Professional Documents
Culture Documents
Project Management
29-10-19 | 1
Where We Are Now
4-11-2015
pag. 2
Conditions Favoring Development of
High Performance Project Teams
4-11-2015
pag. 3
Building High-Performance Project
Teams
• Recruiting Project Members
– Factors affecting recruiting
• Importance of the project
• Management structure used to complete the project
– How to recruit?
• Ask for volunteers
– Who to recruit?
• Problem-solving ability
• Availability
• Technological expertise
• Credibility
• Political connections
• Ambition, initiative, and energy
4-11-2015
pag. 4
Project Team Meetings
Managing
Establishing
Subsequent
Ground Rules
Meetings
Conducting
Relationship Planning
Decisions Project Decisions
Meetings
4-11-2015
pag. 5
Establishing a Team Identity
4-11-2015
pag. 6
Managing Project Reward Systems
• Group Rewards
– Who gets what as an individual reward?
4-11-2015
pag. 7
Managing Conflict within the
Project Team
4-11-2015
pag. 8
Rejuvenating the Project Team
• Informal Techniques
– Institute new rituals.
– Take an off-site break as a team from the project.
– View an inspiration message or movie.
– Have the project sponsor give a pep talk.
• Formal Techniques
– Hold a team building session facilitated by an outsider to
clarify ownership issues affecting performance.
– Engage in an outside activity that provides an intense common
experience to promote social development of the team.
4-11-2015
pag. 9
Managing Virtual Project Teams
• Challenges:
– Developing trust
• Exchange of social information.
• Set clear roles for each team member.
– Developing effective patterns of communication.
• Keep team members informed on
how the overall project is going.
• Don’t let team members vanish.
• Establish a code of conduct to avoid delays.
• Establish clear norms and protocols for surfacing assumptions and
conflicts.
• Share the pain.
4-11-2015
pag. 10
Project Team Pitfalls
Bureaucratic
Groupthink
Bypass Syndrome
4-11-2015
pag. 11
Key Terms
Brainstorming
Dysfunctional conflict
Functional conflict
Groupthink
Nominal group technique (NGT)
Positive synergy
Project kickoff meeting
Project vision
Team building
Team rituals
Virtual project team
4-11-2015
pag. 12
Part 3: Managing the process • PART 3: Process
• Chapter 11: Managing project teams
Project management: the managerial process
Project Management
29-10-19 | 13
Where We Are Now
4-11-2015
pag. 14
Rationale for Reducing Project
Duration
4-11-2015
pag. 15
Options for Accelerating Project
Completion
4-11-2015
pag. 16
Explanation of Project Costs
4-11-2015
pag. 17
Project Cost–Duration Graph
FIGURE 9.1
4-11-2015
pag. 18
Constructing a Project Cost–
Duration Graph
4-11-2015
pag. 19
Constructing a Project Cost–Duration Graph
4-11-2015
pag. 20
Activity Graph
FIGURE 9.2
4-11-2015
pag. 26
Summary Costs by Duration
FIGURE 9.5
4-11-2015
pag. 31
Project Cost–Duration Graph
FIGURE 9.6
4-11-2015
pag. 32
What if Cost, Not Time Is the
Issue?
4-11-2015
pag. 24
Key Terms
Crashing
Crash point
Crash time
Direct costs
Fast-tracking
Indirect costs
Outsourcing
Project cost–duration graph
4-11-2015
pag. 25
Part 3: Managing the process • PART 3: Process
• Chapter 11: Managing project teams
Project management: the managerial process
Project Management
29-10-19 | 26
Where We Are Now
4-11-2015
pag. 27
Structure of a Project Monitoring Information System
4-11-2015
pag. 28
Project Monitoring Information
System
4-11-2015
pag. 29
Project Monitoring System…
(cont’d)
• Information System Structure (cont’d)
– Collecting data and analysis
• Who will collect project data?
• How will data be collected?
• When will the data be collected?
• Who will compile and analyze the data?
– Reports and reporting
• Who will receive the reports?
• How will the reports be transmitted?
• When will the reports be distributed?
4-11-2015
pag. 30
The Project Control Process
• Control
– The process of comparing actual performance against plan to identify
deviations, evaluate courses of action, and take appropriate corrective
action.
