:00 Pull Joint #810
23:17 23:26 0:09:00 Pull Joint #811
23:26 23:32 0:06:00 Pull Joint #812
23:32 23:41 0:09:00 Pull Joint #813
23:41 23:48 0:07:00 Pull Joint #814
23:48 23:56 0:08:00 Pull Joint #815
23:56 0:00 0:04:00 Pull Joint #816

Note: Pipe Pull Joint # reference is related to the Bead Stall, while references in the welding section below, are related to WS3, hence it will always be a difference of 2-3

Page 2 of 4
WORK PROGRESS TO DATE

Item Category Main Items Percentage Item Category Main Items Percentage
1 Pipe load-out 100% 21 Demob Welding equipment 0%

2 Pipeline heads load out 50% 22 Demob NDT equipment 0%


3 Survey equipment load out and set up 100% 23 Demob Survey equipment 0%
4 Welding equipment and materials load out and set up 100% 24 Demob remaining 16" Production pipes 0%
Demobilisation Demob remaining 8" WI pipes
5 NDT equipment load out and set up 100% 25 0%
(Onshore / Offshore)
6 FJC equipment and materials load out 100% 26 Demob remaining 8" anodes 0%
Mobilisation

WORK PROGRESS TO DATE


7 ROV and Diving Equipment set-up 100% 27 Demob FJC spread 0%
(Onshore / Offshore)
8 Rigging load out 100% 28 Demob ROV and diving Spread 0%

9 Bunkering and supplies 100% 29 Demobilise Personnel 0%


10 Mobilise Personnel 100%
11 Set up stinger and firing line 100%

12 Transit and set up in location 100%


13 Rearranging anchor wires on the drums as requested by MWS 100%

14 Initiate 16" Pipeline (head touches seabed) 100%

15 HDD pull-in 100%


16 Transfer from anchors to DP (including related works) 100%

17 Pipe-lay Lay 16" Pipeline 8.3%

18 Initiate 8" Pipeline (head touches seabed) 0%

19 Lay 8" Pipeline 0%


20 Recover initiation system for 8" pipeline 0%
ASSET ACTIVITY
Working Time Barge Downtime
Activity Previous Today Cumulative Activity Previous Today Cumulative
Mobilisation 309:15:00 0:00:00 309:15:00 Mechanical 0:14:00 0:00:00 0:14:00
Transit to field / to port 20:54:00 0:00:00 20:54:00 Electrical 1:30:00 0:00:00 1:30:00
Positioning / AH / in field movement 18:15:00 0:00:00 18:15:00 Support Vessels 0:00:00 0:00:00 0:00:00
Pipe-lay preparations (including preparations for initiation) 13:40:00 0:00:00 13:40:00 ROV 0:00:00 0:00:00 0:00:00
Pipe-lay 16" (including HDD Pull) 194:48:00 17:19:00 212:07:00 Diving 0:00:00 0:00:00 0:00:00
Pipe-lay 8" 0:00:00 0:00:00 0:00:00 Weld Cut-out 4:27:00 0:00:00 4:27:00
Additional work 0:00:00 0:00:00 0:00:00 Weld Repair 9:26:30 0:55:00 10:21:30
Other construction works (Install 2x anode mattresses) 1:50:00 0:00:00 1:50:00 Welding Other (Breakdown equipment etc.) 2:24:00 0:00:00 2:24:00

ASSET ACTIVITY
Interim mob / demob 0:00:00 0:00:00 0:00:00 Survey 1:28:00 0:00:00 1:28:00
Demobilisation 0:00:00 0:00:00 0:00:00 FJC Repair 11:51:30 0:00:00 11:51:30

Rearranging the anchor wires on the drums, as per MWS request 35:10:00 0:00:00 35:10:00 FJC Repair (in parallel with "Other") 1:59:00 0:00:00 1:59:00
Transfer from anchors to DP (including related works) 95:15:00 4:41:00 99:56:00 Mechanical (in parallel with "Other") 0:25:00 0:00:00 0:25:00
FJC Other (Breakdown equipment etc.) 7:24:00 0:05:00 7:29:00

NDT (issues with equipment) 0:00:00 0:16:00 0:16:00


Client (All Stop - HiPo Incident) 26:00:00 0:00:00 26:00:00
Other (S2 Wire Broke, cut pipes and lay again, Mooring etc.) 76:09:00 0:23:00 76:32:00

Waiting for onshore HDD process to be completed 56:56:00 0:00:00 56:56:00


Damaged parent coating (repair) 0:00:00 0:19:00 0:19:00

Cracked Concrete (after tensioners) @ factory repair location 0:22:00 0:00:00 0:22:00
Weather 24:41:00 0:02:00 24:43:00
Total 689:07:00 22:00:00 711:07:00 Total 222:53:00 2:00:00 224:53:00

WELDING ACTIVITY
Pipeline Size 16" OD, 11,9mm WT, 70mm CWC
KP (Bead Stall) @ 23:59 111.530

Water Depth 20.0


Laid Today (joints) 113

Laid To Date (joints) 812

Est Total Required 9962


WELDING ACTIVITY

Pipeline Size 8" OD, 12,7mm WT

KP (Bead Stall) @ 23:59

Water Depth
Laid Today (joints)

