Awal impounding 02-Agu-21

DATA OPERASI BENDUNGAN BENDO


PENGISIAN AWAL
1 Hari ke - 112 Minggu 21 November 2021 12.00.00 WIB BOBOT
2 Volume Total EL.+ 220.62 46,439,969.29 m3 61.78 %
Volume Efektif 38,069,659.65 m3 75.36 %
3 MAW EL. + 209.10 m
4 Volume saat ini 28,689,073.45 m3
Luas Genangan 130.44 Ha 73.22 %
Sebelumnya hari ke- 112 Minggu 21 November 2021 8.00.00 wib
5 MAW EL. + 209.05 c
Volume 28,624,091.48 m3
Kenaikan Elevasi 0.05 m

6 Q-Outflow 0

#1 Pintu 1 Elv. 186.82 100.00% 0.000 m3/det


#2 Emergency 400mm 100.00% 0.406 m3/det
7 Penguapan 0.00 mm/hari 0.000 m3/det
8 Q-Inflow 5.140 m3/det 4

Dam Instruments
9 Rembesan di waduk (mm)
V-notch 2 (kanan) Tergenang 98 4.248 liter/det
V-notch 3 (kiri) Tergenang 21 0.090 liter/det
TOTAL 4.338 liter/det
10 Drainase tebing
V-notch 1 Tergenang 76 2.250 liter/det
V-notch 4 Tergenang 113 6.065 liter/det
TOTAL 8.315 liter/det
14 Curah Hujan Sta. Bendungan Bendo mm
STa. Sooko mm
STa. Poedak mm
15 Temperature max °C
16 Temperature min °C
17 Wind Run Km/hari
18 Barrometer mb

Keterangan: v-notch dilaporkan pada jam 12:00 wib