S.No. Description of work No. Length Breadth Height Quantity Unit Rate Amount Remarks
Plastering Works in 1:6 Ratio of
20mm thick as per specification.
1
1st Circle
R=2.6m,
Riser 1 perimeter= 16.34 0.60 9.80
Q=2*π*R*H
E.R=2.6m,
Trade 1 Area= 6.72 6.72
I.R=2.15
2nd Circle
R=2.15m,
Riser 1 perimeter= 13.51 0.55 7.43
Q=2*π*R*H
E.R=2.15m,
Trade 1 Area= 6.72 6.72
I.R=1.7m
3rd Circle
R=1.7m,
Riser 1 perimeter= 10.68 0.80 8.55
Q=2*π*R*H
E.R=1.7m,
Trade 1 Area= 6.72 6.72
I.R=1.25m
Total 45.92 Sq.M 658.46 30237.8641

2 Punning Work
1st Circle
Externa
Radii=2.6m,
Trade 1 Area= 6.72 6.72
Internal
Radii=2.15
2nd Circle
Externa
Radii=2.15m,
Trade 1 Area= 6.72 6.72
Internal
Radii=1.7m
3rd Circle
Externa
Radii=1.7m,
Trade 1 Area= 6.72 6.72
Internal
Radii=1.25m
Total 20.15 Sq.M 409.92 8258.01717

3 2 coat White Washing


1st Circle
R=2.6m,
Riser 1 perimeter= 16.34 0.60 9.80
Q=2*π*R*H
2nd Circle
R=2.15m,
Riser 1 perimeter= 13.51 0.55 7.43
Q=2*π*R*H
3rd Circle
R=1.7m,
Riser 1 perimeter= 10.68 0.80 8.55
Q=2*π*R*H
Total 25.78 Sq.M 47.51 1224.71588

4 Two coat weather coat pain


1st Circle
R=2.6m,
Riser 1 perimeter= 16.34 0.60 9.80
Q=2*π*R*H
2nd Circle
R=2.15m,
Riser 1 perimeter= 13.51 0.55 7.43
Q=2*π*R*H
3rd Circle
R=1.7m,
Riser 1 perimeter= 10.68 0.80 8.55
Q=2*π*R*H
Total 25.78 Sq.M 789.30 20345.49
S.No. Description of work No. Length Breadth Height Quantity Unit Rate Amount Remarks

Wooden carved information


Board of size 3'x4' including frame
of board and 2 vertical post (iron
pipe) of 2"x2"saze and 2m length
5 fixing in place all complete as per 1 1.00 No 15000 15000
specification.

6 सिला लेख of Marbel 1 1.00 No 5000 5000

7 Art Work 1 1.00 LS 50000 50000

8 Sheep Statue 1 1.00 No 55000 55000

Supply of Street Light Solar


Including
complete set(Solar Panal 200 wt.
Transportation
9 2nos,100Amp Battery, 12V,20 1 1.00 Set 52200 52200
and
Ampsolar charge Controller,
installation.
Solar Bulb of 40 watt all complete.

Transportation
Transportation of Sheep Statue
1 LS 20000 20000
from Chetwan

Machhikhola to Site by tractor for


Cement about 28 Km.
Qty=(0.72*45.
Plaster Work in 1:4 Ratio 0.26 ton
10 92)/100
Total sand Qty. 0.26 ton/km 155 1136.02414
Machhakhola to Laprak by tractor
for Sand
Q=
Plaster Work in 1:4 Ratio 1.73 ton 45.92*2*unit
wt. of sand
Tota Cement Qty. 1.73 ton/km 155 7493.77328
Total Estimated Cost 265895.885
VAT 13% 34566.465
Total including VAT 300462.35