Professional Documents
Culture Documents
method, but also to the compression However, PEMBs do have their draw-
contract documents for of schedules even in traditional backs. Perhaps the most significant
design-bid-build arrangements. from a design standpoint is the fact
bidding by requiring Clients want their projects faster and that PEMB manufacturers generally
cheaper, without sacrificing quality. do not perform any foundation
contractors to design As a result, many structural engineers
are expediting the preparation of con-
design. The engineering consultant
still must complete this task and pro-
tract documents for bidding by requir- vide for the foundations in the con-
certain elements in ing contractors to design certain ele- tract documents. Unfortunately, if the
ments in accordance with specified entire project is issued for bid in one
accordance with parameters. This is especially true package, it is necessary for the struc-
with steel-framed buildings, for which tural engineer to do the following:
specified parameters. a common option for reducing design
time is the specification of a pre-engi- 1. Assume a structural system type
neered metal building (PEMB). (braced and/or rigid frames) and
configuration.
An Alternative Design Process 2. Calculate approximate dead, col-
PEMBs have a long and successful lateral, live, snow, wind, seismic,
history, especially in warehouse con- and other loads.
struction. Initially, an owner could 3. Estimate the building base reac-
simply select a particular size and tions.
configuration out of a catalog to 4. Design the anchor bolts and foun-
obtain the structure needed. Over dations accordingly for bidding
time, the industry has become more purposes.
sophisticated, adding sufficient design
capability to accommodate more com- To prevent excessive changes later, the
plex buildings. For such projects, con- engineer will prepare the contract
sulting engineers do not design or documents, especially the PEMB spec-
detail the building frame. Instead, ification itself, to ensure that the
they provide the necessary criteria to building actually provided will be
permit the PEMB manufacturer to consistent with the foundation design.
perform these tasks. This may limit the PEMB manufactur-
TechBriefs 5
may have lean-to bays on one or Conclusion
both sides. Unless specific provi- Owners have more options than ever
sions are made in the original for the design and construction of
design, PEMBs are generally diffi- their facilities. Naturally, no single
cult to expand except by providing approach is best suited to every proj-
additional rigid frames at one end ect. Owners must give careful consid-
or the other. Also, since members eration to all of the factors affecting
are sized very carefully for the the cost and functionality of the struc-
original design loads, there is not a tures that they develop. They should
great deal of reserve strength, and bring a consulting engineering firm on
even if there is some, it is difficult board as early in the process as possi- Jon Schmidt is a senior struc-
or impossible to determine how ble to assist with the decisions that
much. Reinforcement may be nec- tural engineer, specializing in the
need to be made. A pre-engineered
essary if the building's function or analysis and design of aviation
metal building may be an excellent
layout changes significantly in the and industrial facilities. He has
choice for some projects, but can
years ahead, but may not be practi- become problematic for others. worked for Burns & McDonnell
cal since the structure typically since 1994.
must somehow be unloaded as
much as possible before the
changes can be made. In any case,
an owner cannot undertake any
significant modification of a PEMB
without considerable participation
by its original designer/manufac-
turer.