Laid To Date (joints)

Est Total Required (joints / m)


Welding Remarks

NDT - 16"

Activity Previous Today Total Comments


Total Welds Accepted (NDT Station) 699 113 812
WELDING ACTIVITY

NDT Repairs 9 1 10
NDT Cut Outs 0 0 0
Repairs Prior to NDT 0 0 0
Cut Outs Prior to NDT 0 0 0

Page 3 of 4
WELDING ACTIVITY
NDT - 8"
Activity Previous Today Total Comments
Total Welds Accepted (NDT Station) 0 0 0
NDT Repairs 0 0 0
NDT Cut Outs 0 0 0
Repairs Prior To NDT 0 0 0
Cut Outs Prior to NDT 0 0 0
NDT Remarks

REPAIR DETAILS - 16"

Weld No Defect Location Length Depth Comments


AS-00726 Concavity TOFD 10MHz 15mm 11.9mm

REPAIR DETAILS - 8"

Weld No Defect Location Length Depth Comments

ROV ACTIVITY

ROV Mob/Demob Dive Time Standby Maintenance WOW Breakdown Other Total Number of Dives

Previous 24:00:00 2:21:00 0:00:00 384:00:00 0:00:00 0:00:00 0:00:00 410:21:00 3


Today 0:00:00 0:49:00 0:00:00 8:00:00 0:00:00 0:00:00 0:00:00 8:49:00 3
Cumulative 24:00:00 3:10:00 0:00:00 392:00:00 0:00:00 0:00:00 0:00:00 419:10:00 6
Time Activity Comments

3:48:00 4:10:00 Mojave ROV in water for TDPM - cannot achieve due to environmental conditions 0 visibility, strong currents
ROV Event Log 11:40:00 11:42:00 Mojave ROV in water for TDPM - cannot achieve due to environmental conditions 0 visibility, strong currents
12:00:00 20:00:00 Maintenance of XLX ROV

DIVING ACTIVITY
22:30:00 22:55:00 Mojave ROV in water for TDPM - cannot achieve due to environmental conditions 0 visibility, strong currents
DIVING ACTIVITY

Diving Mob/Demob Dive Time Standby Maintenance WOW Breakdown Other Total Number of Dives

Previous 0:00:00 48:36:00 0:00:00 219:55:00 53:23:00 0:00:00 2:50:00 324:44:00 48


Today 0:00:00 7:13:00 0:00:00 0:00:00 0:00:00 0:00:00 0:00:00 7:13:00 6
Cumulative 0:00:00 55:49:00 0:00:00 219:55:00 53:23:00 0:00:00 2:50:00 331:57:00 54
Time General maintenance Comments

0:02:00 0:26:00 Diver in the water to recover pipeline

9:27:00 10:40:00 Diver in the water to perform electrical connections of the anode mattresses to the pipeline
Diving Event Log 11:20:00 12:15:00 Diver in the water to perform electrical connections of the anode mattresses to the pipeline
11:25:00 13:00:00 Diver in the water to perform electrical connections of the anode mattresses to the pipeline

14:00:00 16:03:00 Diver in the water to perform electrical connections of the anode mattresses to the pipeline
15:07:00 16:10:00 Diver in the water to perform electrical connections of the anode mattresses to the pipeline
ROB

Item Material Previous ROB Made/Rec`d Today Consumed Today ROB Today Quantity Required Remark
1 Fuel Oil (t) 167.4 0 15.6 151.8
2 Lube (l) 6750 0 50 6700
3 Fresh Water (t) 198 0 36 352
CONSUMABLES STATUS

4 Bilge (m3) 19 0 0 19
5 Sludge (m3) 2 0 0 2
6 Waste Oil (l) 3 0 0 3
7 Grease (kg) 885 0 5 880
8 ArCO2 (Racks) 17 0 0 17
9 Ar (Bottles) 19 0 0 19
10 Propane (Bottles) 40 0 0 40
11 Acetylene (Bottles) 28 0 0 29

12 Oxygen (Bottles) 23 0 0 23
MOVEMENT OF PERSONNEL
MOVEMENT OF PERSONNEL

Description Previous On Off POB

Construction Crew 168 0 1 167

Marine Crew 31 0 1 30

Catering Crew 17 0 0 17

Client / Visitors 16 0 0 16

TOTAL 232 0 2 230


MANHOURS RECORDED

Description Personnel per Department Working Time (Per Shift) Today Manhours PREVIOUS TOTAL MANHOURS TOTAL MANHOURS TO DATE

167 12 2004 70176 72180


MANHOURS

Construction Crew
Marine Crew 30 12 360 11700 12060

Catering Crew 17 12 204 7992 8196

Client / Visitors 16 12 192 7372 7564

TOTAL 230 12 2760 97240 100000


MOVEMENT OF HELICOPTERS
MOVEMENT OF
HELICOPTERS

Flight Number Arrival Pax From Depart Pax To

REMARKS
REMARKS

RANK NAME SIGNATURE


APPROVED BY

SUPERINTENDENT Ted Wolford

CLIENT REP. George Grigorescu

Page 4 of 4