Attendees:
COMPANY NAME REPRESENTATIVE EMAIL CONTACT
NUMBER
Pinnacle Cold Storage Inc. PJ Roxas-Chua pj@slkpacific.com
(Client) Nico Arceo nico@pinnaclecoldstorage.com
Asian Filipino Engineering Designs and Engr. Victor Delos Reyes engr.Vic2011@gmail.com 09171096811
Construction Co. (Project Management Engr. Efren Descarga Ecd_mb@yahoo.com
Team) Raul Manansala raulcm_77@rocketmail.com 09916146963
Rovie Arcilla roviezaballaarcilla.0821@gmail.com 09664837835
Adrean Gerona Geronaad@gmail.com 09218570477
Steffany Mae Dominguez Smgdominguez@gmail.com 09365479451
People’s Asia Pacific Construction Anacleto Benusa benusacleto@gmail.com
Corporation Engr. Brian Ammon Manarin ammonmanarin22@gmail.com 0910600291
(Steel Contractor)
M.ESICAT Construction Corporation Engr. Daryl Capua darylcapua@mesicat.com 09972109050
(Structural Contractor) Engr. Kimberlie Julian kimberlie@mesicat.com 09569373260
Bryle Andrei Mendoza bryle@mesicat.com
Ultra-Insulated Panel Systems E.A Gonzalez 09173283015
Corporation Reyman Colmo reymancolmo@gmail.com 09772876941
(Roofing Contractor) Peng Verzosa
Power-Pro (Electrical Contractor) Engr. Dan Michael Justo 09158061342
II. Electrical 1. First Private Pole (to be submitted to 29-May-23. 26-May-23 Waiting for the feedback
Concerns the signed by PEE then will be of Meralco.
submitted by 29 May, 2023.
2.Delivery of Transformer -On Hold- -On Hold- No tentative schedule.
Site should be ready
before delivery.
3. Electrical Plans (Utility Pole) Already given to
M.ESICAT
4. Finalization of Materials for Electrical 18-May-23 18-May-23 18-May-23 MES Done
(should be emailed last May 18, 2023
by MES)
5. Final Electrical Highlights (will be Done
submitted by PM Daryl to Sir PJ)
6. Location and Height of Post 45 ft.
7. Partial deliveries of Electrical 30-May-23
materials/equipment.
8. Second batch of electrical deliveries 01-Jun-23
III. Temporary 2. For completion balance (laptops 30-May-23 (No aircon as of 01-Jun-23 MES Air-conditioning system
and printer) May 31, 2023) already delivered.
Facilities
- aircon will arrive 30 May 2023;
3. Demolition of Temporary Facility 15-May-23 12-Jun-23 MES
(Not yet started)
4. Relocation of barracks & Conference 13-Jun-23 MES
13-Jun-23
room
5. Start of transferring 5-June-23
(Start of
transfer, May
31, 2023)
V. Pinnacle Concerns:
Cold Storage 1. Louver (window manufacturer for
Inc. (Client) bidding)
2. Drainage Area MES
- Need to have the design calculation
for the change of the Pipe Size 04Jun-23 10-Jun-23
approved by consultant; 1 week to
fully set up.
3. Compaction and Backfilling 04-Jun-23 10-Jun-23 MES
- estimated trips still needed to
9. Mobilization August/
September
TIMELINES