THE PRE-ENGINEERED BUILDING CONCEPT

The primary framing system

In conventional steel buildings, mill-produced


hot rolled sections (beams and columns)
are used. The size of each member is selected
on the basis of the maximum internal stress in
the member.

Since a hot rolled section has a constant depth,


many parts of the member (represented by the
hatched area), in areas of low internal stresses,
are in excess of design requirements. Conventional Steel Frame

Frames of pre-engineered buildings are made


from an extensive inventory of standard steel
plates stocked by the PEB manufacturer. PEB
frames are normally tapered and often have
flanges and webs of variable thicknesses along
the individual members.

The frame geomentry matches the shape of the


internal stress (bending moment) diagram thus
optimizing material usage and reducing the total
weight of the structure. Pre-Engineered Steel Frame

The secondary framing system

“Z” shaped roof purlins and wall girts are used


for the secondary framing. They are lighter than
the conventional hot-rolled “I” or “C” shaped
sections in conventional steel buildings. Continuous members

Nesting of the “Z” shaped members at the


frames allows them to act as continuous members
along the length of the building. This doubles
the strength capacity of the “Z” shaped members
at the laps where the maximum internal stresses Strength capacity is doubled at the lap Nesting of two purlins
normally occur.

PO Box 877 Dammam 31421 Saudi Arabia Phone (966 3) 847 1840 Fax (966 3) 847 1291 saudimarketing@zamilsteel.com
The information contained herein is accurate as of the date of its issue. Zamil Steel reserves the right to make changes, without prior notice, when deemed necessary for the
purpose of product improvement or otherwise. Please contact your nearest Zamil Steel representative for current offering.

www.zamilsteel.com
PRE-ENGINEERED STEEL CONVENTIONAL STEEL PRE-ENGINEERED STEEL CONVENTIONAL STEEL
BUILDINGS (PEBS) BUILDINGS BUILDINGS (PEBS) BUILDINGS
Structure Weight Pre-Engineered Buildings are on the average 30% Primary steel members are selected from standard hot Overall Price per square meter may be as much as 30% lower Higher price per square meter.
lighter through the efficient use of steel. Primary rolled “I” sections, which are, in many segments of the Price than conventional steel.
framing members are tapered (varying depth) built-up members, heavier than what is actually required by
sections, with large depths in the areas of highest design. Members have constant cross-sections Architecture Outstanding architectural design can be achieved at Special architectural design and features must be
stress. regardless of the varying magnitude of the local low cost using standard architectural features and developed for each project, which often require
(internal) stresses along the member length. interface details. Traditional wall and fascia materials, research and thus resulting in much higher costs.
such as concrete, masonry and wood, can be utilized.
Secondary members are light gage (light weight) roll- Secondary members are selected from standard hot
formed (low labor cost) “Z” or “C” shaped members. rolled “I” or “C” sections, which are heavier. Sourcing and Building is supplied complete with cladding and all Many sources of supply considerable: project
Co-ordination accessories, including erection (if desired), from a single management time is required to co-ordinate suppliers
Design Quick and efficient; since PEBs are mainly formed of Each conventional steel structure is designed from “one stop” source. and sub-contractors.
standard sections and connections, design time is scratch by the Consultant, with fewer design aids
significantly reduced. Basic designs, based on available to the Engineer. Cost of Change PEB manufacturers usually stock a large amount of Substitution of hot rolled sections, that are infrequently
international design standards and codes, are used Orders rolled by mills, is expensive and time consuming.
basic raw materials that can be flexibly used in many
over and over.
types of PEB projects.
Specialized computer analysis and design programs Substantial engineering and detailing work is required
Change orders are easily accommodated at all stages Change orders that are made, after hot rolled
optimize material required. Drafting is also on every project. Generalized computer analysis
computerized using standard details that minimize the programs require extensive input/output and design of the order fulfillment process. Little or no material is sections are shipped for fabrication, often result in
use of project custom details. alterations. wasted even if a change order is made after redundancies to a lot of hot rolled sections, which
fabrication starts. ultimately result in more cost to the enduser.
Design, shop detail sketches and erection drawings Extensive amount of consultant time is devoted to
are supplied free of charge by the manufacturer. design and drafting, as well as co-ordination and
Approval drawings are usually prepared within 2 review, often resulting in a significant expense. Building Designed to fit the system with standardized and Every project requires special design for accessories
weeks. Accessories interchangeable parts, including pre-designed and special sourcing for each item. Flashing and trims
flashing and trims. building accessories are mass must be uniquely designed and fabricated.
PEB engineers design and detail pre-engineered As each project is a separate case, engineers need produced for economy and are available with the
buildings almost every day throughout the year more time to develop the designs and details of the building. They have been tried in thousands of
resulting in faster and more efficient designs. unique structure. existing buildings.