• Project Control Steps
1. Setting a baseline plan.
2. Measuring progress and performance.
3. Comparing plan against actual.
4. Taking action.
• Tools
– Tracking and baseline Gantt charts
– Control charts
4-11-2015
pag. 31
Developing an Integrated Cost/Schedule
System
3. Develop a time-phased budget
1. Define the work using a WBS. using work packages included in
a. Scope an activity. Accumulate budgets
b. Work packages (PV).
c. Deliverables 4. At the work package level,
d. Organization units collect the actual costs for the
work performed (AC). Multiply
e. Resources
percent complete times original
f. Budgets budget (EV).`
2. Develop work and 5. Compute the schedule variance
resource schedules. (EV-PV) and the cost variance
a. Schedule resources (EV-AC).
to activities
b. Time-phase work packages into a network
4-11-2015
pag. 32
Development of Project Baselines
4-11-2015
pag. 33
Development of Project Baselines
(cont’d)
4-11-2015
pag. 34
Methods of Variance Analysis
4-11-2015
pag. 35
Developing A Status Report: A Hypothetical
Example
• Assumptions
– Each cost account has only one work package, and
each cost account will be represented as an activity
on the network.
– The project network early start times will serve as
the basis for assigning the baseline values.
– From the moment work an activity begins, some
actual costs will be incurred each period until the
activity is completed.
4-11-2015
pag. 36
Indexes to Monitor Progress
• Performance Indexes
– Cost Performance Index (CPI)
• Measures the cost efficiency of work accomplished to date.
• CPI = EV/AC
– Scheduling Performance Index (SPI)
• Measures scheduling efficiency
• SPI = EV/PV
– Percent Complete Indexes
• Indicates how much of the work accomplished represents of
the total budgeted (BAC) and actual (AC) dollars to date.
• PCIB = EV/BAC
• PCIC = AC/EAC
4-11-2015
pag. 37
Additional Earned Value Rules
4-11-2015
pag. 38
Forecasting Final Project Cost
4-11-2015
pag. 39
Key Terms
Baseline budget
Control chart
Cost performance index (CPI) Cost
variance (CV)
Earned value (EV)
Estimated Cost at Completion—Forecasted (EACf)
Estimated Cost at Completion—Revised Estimates (EACre) Percent
complete index—budget costs (PCIB)
Percent complete index—actual costs (PCIC) Schedule
performance index (SPI)
Schedule variance (SV)
Scope creep
To complete performance index (TCPI) Tracking
Gantt chart
Variance at completion (VAC)
4-11-2015
pag. 40
Part 3: Managing the process • PART 3: Process
• Chapter 11: Managing project teams
Project management: the managerial process
Project Management
29-10-19 | 41
Where We Are Now
4-11-2015
pag. 42
Major Tasks of Project Closure
4-11-2015
pag. 43
Project Monitoring Components
4-11-2015
pag. 44
Project Closure
• Types of Project Closure • Close-out Plan:
– Normal Questions to be Asked
– Premature – What tasks are required
to close the project?
– Perpetual
– Who will be responsible
– Failed Project for these tasks?
– Changed Priority – When will closure begin
and end?
– How will the project be
delivered?
4-11-2015
pag. 45
Implementing Closedown
4-11-2015
pag. 46
Creating the Final Report
• Executive Summary • Recommendations
– Project goals met/unmet – Technical improvements
– Stakeholder satisfaction – Corrective actions
with project • Lessons Learned
– User reactions to quality
– Reminders
• of deliverables – Retrospectives
• Analysis • Appendix
– Project mission and objective – Backup data
– Procedures and – Critical information
systems used
– Organization resources
used
4-11-2015
pag. 47
Retrospectives
• Lessons Learned
– An analysis carried out during and shortly after the
project life cycle to capture positive and negative
project learning—“what worked and what didn’t?”
• Goals of Retrospectives
– To reuse learned solutions
– To stop repetitive mistakes
4-11-2015
pag. 48
Retrospectives (cont’d)
4-11-2015
pag. 49
Key Terms
Lessons learned
Organization evaluation
Performance review
Project closure
Project evaluation
Project facilitator
Retrospective
Team evaluation
360-degree review
4-11-2015
pag. 50