Consultant’s in-house design and drafting time is More complicated design, requiring extensive design Future All project records are safely and orderly kept in It would be difficult to obtain project records, after a
considerably reduced, allowing more time for and drafting time from Consultants. Expansions electronic format indefinitely, making it easy for the owner long period of time. It is required to contact more
co-ordination and review, and reduction in design fees. or designer to obtain a copy of his building records at than one party, involved in the project, to obtain
any time. accurate information.
Delivery Average 6 to 8 weeks. Average 20 to 26 weeks.
Future expansion is simple, easy and cost effective. Future expansion would be more difficult and, more
Foundations Simple design, easy to construct and light weight. Extensive, heavy foundations required. One supplier can co-ordinate changes. likely, costlier.

Erection Since the connections of the components are standard, The connections are normally complicated and differ Safety and Single source of supply results in total responsibility Multiple responsibilities can result in questions of who
Simplicity the learning curve of erection for each subsequent from project to project, resulting in longer learning Responsibility by one supplier, including design liability. PEB is responsible when components do not fit properly,
project is faster. curves of erection for new projects. manufacturers can be relied upon to service their insufficient material is supplied, or materials fail to
buildings, long after they are supplied, to protect their perform, particularly at the supplier/contractor
Periodic free-of-charge erection support at the site is reputation. interface. The consultant carries total design liability.
usually provided by PEB manufacturers.

Erection Cost and Both costs and time of erection are accurately known Typically, conventional steel buildings are 20% more Performance All components have been specified and designed Components are custom designed for a specific
Time based upon extensive experience with similar expensive than PEB. In most of the cases, the erection
specifically to act together as a system for maximum application on a specific job. Design and detailing
buildings. costs and time are not estimated accurately.
efficiency, precise fit, and peak performance in the errors are possible when assembling the diverse com-
field. ponents into unique buildings.
PEBs are often erected by specialized PEB builders
with extensive experience in the erection of similar
buildings, offering very competitive rates. PEB builders
usually have a stock of standard components, enabling Experience with similar buildings, in actual field Each building design is unique, so prediction of how
them to complete jobs on time should any shortage or conditions worldwide, has resulted in design components will perform together is uncertain.
site damage occur to materials. improvements over time, which allow dependable Materials which have performed well in some climates
prediction of performance. may not do so in other environments.
The erection process is easy, fast, step by step and Erection is slow and extensive field labor is required.
with hardly any requirement for equipment. Heavy equipment is often needed. Global Zamil Steel is a global supplier of pre-engineered Normally, suppliers of conventional steel are oriented
Experience buildings to over 75 countries. The company has to their local markets with experience in local climatic
Seismic The low-weight flexible frames offer higher resistance Rigid heavy weight structures do not perform well in acquired extensive experience in the performance of conditions only.
Resistance to seismic forces. seismic zones. PEBs in different climatic conditions.

Make ZAMIL STEEL your Global Partner.


PRE-ENGINEERED STEEL CONVENTIONAL STEEL PRE-ENGINEERED STEEL CONVENTIONAL STEEL
BUILDINGS (PEBS) BUILDINGS BUILDINGS (PEBS) BUILDINGS
Structure Weight Pre-Engineered Buildings are on the average 30% Primary steel members are selected from standard hot Overall Price per square meter may be as much as 30% lower Higher price per square meter.
lighter through the efficient use of steel. Primary rolled “I” sections, which are, in many segments of the Price than conventional steel.
framing members are tapered (varying depth) built-up members, heavier than what is actually required by
sections, with large depths in the areas of highest design. Members have constant cross-sections Architecture Outstanding architectural design can be achieved at Special architectural design and features must be
stress. regardless of the varying magnitude of the local low cost using standard architectural features and developed for each project, which often require
(internal) stresses along the member length. interface details. Traditional wall and fascia materials, research and thus resulting in much higher costs.
such as concrete, masonry and wood, can be utilized.
Secondary members are light gage (light weight) roll- Secondary members are selected from standard hot
formed (low labor cost) “Z” or “C” shaped members. rolled “I” or “C” sections, which are heavier. Sourcing and Building is supplied complete with cladding and all Many sources of supply considerable: project
Co-ordination accessories, including erection (if desired), from a single management time is required to co-ordinate suppliers
Design Quick and efficient; since PEBs are mainly formed of Each conventional steel structure is designed from “one stop” source. and sub-contractors.
standard sections and connections, design time is scratch by the Consultant, with fewer design aids
significantly reduced. Basic designs, based on available to the Engineer. Cost of Change PEB manufacturers usually stock a large amount of Substitution of hot rolled sections, that are infrequently
international design standards and codes, are used Orders rolled by mills, is expensive and time consuming.
basic raw materials that can be flexibly used in many
over and over.
types of PEB projects.
Specialized computer analysis and design programs Substantial engineering and detailing work is required
Change orders are easily accommodated at all stages Change orders that are made, after hot rolled
optimize material required. Drafting is also on every project. Generalized computer analysis
computerized using standard details that minimize the programs require extensive input/output and design of the order fulfillment process. Little or no material is sections are shipped for fabrication, often result in
use of project custom details. alterations. wasted even if a change order is made after redundancies to a lot of hot rolled sections, which
fabrication starts. ultimately result in more cost to the enduser.
Design, shop detail sketches and erection drawings Extensive amount of consultant time is devoted to
are supplied free of charge by the manufacturer. design and drafting, as well as co-ordination and
Approval drawings are usually prepared within 2 review, often resulting in a significant expense. Building Designed to fit the system with standardized and Every project requires special design for accessories
weeks. Accessories interchangeable parts, including pre-designed and special sourcing for each item. Flashing and trims
flashing and trims. building accessories are mass must be uniquely designed and fabricated.
PEB engineers design and detail pre-engineered As each project is a separate case, engineers need produced for economy and are available with the
buildings almost every day throughout the year more time to develop the designs and details of the building. They have been tried in thousands of
resulting in faster and more efficient designs. unique structure. existing buildings.

Consultant’s in-house design and drafting time is More complicated design, requiring extensive design Future All project records are safely and orderly kept in It would be difficult to obtain project records, after a
considerably reduced, allowing more time for and drafting time from Consultants. Expansions electronic format indefinitely, making it easy for the owner long period of time. It is required to contact more
co-ordination and review, and reduction in design fees. or designer to obtain a copy of his building records at than one party, involved in the project, to obtain
any time. accurate information.
Delivery Average 6 to 8 weeks. Average 20 to 26 weeks.
Future expansion is simple, easy and cost effective. Future expansion would be more difficult and, more
Foundations Simple design, easy to construct and light weight. Extensive, heavy foundations required. One supplier can co-ordinate changes. likely, costlier.

Erection Since the connections of the components are standard, The connections are normally complicated and differ Safety and Single source of supply results in total responsibility Multiple responsibilities can result in questions of who
Simplicity the learning curve of erection for each subsequent from project to project, resulting in longer learning Responsibility by one supplier, including design liability. PEB is responsible when components do not fit properly,
project is faster. curves of erection for new projects. manufacturers can be relied upon to service their insufficient material is supplied, or materials fail to
buildings, long after they are supplied, to protect their perform, particularly at the supplier/contractor
Periodic free-of-charge erection support at the site is reputation. interface. The consultant carries total design liability.
usually provided by PEB manufacturers.

Erection Cost and Both costs and time of erection are accurately known Typically, conventional steel buildings are 20% more Performance All components have been specified and designed Components are custom designed for a specific
Time based upon extensive experience with similar expensive than PEB. In most of the cases, the erection
specifically to act together as a system for maximum application on a specific job. Design and detailing
buildings. costs and time are not estimated accurately.
efficiency, precise fit, and peak performance in the errors are possible when assembling the diverse com-
field. ponents into unique buildings.
PEBs are often erected by specialized PEB builders
with extensive experience in the erection of similar
buildings, offering very competitive rates. PEB builders
usually have a stock of standard components, enabling Experience with similar buildings, in actual field Each building design is unique, so prediction of how
them to complete jobs on time should any shortage or conditions worldwide, has resulted in design components will perform together is uncertain.
site damage occur to materials. improvements over time, which allow dependable Materials which have performed well in some climates
prediction of performance. may not do so in other environments.
The erection process is easy, fast, step by step and Erection is slow and extensive field labor is required.
with hardly any requirement for equipment. Heavy equipment is often needed. Global Zamil Steel is a global supplier of pre-engineered Normally, suppliers of conventional steel are oriented
Experience buildings to over 75 countries. The company has to their local markets with experience in local climatic
Seismic The low-weight flexible frames offer higher resistance Rigid heavy weight structures do not perform well in acquired extensive experience in the performance of conditions only.
Resistance to seismic forces. seismic zones. PEBs in different climatic conditions.

Make ZAMIL STEEL your Global Partner.


THE PRE-ENGINEERED BUILDING CONCEPT
The primary framing system

In conventional steel buildings, mill-produced


hot rolled sections (beams and columns)
are used. The size of each member is selected
on the basis of the maximum internal stress in
the member.

Since a hot rolled section has a constant depth,


many parts of the member (represented by the
hatched area), in areas of low internal stresses,
are in excess of design requirements. Conventional Steel Frame

Frames of pre-engineered buildings are made


from an extensive inventory of standard steel
plates stocked by the PEB manufacturer. PEB
frames are normally tapered and often have
flanges and webs of variable thicknesses along
the individual members.

The frame geomentry matches the shape of the


internal stress (bending moment) diagram thus
optimizing material usage and reducing the total
weight of the structure. Pre-Engineered Steel Frame

The secondary framing system

“Z” shaped roof purlins and wall girts are used


for the secondary framing. They are lighter than
the conventional hot-rolled “I” or “C” shaped
sections in conventional steel buildings. Continuous members

Nesting of the “Z” shaped members at the


frames allows them to act as continuous members
along the length of the building. This doubles
the strength capacity of the “Z” shaped members
at the laps where the maximum internal stresses Strength capacity is doubled at the lap Nesting of two purlins
normally occur.

PO Box 877 Dammam 31421 Saudi Arabia Phone (966 3) 847 1840 Fax (966 3) 847 1291 saudimarketing@zamilsteel.com
The information contained herein is accurate as of the date of its issue. Zamil Steel reserves the right to make changes, without prior notice, when deemed necessary for the
purpose of product improvement or otherwise. Please contact your nearest Zamil Steel representative for current offering.

www.zamilsteel.com